main 12 HE, 15 HE, 18 HE, 24 HE, 9 HE User guide

© Baxi Heating UK Ltd 2009
Installation & Service Instructions
Only a flue approved for the Main HE can be used.
These instructions include the Benchmark Commissioning Checklist
and should be left with the user for safe keeping.
Main HE
Condensing
© Baxi Heating UK Ltd 2009
2
Contents
1. Introduction.....................................................4
2. Technical Data.................................................6
3. Installation Requirements..............................8
3.1 General Information........................................8
3.2 Legislation, Standards & Codes of Practice....8
3.3 Gas Supply......................................................8
3.4 Electricity Supply.............................................9
3.5 Location of Boiler............................................9
3.6 Condensate Disposal....................................10
3.7 Air Supply......................................................11
3.8 Flue Systems...........................................11
3.9 Plume Displacement....................................18
3.10 Water Circulating Systems...........................22
4. Installation.....................................................26
4.1 Unpack, Prepare the Wall & Boiler................26
4.2 Install the Flue...............................................27
4.3 Electrical Connections..................................28
4.4 Connect the Gas Supply...............................29
4.5 Connect the Water System...........................29
4.6 Connect the Condensate Drain.....................29
5. Wiring Diagrams............................................30
6. Commissioning.............................................32
6.1 Commission the Systems.............................32
6.2 Commission the Boiler..................................32
6.3 Flush the System..........................................32
6.4 Final Adjustments.........................................33
6.5 Advise the User.............................................33
6.6 Documentation.............................................33
7. Control Sequence.........................................34
8. Fault Finding Guides.....................................35
9. Servicing & Parts Replacement...................42
9.1 Servicing Procedure.....................................42
9.2 General Access............................................44
9.3 PCB Enclosure.............................................44
9.4 Gas Valve......................................................44
9.5 Air Pressure Switch.......................................45
9.6 Spark Igniter..................................................45
9.7 Flow/Casting Sensors...................................45
9.8 Overheat Sensor...........................................45
9.9 Fan & Flue Hood...........................................46
9.10 Electrodes/Burner.........................................47
9.11 Injector..........................................................47
9.12 Combustion Chamber Insulation...................48
9.13 Condensate Trap...........................................49
9.14 Primary Heat Exchanger...............................50
9.15 Secondary Heat Exchanger..........................51
10. Short Spares List......................................52
Benchmark Commissioning Checklist ............54
Building Regulations and the Benchmark Commissioning Checklist
Building Regulations (England & Wales) require notification of the installation of a heating appliance to the relevant Local Authority Building Control Department. From 1 April 2005 this can be achieved via a Competent Persons Self Certification Scheme as an option to notifying the Local Authority directly. Similar arrangements will follow for Scotland and will apply in Northern Ireland from 1 January 2006.
The Health & Safety Executive operates the ‘Gas Safe Register’, a self-certification scheme for gas heating appliances.
These arrangements represent a change from the situation whereby compliance with Building Regulations was accepted as being demonstrated by completion of the Benchmark Logbook (which was then left on site with the customer).
With the introduction of Self Certification Schemes, the Benchmark Logbook is being withdrawn. However, a similar document in the form of a commissioning checklist and service interval record is incorporated at the back of these instructions.
This company is a member of the Benchmark initiative and fully supports the aims of the programme. Its aim is to improve the standards of installation and commissioning of central heating systems in the UK and to encourage the regular servicing of all central heating systems to ensure safety and efficiency.
Building Regulations require that installations should comply with manufacturer's instructions. It is therefore important that the commissioning checklist is completed by the installer. The relevant section of Building Regulations only relates to dwellings. Therefore the checklist only applies if the appliance is being installed in a dwelling or some related structure.
The flowchart opposite gives guidance for installers on the process necessary to ensure compliance with Building Regulations.
0086
ISO 9001
FM 00866
© Baxi Heating UK Ltd 2009
3
Installer Notification Guidelines
Choose Building
Regulations Notification
Route
Competent Person's
Self Certification Scheme
Install and Commission this appliance to manufacturer's
instructions
Complete the
Benchmark Checklist
If you notify via the ‘Gas Safe
Register’, the register will issue
the Building Regulations
certificate on members’ behalf
Building Control
Contact your relevant Local
Authority Building Control
(LABC) who will arrange
an inspection or contact a government approved
inspector
Install and Commission this appliance to manufacturer's
instructions
Scheme Members only
Call ‘Gas Safe Register’ on:
www.GasSafeRegister.co.uk
You must ensure that the
certificate number issued by
the ‘Gas Safe Register’ is written
onto the Benchmark Checklist
‘Gas Safe Register’ will issue a
Building Regulations Compliance
Certificate to the property owner
and inform the relevant LABC
0800 408 5577
or log onto:
within 10 days
Complete the
Benchmark Checklist
LABC will record the data
and will issue a
certificate of compliance
© Baxi Heating UK Ltd 2009
4
1. Introduction
Potterton Main HE
Main 9 HE G.C. No. 41 474 01 Main 12 HE G.C. No. 41 474 02 Main 15 HE G.C. No. 41 474 03 Main 18 HE G.C. No. 41 474 04 Main 24 HE G.C. No. 41 474 05
Main HE boilers are fully automatically controlled, wall mounted, fan powered, balanced flue condensing boilers using a cast iron primary heat exchanger.
Main HE boilers meet the requirements of Statutory Instrument “The Boiler (Efficiency) Regulations 1993 No 3083” and deemed to meet the requirements of Directive 92/42/EEC on the energy efficiency requirements for new hot water boilers fired with liquid or gaseous fuels:-
Type test for purpose of Regulation 5 certified by: Notified Body 0087.
Product/Production certified by: Notified Body 0086.
For use with Natural Gas (G20) only at 20mbar and for use in GB/IE only.
Gas Safe
All Gas Safe registered engineers carry a ID card with their licence number and a photograph. You can check your engineer is registered by telephoning 0800 408 5500 or online at www.GasSafeRegister.co.uk
Identification
To gain access to the identification labels, pull the door down.
The data label is on a swing out plate located just above the operating lights and temperature control knob.
A seven digit version of the serial number is located on the operating label attached to the rear of the door.
Important Installation Notes
The boiler is suitable for use with fully pumped open vented and sealed systems with an indirect coil type high efficiency cylinder.
The gas type, supply size and pressure must be checked for suitability before connection.
Failure to install the condensate discharge pipework correctly could affect the reliable operation of the boiler.
For the boiler to operate correctly all air must be vented from the system prior to commissioning and the system itself must be suitably vented.
The system must be designed to always provide a route for water to circulate between the boiler flow and return.
For optimum boiler performance, pump performance must meet the requirements shown on Page 23.
Failure to flush and add inhibitor to the system may invalidate the boiler warranty.
Failure to commission the boiler correctly may result in the installer being charged for any visits made by Potterton.
© Baxi Heating UK Ltd 2009 All rights reserved. No part of this publication may
be reproduced or transmitted in any form or by any means, or stored in any retrieval system of any nature (including in any database), in each case whether electronic, mechanical, recording or otherwise, without the prior written permission of the copyright owner, except for permitted fair dealing under Copyrights, Designs and Patents Act 1988.
Applications for the copyright owner’s permission to reproduce or make other use of any part of this publication should be made, giving details of the proposed use, to the following address:
The Company Secretary, Baxi Heating UK Ltd, The Wyvern Business Park, Stanier Way, Derby, DE21 6BF.
Full acknowledgement of author and source must be given.
WARNING: Any person who does any unauthorised act in relation to a copyright work may be liable to criminal prosecution and civil claims for damages.
The Benchmark Scheme
Benchmark places responsibilities on both manufacturers and installers. The purpose is to ensure that customers are provided with the correct equipment for their needs, that it is installed, commissioned and serviced in accordance with the manufacturer’s instructions by competent persons and that it meets the requirements of the appropriate Building Regulations. The Benchmark Checklist can be used to demonstrate compliance with Building Regulations and should be provided to the customer for future reference.
Installers are required to carry out installation, commissioning and servicing work in accordance with the Benchmark Code of Practice which is available from the Heating and Hotwater Industry Council who manage and promote the Scheme. Visit www.centralheating.co.uk for more information.
© Baxi Heating UK Ltd 2009
5
Health and Safety Information for the Installer and Service Engineer
Under the Consumer Protection Act 1987 and Section 6 of the Health and Safety at Work Act 1974, we are required to provide information on substances hazardous to health.
Small quantities of adhesives and sealants used in the product are cured and present no known hazards. The following substances are also present.
Man-Made Mineral Fibre
a) Some component parts of this boiler (insulation
pads, gaskets and rope seals) are manufactured from man-made mineral fibre.
b) Prolonged or excessive exposure to this material
may result in some irritation to the eyes, skin or respiratory tract.
c) It is advisable to wear gloves when handling these
items.
d) Irritant dust will only be released from the items if
they are broken up or subjected to severe abrasion. In these instances a suitable dust mask and goggles should be worn.
e) Always thoroughly wash hands after installation,
servicing or changing components.
f) When disposing of any items manufactured from
man-made mineral fibre care must be exercised.
g) If any irritation of the eyes or severe irritation of
the skin is experienced seek medical attention.
© Baxi Heating UK Ltd 2009
6
Model Seasonal Efficiency
(SEDBUK) (%)
9 86.1 12 86.4 15 86.2 18 86.2 24 86.2
Models 9 HE 12 HE 15 HE 18 HE 24 HE
Heat Input - Gross kW 10.22 13.62 17.04 20.43 27.25
Btu/h 34,877 46,465 58,129 69,717 92,968
Heat Output
(Non Condensing) kW 8.82 11.78 14.76 17.72 23.63
Btu/h 30,093 40,181 50,350 60,466 80,641
Heat Output (Condensing) kW 9.50 12.64 15.66 18.83 24.94
Btu/h 32,430 43,111 53,431 64,232 85,105
Gas Rate m
3
/h 0.98 1.30 1.63 1.95 2.60
ft
3
/h 34.5 45.9 57.5 68.9 91.9
Burner Pressure - Hot mbar 8.6 10.4 9.0 8.4 12.8
in wg 3.44 4.16 3.6 3.36 5.12
Gas Supply Pressure mbar 20 20 20 20 20
Injector Size mm 2.8 3.1 3.5 3.9 4.1
Water Content litres 2.3 - 9, 12 & 15 2.7 - 18 & 24
Boiler Weight kg 39.0 - 9, 12 & 15 42.8 - 18 & 24
(Lift/Installed - Dry)
Nox Class 2 2 2 2 2
Maximum Working Head 30.5m (100 ft)
Minimum Working Head 150mm (6 in)
Flow Temperature Range 63°C - 82°C
Gas Supply Connection 15 mm Tail
Flow/Return Connections 22 mm Copper
Condensate System Connection 21.5 mm PP
Electricity Supply 230v ~ 50Hz
External Fuse 3A
Internal Fuse Type 3.15AT
Power Consumption 80 Watts (excluding pump)
Electrical Protection IP20
Boiler Type C
12, C32, C52
Boiler Category CAT 1
2
H 2H - G20 - 20 mbar
2. Technical Data
SEDBUK Declaration for Main HE
This value is used in the UK Government's Standard Assessment Procedure (SAP) for energy rating of dwellings. The test data from which it has been calculated have been certified by 0087.
© Baxi Heating UK Ltd 2009
7
595 mm
400 mm
5 mm
clearance
125 mm clearance
130 mm servicing clearance 50 mm installation clearance*
5 mm clearance
410 mm overall
clearance
850 mm
770 mm*
overall
clearance
Fan and Flue Hood
Air Pressure Switch
Secondary Heat Exchanger
Condensate Trap 75 mm
Gas Valve
Primary Heat Exchanger
PCB Enclosure
Burner & Electrodes
Flow Connection
Return Connection
Spark Igniter
Flow Sensor
Overheat Sensor
Casting Sensor
610 mm
servicing
clearance
260 mm
15 mm
clearance
Condensate Connection
Wiring Centre
Data Label
'O' Ring and Clip Joints
Gas Connection
Fig. 1
© Baxi Heating UK Ltd 2009
8
3.3 Gas Supply
The meter and supply pipes must be capable of delivering the required quantity of gas in addition to the demand from any other appliances in the house and must be governed at the meter.
The pipe diameter required will depend on the boiler model and the pipe length from the gas meter.
The gas installation should be in accordance with BS6891.
3. Installation Requirements
3.1 General Information
Optional Extras
Various flue extensions, bends, vertical flue kits, control accessories etc. are available as optional extras. These are detailed in a separate publication.
Lifting
Important - This product should be lifted and handled by
two people. Stooping should be avoided, and protective equipment worn when necessary. Carrying and lifting equipment should be used as required, for example when installing in a loft space.
