KSB WK, WK 40, WK 100, WK 50, WK 65 Series Manual

...
Page 1
Contents
WK
Point Description Page No. No.
0 Introduction 1
1 Pump construction 1
1.1 Casing 1
1.2 Rotor 1
1.3 Bearing arrangement 2
1.4 Lubrication 3
1.4.2 Grease lubrication 4
1.5 Shaft seal 4
1.5.1 Stuffing boxes 4
1.5.1.1 Cooling liquid for stuffing boxes 5
1.5.1.2 Packing the stuffing boxes 5
1.5.1.3 Packing material 7
1.5.2 Mechanical seals 7
1.6 Coupling 7
2 Mode of operation of pump 7
3 Drive 8
4 Transport 8
5 Painting 8
6 Condition of equipment as supplied 8
7 Accessories 9
8 Installing the pumping set 9
8.1 Description of site prior to commencement of erection 9
8.2 Installation and preliminary levelling up 9
8.4 Grouting in the baseplate 10
8.5 Final alignment 10
9 Piping 11
9.1 Suction lift line and positive Suction head line 11
9.1.1 Strainers in suction head line/suction lift line 11
9.2 Isolating valves 12
9.3 Non-return valves 12
9.3.1 Automatic recirculation valve 12
9.4 Final coupling check 13
9.5 Measuring instruments 13
10 Commissioning 13
10.1 Preliminary remarks regarding commissioning 13
10.2 Start-up 13
10.3 Operation and supervision of pump 14
Point Description Page No. No.
10.4 Shutting the pump down 14
10.5 Preserving the pump 15
10.6 Sending the pump back to our Works 15
11 Dismantling the pump 15
11.1 Preparations prior to dismantling 15
11.2 Dismantling the bearing 15
11.2.1 Dismantling the drive end bearing 15
11.2.2 Dismantling the end side bearing 16
11.2.2.1 Standard bearing construction 16
11.2.2.2 Heavy duty bearing construction 17
11.3 Removing the shaft seal 17
11.3.1 Soft-packed stuffing box construction 17
11.4 Dismantling the pump body 17
11.5 Inspection of individual pump components 19
11.6 Dynamic balancing of pump rotor 20
12 Assembly of pump 20
12.1 Preparations prior reassembly 20
12.2 Assembling the pump body 20
12.3 Assembly of shaft seal 22
12.3.1 Pump construction with soft-packed stuffing box 22
12.4 Assembly of bearings 23
12.4.1 Assembly of end side bearing 23
12.4.2 Assembly of drive end bearing 23
13 Operating troubles, causes and remedies 25
13.1 Operating troubles 25
13.2 Causes for damage 25
13.3 Suggested remedies 26
14 Spare parts 27
15 Check list 28
15.1 Pre-requisites for initial commissioning 28
15.2 Initial start-up with cold water 28
15.3 Priming the boiler 28
15.4 Initial operation with hot fluid 28
15.5 Supervision of operations & maintenance 28
16 Sectional drawings and list of
components 29
Balancing liquid piping 31
Page 2
WK
water compartment, which is sealed off against atmosphere by the stuffing box housing cover (165) with flat gasket (400.3) and O-ring (412.4) (See Fig. 2)
7A/7E
Fig. 1
0. Introduction
WK pumps are High Pressure Horizontal Centrifugal Pumps. In accordance with the latest state of the art of pump design and construction, our pumps combine favourable hydraulic characteristics with a long service life, reliability of operation and simple maintenance and operation.
A pre-requisite for trouble-free operation of the pumps is the careful observance of the recommendations contained in this operating instruction manual. It should therefore, always be at the disposal of the personnel entrusted with the erection, maintenance and operation of the pump.
It goes without saying that the pumps should only be operated under the duty conditions specified (see data sheet). The terms of our Guarantee naturally apply within this range of conditions. Our Guarantee will become invalid if the pumps are dismantled, either completely or partially, without our prior consent. The first assembly and dismantling of the pump should be carried out by skilled fitters and erectors, and this also applies to the initial start-up (commissioning) of the pumping set.
400.3
350
165
452
412.3 412.4 461.1
400.3
451
524.2 (524.1)
Fig. 2 Stuffing box housing with cooling compartment cover
Depending on the number of stages and on the temperature of the product pumped, the pump feet are integrally cast onto the suction and discharge casings (106 and 107) either at the bottom, or at shaft centerline height. The suction nozzle can be arranged to point horizontally to the left or right hand side, or vertically upwards, if the pump feet are arranged at the bottom of the pump; if they are arranged at shaft centerling height, the suction nozzle can only be arranged to point vertically upwards the discharge nozzle points radially upwards on both types of pump feet arrangement.
In order to achieve a favourable NPSH required, the suction nozzles on all sizes of pumps are made one nominal size larger than the discharge nozzles. The flange construction is specified in the data sheet.
1.2 Rotor
All the rotating components assembled on the shaft make up the complete pump rotor (See Fig. 3 and 4)
1. Pump Construction
(For item numbers, see under section 16, Sectional drawings.)
