Lattner Boiler Company SPACE SAVER Operating Instructions Manual

INSTALLATION,
MAINTENANCE, AND
SERVICE INSTRUCTION
MANUAL
INDEX
SPACE SAVER
General Information …………………………….Page 1 Installation ………………………...……………..Page 2 Start Up …………………………………………..Page 3 Maintenance ……………………….……………..Page 3 Control ……………………………………………..Page 4 Service Instructions …………………………….Page 5 Limited Warranty ………………………………Page 6
BOILERS
GENERAL INFORMATION
Application
UL Listed under File No. E30432 to 600 volts and 120 KW as primary heat source, secondary heat source, or as standby heat source for solar, hydronic, and water source heat pump systems.
Vessel
ASME Code, Section IV “H” stamped, National Board registered, rated to 160 psig and 250 degrees Fahrenheit.
Insulation
4” fiberglass blanket on vessel.
Elements
Incoloy sheathed, 75 watts per inch, mounted in 150 pound ASA steel flange, individually removable.
Enclosure
Ventilated integral control panel constructed of heavy gauge steel contains line terminals, fuses, contactor(s), temperature controller, and safety high limit devices. All surfaces are phosphatized and protected against corrosion with factory applied finish.
1
INSTALLATION
1. Install drain valve furnished with boiler.
2. Set boiler in position to conform to local codes. Minimum clearances: Front – 6 inches to door or 3 feet to wall; back – 1 inch; left side – 1 inch; right side – 10 inches. A minimum distance of 34 inches must be maintained above the boiler for element removal.
3. Suitable for closet installation. Subject to minimum spacing requirements shown below. Closet door must be vented at the top and bottom of the door with 24 by 12 inch openings.
4. Be certain unit is installed on a level, non­combustible surface.
5. Connect the supply and return piping according to applicable codes. Pipe relief valve discharge to nearest floor drain or downward, away from any potential hazard to other equipment or personnel.
6. Boiler feed connection may be tee’d into return connection.
7. Electrical knockouts are provided for wiring access. All wiring must conform to applicable codes and conductors cannot be smaller than sixes listed on wiring diagrams located inside the control panel door.
8. Provide expansion tank and circulating pump for boiler piping system; install to conform to applicable codes. Installation of flow switch is recommended. Connect vent tube to (top of vessel) to expansion tank.
2
START UP
1. Place disconnect switch and control circuit switch in the OFF position. Fill system with water to pre-determined cold fill pressure (one pound of pressure is required for every 2.31 feet of piping system height above the pressure gauge).
2. Purge all air at the highest point in the system and vent all points where air is likely to be trapped.
3. Energize circulator pump and verify direction of rotation on three phase units. DO NOT
MAINTENANCE
A periodic check of all control components will ensure proper operation.
1. Check wiring and terminations for tightness.
2. Check all controls and safety devises for proper operation.
3. Check pressure relief valve to ensure that it is not leaking and that no corrosion exists.
4. Check circulator pump and lubricate according to manufacturer’s instructions.
At least once a year, boiler elements should be checked.
1. Disconnect all power to boiler.
2. If a faulty open element is indicated, the element may be replaced in the following manner:
a. Isolate boiler from system by closing hand
valves in supply and return piping. b. Drain boiler completely of water. c. Remove ALL wiring from the elements,
tagging both the wires and element
terminals.
energize the boiler unless circulator pump is operating.
4. Close boiler control panel door and energize the main disconnect switch.
5. Check all piping connections and valves for leaks.
6. Turn boiler control circuit switch to the ON position. If contactor(s) do not close, see service section (page 4).
d. Mark element flange position with respect
to the vessel flange for proper alignment upon reinstallation; remove flange bolts.
e. Remove the element flange from the
vessel.
f. Remove element retaining nut using a
11/16 socket wrench.
g. Remove ferrules (2 compressed rings)
from the element ends and remove element from back side of flange.
h. Insert new element and ferrules and
tighten element retaining nuts into flange.
i. Replace flange in boiler vessel using new
gasket. Align previously made marks on flanges and install flange bolts, torqueing each bolt to 70 foot pounds (minimum).
j. Reconnect electrical wiring, making sure
all wiring is connected to the proper element termination.
k. Refill boiler following procedure listed in
INSTALLATION section. l. Check elements and flanges for leaks. m. Replace vessel enclosure cover. n. Turn disconnect on.
3
Loading...
+ 4 hidden pages