3.2 Legislation, Standards & Codes of Practice
The boiler is suitable only for installation in GB and IE and must be installed in accordance with the
manufacturer’s instructions and the rules in force, and only used in a suitably ventilated location.
Any purpose provided ventilation should be checked periodically to ensure that it is free from obstruction.
Installation, Commissioning, Service & Repair
In GB, the installation must be carried out by a Competent Person. It must be carried out in accordance with the relevant requirements and current edition of:
The G
AS SAFETY (Installation and Use) REGULATIONS.
The appropriate BUILDING REGULATIONS either the Building Regulations, The Building Regulations (Scotland), Building Regulations (Northern Ireland). The W
ATER FITTINGS REGULATIONS OR WATER BYELAWS in
Scotland. The I.E.E. WIRING REGULATIONS. Where no specific instructions are given, reference should be made to the relevant BRITISH STANDARD
CODES OF PRACTICE. Reference should also be made to B
RITISH GAS
GUIDANCE NOTES FOR THE INSTALLATION OF DOMESTIC GAS CONDENSING BOILERS.
Definition of competence: A person who works for a Gas Safe registered company and holding current certificates in the relevant ACS modules is deemed competent.
Important – Failure to install and commission this boiler to manufacturer’s instructions may invalidate the warranty. This does not affect your statutory rights. In IE, the installation must be carried out by a competent person and installed in accordance with the current edition of:
I.S.813 “D
OMESTIC GAS INSTALLATIONS”.
The current BUILDING REGULATIONS. Reference should also be made to the ETCI rules for electrical installation.
STANDARD B.S. 6891 B.S. 5440: Pt 1 B.S. 5440: Pt 2 B.S. 5546
B.S. 7074
B.S. 5449 B.S. 6798
B.S. 7593
B.S. 7671
SCOPE Gas Installation. Flues. Air Supply. Installation of hot water supplies
for domestic purposes.
Expansion vessels and ancillary equipment for sealed water systems.
Forced circulation hot water systems. Installation of gas fired hot water
boilers. Treatment of water in domestic hot water central heating systems. IEE Wiring Regulations
STANDARD I.S. 813
B.S. 5546
B.S. 7074
B.S. 5449 B.S. 7593
SCOPE Domestic Gas Installations.
Installation of hot water supplies for domestic purposes.
Expansion vessels and ancillary equipment for sealed water systems.
Forced circulation hot water systems. Treatment of water in domestic hot
water central heating systems.
In IE:
The following BS standards give valuable additional information
In GB the following Codes of Practice apply:
© Baxi Heating UK Ltd 2009
9
3.4 Electricity Supply
230V ~ 50Hz via a fused double pole switch with a contact separation of at least 3 mm in both poles.
There must be only one common isolator for the boiler and its control system, it must provide complete electrical isolation and be fitted adjacent to the boiler.
There is no method of isolating the boiler at the user interface.
The power cable to the boiler must be 4-core to supply permanent live, neutral, earth and switched live.
Electrical installation should be in accordance with BS7671.
WARNING: THIS BOILER MUST BE EARTHED AND
CORRECTLY POLARISED.
3.5 Location of Boiler
The boiler must be mounted on a flat wall which is sufficiently robust to take the weight of the boiler.
Location
The boiler should be fitted within the building unless otherwise protected by a suitable enclosure.
Clearances
The boiler requires only the clearances shown on Page 7, after installation.
Combustible Wall
The boiler is suitable for installation to a combustible wall e.g. wood cladding, provided that the flue duct is not closer than 25 mm to combustible material. A metal sleeve should be installed to surround the flue duct to provide a 25 mm annular space. Further guidance is given in BS5440: Pt 1.
Timber Frame
If the boiler is to be fitted into a building of timber frame construction then reference must be made to the current edition of Institution of Gas Engineers Publication IGE/UP/7/ (Gas Installation in Timber Framed Housing).
Bath or Shower Room
If the boiler is fitted in a room containing a bath or shower, it cannot be fitted in zone 0, 1 or 2 (Figs. A & B shows zone dimensions for a bathtub. For other examples refer to the Current I.E.E. Wiring Regulations) reference must be made to the relevant requirements. In GB this is the current I.E.E. Wiring Regulations and Building Regulations. In IE reference should be made to the current edition of I.S. 813 “Domestic Gas Installations” and the current ETCI rules.
Cupboard or Compartment
A cupboard or compartment used to enclose the boiler must be designed and constructed specifically for this purpose. An existing cupboard or compartment may be used provided that it is modified for the purpose. Details of essential features of cupboard/compartment design including airing cupboard installations are given in BS6798 and BS5546.
Service Access
Pipes and wiring must not restrict service access to the boiler
Zone 1
Zone 0
Zone 2
Zone 2
Window Recess
Window Recess
0.6 m
Ceiling
Outside Zones
Zone 2
Zone 1
Zone 0
2.25 m
Window Recess Zone 2
0.6 m
Fig. A
Fig. B
In GB Only
In GB Only
Zone 2
© Baxi Heating UK Ltd 2009
10
3.6 Condensate Disposal
This boiler incorporates a 75 mm trap.
Ensure the disposal of condensate complies with any national or local regulations in force.
Failure to install the condensate disposal pipework correctly will affect the reliable operation of the boiler.
The pipe must always slope continually downward away from the boiler by at least 50 mm in every metre (approx. 2.5°). No air breaks are required in the pipe.
1. The pipe should be run in a proprietary drain pipe material e.g. PVC, PVC-U, ABS, PVC-C or PP. Metal pipework is NOT suitable for use in condensate disposal systems.
2. The pipe should be a minimum of 21.5 mm diameter and must be supported using suitably spaced clips to prevent sagging.
3. To reduce the risk of condensate being trapped, as few bends and fittings as possible should be used.
4. When disposing condensate into a soil stack or waste pipe the effects of existing plumbing must be considered. If soil pipes or waste pipes are subjected to internal pressure fluctuations when WC's are flushed or sinks emptied then back-pressure may force water out of the boiler trap and could affect the operation of the boiler.
5. Any condensate pipework external to the building (or in an unheated part of it e.g. garage) should not exceed 3 metres in length and when in an exposed position, waterproof insulation is recommended. It is also recommended that the pipe diameter is increased to 32 mm.
If the boiler is fitted in an unheated location the entire condensate pipe should be treated as an external run.
Examples are shown of the following methods of termination in order of preference:-
i) via an internal discharge branch
(e.g. sink waste) - Fig. 4. ii) to an internal soil & vent pipe - Fig. 5. iii) to a drain or gully - Fig. 6. iv) to a purpose made soakaway - Fig. 7.
BS 6798 & Part H1 of the Building Regulations give further guidance.
Boiler
50 mm per metre (2.5°)
Minimum fall
Termination to an internal soil and vent pipe
450mm min
Boiler
Termination via internal discharge branch e.g sink waste - downstream
Sink
Pipe must terminate above water level but below surrounding surface
Boiler
Pipe must terminate above water level but below surrounding surface
Termination to a drain or gully
Boiler
500mm min
Termination to a purpose made soak-away
Holes in the soak-away must face away from the building
Fig. 4
Fig. 5
Fig. 6
Fig. 7
© Baxi Heating UK Ltd 2009
11
3.7 Air Supply
The room in which the boiler is installed does not require a purpose provided air vent.
3.7.1 Ventilated Cupboard/Compartment
If the boiler is installed in a cupboard or compartment (with the exception of those installations covered by Section 3.7.2), permanent air vents are required in the cupboard or compartment, one at high level and one at low level, either direct to the outside air or to a room. Both high level and low level air vents must communicate with the same room or must be on the same wall to outside air. Both the high level and low level vent to a room must each have a free area as stated below. The free area of each vent may be halved if the ventilation is provided directly from outside.
Models: 9 HE: 92 cm
2
18 HE: 184 cm
2
12 HE: 123 cm
2
24 HE: 246 cm
2
15 HE: 154 cm
2
The minimum size of ventilated compartment is 850 mm high by 410 mm wide. If the cupboard or compartment has a door the depth must be a minimum of 275 mm. This will allow for a minimum of 15 mm clearance between the front of the boiler and the door for air movement.
3.7.2 Unventilated Compartment
The 9, 12 and 15 models can be installed in an unventilated compartment providing the following conditions are met and no other heat sources are present within the compartment:
1. Minimum sizes for alternative compartments that include the required clearances are shown in Table 1.
2. Maximum Horizontal flue length from turret for boiler in unventilated compartment is 560 mm.
Ventilation should be in accordance with BS 5440: Pt 2.
3.8 Flue Systems
Horizontal
The standard flue/terminal assembly can be cut and is suitable for an installed length from 160 mm up to 700 mm.
1 m flue extensions are available. Maximum straight flue length 3.55 m (3 extensions) (equivalent resistance = 3.55 m). It is recommended that the flue is supported at least once per metre.
All lengths quoted exclude the boiler elbow.
Example layouts are shown on the Page 13.
Bends
A 93° bend is equivalent to a 1m length of flue. A 135° bend is equivalent to a 0.5m length of flue.
Vertical
For information on vertical flues consult the instructions supplied with the vertical flue kits.
3.8.1 Flue Terminal Location
The following guidelines indicate the general requirements for siting balanced flue terminals.
With a condensing boiler a plume of water vapour will be discharged from the flue. This should be taken into account when siting the flue and the effect it could have on neighbouring property and occupants.
If a terminal is less than 2 metres above a balcony, above ground, or above a flat roof to which people have access a suitable terminal guard must be fitted centrally about the terminal.
If the terminal discharges onto a pathway or passageway, check that the combustion products will not cause a nuisance and that the terminal will not obstruct the passageway.
For fitting under low soffits, eaves and to extend beyond guttering it is acceptable for the flue to project up to 500 mm from the face of the wall to the inside of the air intake. This can be painted if required using a suitable external paint.
The terminal location should be in accordance with, in GB, BS 5440 Pt. 1. and IE, I.S. 813 "Domestic Gas Installations".
Table 1
Unventilated Compartments
Example 1 Example 2
Height 1295 mm Height 990 mm Width 550 mm Width 750 mm Depth 540 mm Depth 750 mm
Minimum clearances within compartment
Top 450 mm Top 265 mm Bottom 250 mm Bottom 130 mm Side 75 mm Side 175 mm Front 280 mm Front 490 mm
© Baxi Heating UK Ltd 2009
12
IMPORTANT:
• Only ONE 25mm clearance is allowed per installation.
• Under car ports we recommend the use of the plume displacement kit.
• The terminal position must ensure the safe and nuisance - free dispersal of combustion products.
Fig. 8
Fig. 9
300 min
Terminal Assembly
Top View Rear Flue
Property Boundar y Line
NOTE: The distance from a fanned draught appliance terminal installed parallel to a boundary may not be less than 300mm in accordance with the diagram below
Terminal Position with Minimum Distance (Fig. 8) (mm)
AaDirectly below an opening, air brick, opening windows, etc 300 BaAbove an opening, air brick, opening window etc. 300 CaHorizontally to an opening, air brick, opening window etc. 300 D Below gutters, soil pipes or drain pipes. 25 E Below eaves. 25 F Below balconies or car port roof. 25 G From a vertical drain pipe or soil pipe. 25 H From an internal or external corner. 25 I Above ground, roof or balcony level. 300 J From a surface or boundary line facing a terminal. 600 K From a terminal facing a terminal (Horizontal flue). 1200
From a terminal facing a terminal (Vertical flue). 600
L From an opening in carport (e.g. door, window)
into the dwelling. 1200
M Vertically from a terminal on the same wall. 1500 N Horizontally from a terminal on the same wall. 300 R From adjacent wall to flue (vertical only). 300 S From an adjacent opening window (vertical only). 1000 T Adjacent to windows or openings on pitched and flat roofs 600 U Below windows or openings on pitched roofs 2000
a
In addition, the terminal should be no nearer than 150 mm to an opening in the building fabric formed for the purpose of accommodating a built-in element such as a window frame. See BS 5440 Pt. 1.
*
Opening Window or Door
100mm MIN.
IMPORTANT: If fitting a Plume Displacement Flue Kit, the air inlet must be a minimum of 100mm from any opening windows or doors (see Plume Displacement Section 3.9).