1.1 Casing
WK high pressure centrifugal pumps are single or multistage centrifugal pumps with a radially split casing. This consists of the suction and discharge casing (106 and 107) together with a number of stage casings (108). If the extraction of a given quantity of the liquid pumped at one of more intermediate pressures is required, the corresponding stage casings can be provided with extraction (Bleed off) nozzles. The individual casing components are sealed off against one another by flat gaskets (400.2) or by ‘O’ rings (412) and clamped together by connection rods (905). The diffusers (171.1 and 171.2) are arranged in the stage casings and in the discharge casing respectively (108 and 107 respectively). They are centered in the casings at their outer periphery and secured against twisting.
The stuffing box housings (451) and bearing housing (350) are flanged onto the suction and discharge casing respectively (106 and 107) and attached by studs (902.1). The stuffing box housings (451) are sealed off from the suction and discharge casings respectively (106 and 107) by a flat gasket (400.3). On pumps fitted with special hot water stuffing boxes or with mechanical seals, the shaft seal is surrounded by a cooling
The shaft (210) transmits the torque generated by the drive onto the impellers. The impellers (230) are mounted is sequence on shaft (210), and they all point in the same direction. They are secured against twisting by keys.
The narrow clearance gap between impeller neck and casing wearing ring (502) at the suction and discharge end of each impeller prevents the equalization of presure between one stage and the next.
The shaft (210) is protected inside the pump against attack by the fluid pumped by means of spacer sleeve (525.1/2) and distance bushes stage (521). The distance bushes/stage also serve to locate the impellers axially on the shaft. The shaft (210) is protected by the shaft protection sleeves (524.1/.2) in the region of the shaft seal. These protection sleeves are screwed onto shaft (210) by means of screw threads with opposed hand to the direction of rotation of the shaft.
Fig. 3 Assembled rotor
1
Page 3
WK
5412 and standard bearing bracket (No adaptor sleeve provided on pump size 150).
End side : 1 deep groove ball bearing in accordance with DIN 625 and standard bearing housing (see Figs. 7 and 8).
Heavy Duty Bearing Construction :
Drive end : Same as atandard bearing construction. End side : 2 matched angular contact ball bearings in accordance with DIN 628; X arrangement and heavy duty bearing bracket (see Fig. 9).
Fig. 4 Dismantled rotor
In order to balance the axial thrust, throttling passages are arranged at the impeller necks at the suction and discharge end of each impeller, and additional balancing holes are provided in the impeller necks at the discharge end (See Fig. 5).
A fixed bearing absorbs the residual axial thrust generated and also locates the rotor in the axial position; in the standard bearing construction, this bearing consists of a deep groove ball bearing (321) and in the pump construction with heavy duty bearing bracket, it consists of two angular contact ball bearings (320).
Fig. 5 Rotor
1.3 Bearing Arrangement
WK pumps are fitted with different types of beaings and bearing housing, depending on the differential head (generated pressure) of the pump. In the case of low differential heads, the standard bearing construction is provided. In the case of higher total heads, the heavy duty bearing construction is provided to absorb the increased residual thrust.
The pump manufacturer decides which type of bearing arrangement shall be provided.
361 920.4 321 350 350 731.2 322 400.4 901.2
400.4
903.4 (13B)
507
507 52-1 360 210
Fig. 7 Bearing construction, size 40 to 125
400.4 920.4 350 525.4
903.12
361 543 321 932 507 932 322 543
507 525.4 350 360
Fig. 8 Bearing construction, size 150
Drive end
Fig. 6 Individual bearing components (drive end)
Part 1 = Outer race with cage and rollers Part 2 = Adaptor Sleeve Part 3 = Inner bearing race Part 4 = Locking Washer Part 5 = Withdrawal Nut
Standard Bearing Construction :
Drive end : 1 Cylindrical roller bearing in accordance with DIN 5412 (see Fig. 6) with adaptor sleeve in accordance with DIN
901.3 361 913 350.2 412.7 507
903.5 (
)
13B
412.7 644 644 360.2
543400.5
525.8160
901.4
720.3 (8B)
210
932508320320923
525.5
902.3
Fig. 9 Bearing construction with heavy duty bearing bracket size 150.
