Lincoln Electric FCAW-G User Manual

SUCCESS
WELDING CONSUMABLES
Flux-Cored (FCAW-G) Welding
Welding on Pipe
Contractor U.S. Pipeline turned to new Lincoln Electric Pipeliner®G80M gas-shielded flux-cored wire to weld the pipe tie-ins for the 380-mile Cheyenne Plains Gas Pipeline project, which used X-80 grade pipe.
-CHALLENGE-
The Cheyenne Plains Gas Pipeline project was the first major pipeline in the U.S. to use high strength X-80 grade pipe. The contractor, U.S. Pipeline, was looking for ways to increase productivity while still creating high quality welds that could pass radiographic inspection.
-SOLUTION-
Lincoln Electric Pipeliner gas-shielded flux-cored wire for use on the pipe tie-ins at connection points and railroad crossings near populated areas.
®
G80M
Cheyenne Plains Pipeline
uring the summer and fall of 2004, the plains of the west
D
bustle of cranes, trucks, heavy equip­ment and supplies to lay pipe for the Cheyenne Plains Gas Pipeline Project. The 380-mile, 36-inch natural gas pipeline runs from the Cheyenne hub in Colorado to existing pipelines near Greensburg, Kan. Once operational in early 2005, the pipeline will export 560 million cubic feet of natural gas per day from Wyoming to growing markets in the mid-continental U.S. and further east.
The $425 million pipeline, owned by El Paso Corporation, was being con­structed in three spreads which were connected in the final phase of the project. Spread one was contracted to Associated Pipelines while spreads two and three were handled by U.S. Pipeline, Inc.
The Cheyenne Plains Gas Pipeline Project was the first major pipeline in the U.S.
were busy with the hustle and
to use X-80 grade pipe. Already a standard in other parts of the world, the X-80 pipe provides higher strength with a thinner wall.
As on any pipeline project, welding plays a critical role in the construction process. But what made this project unique was the extensive use of wire welding to provide high productivity. A new consumable from the Lincoln Electric Company, the Pipeliner gas-shielded flux-cored wire, was selected by the evaluation team at U.S. Pipeline, Inc. for use on the pipe tie-ins at connection points and road crossings near populated areas. These welds, completed manually by inde­pendent pipeline contractors, connect the mainline pipe to the thicker walled pipe of the tie-ins.
For the mainline pipe, a CRC-Evans automated welding system was used in combination with Lincoln’s premium SuperArc metal arc wire.
®
L-56 copper coated gas
®
G80M
®
-RESULTS-
Using a wire process yielded results that were three to five times faster than the stick welding typically used for pipeline welding. The Pipeliner G80M provided high quality and flawless operation with its smooth arc and low spatter levels.
www.lincolnelectric.com
MC05-114 7/05
WELDING CONSUMABLES
SUCCESS
Flux-Cored (FCAW-G) Welding
Welding on Pipe
“We chose the Lincoln Pipeliner G80M wire for this project for a number of reasons. First, it met the mechanical requirements of
the job and also offered a
crisper arc,” said Bratcher.
“In addition, we felt that the
Lincoln product flowed better
and was more suitable for
outdoor use.”
An Overview of the Pipe Installation Process
More than 140,000 tons of pipe and 25,000 individual sections were used to complete this project. Each section of pipe is 78-feet long and per industry standards, was buried at least 30 inches below the ground through a trenching process.
Cheyenne Plains Pipeline
and then lowered it into the trench. Finally, the construction crews at the rear were responsible for conducting hydrostatic pressure testing, backfilling the trench and restoring the land as close as possible to its original condi­tion.
Welding Connection Points and Road Crossings
After a lengthy process of evaluating solid and flux-cored electrodes for the job, U.S. Pipeline, Inc. selected a .045­inch diameter Pipeliner G80M wire as the consumable of choice for the vertical up welding of the pipe tie-in fill and cap passes. The Cheyenne Plains Pipeline Project marked the first time this new consumable was used in the field and for many of the pipeline con-
tractors, it was also the first time they had made the switch from a traditional Stick process to complete the tie-ins for the job.
“We chose the Lincoln Pipeliner G80M wire for this project for a number of reasons. First, it met the mechanical requirements of the job and also offered a crisper arc,” said Dana Bratcher, Welding Foreman, U.S. Pipeline, Inc. “In addition, we felt that the Lincoln product flowed better and was more durable for outdoor use. We also were attracted to the fact that the pipe supplied from the manufacturer was welded using a Lincoln consumable.”
This electrode, specifically designed for pipeline welding, is easier for the operator to use and provides a smooth arc, lower spatter levels and less frequent clogging of gun nozzles when compared to other flux-cored wire electrodes.
2/4
and cap. Each welder also had an assistant who performed tasks such as preheating the joints, setting the clamp to align the two lengths of pipe, setting up the welding equipment and complet­ing the finish wire brushing on the joint.
Every tie-in weld was inspected with a radiographic process and throughout the job the weld quality had been excel­lent. “We had a low repair rate with the Lincoln wire. It was consistent and worked wonderfully,” noted Bratcher. “Our welding operators liked the fact that they were able to see how the puddle flowed.”
The use of Pipeliner G80M wire to weld the spiral seam pipe’s fill and cap pass­es provided significantly increased productivity and high quality welds. “The wire is about three to five times faster than stick welding,” said Ray Edwards, an independent pipeline welder from the Pipeliners Union 798 and one of the welders on Spread Two of the project. “The same length of weld bead that would take up to five minutes with stick welding is now taking me about one minute.”
In addition, Lincoln’s Shield-Arc 70+ stick electrode was used to complete the tack welds and vertical down root pass on these tie-ins. This rod was cho­sen for its ability to accomplish the out­of-position welding required for this job.
Much like an assembly line where each worker is responsible for a certain por­tion of the job, construction crews in each spread followed after each other along the length of the pipe to complete specialized tasks. Crews at the front staked the area and prepared the right­of-way. Those following behind aligned the pipe, welded and inspected the pipe
www.lincolnelectric.com
All tie-in welds were performed manually because of the special­ized skills needed to handle fit-up issues between the thinner main­line pipe and thicker tie-ins. Each manual welding team consists of two welders, one on each side of the pipe performing one-half of the welding pass – root, hot, fill
Loading...
+ 2 hidden pages