Plume Displacement Kit
Air Inlet
Fig. 10
T
J,K
R
N
M
U
D
C
E
A
I
I
F
L
Likely flue positions requiring a flue terminal guard
I
S
I
B
F
A
G
A
H
H
J,K
I
© Baxi Heating UK Ltd 2009
13
3.8.2 Horizontal Flue Systems
1. The standard flue is suitable only for horizontal applications.
2. Maximum permissible equivalent flue lengths is:-
Horizontal Concentric 3.55m
3. Any additional “in line” bends in the flue system must be taken into consideration. Their equivalent lengths are:­Concentric Pipes:
135° bend 0.5 metres 93° bend 1.0 metres
Twin Flue Pipe
135° bend 0.25 metres
91.5° bend 0.50 metres
The elbow supplied with the standard horizontal flue is not included in any equivalent length calculations.
NOTE: Flue length is measured from point X to Y as shown.
Important: All flue systems must be securely supported at least once every metre. Suitable pipe supports are available as accessories.
Horizontal Flues
Y
X
Plume Displacement Kit
60 /100 Ø
1M Extensions, 45° & 93°
elbows are also available - see
Plume Displacement
Section 3.9
NOTE: Horizontal flue pipes should always be installed with at least a
1.5° fall from the terminal to allow condensate to run back to the boiler.
Y
X
This bend is equivalent to 1 metre
Total equivalent length =
A+B+C+2x90°Bends
B
A
C
This bend is equivalent to 1 metre
© Baxi Heating UK Ltd 2009
14
Vertical Flues (Twin Pipe)
Y
X
Vertical Flues
Y
X
The total equivalent length for this
example is = 5.5 metres.
1m extension
135°bend
91.5°bend
1m
0.25m
0.5m
4
2
2
4.0m
0.5m
1.0m
AIR DUCT
Noof
fittings/pipes
Sub total
Equivalent
Length Value
Equivalent Length Air Duct = 5.5m
1m extension
135°bend
91.5°bend
1m
0.25m
0.5m
4
2
2
4.0m
0.5m
1.0m
FLUE DUCT
Noof
fittings/pipes
Sub total
Equivalent
Length Value
Equivalent Length Flue Duct = 5.5m
Y
X
C
Roof
Terminal
A
B
This bend is equivalent to 1 metre
Total Equivalent Length = A+B+C+1x90°Bend
All vertical and angled runs must be included, measured from the boiler adaptor (point X) to the joint with the flue terminal (point Y). One
91.5° bend or two 135° bends can be included without reduction of the flue length.
If further elbows are required the flue length must be reduced by the following amounts:-
1 metre for each 91.5° bend
0.5 metre for each 135° bend
3.8.3 Twin & Vertical Flue Systems
1. Maximum permissible equivalent flue lengths are:-
Vertical Concentric 1.9m Vertical Twin Pipe 6m*
* Both the air and flue duct can be up to 6 metres long each.
2. Any additional “in line” bends in the flue system must be taken into consideration. Their equivalent lengths are:­Concentric Pipes:
135° bend 0.5 metres 93° bend 1.0 metres
Twin Flue Pipe
135° bend 0.25 metres
91.5° bend 0.50 metres
The elbow supplied with the standard horizontal flue is not included in any equivalent length calculations
NOTE: Flue length is measured from point X to Y as shown.
Important: All flue systems must be securely supported at least once every metre. Suitable pipe supports are available as accessories.
Y
X
© Baxi Heating UK Ltd 2009
15
Key Accessory Size Baxi Code No
FLUE GROUP A Concentric Flue System 100mm diameter
A3 Telescopic Internal Flue Kit 315-500mm 5119654 A2 Telescopic Flue
(incl elbow) 5118069
A Horizontal flue Terminal
(incl elbow) 5118489
B Flue extension 1000mm 5111074 C Flue Bend 93° 5111075 D Flue Bend
(pair) 135° 5111085
U Pipe support
(painted) 100mm 5111080
R Vertical flue adaptor
(use with 5111078) 5111070
T Vertical flue boiler adaptor 5111065 P Wall Liner 5111067 S Flue Terminal Deflector 5111068
FLUE GROUP N Twin Flue System 80mm diameter
E Flue extension
(pair) 1000mm 5111087
F Flue Bend
(pair) 90° 5111072
G Flue Bend
(2 pair) 135° 5111086
O Vertical flue boiler adaptor kit 5111071 H Vertical flue adaptor 5111084 W Pipe support
(pair) 80mm 5111081
FLUE GROUP A, N,
Vertical Flue Kits
K Vertical flue terminal
(use with 5111070) 5111078
L Lead tile 25°/50° 5122151 M Roof cover plate 246143 N Flat roof flashing 246144
A
B
K
R
D
C
N
U,W
S
L
H
M
E
G
F
P
3.8.4 Flue Accessories
A2
A3
O
T
© Baxi Heating UK Ltd 2009
16
For Twin Flue Systems fit the adaptors as follows:-
3.8.5 Vertical Flue Duct Adaptor (Fig. 11)
1. Remove the flue elbow from top of the boiler and replace with the vertical flue duct adaptor ensuring the existing gasket is still in place.
3.8.6 Twin Vertical Flue Boiler Adaptor (Fig. 12)
1. Remove the flue elbow from top of the boiler and replace with the twin vertical flue duct adaptor ensuring the existing gasket is still in place.
2. Attach the rubber spacer to the base of the adaptor.
3. Fit the adaptor to the top of the boiler and secure it to the four hole fixing plate using the long screws supplied.
4. Continue to fit the twin flue system.
Vertical Flue Boiler Adaptor
Gasket
Gasket
Position of Adaptor
Twin Vertical Flue Boiler Adaptor
Fig. 11
Fig. 12
Screw
Original seal
Four hole fixing plate
Stick rubber spacer here
© Baxi Heating UK Ltd 2009
17
Fig. 13
Fig. 14
100mm
685mm
Push Fit Adaptor
Air Duct
Flue Duct
Cut the same amount off the Air Duct & Flue Duct
Approx
1425mm
3.8.7 For Roof Terminals
1. In the case of a pitched roof 25 - 50 degrees, position the lead tile to replace/flash over existing roof tiling. Make an aperture in the roof suitable for the lower tube of the roof terminal and ensure the integrity of the roof cover is maintained. The adjustable plastic collar can either be positioned on the lead tile or the lower tube of the roof terminal prior to the final positioning of the vertical flue through the tile. Check the collar is correctly located to suit required roof pitch (either 25° to 38° or 37° to 50°). From inside the roof adjust the flue to a vertical position and secure to the roof structure with the clamp supplied.
2. For flat roof installations the aluminium flashing must be incorporated into the roof covering and the appropriate aperture made in the roof decking. The vertical flue is lowered onto the flashing making sure the collar of the flue locates securely with the flashing. (A mastic seal may be necessary). From inside the roof, adjust the flue to a vertical position and secure to the roof structure with the clamp supplied.
3.8.8 Flue Dimensions
The standard horizontal flue kit allows for flue lengths between 100mm and 685mm from elbow to terminal (Fig. 13).
The maximum permissible equivalent flue length is: 3.55 metres
NOTE: Each additional 45° of flue bend will account for an equivalent flue length of 0.5m. eg. 45° = 0.5m, 90° = 2 x 45° = 1m etc.
3.8.9 Flue Trim
1. The rubber flue trim supplied may be fitted to either the outside wall or on the inner wall of installation.
3.8.10 Terminal Guard (Fig. 14)
1. When codes of practice dictate the use of terminal guards, they can be obtained from most Plumbers’ and Builders’ Merchants.
2. There must be a clearance of at least 50mm between any part of the terminal and the guard.
3. When ordering a terminal guard, quote the appliance name and model number.
4. The flue terminal guard should be positioned centrally over the terminal and fixed as illustrated.
3.8.11 Flue Deflector (Fig. 13a)
1. If required a flue deflector is available from your Main stockist.
2. Push the flue deflector over the terminal end and rotate to the optimum angle for deflecting plume. Secure the deflector to the terminal with screws provided.
Flue Deflector
Fig. 13a
© Baxi Heating UK Ltd 2009
18
3.9 Plume Displacement Kit (Fig. 14b)
Kit No 5118638
Content of kit
1 0.9m 60/100 Concentric Flue 1 1m 60 Dia Exhaust Flue Pipe 1 Adaptor 2 60 Dia Support Brackets 1 93° Elbow/Plume Outlet Assembly 1 Flexible Flue Trim 3 “O” Rings 1 ‘Jubilee Clip 1 Boiler Elbow
1. This kit is recommended for installations where the condensate plume emitted from the flue may cause a nuisance or affect the surroundings.
2. The terminal must be positioned outside the building with the air inlet facing downward and outlet connection upwards.
3. The plume outlet must always be at least 45° to the wall, with the ‘peak’ uppermost to prevent rain entry (Figs. 15 & 16), and be at least 2 metres above ground level. It must be secured as shown in Fig. 12a. The plume outlet must also be at least 500mm from the air inlet in any direction (Fig. 16).
NOTE: The outlet must be positioned so that any condensate plume is directed away from adjacent surfaces. There must be a constant fall along the entire length of the flue system from the outlet back to the boiler.
4. It is possible to reduce or increase (with the addition of extensions) the length of either or both the 60/100 concentric and 60Ø exhaust.
5. Standard concentric flue extension kits may be added between the boiler elbow and the terminal assembly.
6. The minimum length of the concentric flue is 100mm when measured from the edge of the flue elbow.
IMPORTANT: The maximum equivalent length of concentric flue is:-
3.55 metres Main (9,12,15,18 HE)
3.0 metres Main (24 HE)
Additional bends may be fitted in the concentric flue, but the equivalent length must be reduced by 1 metre (93° elbow) or 0.5 metres (45° elbow).
7. 60Ø 1 metre extensions (including support bracket), and additional 93° & 45° elbows are available. Any additional 93° & 45° elbows must be accounted for when calculating flue lengths.
NOTE: Permitted positions of the plume outlet relative to doors, windows etc. are the same as for conventional concentric flues as detailed in the main Installation & Servicing Instructions and BS5440 Pt. 1. It is NOT necessary to fit a terminal guard over the air inlet or the plume outlet.
Air Inlet at Bottom
‘Peak’ Uppermost
Fig. 15
Fig. 16
500mm Min.
45°
45°
Outlet must be at least 45° from wall face
93° Elbow/Plume Outlet Assembly
60Ø Exhaust Flue Pipe
60Ø Support Bracket
60Ø Support Bracket
Flexible Flue Trim
60/100Ø Concentric Flue
Adaptor
O Ring
O Ring
O Ring
‘Jubilee’ Clip
0.9 metres
Fig. 14b
Fig. 14a
Elbow
© Baxi Heating UK Ltd 2009
19
Concentric 60/100 Flue
60Ø Exhaust
X
Y
Fig. 17
Fig. 18
Flue Length - Worked Example Main 24 HE
In Fig. 18 opposite an additional 93° elbow has been included in the 60Ø exhaust. with 2 x 1metre extensions which have been cut to 0.25metres and fitted. The waste is discarded.
To calculate total length:-
2 x 0.25 metre Lengths = 0.5 metres 1 x 93° Elbow = 1 metre
Total 60Ø Exhaust = 1.5 metres
After consulting the table in Example 3 it can be determined that the concentric flue could be up to approximately 6.25 metres long.
Concentric Flue
Support Bracket
93° Elbow
Extension
Additional Accessories
A - 93° Elbow 5117381 B - 45° Elbow (Pair) 5117382 C - 1 metre 60Ø Extension 5117380
3.9.1 Determining Permissible Lengths
In the graph the solid line diagonal represents the relationship between the concentric flue assembly (and any extensions) and the 60Ø exhaust (and any extensions or additional bends).
Example 1 - Not Permissible
If, for instance, a concentric length of 2.5 metres was required and the 60Ø exhaust needed to be 16 metres the graph shows that this combination would NOT be permissible as the intersection point would be above the solid diagonal line.
Example 2 - Flue Lengths OK
Where both lengths have been determined they can be applied to the graph to check that the installation is permissible. For example, if it was known that 1 metre of concentric flue and 6 metres of 60Ø exhaust were required, the values could be applied to the graph as shown in Example 2. As the point of intersection of the dotted lines is below the solid diagonal line, the combination of lengths is shown to be acceptable.
Example 3 - Flue Lengths OK
In the example shown, assume that the concentric part of the flue needs to be 2 metres long. Find the position of ‘2’ on the horizontal axis of the graph and then project upwards to the solid diagonal line. This is represented by the vertical thick dotted line. Where this dotted line intersects with the solid diagonal line on the graph, project across to the vertical axis. As can be seen this corresponds with 5.5 metres. Therefore, the total equivalent length of the 60Ø exhaust can be up to 5.5 metres. Any elbow equivalences must be accounted for i.e. 93° elbows are equal to 1 metre, each 45° elbow to 0.5 metres.