2
Page 4
WK
Standard Construction
Pump size 40 50 65 80 100 125 150
Drive end :
cylindrical roller bearing NU 206 K NU 207 K NU 207 K NU 208 K NU 208 K NU 210 K NU 410 designation in accordance C 3 C 3 C 3 C 3 C 3 C 3 C 3 with DIN 5412
Adaptor sleeve in accordance with DIN 5412
Non Drive end :
Deep groove ball bearing designation in accordance 6403/C 3 6404/C 3 6404/C 3 6405/C 3 6405/C 3 6405/C 3 6410/C 3 with DIN 625
Oil fill in litres 0.16 0.18 0.18 0.25 0.25 0.28 0.45
Heavy Duty Bearing Bracket
Pump size 40 50 65 80 100 125 150
Drive end :
cylindrical roller bearing NU 206 K NU 207 K NU 207 K NU 208 K NU 208 K NU 210 K NU 410 designation in accordance C 3 C 3 C 3 C 3 C 3 C 3 C 3 with DIN 5412
Adaptor sleeve in accordance with DIN 5415
Non Drive end :
Angular contact ball bearing Din 628, 7305 BG 7306 BG 7306 BG 7307 BG 7307 BG 7309 BG 7310 BG matched pair, X arrangement Manufacturer SKF
FAG
Oil fill in litres 0.65 0.70 0.70 0.90 0.90 1.2 1.2
H 206 H 207 H 207 H 208 H 208 H 210 ---
H 206 H 207 H 207 H 208 H 208 H 210 ---
7305 B. UA 7306 B. UA 7306 B. UA 7307 B. UA 7307 B. UA 7309 B. UA 7310 B. UA
Drive at both Ends
Pump size 40 50 65 80 100 125 150
Suction side :
cylindrical roller bearing NU 206 K NU 207 K NU 207 K NU 208 K NU 208 K NU 210 K NU 410 designation in accordance C 3 C 3 C 3 C 3 C 3 C 3 C 3 with DIN 5412
Adaptor sleeve in accordance with DIN 5412
Discharge side :
Deep groove ball bearing designation in accordance 6305/C 3 6306/C 3 6306/C 3 6307/C 3 6307/C 3 6308/C 3 6410/C 3 with DIN 625
Oil fill in litres 0.16 0.18 0.18 0.25 0.25 0.28 0.45
Fig. 10 Bearing end oil requirement table
In case of the pump construction with drive at both ends, the bearing arrangement at the suction end corresponds to the standard construction. At the discharge end, deep groove ball bearings in accordance with DIN 625 are fitted, but they are of bearing series 63.
See Fig. 10 ‘‘Bearing and oil requirement table’’ for precise bearing designation and size for the individual pump sizes. Splash ring (507) on shaft (210) prevent the penetration of any leakage liquid from the stuffing box into the bearing housing.
H 206 H 207 H 207 H 208 H 208 H 210 ---
1.4 Lubrication
1.4.1 Oil Lubrication
Standard construction WK pumps are provided with oil splash lubrication. The antifriction bearings are slightly submerged in the oil sump, ensuring perfectly satisfactory lubrication at all times. The max. oil level is automatically attained during topping up when oil starts pouring out of the over-flow holes in the bearing covers (360/361).
On request, we can fit constant level oilers (638), which will necessitate the sealing of the shaft against the bearing bracket by means of felt rings (422.1) (See Fig. 11 to 13).
3
Page 5
WK
Oil Quality : Machinery oil possessing good air release
properties and corrosion prevention characteristics; kinematic viscosity 36 cSt approx. = 4.80E at 500C; flash point 1500C minimum; pour point lower than -200C.
Lubrication times : First oil change after the first 500 hours of operation, subsequent oil changes after every 3000 hours of operation approx., but at least once a year.
Overflow hole
Oil sump
Fig. 11 Oil splash lubrication
422.4
500.4
500.1 913 422.1
X
Portable (mobile) pumps, and pumps installed on board ship have grease-lubricated bearings (See Fig. 14). Use a good quality lithium soap ball and roller bearing grease, free of resin and acid, and possessing rust preventive properties. The grease should have a penetration number situated between 2 and 3, corresponding to a worked penetration situated between 2220 and 295 mm/10. Its drop point should be not less than
0
C.
175
731.2 636
Fig. 14 Grease lubricated bearing construction
The bearing temperature may be allowed to rise up to 400C above room temperature, but should not exceed 800C. The grease fill will last for 15000 hours of operation i.e., for 2 years approx. If the operating conditions are arduous, the bearings should be serviced once a year. A grease fill amounts to 10-20 grammes of grease, depending on the pump size. The pump bearings are packed with grease at our Works before despatch.
End side (Heavy duty bring bracket)
Drive end
Fig. 12 Construction with constant level oiler and sealing of the bearing housing.
638
Fig. 13 Constant level oiler viewed from X
Topping up of the oil fill at least once a month.
The bearing temperature may be allowed to rise up to 40
0
above room temperature, but should not exceed 800C.
1.4.2 Grease Lubrication
(Cannot be provided on heavy duty bearing construction pumps).
1.5 Shaft Seal
The shaft is sealed at its exits through the casings by softpacked stuffing boxes or by mechanical seals. If the pump is fitted with special stuffing boxes, mechanical seals can be fitted in lieu of soft packing (or vice versa) at any time during the service life of the pump, with a minimum of machining of the cooling compartment covers. On the other hand, the fitting of mechanical seals to pumps equipped with standard or hot water type soft-packed stuffing boxes necesitates the fitting of new pump components. Particulars can be obtained from the pump manufacturer.
1.5.1 Stuffing Boxes
Soft-packed stuffing boxes reduce the flow of leakage liquid at the clearance gap between casing and shaft protection sleeve when the pressure inside the pump is higher than atmospheric. Conversely, on pumps which operate on suction lift, the soft­packed stuffing box prevents the ingress of air into the pump. Sealing is effected by means of soft packing (461.1) arranged in a number of rings in the annular space between the stuffing box housing (451) and the shaft protection sleeve (524.1/2) and lightly compressed by the stuffing box gland (452).