Example 1
Flue Lengths - Not Permissible
Example 2
Flue Lengths - OK
Example 3
Flue Lengths - OK
Graph Line F is suitable for Main 9, 12, 15, 18 HE Graph Line G is suitable for Main 24 HE
20
18
F
16
14
12
G
10
60 Ø Exhaust (metres)
8
6
4
2
0
0
1
Concentric 60/100 Flue (metres)
2
20
18
F
16
14
12
G
10
60 Ø Exhaust (metres)
8
6
4
2
0
0
3
1
Concentric 60/100 Flue (metres)
20
18
F
16
14
12
G
10
60 Ø Exhaust (metres)
8
6
4
2
0
0
1
Concentric 60/100 Flue (metres)
2
2
3
3
© Baxi Heating UK Ltd 2009
20
Min. 2 metres
Fig. 19
Flue Trim
Position of ‘Jubilee’ Clip screw
Fig. 24
30mm
Fig. 21
Fig. 23
Fig. 20
Fig. 22
Adaptor
Spigot
3.9.2 General Fitting Notes
1. Cut a hole in the external wall which the concentric flue assembly will pass through. The hole should allow the flue to fall back to the boiler at an angle of at least 1.5°.
2. When completed the terminal must be at least 2 metres above ground level (Fig. 19).
3. Measure and cut to size the concentric assembly and any extensions that are being used.
4. Insert the concentric assembly through the hole from outside the building.
5. If required, the flexible flue trim should be fitted prior to this as it cannot be fitted after. Use the large ‘Jubilee’ clip to secure the trim to the flue (See Fig. 20, trim shown dotted), with the screw part of the clip at the bottom.
6. Connect any extensions or elbows that are being used to the concentric assembly. Engage the extension, elbow or concentric assembly in the boiler flue elbow. Fit the boiler flue elbow to the boiler adaptor.
7. Ensure that the concentric assembly and any extensions fall back to the boiler at an angle of at least 1.5° and that the external air inlet is to the bottom.
8. Use suitable brackets to support the concentric assembly and any extensions, and make good inside and outside.
9. The 60Ø exhaust can now be fitted. Slide the adaptor over the plain end of the 60Ø exhaust (Fig. 22) and engage the exhaust in the terminal. Slide the adaptor down over the spigot. Mark and drill the adaptor, using a 2mm bit, as shown in Fig. 21. Secure the adaptor to the spigot using one of the screws supplied.
10. If it is necessary to shorten the 60Ø exhaust or any of the extensions, the excess material must be cut from the plain end of the pipe.
11. Determine the position of the 60Ø exhaust and mark on the wall a suitable position for the support bracket. If extensions are being used, a support bracket is supplied in each kit.
12. Drill the wall, and fit the bracket(s) using the plug and screw provided.
13. Mark and drill the 60Ø exhaust, using a 2mm bit, as shown in Fig. 23. Complete the installation of the 60Ø exhaust, securing in the brackets.
14. Fit the 93° elbow/plume outlet and secure with the two remaining screws supplied. Ensure the plume outlet is at least 45° to the wall and that the ‘peak’ is uppermost (Fig.
24).
50mm
30mm
© Baxi Heating UK Ltd 2009
21
3.9.2 General Fitting Notes (cont.)
15. For aesthetic purposes it is permissible to route the 60Ø exhaust in an enclosed box, but the air inlet and plume outlet MUST remain in free air.
16. It is also possible to separate the plume outlet from the 93° elbow to allow the flue to be installed as shown in Fig. 25.
17. To do this, first slacken the two screws retaining the plume outlet to the elbow, and remove the outlet (Fig. 26). The elbow can now be used to connect the vertical to horizontal 60Ø exhaust (Fig. 25). Retighten the screws in the elbow.
18. The outlet can now be fitted into the female end of an 60Ø extension piece. It must be secured using two of the screws supplied in the bag with the ‘Jubilee’ clip.
19. Mark the female end of the extension at 30mm as shown in two positions, directly opposite each other (Fig. 27).
20. Using a suitable bit (e.g. 2mm), drill through the extension and outlet. Secure using two of the screws supplied.
21. The remaining screw must be used to secure the adaptor to the concentric terminal.
22. When the plume outlet is positioned under a balcony or other projection (Fig. 28) it must protrude at least 200mm (it is not necessary to extend it further than this).
23. When under balconies or projections it is permissible to rotate the concentric flue length up to 70°, clockwise or anti-clockwise (Fig. 29), if there is insufficient space to connect vertically.
24.This will allow the connection of the exhaust to the outlet spigot.
25. All other minimum & maximum dimensions must be adhered to, and the air inlet positioned such that it will not be subject to rain entry.
30mm
Fig. 26
Fig. 27
Fig. 25
Fig. 28
Plume Outlet
Elbow
Fig. 29
Outlet Spigot
Concentric Flue Length (shown end-on)
500mm Min.
200mm Min.
70°
© Baxi Heating UK Ltd 2009
22
3.10 Water Circulating Systems
The boiler is suitable for use with fully pumped open vented and sealed systems with an indirect coil type high efficiency cylinder.
The following conditions should be observed on all systems:
• The static head must not exceed 30.5 m (100ft) (3 bar) of water or be less than 150 mm (6 in).
• The flow pipe from the boiler must always be higher than the return pipe.
• To ensure correct operation, the pump must be wired to the boiler terminal block.
3.10.1 Treatment of Water Circulating Systems
All recirculatory water systems will be subject to corrosion unless they are flushed and an appropriate water treatment is applied.
To prevent this, follow the guidelines given in BS 7593 “Treatment of water in domestic hot water central heating systems” and the treatment manufacturers instructions.
Failure to flush and add inhibitor to the system may invalidate the boiler warranty.
Treatment must involve the use of a proprietary cleanser, such as BetzDearborn Sentinel X300 or X400, or Fernox Superfloc and an inhibitor such as BetzDearborn Sentinel X100, or Fernox MB-1 or Copal.
Full instructions are supplied with the products, for further information contact BetzDearborn (+44 151 420
9563) or Fernox (+44 1799 550 811) directly.
It is important to check the inhibitor concentration after installation, system modification and at every service in accordance with the inhibitor manufacturer’s instructions. (Test kits are available from inhibitor stockists.)
3.10.2 System Design
Pipe Sizing
The flow and return connections on the boiler are 22 mm. The sizes of the system flow and return pipes from the boiler should be determined by normal methods, according to the system design requirements. See Fig. 30. and Table 2.
Air Vents
It is recommended that automatic air vents are fitted within the system pipework to prevent air locks during filling, commissioning and normal operation.
To ensure correct circulation, it is essential to vent all air from the system prior to commissioning the boiler.
System Drain Off Points
Drain off points should be fitted in the pipework close to the boiler and in the low points of the system.
Plastic Pipework
If plastic pipe is used for the central heating circuit there must be a run of at least 2 metres of uninsulated copper pipe from the boiler flow and return connections including any branches.
3.10.3 Bypass Requirements
The system must be designed to always provide a route for water to circulate between the boiler flow and return. Best Practice is to use an automatic bypass although it may be possible to use an existing fixed bypass such as a landing or bathroom radiator fitted with two lockshield valves or a bypass fitted with a balancing valve. See Fig. 30.
Systems with Two Port Valves
Where a pair of two port zone valves are used, the total length of the by-pass circuit taken from the boiler connections should be greater than 4 metres of 22 mm pipe. The bypass should be capable of maintaining a minimum flow through the boiler of 4.5 litres/min (1 gal/min).
Systems with Thermostatic Radiator Valves (TRV’s)
Where mechanically operated thermostatic control valves are used, the total length of the by-pass circuit taken from the boiler connections should be greater than 2 metres of 22 mm pipe. The bypass should be capable of maintaining a minimum flow through the boiler of 9.0 litres/min (2 gal/min).
3.10.4 System Controls
For optimum operating efficiency, the heating system into which the boiler is installed should include a control system. Best Practice suggests such a system should comprise: a programmer, room and cylinder thermostats, control valves giving boiler interlock.
Frost Protection - System
The system pipework may require insulation and the protection of an additional frost thermostat.
If the system is drained isolate the external gas and electrical supplies.
© Baxi Heating UK Ltd 2009
23
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
2
2.2
0 5 10 15 20 25 30 35 40
Min. 11°C Max. 20°C
l/min
11.5
15.2
19.2
22.9
30.5
mbar
21.2
34.1
53.0
73.5
124.6
m
0.22
0.35
0.54
0.75
1.27
9 HE
12 HE
15 HE
18 HE
24 HE
Water level
22mm
Flow
Return
Top of casing
Boiler
Max. 30.5m (100ft)
Min. 150mm (6")
Optional 2 port valves
Indirect HE Cylinder
Auto air vent
Alternative existing by-pass arrangement using the bathroom radiator fitted with two lockshield valves
Typical Fully Pumped System fitted with a Close Coupled Feed and Open Vent
** If plastic pipe is used for the central heating circuit there must be a run of at least 2 metres of uninsulated copper pipe from the boiler flow and return connections including any branches.
2m **
Automatic by-pass or existing by-pass balancing valve
Optional 3 port valve
Auto air vent
150 mm Max.
Boiler drain off
point inside casing
Pump with isolating valves
Table 2
3.10.5 Boiler Protection
• A frost thermostat is fitted within the boiler controls which operates even if the temperature control knob is at the ( ) position. The boiler will operate as necessary to maintain the boiler temperature above freezing.
• The boiler is fitted with a timed pump overrun that will operate for around 2 minutes after boiler shutdown.
• The boiler control will operate the pump for around 2 minutes every 24 hours to maintain free running of the pump.
3.10.6 Pump Requirements
• Resistance through the heat exchanger is shown in the graph and Table 2 opposite.
• If other control valves are used in the system the resistance through them, quoted in their manufacturers literature must be taken into account.
3.10.7 Further Details
• Further details on systems are shown in BS5449 and BS6798
Fig. 30
l/min
6.3
8.4
10.6
12.6
16.8
mbar
6.3
10.8
16.9
23.7
41.2
m
0.06
0.11
0.17
0.24
0.42
Water Flow Rate (l/min) and Boiler Resistance (mbar/m)
 
  
  
© Baxi Heating UK Ltd 2009
24
3.10.6 Sealed Systems
System Components
All components used in the sealed system must be suitable for operation at 110°C and at the maximum pressure allowed by the pressure relief valve (normally 3 bar).
Pressure Relief Valve
A pressure relief valve, set to a maximum 3 bar opening pressure must be fitted.
Pressure Relief Valve Discharge Pipe
The pressure relief valve discharge pipe should be not less than 15mm diameter and run continuously downward. It should be routed in such a manner that no hazard occurs to occupants or damage caused to wiring or electrical components.
Consideration must be given to the possibility that boiling water/steam could discharge from the pipe.
The discharge must be outside the building, but must not be above a window, entrance or other public access.
The end of the pipe should terminate facing down, towards the wall and preferably over a drain.
Pressure Gauge
A pressure gauge of minimum range 0-4 bar with a fill pressure indicator must be connected to the system, preferably at the same point as the expansion vessel in a position easily visible from the filling point.
Expansion Vessel
An expansion vessel complying with the requirements of BS 4814 must be connected to the system close to the inlet side of the circulating pump in accordance with the manufacturers instructions, the connecting pipe being unrestricted and not less than 15mm nominal size.
The volume of the vessel should be suitable for the system water content and the nitrogen or air charge pressure should not be less than the system static head.
Calculation
To size the expansion vessel it is first necessary to calculate the volume of water in the system in litres. The following volumes may be used as a conservative guide to calculating the system volume.
Boiler Heat Exchanger: 2.7 litres Small Bore Pipework: 1 litre per kW of system output Micro Bore Pipework: 7 litres Steel Panel Radiators: 8 litres per kW of system output Low Water Capacity Radiators: 2 litres per kW of system output Hot Water Cylinder: 2 litres
The vessel size can now be determined from the information in Table 3 where V = System size in litres.
Where a vessel of the calculated size is not available, the next available larger size should be used.
If the system is extended, the expansion vessel volume may have to be increased unless provision has been made for extension.
Filling Point
A filling point connection on the return pipework must be provided to facilitate initial filling and pressurising and any subsequent water loss replacement/refilling.
The filling method adopted must be in accordance with all relevant water supply regulations and use approved equipment. Your attention is drawn to, in GB, Guidance G24.2 and recommendation R24.2 of the Water Regulations Guide. and IE, the current edition of I.S. 813 “Domestic Gas Installations”.
The system may be filled or replenished by means of a temporary connection between the circuit and a supply pipe, provided a ‘Listed’ double check valve or some other no less effective backflow prevention device is permanently connected at the inlet to the circuit and the temporary connection is removed after use - See Fig. 32.