Caution : On pumps which have a high discharge pressure, the stuffing box at the discharge end is relieved of pressure, via a balance liquid line, down to the suction pressure, provided that the differential pressure across the pump exceeds 20 bar. This ensures that the stuffing boxes at the suction and discharge ends of the pump have the same admission pressure. This arrangement applies to pump sizes 40 to 65 if the discharge
C
pressure exceeds 20 bar and to pump sizes 80 to 150 if the discharge pressure exceeds 15 bar.
Single stage pumps require no special pressure relief even at high discharge pressures. The pressure is relieved via the balance holes in the impeller.
4
Page 6
WK
Soft-packed stuffing box, ‘‘Standard’’ (N) construction.
Standard construction with 4 packing rings (461.1) used for temperatures of the fluid pumped up to 1050C. The stuffing box compartment cannot be cooled.
400.3
350
452
412.3
461.1
451
524.2 (524.1)
Fig. 15 ‘‘Standard’’ (N) construction stuffing box
7A/7E
400.3
350
165
452
412.3 412.4 461.1
400.3
451
524.2 (524.1)
Fig. 16 ‘‘Hot Water’’ (HW) construction stuffing box
Soft-packed stuffing box, ‘‘Hot Water’’ (HW) construction. Construction with 4 packing rings (461.1) and cooling of the stuffing box compartment. Used for temperatures of the fluid pumped in excess of 105
0
C up to 2300C max.
Special stuffing box, ‘‘Extra-deep’’ (V) construction. Construction with 7 packing rings (461.1) and cooling of the stuffing box compartment, used mainly in process industry applications.
7A/7E
400.3
451
524.2 (524.1)
165
452
412.3
400.3
350
412.4 461.1
Fig. 17 Special soft packed stuffing box ‘‘Extra deep’’ (V)
Special stuffing box, ‘‘VSM’’ Constructed VSM is the abbreviation (in German) of ‘‘Extra deep with lantern ring at the centre’’.
Construction with 5 packing rings (461.1) and one seal case ring (458) arranged at the centre of the packing compartment; used mainly for operation under vacuum or suction lift, and where malodorous fluids are pumped. For operation under vacuum, the lantern ring (458) is fed with a sealing liquid, and it prevents the ingress of air into the pump.
10A/10E
400.3
350
165
452
412.3 412.4 461.1
458
400.3
451
524.2 (524.1)
Fluids pumped : Operation under vacuum or pumping of malodorous fluids (ammonia and solvents).
Sealing liquid consumption 1 to 3 litres/hours approx.
Fig. 18 Special stuffing box VSM
Special stuffing box, ‘‘VSH’’ constructed. VSH is the abbreviation (in German) for ‘‘Extra deep with seal cage ring at the bottom of the box’’. The construction with 5 packing rings (461.1) and a seal cage ring (458) arranged at the bottom of the packing compartment is used where fluids containing abrasive particles are pumped. The flushing liquid, which should be fed through the cage ring (458) at a pressure of at least 1 to 4 bar (max.) above the suction pressure, penetrates inside the pump and protects the stuffing box packing (461.1) against abrasive substances.
11E
458
400.3
451
524.2 (524.1)
Fluids :
Products containing abrasive particles, which must be kept away from the stuffing box packing, so as not to erode the latter (oils containing diatomite (kieselguhr), fractions from catalytic cracking containing abrasive catalyst particles). Flushing liquid consumption 300 to 500 litres/hour approx.
165
452
412.3
400.3
350
412.4 461.1
Fig. 19 Special stuffing box VSH.
1.5.1.1 Cooling Liquid for Stuffing Boxes
Treated cooling water which does not tend to precipitate salts causing hardness out of solution should be used as cooling liquid. The cooling water should be allowed to flow out freely and visibly, so that it can be checked at any time in respect of rate of flow and temperature. The temperature differential between cooling water inlet and outlet should not exceed 10 The max. permissible cooling water outlet temperature should not exceed 500C. The cooling water pressure should be situated between 1 bar min. and 10 bar max.
An isolating valve should be incorporated in the cooling water supply line, to enable the rate of flow of cooling water to be adjusted, and the supply of cooling water to be turned off when the pump is shut down. The cooling water should only be turned off after the temperature of the fluid inside the pump has dropped to below 80
0
C.
1.5.1.2 Packing the Stuffing Boxes
Caution : The pump is despatched from our works with the
stuffing boxes unpacked. An adequate quantity of packing material is supplied loose with the pump. The stuffing box will only be able to perform its vital function satisfactorily on condition that it is carefully packed and properly maintained as prescribed.
Before packing, thoroughly clean stuffing box gland (452), packing compartment and shaft protection sleeve (524.1/.2).
5
0
C.
Page 7
Fig. 20 Cutting the packing rings of length.
To cut the packing rings to correct length, use a suitable wooden cutting jig (we can supply same on request), to ensure that the packing rings are of the correct length and that their ring butts come into correct contact with one another (see Fig. 20).
WK
Fig. 23 Tightening the stuffing box gland
Fig. 21 Stuffing box packing
If the packing rings are either too long or too short, the stuffing box will not be able to perform its function properly. In the case of asbestos-graphite packing material, the rubbing faces of the individual rings should be lightly coated with molybdenum disulphide before insertion in the packing compartment. The first packing ring is then inserted and pushed home into the compartment with the aid of the stuffing box gland.
The following packing rings are then inserted into the packing compartment one by one, making sure that the butt joint of each ring is offset 90
0
approx. in relation to the butt joint of the preceding ring; the individual rings are pushed home into the packing compartment with the aid of the stuffing box gland (see Fig. 21 and 22). The packing rings should only be pressed lightly against one another. They should not be inserted in the packing compartment in such a way that a clear gap of 6 to 8 mm is left at the outer end of the compartment for the positive guidance of the stuffing box gland.
Fig. 24 Information plate regading seal cage ring
The inserted packing rings should then be compressed moderately with the aid of the stuffing box gland (452) and the nuts (see Fig. 23). Then the nuts should be slackened again by one to two complete turns, and thereafter tightened lightly by hand. The correct and even seating of the stuffing box gland (452) should be checked when the pump is subjected to suction pressure, by inserting a feeler gauge between the gland (452) and the shaft protection sleeve (524.1/.2).
In the case of the special stuffing boxes, a seal cage ring is also inserted in the packing compartment, viz. at the centre of the compartment (between the packing rings) in the case of construction ‘‘VSM’’, and at the bottom of the compartment in the case of construction ‘‘VSH’’. In these cases, an information plate (see Fig. 20) is affixed to the stuffing box housing, showing the position of the lantern ring. The seal cage ring must register beneath the drilled hole in the stuffing box housing, to enable the sealing of flushing liquid to flow through the hole and the ring. The sealing or flushing liquid pressure should be 1 to 4 bar above the pressure reigning in the packing compartment of the stuffing box.
Fig. 22 Insertion of packing rings with the aid of the stuffing box gland
The packing of the stuffing boxes should be carried out with great care, to avoid an excessively high radial pressing force of the packing rings against the shaft protection sleeve, which might damage the latter. If the shaft protection sleeve is scored or grooved, even a new packing cannot be expected to last very long in service.
6
Page 8
A newly packed stuffing box should leak profusely at first. If this leakage does not cease of its own accord after a relatively short period of operation, the nuts on the gland should be tightened slowly and evenly while the pump is running, until the stuffing box only drips tightened evenly and not askew, as otherwise the shaft protection sleeves (524.1/.2) might be damaged (see Fig. 23).
The leakage rate in service of a soft-packed stuffing box should amount to 3 to 5 litres/hours approx.
If the newly packed stuffing boxes start to smoke when the pump is started up for the first time, the pump should be switched off. If the smoking persists after the pump has been started up again and operated several times in succession, the nuts on the gland should be slackened slightly, or the stuffing box should be inspected if necessary.
WK
Fig. 31 Mounted spacer-type flexible coupling
1.5.1.3 Packing Material
When selecting the packing material, make sure it is compatible with the fluid pumped (consult the manufacturer in case of doubt).
In steam generating plants, the asbestos-graphite packing material specially developed for hot water service has given good results. Packing material which has been dept in store for a certain period has a longer service life than packing material fresh from the packing manufacturer.
1.5.2 Mechanical Seals
Mechanical seals can be fitted as shaft seals in lieu of soft­packed stuffing boxes. If it is intended to replace soft-packed stuffing boxes by mechanical seals after the pump has been in service for some time, it is necessary for the pump to be equipped with stuffing box holdings (451) for ‘‘V’’ special stuffing boxes. It is also necessary to re-machine two tapped holes in the cooling cover (165) for the attachment of the seal cover (471).
1.6 Coupling
The pump on connected to the driver by a flexible coupling. Fig. 29 illustrated the type of coupling most frequently used.
2. Mode of Operation of Pump
The fluid flows through the suction casing towards the impeller at a given pressure. Energy is transmitted to the fluid by the impeller, which is fitted with vanes. From the impeller, the fluid flows into the diffuser, where kinetic energy is converted into potential energy, increasing the pressure rise still further.
The return guide vanes arranged on the discharge end cheek of the diffuser (171.1) guide the fluid under hydraulically favourable conditions towards the eye of the following stage impeller (230). This process is repeated from one stage to the next, and the pressure rise by the same amount in each stage, viz. by the stage generated pressure. After leaving the final stage diffuser (171.2), the fluid flows through the discharge casing (107) into the discharge line connected to this casing.
The generated pressure creates an axial thrust on the pump rotor of single and multistage centrifugal pumps. By the provision of narrow throttling gap between the impeller necks and the casing wearing rings at either side of each impeller, equal size lateral impeller space, and therefore almost identical pressure conditions are created at the suction and discharge ends of each impeller (see Fig. 34).
Fig. 29 Flexible coupling
Spacer type couplings (see Figs. 30 and 31) enable inspections and minor repairs (e.g. the fitting of new bearings or shaft protecting sleeves) to be carried out without removing the driver.
Fig. 30 Spacer type flexible coupling
Balance hole
Fig. 34 Axial forces acting on impeller
The balance holes in the discharge side impeller cheeks ensure a compensation of pressures between the suction and discharge sides of the impellers in the region situated between the impeller hub and the throttling gap, thus again preventing the creation of any appreciable axial thrust in this region of the impeller. Any residual axial thrust is absorbed by the fixed bearing in the discharge end bearing housing. This fixed bearing also locates the axial rotor position.