Further Details on Sealed Systems
Further details of sealed system design are shown in BS5449, BS6798 and BS7074.
1.5
1.5
V x 0.125
Vessel Charge Pressure (bar)
Initial System Pressure (bar)
Expansion Vessel Size (litres)
0.5
1.0
V x 0.11
Table 3
© Baxi Heating UK Ltd 2009
25
22mm
Flow
Return
Boiler
Optional 2 port valves
Indirect HE Cylinder
Auto air vent
Typical Fully Pumped Sealed System
** If plastic pipe is used for the central heating circuit there must be a run of at least 2 metres of uninsulated copper pipe from the boiler flow and return connections including any branches.
Specification of all components 110˚C and 3 bar
2m **
Automatic by-pass or existing by-pass balancing valve
Optional 3 port valve
Auto air vent
Pressure gauge visible from filling point
Safety valve
Expansion vessel
Alternative existing by-pass arrangement using the bathroom radiator fitted with two lockshield valves
Pump with isolating valves
Manual Filling and Make Up Point
Sealed system manual filling and make up point requirements
Stop Valve
Temporary Hose
Stop Valve
Double Check Valve
From Mains
Fig. 31
Fig. 32
© Baxi Heating UK Ltd 2009
26
Fig. 33
4. Installation
4.1 Unpack & Prepare the Wall & Boiler
These instructions assume you have chosen a suitable boiler location which will also allow correct installation of the condensate and flue systems.
1. Carefully unpack the boiler, leave the
packing around the base of the boiler fitted. Do not discard other packaging until
all the items are accounted for and/or the boiler is installed.
2. Place the mounting template in the proposed boiler position ensuring that it is level.
Minimum clearances, fixing points, pipework centrelines and flue incline are all accounted for on the template.
3. Mark the flue hole, mounting bracket fixing positions (two), boiler securing point and pipework centre lines then remove the template.
4. Drill (7 mm drill) and plug the three mounting holes.
Drill (on an incline, approx. at least 1.5° to ensure the condensate drains back to the boiler) a 105mm diameter hole for the flue through the wall or a 127mm diameter hole if the Internal Fitment Kit is being used.
5. Secure the mounting bracket to the wall using two No. 12 x 2" woodscrews (supplied).
6. Lift the boiler by the packing at the base onto the mounting bracket.
7. Remove the packing from the base and square boiler to the wall using the alignment screws on the back panel. Pull the door panel down and remove the two securing screws. Slide off the controls cover assembly and put safely aside.
8. Ensure the boiler is secured to the wall (using the third No. 12 x 2" woodscrew) through the hole in the bracket at the rear of the boiler case.
Note: The anti-theft securing kit (Part No. 238035POT) may be used in place of the third woodscrew if required.
MINIMUM CLEARANCE
Centre Line
Centre Line
Flow
Return
Key Installation Points - Refer to the Installation & Service and/or Flue Kit Instructions for more information.
Condensate Pipe - This must be plastic and always slope continually downwards from the boiler by at least 50 mm
!
in every metre (approx. 2.5˚). No air breaks are required in the condensate pipe.
Termination via internal discharge
Boiler
branch e.g. sink waste - downstream
50
mm
pe
r m
M
Sink
inim
u m
F
all
BOILER OUTLINE
Boiler
Termination to a drain or gully
Boiler
Termination to an internal soil and vent pipe
450mm Min
Boiler
Termination to a purpose made soak-away
BOILER OUTLINE
MINIMUM CLEARANCE
Core Drill Flue Hole
105mm (4")minimum
or 127mm (5") mimimum for Internal Fitment Kit
STAND OFF KIT-
Top Mounting Points
WALL MOUNTING BRACKET
Drill and plug - 7 mm
Secure using woodscrews supplied
etre (2
.5
˚)
Pipe must terminate above water level but below surrounding surface
Pipe must terminate above water level but below surrounding surface
Boiler Mounting
Bracket
500mm Min
Holes in the soak-away must face away from the building
STAND OFF KIT-
Bottom Mounting Points
Boiler Securing Point
Cut with 3° Rise
The dimensions shown ensure the flue is installed with the correct rise of 53 mm
!
in every metre (approx. 3˚) from the boiler.
Dimension 'A'
centre of flue elbow to inside of wall 100 mm 500 mm 1000 mm 1500 mm 2000 mm 2500 mm 3000 mm 3500 mm
Front Clearance
!
For the boiler to operate correctly all air must be vented from the system prior to
!
commissioning and the system itself must be suitably vented.
BOILER SECURING POINT
Drill and plug - 7 mm
Secure using woodscrew supplied or optional Anti-theft kit
Centre Point
Gas
connection
Centre Line
Gas
Centre Line Condensate
MINIMUM CLEARANCE
'A'
Dimension 'B'
vertical offeset required
5 mm 27 mm 53 mm 79 mm 105 mm 131 mm 158 mm 184 mm
275 mm
15 mm Operational clearance and
610 mm Servicing clearance
MINIMUM CLEARANCE
'B'
BOILER OUTLINE
BOILER OUTLINE
Woodscrews
Woodscrew
or
Anti-theft kit
Boiler Mounting Bracket
Lifting points
in base of packing
© Baxi Heating UK Ltd 2009
27
4.2 Install the Flue
These instructions are for standard horizontal rear and side flue applications which have a maximum horizontal installed length of 700 mm when fitted.
The flue elbow is supplied set to the rear. For side outlet slacken the screws and turn the elbow to the required position and re-tighten screws. Ensure all flue elbow seals are still correctly located.
If using a left hand side flue application we recommended you make the flow and return water connections before fitting the flue.
1. Measure dimension X from the centre point of the flue elbow to the outside of the wall and add 50 mm.
2. Mark the dimension to be cut onto the flue as shown. Re-check measurements and ensure the inner flue support bracket is pushed beyond the cut line before cutting.
Cut outer tube and then cut the inner tube flush with the outer. Deburr both tube ends.
3. Slide the wall seal along the flue and into position behind the terminal.
4. To ease assembly of the flue system apply the silicone grease (provided) to the inner seal of the flue elbow. Pass the flue through the wall and push firmly into the flue elbow. The flue is correctly located when the visual check holes are blocked.
5. Ensure the terminal shroud is vertical as shown opposite.
6. Make good the wall around the flue.
7. Refer to Page 17 for flue deflector and or terminal guard requirements
Fig. 34
Silicone Grease Safety Data
The grease supplied is not regarded as a health or environmental hazard under current legislation.
First Aid Measures
Inhalation - Not relevant
Ingestion
Never make an unconscious person vomit or drink fluids ! Rinse mouth thoroughly and drink plenty of water. Get medical attention if any discomfort continues.
Skin Contact
Remove affected person from source of contamination. Get medical attention if irritation persists after washing.
Eye Contact
Make sure to remove any contact lenses from the eyes before rinsing. Promptly wash eyes with plenty of water while lifting the eye lids. Continue to rinse for at least 15 minutes. Get medical attention if any discomfort continues.
Standard Horizontal Flue
Minimum dimension X including wall thickness = 160 mm
Rear flue
Maximum dimension X = 700 mm
Wall seal
Dimension
X
Visual check hole
waste
Inner flue support bracket
Side flue
Dimension
X
Silicone grease to be applied to the single lip inner seal
Dimension X + 50 mm
Wall seal
Orientation of shroud must be vertical as shown
Terminal guard if required
© Baxi Heating UK Ltd 2009
28
4.3 Electrical Connections
For the boiler to operate correctly it requires a four wire connection. There must be mains Permanent Live, Neutral, Earth and a Switched Live from the system.
For the pump to operate correctly it must be wired back to the ‘Pump’ section of the boiler terminal block.
Ensure that the length of the earth wires are such, that if the supply cables are pulled out of the cable clamps the live and neutral wires become taut before the earth wire.
1. Remove the securing screw and pull the wiring centre (See Fig. 1) fully forward.
The wiring must be routed through the cable clamp.
Connect the power supplies as follows;
Permanent Live to 'Mains L'. Neutral to 'Mains N'. Earth to 'Mains E'. Switched Live (from system) to ‘SwL’
Pump Live to ‘Pump L’ Pump Neutral to ‘Pump N’ Pump Earth to ‘Pump E’
2. If fitting a frost thermostat do so as described in the kit.
3. If fitting the optional integral programmer (Part No. 5111963) do so as described in the kit.
4. Carry out preliminary electrical system checks i.e. Earth Continuity, Short Circuit, Polarity and Resistance to Earth.
For safety, leave the electrical supply switched off and isolated until boiler installation is complete.
See Page 31 for typical system wiring.
Schematic wiring with boiler interlock
Fig. 35
There must be both mains Permanent Live and Switched Live from the system to the boiler terminal block for the boiler protection devices to operate correctly.
The pump must be wired to the boiler terminal block for the pump overrun to operate correctly.
Boiler PCB
Mains
N
EESwL
L
Pump
L
N
Typical Frost Stat
Typical Potterton External Programmer
Fused 3A Mains Supply
Typical Frost Stat
br
L
b
N
g/y
Boiler PCB
Mains
EESwL
br
br
g/y
b
Pump supplied from boiler
To System Wiring
br - brown b - blue g/y - green yellow
Pump
L
N
off out
Optional Integral Programmer
DHW
DHW
CH
on
out
To System Wiring
g/y
b
Pump supplied from boiler
Fused 3A Mains Supply
br
b
g/y
From System Wiring
br - brown b - blue g/y - green yellow
© Baxi Heating UK Ltd 2009
29
Flow 22 mm
Return 22 mm
Case Seals
30
35
58
55
Front View
Mounting Bracket
Wall
Side View
30
4.4 Connect the Gas Supply
1. Ensure that the gas supply is isolated at the meter.
2. Solder the gas tail (supplied) to main gas supply before connecting the tail to the gas cock.
To prevent blow lamp damage to the wiring and condensate trap, any soldering of gas pipework must be done away from the boiler.
Do not turn the gas supply on until soundness test and boiler installation are complete.
4.5 Connect the Water System
1. Connect system pipework to the boiler.
Compression fittings must be used to allow future disconnection.
We recommend using two spanners when making the connections.
Heat from a blowlamp could damage the case seals.
4.6 Connect the Condensate
System
1. The condensate connection is a 21.5 mm
PP pipe. To allow access for servicing, we recommend the first connection to the system is a ‘push fit’ type.
2. Prime the condensate system to seal the
trap.
Method 1 - Pour 1/2 litre of water down through the flue products (inner) tube at the terminal.
Method 2 - Pour 1/2 litre of water via a plastic tube inserted into one of the flue sample points on the flue elbow.
3. Check the the condensate disposal
system for soundness.
Open
Securing screws
Gas cock
Remove 'O' Ring from gas cock
before soldering pipework
Fig. 36
Fig. 37
Fig. 38
Plastic nut & washer
Flat face union pipe
Disposal pipework
© Baxi Heating UK Ltd 2009
30
5. Wiring Diagrams
Boiler Wiring
Fig. 39
Earth to
Burner
g/y
g/y
g/y
g/y
g/y
b
y
r
g/y
w
bk
p p
bk
b
Mains Pump
L N E SwL L N E
br
Flame
Detection
Electrode
Fan
br
b
Overheat
Stat
bk
Spark
Spark
Generator
Electrode
r
or
Gas
bk
Valve
y
Flow
Thermistor
y
b
or
Casting
Thermistor
Air Pressure
Switch
b - blue
bk - black
br - brown
g/y - green/yellow
or - orange
p - purple
y - yellow
r - red
b
w - white
© Baxi Heating UK Ltd 2009
31
Fig. 40
Typical System Wiring
CH on
HW off
N
L
E
HW on
Optional
external
programmer
DHW Zone valve
Not used
Pump
supplied
from
boiler
g/y
N
b
Pump
L
br
12
12
11
11
NO
Cyl
NC
NC
stat
stat
Room
C
7894105
6
N
C
Typical System Wiring - two zone valves (S Plan)
External Programmer
The Pump can be wired through the wiring centre
but must be wired direct to Pump L, N & Earth
on boiler terminal block.
Boiler PCB
b - blue
br - brown
EESwL
N
L
Mains
This Appliance must be Earthed
E
NL
17283941056
b
g/y
br
Typical wiring centre
HW off
12 way shown
Pump
supplied
from
boiler
12
12
11
11
NO
Cyl
NC
stat
C
CH Zone valve
Fused 3A
Mains Supply
g/y - green yellow
Frost stat
Optional
external
programmer
CH on
N
L
E
HW on
Boiler PCB
Typical System Wiring - mid position valve (Y Plan)
External Programmer
Mains supply direct to wiring centre
The Pump can be wired through the wiring centre
but must be wired direct to Pump L, N & Earth
on boiler terminal block.
b - blue
br - brown
N
L
EESwL
N
L
Pump
Mains
This Appliance must be Earthed
g/y b
7894105
6
br
E
NL
17283941056
N
NC
stat
Room
C
Mid position valve
b
g/y
br
Typical wiring centre
Frost stat
g/y - green yellow
12 way shown
Fused 3A
Mains Supply
© Baxi Heating UK Ltd 2009
32
6.1 Commission the Water, Electrical and Gas
Systems
Water
The system should be cold flushed. After re-filling, all air must be vented from the system before the boiler is commissioned. On Sealed Systems, manually test the safety valve and fill until the pressure gauge registers 1.5 bar.
Electrical
Ensure that the preliminary electrical safety checks detailed on Page 28 have been carried out.
Gas
The whole of the gas installation including the meter must be checked for soundness and purged according to in GB BS 6891 and in IE I.S. 813 “Domestic Gas Installations”.
6.2 Commission the Boiler
Ensure the top cover and door are correctly fitted.
1. Ensure that the main electricity supply is ‘On’, the
‘Mains On’ (Green) light will flash.
2. Ensure that the main gas supply is turned ‘On’ and
that the boiler gas service cock is in the ‘On’ position.
3. Check that the programmer and any other external
controls, if fitted, are in an ‘On’ position and calling for heat.
4. Turn the temperature control knob to its maximum
setting, the ‘Burner On’ (Green) light will flash and after several seconds, the burner will light automatically.
5. When the burner flame has established, the ‘Burner On’ (Green) light will be on and flames will be visible through the sight glass.
6. With the burner running, check the boiler for gas
soundness using leak detection fluid.
7. Check that the gas supply pressure, burner
pressure and gas rate are correct. See data label
or refer to Page 6.
If adjustment of the burner pressure is required follow Section 9.4.
8. Check that the burner flames are blue and stable.
9. Turn the temperature control knob to ( ) position and check that the burner shuts down.
10. Remove the pressure gauge, re-fit the screws and
check for gas soundness.
11. Re-fit the controls cover assembly and secure with
the screws previously removed.
6.3 Flush the system
1. Drain the system whilst still hot.
2. Re-fill, vent the system, make a final check for
water soundness and add a suitable inhibitor.
3. Complete any labels supplied with the inhibitor and attach to the boiler for future reference.
4. Set the system flow rate to give the required
temperature rise. Set the bypass flow rate.
5. On sealed systems fill until the pressure gauge
registers 1.5 bar. Set the pressure gauge pointer to the system design pressure.
If the boiler fails to light
After five attempts (possibly due to air in the gas supply) it will lockout and the ‘Lockout’ (Red) light will be on.
To reset - Turn the temperature control knob to ( ) position. Wait until the ‘Lockout’ (Red) light switches off. Turn the temperature control knob back to the required setting. The boiler should reset and return to normal operation.
If the boiler fails to operate
Check for fault or lockout codes on the control display and refer to one or a combination of the following:­User Operating label on the boiler. Wiring Diagram, Control Sequence and Fault Finding sections in these instructions.
6. Commissioning
Mains On (Green)
Temperature Control Knob
Burner On
(Green)
Lockout (Red)
Fig. 41
© Baxi Heating UK Ltd 2009
33
6.4 Final Adjustments
Temperature Control
Turn the temperature control knob to adjust the radiator surface temperature and hot water tap temperature between approximately 63°C and 82°C.
Overheat Thermostat
The boiler will require re-setting if an overheat condition occurs (the ‘Lockout’ (Red) light will flash).
Other Boiler Controls
No further setting or checking is necessary as all boiler mounted controls are fail safe.
System Controls
Check that any other external controls connected in the system, such as thermostats are set as required. If a programmer is fitted, set the time and programme the required settings as shown in the instructions supplied with the programmer.
6.5 Advise the User
On completion of the installation, the installer should hand over all instructions and demonstrate the operation of the boiler and its associated controls.
Advise the user of the precautions necessary to prevent damage to the system and to the building in the event of the system remaining inoperative during frost conditions.
Advise the user that this boiler has frost protection, pump overrun and pump anti-seize features (See 3.9.4).
Advise the User that for continued efficient and safe operation of the boiler it is important that adequate servicing is carried out at least once a year.
6.6 Documentation
Carefully read and complete all sections of the “Benchmark” Commissioning Checklist at the rear of this publication that are relevant to the boiler and installation. The details will be required in the event of any warranty work. This publication must be handed to the user for safe keeping and each subsequent regular service visit recorded.
For IE, it is necessary to complete a “Declaration of Conformity” to indicate compliance to I.S. 813. An example of this is given in I.S. 813 “Domestic Gas Installations”. This is in addition to the “Benchmark” Commissioning Checklist.
© Baxi Heating UK Ltd 2009
34
7. Control Sequence
Fig. 42
Indicate thermistor fault
No
Standby
Switched live - ON On/Off switch - ON
Check
thermistors
give valid
readings
Pump ON
Flow
temperature
> 100C
Yes
Flame On
Indicate thermistor fault
Indicate circulation fault
Indicate APS stuck fault
No
Indicate false flame fault
Overheat Lockout
No
No
casting thermistor
No
No
No
Pre-purge 10 secs.
Check
thermistors
read within 8C
Check
< 76C
APS
Off
Flow temp
< (setpoint -6C)
Flow temp
< 100C
APS On
Flame Off
Overheat
stat Off
Ignition 5 secs.
Safety shutdown
No
> 10 mins
No
Indicate APS fault
No
Indicate false flame fault
No
Overheat Lockout
Ignition Lockout
5 mins
Fault
condition
Yes
Yes
flow thermistor
> casting
thermistor
temperature
< setpoint
Pump overrun
temperature
Post purge
Check
Flow
2 mins
Flow
> 100C or
overheat
stat Off
Ignition
attempt or
casting
thermistor
fault
5 secs
Overheat Lockout
Yes
No
Indicate water circulation fault
No
Burner
Off
APS On
Check casting
thermistor
< 80C
No
No
Air Proving Lockout
APS Off 4
times in 15 mins
Casting
temp exceeded
4 times
Circulation Lockout
No
No
Go to **
Flame On
Overheat
stat Off
Run
No
No
5 ignition
attempts made
Overheat Lockout
No
Overheat
stat Off
Check
thermistors
give valid
readings
Switched
live On
On/Off switch
On
No
No
No
Overheat Lockout
Indicate thermistor fault
** from
"casting temp
exceeded
4 times"
© Baxi Heating UK Ltd 2009
35
8. Fault Finding Guide
Fig. 43
Lockout Codes
Key
FAULT
Lockout Burner Mains
Electrical Supply Fault
Lockout Burner Mains
Ignition LOCKOUT
Lockout Burner Mains
Overheat LOCKOUT Manual
Lockout Burner Mains
False Flame Fault Automatic
= off = flashing = on
CONTROL DISPLAY RESET
Manual
Water Circulation
LOCKOUT
PCB Fault
(Replace PCB)
Air Proving
LOCKOUT
APS Stuck Fault Automatic
Flow Thermistor Fault Automatic
Casting Thermistor Fault Automatic
Lockout Burner Mains
Manual
Lockout Burner Mains
Automatic
Lockout Burner Mains
Manual
Lockout Burner Mains
Lockout Burner Mains
Lockout Burner Mains
© Baxi Heating UK Ltd 2009
36
Electrical Supply Fault
Fig. 44
Refer to the boiler wiring diagram
This boiler requires both a
permanent live and a switched live.
Both need to be a
minimum of 190V to function
Is there 230V
at boiler terminal block
(Mains L and N) ?
Yes
Is
terminal block
fuse OK ?
No
No
No Permanent Live to boiler
Check systems controls
and system wiring
Check for shorts on pump,
fan and gas valve
Replace if shorted
and replace fuse
Lockout Burner Mains
off
offoff
Yes
Is there 230V
at 6 way plug to PCB
(Mains L and N) ?
Yes
Replace PCB
No
Check wiring from
terminal block to PCB
© Baxi Heating UK Ltd 2009
37
Ignition Lockout
Fig. 45
Refer to the boiler wiring diagram
Lockout Burner Mains
Is more than
17 mbar dynamic
pressure at the
gas valve
inlet ?
Yes
Are Live and
Neutral to boiler
reversed ?
No
Using meter test
dial, does gas flow
during ignition
sequence ?
Yes
No
Yes
No
Incorrect gas supply
to boiler
Correct the Live and
Neutral connections
Replace gas valve
Yes
Is there 200 VDC
at the gas valve
during ignition
sequence ?
on
Replace PCB
Yes
No No
Rectify wiring
No
Check the
continuity of the
gas valve lead
Replace spark generator
onoff
Lead from PCB
to gas valve faulty
Yes
Is there
a spark ?
Yes
Does flame
establish and then
extinguish ?
No
Yes
Is
spark electrode
damaged ?
Yes
Replace electrode
Yes
Is flame
detection electrode
damaged ?
Yes
Check the continuity of the spark generator
lead
No
Set gap to correct position over falme strip
No
Is the
electrode gap
between
3 and 4 mm ?
Is the
flame detection
gap between 3 and 4 mm ?
Yes
No No
No
8 way connector.
Is there 230 V to
spark generator when gas valve
No
Yes
Refit
opens ?
Is wiring from
spark generator
to electrode OK ?
Rectify wiring
Is wiring to
the detection
electrode OK ?
Yes
No
No
Replace PCB
Yes
© Baxi Heating UK Ltd 2009
38
Overheat Lockout
Fig. 46
Refer to the boiler wiring diagram
Lockout Burner Mains
Wait until the temperature at the flow pipe is <60C
Unplug
the 8 way
connector from PCB.
Is there continuity
between the
2 black wires ?
No
Remove
connectors
from overheat thermostat.
Is there continuity
across the
terminals
No
Replace the overheat
thermostat
False Flame Fault
Yes
Yes
Check as the
'Water Circulation Lockout' fault
Wiring faulty between the PCB
and the overheat thermostat
flashing
onoff
Refer to the boiler wiring diagram
A check is made that no flame is present before an ignition attempt is made. The presence of flame is continually checked during the run period. Note: An unstable flame will cause intermittent problems.
Is the flame
detection electrode
un-damaged ?
Yes
Is the
electrode gap
between
3 and 4 mm ?
Yes
Is the wiring
to the detection
electrode OK ?
No
Replace electrode
No
Set gap to correct
position over flame strip
No
Rectify Wiring
Lockout Burner Mains
flashing
flashingflashing
Yes
Replace PCB
© Baxi Heating UK Ltd 2009
39
Water Circulation Lockout
Fig. 47
Refer to the boiler wiring diagram
This indication can be activated by two faults:
1) Flow direction is checked after 1 minute of burner fire. If the casting thermistor reads a higher temperature than the flow thermistor, the fault occurs. This does not cause a lockout.
2) Adequate circulation is checked continuously during burner fire. If the casting thermistor exceeds 80C the fault occurs. A lockout is activated if this happens 4 times.
Is the system
full of water
Yes
Is the pump
running
Yes
No
Fill system with water and
bleed out all air
No
Is there 230V at
the terminal block
(Pump L and N) ?
Pump or pump wiring fault
Reset
lockout
No
Yes
Wiring from terminal block
Check the
continuity of the
Pump L and N wiring from the
terminal block
to PCB
Yes
to PCB faulty
No
Lockout Burner Mains
on
Replace PCB
flashingflashing
Is there sufficient water flow around the
system ?
Yes
Is the
flow in the
right direction
Yes
Replace PCB
No
No
Air Proving Lockout
Open bypass/TRV's
and check for blockages
Rectify flow and return
pipework
Lockout Burner Mains
on
offoff
The APS is not maintaining its signal.
This has occurred 4 times from a switched
live being present and the burner being lit
Check for blockages in the condensate
system, the flue system and the heat
exchangers
© Baxi Heating UK Ltd 2009
40
Fig. 48
Air Pressure Switch Stuck Fault
Refer to the boiler wiring diagram
Lockout Burner Mains
Yes
No
After 15
seconds,
does the fan run
Switch the boiler on
Yes
No
Unplug
the 12 way
connector from PCB.
Is there continuity
between the
2 orange
wires
No
Refit the
12 way
connector to PCB.
Unplug one APS lead
Switch boiler on. Does fan
run ?
Replace PCB
Yes
Replace fan
Yes
Unplug the APS leads
Is there continuity
across the
the APS
APS stuck in the
On position. Replace
Short circuit on the
wiring - rectify
No
Yes
Rectify fault
Switch off
Unplug the
12 way connector and
both APS leads
Is there continuity
between the
2 orange
wires
Open circuit on the APS wiring - rectify
Yes
Check the
tubes from venturi
to the APS. Check for
blockages in condensate
system, flue and
heat exch.