7
Page 9
WK
Fig. 35 Characteristics for constant pump rotational speed
As can be seen in the Fig. 35 the power absorbed by the pump does not decrease proportionately with decreasing rate of flow, but remains relatively high at the pump shut-off point (capacity Q = 0).
This absorbed power is almost wholly converted into heat inside the pump and this heating up process can lead to rapid evaporation of the fluid inside the pump, particularly if the driving motor is powerful and the fluid pumped is hot; this happens at the pump shut-off point (Q = 0) and at very low rate of flow.
In order to avoid such evaporation which might damage the pump, It is necessary to ensure a given minimum rate of flow through the pump at all times, which removes the heat generated.
For this purpose, an automatic recirculation valve (combined with a non-return valve) is provided (see section 9.3.1); this valve automatically opens a by-pass line when the rate of flow drops below a given preset value. If such a valve is not incorporated in the plant, the pump must not be operated below a given minimum rate of flow, nor must it be allowed to run against a closed discharge valve. After start up against a closed discharge valve, the latter should be opened immediately. If the pump handles a hot fluid or a fluid with a low boiling point (highly volatile), or if it operates on suction lift, steps must be taken to ensure that the fluid at the pump inlet nozzles has attained the pressure prescribed in the Confirmation of Order, in order to prevent vapour formation and the resulting damage caused by cavitation particularly the disintegration of the first stage impeller). If the back pressure is too low, the capacity of the pump will increase unduly, and the danger than arise of overloading and overheating of the driving motor.
Fig. 36 Slinging the ropes under the pump and driver mounted on a combine baseplate
5. Painting
Standard construction pumps operating at temperatures below 1400C are provided with a coat of primer and a top coat of synthetic resin base blue enamel paint (RAL 5001). If the operating temperature exceeds 1400C, the ‘‘hot’’ pump components, i.e. casing, pressure gauge piping and connection rods are provided with a coat of aluminium bronze paint (RAL 9006 silver bronze). All the ‘‘Cold’’ pump components, viz. the base-plate, bearing brackets etc. receive a coat of primer and a top coat of blue enamel paint (RAL 5001).
Special painting to customer’s specification can be carried out on request in accordance with the Confirmation of Order. All bright aprts and surfaces on the pump are coated with oil grease.
6. Condition of Equipment as Supplied
The following constructions can be supplied on request (see Confirmation of Order for certified and binding data) :
1. Pump without baseplate (Fig. 0).
2. Pump mounted on short baseplate (Fig. 4). (designed to accomodate pump only)
3. Pump and driver mounted on combbined baseplate (Fig. 3).
If the pump is supplied with a short baseplate or without a baseplate, the ropes should be slung under the connection rods as illustrated in Fig. 37.
3. Drive
The driver is usually connected to the stub shaft at the suction end of the pump. The direction of rotation is clockwise viewed from the driver into the pump. On request, the drive can be arranged at the discharge end of the pump (direction of rotation anticlockwise) or the pump can be provided with a stub shaft at both ends.
There are too many different types of drivers to allow them to be described in detail here, and we would therefore refer you to the operating instructions for the driver, published by the driver manufacturer, which are attached.
4. Transport
If the pump is supplied as a unit bolted onto a baseplate, the ropes for handling and transport should be slung under the pump and driver as illustrated in Fig. 36.
Caution : When slinging the ropes for transport, never sling them under the pump stub shafts or under the bearing brackets.
The internal interconnecting piping for the pressure relief of the shaft seal, and any cooling liquid supply and drain lines or sealing liquid lines, in so far as required, are already laid at our works prior to despatch, up to the limit of the Extent of Supply. The coupling and coupling guard are already mounted on the pump.
When a pump is supplied mounted on a combined baseplate, only the pump is dowelled to the baseplate, after having been aligned with the driver.
The driver is dowelled on site with cylindrical dowel pins after the final alignment on site. The necessary cylindrical dowel pins are supplied loose with the pump.
8
Page 10
Fig. 37 Slinging the ropes on a pump with short baseplate Fig. 4
WK
Our erection staff will check the correct orientation of the foundations in relation to the space axis after c;earamce fpr erection has been given. The site management is responsible for the zero point marking of the foundation (see ‘‘Conditions of Erection’’).
The areas for the packing plates (shims) should now be marked out and trued up in accordance with the foundation drawing. Then thick packing plates should be laid in position and levelled up with a spirit level.
The packing plates should lie flush on the foundation and be levelled up as truly horizontal as possible to facilitate the subsequent alignment and levelling up of the complete pumping set as accurately as possible. The exact height is of less importance at this stage, because any difference in heights can be compensated by the insertion of shims of varying thickness when the set itself is levelled up. Three point support should be adopted for the preliminary levelling up.
Surface for shims (packing plates)
Caution :
1. The pump bearings are not filled with oil.
2. The stuffing boxes are not packed. All apertures are plugged with PVC stoppers.
7. Accessories
As a general rule, the following items are supplied loose with the pump :
1 set of binding bolts (only supplied loose if the pump is supplied without a baseplate).