APS stuck in Off position
Replace
No
No
flashing
offoff
Yes
Is
there 230 V at the fan ?
Open circuit on
the wiring. Rectify
No
© Baxi Heating UK Ltd 2009
41
Thermistor Fault - Flow and Casting
Fig. 49
Refer to the boiler wiring diagram
There are two types of fault which can occur:
1) The thermistors are reading outside of limits (this is checked before the PUMP is switched on and during Burner on).
2) The difference between the thermistor readings are outside of limits (this is checked during PUMP on stage).
Check that the Pump is running and there is
adequate circulation of water.
Unplug the 12 way
connector to the PCB
Measure resistance
between the 2 blue
wires (casting thermister)
and the 2 yellow wires
(flow thermister)
Are the
resistances
between
0.5kΩ - 20kΩ and within
25% of
each other
Yes
Replace PCB
Lockout Burner Mains
on
Flow thermistor fault
Lockout Burner Mains
flashing
Casting thermistor fault
onflashing
offflashing
No
Remove connectors from the thermistors
Measure resistance
of thermistors
Do
resistances
vary from ones
previously measured
No
Replace Faulty Thermistor
---------------------
This can be identified by
removing both thermistors
and holding the brass
probe between your fingers
The resistance should be
approximately 8kΩ
Yes
Wiring from PCB
to thermistor faulty
© Baxi Heating UK Ltd 2009
42
9. Servicing
For reasons of safety and economy the boiler should be serviced annually by a competent person.
Any 'O' rings, seals or gaskets disturbed during
servicing or replacement of parts must be visually inspected and replaced if worn or damaged.
Important: Always test for gas soundness after servicing or replacement of gas carrying components and carry out functional checks of controls.
Ensure you are using the correct Main approved
spare part when replacing any items as incorrect or
sub standard parts could affect the operation of the boiler.
Some seals on this boiler are special ‘wet’ type designed for use with condensing boilers.
9.1 Servicing Procedure
1. With the outer case correctly fitted, fire the boiler and check that the flames visible through the sight glass are blue and stable. Yellow flame and excessive lifting indicate poor combustion.
2. Turn the temperature control knob to ( ) position and check that the burner shuts off. Allow the boiler to cool and isolate the gas and electricity supplies.
The boiler cannot be isolated at the user interface. Isolate the electricity supply at the mains supply point.
Warning: The 24 model is fitted with a
325Vdc fan. Ensure the mains supply is isolated.
3. Pull the door panel down and remove the two screws. Carefully slide the bottom cover out and away from the boiler.
4. Remove the three screws and carefully lift the outer case away from the boiler.
5. Remove the combustion chamber cover - See 9.9.
6. Visually check for debris/damage and clean or replace if necessary the following.
a. Combustion Chamber Insulation - replace if
required, see 9.12.
b. Fan - remove as shown in 9.9.
Examine the fan impeller and carefully clean if necessary. Check the condition of the sensing tubes at the Fan and Air Pressure Switch.
c. Burner - remove if required, see 9.10.
Brush the burner top and check that the flame ports are clear. Any blockage may be removed with a fine wire brush. Turn the burner upside down and tap gently to remove any debris (Protect the electrodes).
d. Electrodes - remove if required, see 9.10.
If the electrodes require cleaning wipe the surface using a solvent.
e. Injector - remove if required, see 9.11.
Omit this operation if the gas rate is correct, otherwise clean by blowing through. Do NOT clear the injector with a pin or wire.
f. Condensate trap - remove if required, see 9.13.
Place a vessel underneath to catch the condensate then remove the trap drain plug. Take care as the condensate could be hot. Clear out any debris then re-prime the trap, see 4.6.
g. Primary heat exchanger - remove flue hood,
see 9.9. Place a sheet of paper under the heat exchanger then using a flat blade tool (Part No. 907736), scrape the flueway fin surfaces in a downward movement. This will ensure that most of the deposits will be collected on the paper.
h. Secondary heat exchanger - remove the hood
and sump as shown in 9.15 and clean as required.
j. Check the condition of all electrical cables and
connectors.
k. On re-assembly ensure that the outer white case
is correctly fitted and that the sealing strip fitted to the door is forming a tight seal with the boiler casing.
7. Inspect the flue terminal for blockage and integrity, rectify if necessary.
8. Inspect the condensate disposal system for damage, rectify if necessary.
9. Carry out a functional test of the controls and check the gas rate.
10.Check the dilution of the system inhibitor and top up as required. Failure to check and correct inhibitor concentration may damage the heat exchanger.
11. Complete the relevant Service Interval Record section of the ‘Benchmark’ Commissioning Checklist at the rear of this publication.
© Baxi Heating UK Ltd 2009
43
Flow Connection
Fig. 50
Flow Sensor
Overheat Sensor
Return Connection
Flue Sample Point
Casting Sensor
Fan and Flue Hood
Primary Heat Exchanger
Burner & Electrodes
Data Label
Wiring Centre
PCB Enclosure
Air Pressure Switch
'O' Ring and Clip Joints
Secondary Heat Exchanger
Condensate Trap
Gas Connection
Spark Igniter
Gas Valve
Condensate Connection
© Baxi Heating UK Ltd 2009
44
9.2 General Access
1. Isolate the supplies as detailed in 9.1.2.
2. Pull the door panel down and remove the two screws. Carefully slide the bottom cover out and away from the boiler.
3. Remove the three screws and carefully lift the outer case away from the boiler.
9.3 PCB Enclosure
1. Perform General Access - See 9.2. Removal of the outer case is not necessary.
2. Disconnect all electrical plugs and slide the enclosure out of its frame.
3. On re-assembly refer to the wiring diagram when re-connecting electrical plugs.
9.4 Gas Valve
1. Perform General Access - See 9.2. Removal of the outer case is not necessary.
2. Note how it fits then disconnect the electrical plug from the gas valve.
3. Remove the gas cock by unscrewing the four long hexagonal head screws from the side of the valve.
Note: Loosen the condensate trap securing screws to improve access to the gas valve.
4. Using the service spanner supplied with the new valve, remove the front screw and loosen the two rear screws securing the gas valve to the manifold.
5. Slide the valve backwards and carefully remove from the boiler.
6. Re-assemble in reverse order using a new ‘O’ ring. Remember to re-tighten the condensate trap and ensure the electrical plug to the gas valve is in the correct orientation.
7. Check the burner pressure (see data label
for pressures). If adjustment is required, turn pressure adjusting screw anti-clockwise to increase pressure or clockwise to decrease.
Disconnect electrical plugs
Remove four screws
gas cock
Disconnect electrical plug
Loosen rear screws
Remove front screw
Burner pressure adjustment
Fig. 52
Fig. 51
Fig. 53
9.3
9.4
9.4
9. Parts Replacement
Burner pressure test point
Inlet pressure test point
© Baxi Heating UK Ltd 2009
45
9.5 Air Pressure Switch
1. Perform General Access - See 9.2.
2. Disconnect the wires at the switch.
3. Note how they are fitted then disconnect the sensing tubes at the switch.
4. Ease the front of the bracket forwards and carefully prise the switch out of the bracket. If the bracket is removed for any reason, note that the hole in the side face locates around
a rivet head.
5. Re-assemble in reverse order, polarity is not important when connecting the wires.
The coloured sensing tube fits to the outer of the two connections.
9.6 Spark Igniter
1. Perform General Access - See 9.2.
2. Disconnect ignition lead at the ignition electrode.
3. Loosen securing screws, slide unit back to clear screws and lift away from the boiler.
4. Disconnect the electrical plug. Disconnect ignition lead if required.
4. Re-assemble in reverse order.
9.7 Flow & Casting Sensors
1. Perform General Access - See 9.2.
2. Disconnect the electrical plug from the sensor and unscrew the sensor from the pocket.
3. Re-assemble in reverse order. Use a heat sink compound on the sensor shaft, insert and tighten to finger tight and a quarter turn.
9.8 Overheat Sensor
1. Perform General Access - See 9.2.
2. Disconnect the spade connectors from the sensor and unscrew the sensor from the pipe.
3. Re-assemble in reverse order, polarity is not important when connecting the wires. Insert and tighten to finger tight and a quarter turn.
Disconnect wires
Disconnect tubes
Ease bracket open
Loosen screws
Electrical plug
Ignition lead
Overheat sensor
Flow sensor
Casting sensor
Fig. 54
Fig. 55
Fig. 56
9.5
9.6
9.7
9.8
© Baxi Heating UK Ltd 2009
46
9.9 Fan and Flue Hood
a.c fan - 9 to 18 models d.c. fan - 24 model
1. Perform General Access - See 9.2.
2. Remove the screw securing the front combustion chamber cover. Pull the cover out slightly then down to unhook and lift away from the boiler.
3. Note how they are fitted then disconnect the sensing tubes from the venturi.
4. Disconnect the electrical spade connectors from the fan motor (9 to 18) or electrical plugs (24).
5. Roll the gaitor away from the venturi towards the secondary heat exchanger.
6. Slide the fan and flue hood forwards and away from the boiler.
7. Remove the four screws securing the fan to the flue hood and the screw securing the venturi to the fan.
8. On re-assembly:-
Remove all traces of gasket from the flue hood then attach new gasket. Fit the fan to the flue hood and secure using four screws previously removed. Fit the venturi assembly to the replacement fan.
Ensure that the flue hood locates under the clips at the rear of the chassis. The front of the flue hood will rise slightly under the pressure of the clips.
Re-assemble all remaining parts in reverse order. Polarity is not important when re­connecting a.c. fan wires.
Ensure the sensing tubes are fitted correctly,
the coloured tube will be nearest to the fan.
Warning
Combustion chamber cover screw
Sensing tubes
Gaiter
Venturi
Fan motor 9 - 18 shown
Combustion chamber cover locating lip
Fig. 57
9.9
9.9
Flue hood
Gasket
325V d.c
Isolate the
mains supply.
© Baxi Heating UK Ltd 2009
47
9.10 Electrodes/Burner
1. Perform General Access - See 9.2.
2. Remove the combustion chamber cover ­See 9.9.
3. Disconnect the ignition lead from the ignition electrode and the sensing lead and earth lead from the sensing electrode.
If replacing electrode(s), remove securing screw(s) as appropriate.
4. Remove the securing screw at the right hand side, hold the burner , apply greater pressure at the right hand side and pull to disconnect from the spring clips on the support bracket.
5. Transfer electrodes onto replacement burner before re-fitting.
6. Re-assemble in reverse order.
Check that the gap between the electrode tip and the burner face is 3 - 4 mm, adjustment can be made by careful use of pliers.
9.11 Injector
1. Remove the Burner - See 9.10
Use a 13 mm (A/F) or 1/2” (A/F) socket spanner to remove the injector.
2. Unscrew the injector.
3. Re-assemble in reverse order. Use a new sealing washer on the injector and test for gas soundness.
Remove screw
Ignition electrode
Sensing electrode
Fig. 58
Fig. 59
9.11
9.10
Ignition lead
9.10
Ensure electrodes are sat over flame ports as shown and have 3 - 4 mm gaps between tip and burner face.
1
2
Rear
Front
Remove injector
Remove screw
Pull forward to disconnect from support bracket
Burner support bracket
© Baxi Heating UK Ltd 2009
48
9.12 Combustion Chamber Insulation
Important: See Section 3.1, Health and Safety information before handling insulation.
1. Perform General Access - See 9.2.
2. Remove the screw securing the front combustion chamber cover. Pull the cover out slightly then down to unhook and lift away from the boiler.
3. Remove the Burner - See 9.10.
4. Remove the two screws securing the side and rear insulation assembly to the front of the chassis.
5. Pull the assembly forwards and away from the boiler. Replace insulation pieces as required, replace any securing clip if damaged.
6. Re-assemble in reverse order, ensure the insulation assembly has located correctly over the tabs at the rear of the casing below the casting and is NOT hanging down.
Insulation assembly correctly fitted and held in location tabs
Insulation assembly incorrectly fitted
Fig. 60
Location lip
9.12
9.12
9.12
© Baxi Heating UK Ltd 2009
49
9.13 Condensate Trap
1. Perform General Access - See 9.2.
Place a vessel underneath to catch the condensate then remove the drain plug. Take care as the condensate could be hot.
2. Disconnect condensate disposal pipework from the flat faced union on the trap and swing pipework away from boiler.
3. Release the spring clip securing the rubber tube to the base of the sump.
4. Loosen the left hand and remove the right hand screw securing the trap to the boiler.
5. Slide the trap to the right to release from the left hand screw then pull the unit (complete with tube) down and away from the boiler.