1 set of foundation bolts (if the pump is supplied with a baseplate).
On request, the following items can be supplied, amongst others :
Pressure gauge holder or pressure gauge bridge Pressure gauge Pressure vacuum gauge Stop valve for pressure gauge Coupling extractor device 1 set of shims and packing plates for levelling up 1 wooden cutting jig for packing rings 1 set of special tools
8. Installing the Pumping Set
Foundation bolt
Foundation axis
Fig. 38 Preparation of foundation
8.2 Installation and preliminary Levelling Up
The pumping set should only be placed on the foundation after the latter has set quite firmly, and the preparations for the foundation described above should be carefully followed. Before placing the set on the foundation, suspend the foundation bolts in the baseplate. Then fix the longitudinal and lateral directions and the correct height, then carry out a preliminary levelling up with the aid of a spirit level, and grout in the foundation bolts.
8.3 Aligning the Coupling
If the bare pump only is supplied, i.e. the motor or gearbox are not mounted, the flexible coupling should be pre-heated to 100-
0
C approx. in an oil bath before mounting on the stub shafts.
120 The flexible elements should be removed beforehand.
8.1 Description of Site prior to Commencement of
Erection
When our erection staff arrive on site, the pump foundation must have been checked for dimensional conformity with our foundation drawing data by the site management, and cleared for erection to preceed. The foundation and its immediate surroundings must be in a suitable condition to enable the efficient and speedy erection of the pump and accessories to proceed with out hindrance.
Our erection staff must be able to make use of customer’s hoisting gear, e.g. the engine room crane etc. for transport and erection if required.
Caution : Never drive the half coupling onto the shaft by hammer blows. Always use a pusher device to mount it on the shaft. (see Fig. 39).
In order to align the shafts, the pump and driver should be pushed towards each other until the two coupling halves are separated by the axial gap specified in the foundation or installation drawing.
The preliminary alignment of the coupling is effected by means of a short steel straight edge and feeler gauge.
9
Page 11
WK
Wrong
Right
Fig. 39 Mounting the coupling
Straight edge
A
B
C
Max. clearance 0.04 mm
Fig. 42 Coupling alignment jig
Spacer type coupling
a
1
ab
Straight edge Gauge
E
b
1
Fig. 40 Aligning the coupling bby means of a straight edge and gauge
Check the axial gap ‘‘E’’ at various points around the periphery, with the aid of a feeler gauge, and place a short straight edge across the outer diameter of the two coupling havles, forming bridge. If the gap ‘‘E’’ remains constant around the periphery, and if the straight edge lies flush at all points, the preliminary alignment can be considered satisfactory (see Fig. 40 and 41).
The accurate coupling alignment requires the manufacturer of a coupling alignment jig. This can be made from 20 x 20 flat bar steel or similar, the jig should be attached to the shafts (see Fig. 42).
Straight
D
edge
D
The coupling can be considered correctly aligned with the aid of the jigs illustrated if the difference measured does not exceed
0.04 mm both in the radial and axial directions, measurements being taken in 4 planes at 90
0
intervals. The coupling alignment check should be repeated after the piping has been connected to the pump.
8.4 Grouting in the Baseplate
After alignment of the coupling, the holes for the foundations bolts and the baseplate should be grouted in with a quicksetting cement mortar in 1:2 ratio (1 part of cement on 2 parts sand and gravel). Make sure that all the boxes in the baseplate are completely filled with the cement mortar and that no cavities remain.
The foundation bolts should be tightened evenly and firmly after the grout has set firmly. Then check with the aid of a dial micrometer that the alignment is still correct.
8.5 Final Alignment
After all the pipelines have been connected and the direction of rotation check has been carried out (with the pump disconnected from the driver), the final alignment of the pumping set should be effected. The same procedure would be followed as for the preliminary alignment, i.e. the relevant alignment jigs with 3 dial micrometers should be used and the measurements previously described should be carried out at the various shaft position (see section 8.3 ‘‘Aligning the Couplings’’).
Gauge
Fig. 41 Aligning the spacer-type coupling by means of a straight edge and gauge
Caution : The pump feet must be pulled tight against their seating on the baseplate. The alignment can be considered satisfactory if the dimensional deviations do not exceed 0.04 mm both in the case of the radial measurement and in the case of the axial difference measurement (see section ‘‘Alignment’’).
The final measurement readings should be entered in the system of coordinates on the erection check list. Any necessary height adjustments should be effected by inserting shims of appropriate thickness under the feet of the individual machines.
10
Page 12
9. Piping
The main piping should be connected to the pump without transmitting any stresses or strains onto the latter. Any appreciable piping forces which are transmited to the base­plate via the PUMP can detrimentally affect the alignment and the running of the pump. Such forces should therefore be kept to a minimum at all costs.
9.1 Suction Lift Line and Positive Suction Head Line
The pipe line connected to the suction casing (106) is called either a suction lift line or a (positive) suction head line, depending on whether the pressure at the pump inlet is below or above atmospheric pressure. This line should be kept as short as possible. (see Figs. 43 and 44)
Suction lift lines should rise all the way towards the pump, they should also be absolutely leak tight and be laid in such a way as to prevent the formation of air pockets at any point. (see Fig. 43).