6. Re-assemble in reverse order using a new case seal.
Pour half a litre of water into the trap to prime it before re-fitting.
Ensure the tube and spring clip locate correctly onto the sump.
7. Re-connect condensate disposal pipework.
Disconnect condensate pipework
Spring clip
Right hand screw
Fig. 61
9.13
© Baxi Heating UK Ltd 2009
50
9.14 Primary Heat Exchanger
1. Perform General Access - See 9.2.
2. Drain the system as necessary.
3. Remove the combustion chamber cover ­See 9.9.
4. Drain the heat exchanger, a drain point is located on the left hand side bottom of the heat exchanger. Attach a tube to the drain point, turn anti-clockwise to open and drain water away from the electronics.
5. Remove the Casting Sensor - See 9.7.
6. Remove the Fan and Flue Hood - See 9.9.
7. Remove the Burner - See 9.10.
8. Remove the Combustion Chamber Insulation
- See 9.12.
To ease the removal of the primary heat exchanger it may be necessary to:-
- Release the flow pipe compression fitting
above the boiler.
- Remove the clip securing the return pipe
from the secondary to the primary heat exchanger.
9. Release the flow and return unions at the heat exchanger and lift the pipes clear.
10.Remove the screw from the top right hand side and bolt and nut from the left hand side mounting brackets.
11. Support the heat exchanger, spring out the left hand mounting bracket to clear the stud and withdraw the heat exchanger.
12.Re-assemble in reverse order. Ensure all seals are replaced as necessary.
- Ensure the return pipe is fully engaged
and re-insert the pipe clip to lock it in position. Check the joint will not pull apart.
13.Check the inhibitor concentration when re­commissioning the system.
14.Vent all air from boiler and system before firing boiler.
Drain point
Screw
Bolt
Nut
Flue duct securing bracket
Fig. 62
Screw
9.14
3 way casting shown
© Baxi Heating UK Ltd 2009
51
9.15 Secondary Heat Exchanger
1. Perform General Access - See 9.2.
2. Drain the system as necessary.
3. Drain the Heat Exchanger - See 9.14, 4.
4. Remove the Spark Igniter - See 9.6.
To ease removal of the secondary heat exchanger it may be necessary to:-
- Remove the Air Pressure Switch - See 9.5.
- Remove the air pressure switch mounting bracket.
- Remove the Fan and Flue Hood - See 9.9.
- Disconnect secondary to primary heat exchanger return pipe.
5. Remove the screw securing the flue duct mounting bracket to the inner case and remove the bracket - See Fig. 42.
6. Remove the two pipe clips securing the flow and return pipes to the secondary heat exchanger.
7. Remove the Condensate Trap - See 9.13. This will allow access through the hole in the case to the rear sump screw.
8. Loosen the rear and remove the front sump screws. Carefully slide the sump forwards to remove from boiler.
9. Support the heat exchanger then remove the screw and front supporting bracket.
10.Manoeuvre the heat exchanger out to disconnect the gaitor and flue duct from the hood, pull down to release the pipe ‘O’ ring connections and lift away from the boiler.
11. Check and replace seals, washers, ‘O’ rings etc as necessary. Lubricate ‘O’ rings prior to fitting.
12. Re-assemble as follows:-
- Align the flow and return pipes, lift the heat
exchanger slightly to engage the ‘O’ ring joints and locate onto the rear case mounting bracket.
- Re-fit the front mounting bracket and screw.
- Ensure the flow and return pipes are fully
engaged and re-insert the pipe clips to lock them in position. Check the joints will not pull apart.
- Re-connect the secondary to primary heat
exchanger return pipe.
Pipe clips
Sump
Fig. 63
- Re-fit the sump.
- Re-fit the flue duct mounting bracket and screw.
- Re-assemble all remaining parts in reverse order.
13.Check the inhibitor concentration when re- commissioning the system.
14.Vent all air from boiler and system before firing boiler.
Spark igniter
9.15
9.15
© Baxi Heating UK Ltd 2009
52
10. Short Spares
Fig. 64
216 [18,24HE]
308
216 [9,12,15HE]
217
329
330
306
332
207 331
322
206 [9,12,15HE]
305
206 [18,24HE]
200 [24HE]
200 [9,12,15,24HE]
318
121
120 209
219
313
202
© Baxi Heating UK Ltd 2009
53
Drg. Ref. G.C. No. Description Qty Part No.
120 114-852 Sight glass mica 1 238162 121 114-872 Mica retainer outer 1 238106 200 Fan and gasket kit 9 HE 1 5112318
Fan and gasket kit 12 HE 1 5112319 Fan and gasket kit 15 & 18 HE 1 5112320 Fan and gasket kit 24 HE 1 5112321
202 Venturi assembly 9 & 12 HE 1 5112322
Venturi assembly 15 HE 1 5112323 Venturi assembly 18 HE 1 5112324 Venturi assembly 24 HE 1 5112326
206 Heat exchanger - 3 way - primary 1 5113375
Heat exchanger - 4 way - primary 1 5113376 207 Temperature sensor 1 5113044 209 114-852 Sight glass mica 1 238162 216 114-854 Burner sub-assembly 9,12,15 HE 1 238244
114-856 Burner sub-assembly 18,24 HE 1 238246 217 E78-614 Electrode 2 407776 219 Condensate trap assembly 1 5111451 305 PCB assembly 1 5110550 306 364-866 Temperature control knob 1 230981 308 Igniter assembly 1 5111922 313 Air pressure switch 9 HE 1 5112195
Air pressure switch 12 HE 1 5112196 Air pressure switch 15 HE 1 5110350 Air pressure switch 18 HE 1 5112197
Air pressure switch 24 HE 1 5110393 318 Heat exchanger - secondary 1 5113517 322 Gas valve kit 1 5112334 329 173-133 Burner injector 9 HE 2.8 mm dia 1 411021
173-134 Burner injector 12 HE 3.1 mm dia 1 411022 173-135 Burner injector 15 HE 3.5 mm dia 1 411023 173-137 Burner injector 18 HE 3.9 mm dia 1 411025
173-138 Burner injector 24 HE 4.1 mm dia 1 411026 330 Washer - Injector 1 5112209 331 Temperature sensor 1 5113044 332 173-130 Overheat thermostat 1 404517
GAS BOILER SYSTEM COMMISSIONING CHECKLIST
CONTROLS Tick the appropriate boxes
Time and Temperature Control to Heating Room Thermostat and Programmable Load/Weather Optimum Start
remiT/remmargorP
Room Thermostat Compensation Control
remiT/remmargorP dna tatsomrehT rednilyC retaW toH ot lortnoC erutarepmeT dna
emiT Combination Boiler
dettiF sevlaV enoZ gnitaeH Not Required
dettiF sevlaV enoZ retaW toH Not Required
dettiF sevlaV rotaida
R citatsomrehT Not Required
dettiF metsyS ot ssapyB citamotuA Not Required
dedivorP kcolretnI relioB
ALL SYSTEMS
The system has been fl seY snoitcurtsni s’rerutcafunam reliob dna 3957SB htiw ecnadrocca ni denaelc dna dehsu
What system cleaner was used?
What inhibitor was used? Quantity litres
CENTRAL HEATING MODE Measure and Record:
Gas Rate
m3/hr OR
ft
3
/hr
)elbacilppa fi( erusserP gnitarepO renruB
mbar OR Gas Inlet Pressure mbar
Central Heating Flow Temperature °C
Central Heating Return Temperature °C
COMBINATION BOILERS ONLY
Is the installation in a hard water area (above 200ppm)? Yes No
If yes, has a water scale reducer been fi tted? Yes No
What type of scale reducer has been fi tted?
DOMESTIC HOT WATER MODE Measure and Record:
etaR saG
m
3
RO rh/
ft
3
/hr
)etar mumixam ta( erusserP telnI saG RO rabm )etar mumixam ta( erusserP gnitarepO renruB mbar
erutarepmeT telnI retaW dloC °C
Hot water has been checked at all outlets Yes Temperature °C
etaR wolF retaW l/min
CONDENSING BOILERS ONLY
seY 8976SB/6455SB ro/dna snoitcurtsni s’rerutcafunam eht htiw ecnadrocca ni dellatsni neeb sah niard etasnednoc ehT
ALL INSTALLATIONS
OC gniwollof eht drocer ,rerutcafunam eht yb deriuqer fI
2
% OR CO ppm OR CO/CO2Ratio
seY snoitalugeR gnidliuB etairporppa eht htiw seilpmoc metsys retaw toh dna gnitaeh ehT
seY snoit
curtsni s’rerutcafunam eht htiw ecnadrocca ni denoissimmoc dna dellatsni neeb evah stcudorp detaicossa dna reliob ehT
seY remotsuc eht yb dootsrednu dna ot detartsnomed neeb evah slortnoc metsys dna rel
iob eht fo noitarepo ehT
The manufacturer’s literature, including Benchmark Checklist and Service Record, has been explained and left with the customer Yes
*
All installations in England and Wales must be notifi ed to Local Authority Building Control (LABC) either directly or through a Competent Persons Scheme. A Building Regulations Compliance Certifi cate will then be issued to the customer.
©Heating and Hotwater Industry Council (HHIC) www.centralheating.co.uk
Commissioning Engineer’s Signature
Customer’s Signature
(To confi rm satisfactory demonstration and receipt of manufacturer’s literature)
This Commissioning Checklist is to be completed in full by the competent person who commissioned the boiler as a means of demonstrating compliance with the appropriate Building Regulations and then handed to the customer to keep for future reference.
Failure to install and commission this equipment to the manufacturer’s instructions may invalidate the warranty but does not affect statutory rights.
Customer Name Telephone Number
Address
Boiler Make and Model
Boiler Serial Number
Commissioned by (print name)
Company Name Telephone Number
Gas Safe Register licence No.
Company Address
Commissioning Date
To be completed by the customer on receipt of a Building Regulations Compliance Certifi cate
*
:
Building Regulations Notifi cation Number (if applicable)
54
SERVICE RECORD
It is recommended that your heating system is serviced regularly and that the appropriate Service Record is completed.
Service Provider
Before completing the appropriate Service Record below, please ensure you have carried out the service as described in the manufacturer’s instructions.
Always use the manufacturer’s specifi ed spare part when replacing controls.
SERVICE 1 Date
Energy Effi ciency Checklist completed? Yes No
Engineer Name
Company Name
Telephone Number
Comments
Signature
SERVICE 3 Date
Energy Effi ciency Checklist completed? Yes No
Engineer Name
Company Name
Telephone Number
Comments
Signature
SERVICE 5 Date
Energy Effi ciency Checklist completed? Yes No
Engineer Name
Company Name
Telephone Number
Comments
Signature
SERVICE 7 Date
Energy Effi ciency Checklist completed? Yes No
Engineer Name
Company Name
Telephone Number
Comments
Signature
SERVICE 9 Date
Energy Effi ciency Checklist completed? Yes No
Engineer Name
Company Name
Telephone Number
Comments
Signature
SERVICE 2 Date
Energy Effi ciency Checklist completed? Yes No
Engineer Name
Company Name
Telephone Number
Comments
Signature
SERVICE 4 Date
Energy Effi ciency Checklist completed? Yes No
Engineer Name
Company Name
Telephone Number
Comments
Signature
SERVICE 6 Date
Energy Effi ciency Checklist completed? Yes No
Engineer Name
Company Name
Telephone Number
Comments
Signature
SERVICE 8 Date
Energy Effi ciency Checklist completed? Yes No
Engineer Name
Company Name
Telephone Number
Comments
Signature
SERVICE 10 Date
Energy Effi ciency Checklist completed? Yes No
Engineer Name
Company Name
Telephone Number
Comments
Signature
Gas Safe Register licence No. Gas Safe Register licence No.
Gas Safe Register licence No. Gas Safe Register licence No.
Gas Safe Register licence No. Gas Safe Register licence No.
Gas Safe Register licence No. Gas Safe Register licence No.
Gas Safe Register licence No. Gas Safe Register licence No.
55
Publication No. 5116960 - Iss 4 (5/09)
© Baxi Heating UK Ltd 2009
MAIN
A Trading Division of Baxi Heating UK Ltd (3879156) A Division of Baxi Group
Brooks House, Coventry Road, Warwick. CV34 4LL After Sales Service 08701 655 644 Technical Enquiries 08706 049 049 Website www.mainheating.co.uk e&oe
All descriptions and illustrations provided in this leaflet have been
carefully prepared but we reserve the right to make changes and
improvements in our products which may affect the accuracy of the
information contained in this leaflet. All goods are sold subject to our
standard Conditions of Sale which are available on request.
Loading...