Eccentric reducer (fitted belly down)
>0.5m
Suction strainer basket
>0.5m
Fig. 43 Suction lift line
The nominal size of the pump suction flange is no accurate guide to the size of the suction lift line. The latter should be sized, as a first approximation to give a velocity of 2m/sec. approx. In principle, every pump should be equipped with its own individual suction lift line. If this is not feasible for particular reasons, the common suction lift line should be sized for a s low a velocity as possible and preferably for a constant velocity right up to the last pump on the line (see Fig. 45).
WK
Correct
Wrong
Fig. 45 Common suction lift line for several pumps
In addition, pumps connected to a common suction lift line should be equipped with VSM stuffing boxes.
If the suction lift line is buried, it should be hydrostatically tested at 3 to 4 bar before burial.
The same remarks as above apply to the nature and laying of (positive) suction head lines. Horizontal lenngths of suction head lines should however be laid with a slightly rising slope towards the suction vessel. If it is not feasible to avoid apexes in the suction head line, each apex should be equipped with a vent cock. It is also advisable to avoid any appreciable length of horizontal suction head line laid close beneath the suction vessel because of the danger of evaporation (see Fig. 44).
9.1.1 Strainers in Suction Head Line/Suction Lift Line
Before a new pumping installation is commissioned, all the vessels, piping and connections should be thoroughly cleaned, flushed through and blown though. It often happens that welding beads, pipe scal and other dirt only become detached from inside the piping after a considerable period of service; they must therefore be prevented from penetrating inside the pump by the provision of a strainer in the suction head or suction lift line. This strainer should have a free area of holes equal to 3 times the pipe cross section area approx., in order to avoid an excessive pressure drop when foreign bodies tend to clog the strainer.
Conical (hat shaped) strainers have given good results in service (see DIN 4189), they should have a woven wire insert of corrosion-resistant material with a 1.0 mm. mesh width of
0.5 mm. diameter wire. The fine strainer should precede the coarse strainer in respect of direction of flow of the fluid. During the initial period of commissioning, the suction pressure should be kept under frequent observation. If the NPSH available is found to decrease, this may be due to clogged strainers (the pressure drop acros the strainer should be measured with the aid of a differential pressure gauge). The strainers should then be cleaned. (see Figs. 46 and 47).
Fig. 44 Suction head line
Unless anything to the contrary has been specified, the max. permissible pressure drop across the strainer should not exceed 3 meters.
11
Page 13
WK
1. Strainer holder
2. Fine strainer
3. Coarse strainer
4. Pump
1
Fig. 46 Conical strainer for suction head line
2
3
4
Fig. 47 Conical strainer with monitoring of pressure drop.
min.
max.
9.2 Isolating Valves
An isolating valve (gate valve) should be provided in the suction lift line, to enable the supply of fluid to a pump to be shut off if necessary. An isolating valve should also be incorporated in the discharge line of every pump, as close as possible to the pump itself. This valve can be used to adjust the operating point (rate of flow) apart from its function of isolating the discharge line. Isolating valves in suction head lines should only be used to isolate the line (in the event of repairs etc.). They must always remain fully open when the pump is running. If the pump operates under vacuum or suction lift, the isolating valve should be provided with a sealing liquid connection or with a closed water seal, to prevent any ingress of air into the stuffing box of the valve stem. To facilitate venting the isolating valves should be fitted in the line with their stems horizontal.
9.3 Non-Return Valves (in the discharge line)
A check valve or non-return valve should be incorporated between the pump and isolating valve. Depending on the circumstances, this can be either a check valve, or a non return valve or an automatic recirculation valve. The object ofthe non return valve is to prevent a reflus of fluid through the pump when the latter stops suddenly. A blocked or leaky non return valve may cause the pump to rotate in reverse, slackening the shaft protection sleeves and damaging the pump.
2 15 6 18 16 21 3 8 19 11
10 20
9 23 22 13 12 17 14 1
24 25
‘‘Construction with manual operation nozzle’’
Fig. 48 Automatic recirculation valve
The greater the flow of fluid, the higher the valve cone is lifted by the fluid pumped. A connecting rod in the shape of a lever the slide valve lever is connected at one end to the valve cone and at the other end to the shut-off valve (slide valve) on the bypass (leak-off) outlet. As the valve cone rises and falls, the shut-off valve is actuated by this lever, and the opening of the bypass is controlled in such a way that the bypass closes when the rate of flow has attained a given value, and opens when it drops below this value. The minimum flow rate is calculated and adjusted so as to avoid any excessive overheating inside the pump (see Fig. 49).
9.3.1 Automatic Recirculation Valve
The schroeder system automatic recirculation valve (minimum flow device) is a safety device, the purpose of which has already been explained in section 2 ‘Mode of Operation of Pump’. It should always be installed immediately downstream of the pump, always upstream of the isolating valve, and always vertical, with the direction of flow from bottom to top (see Fig.
48).
Each automatic recirculation valve is supplied in accordance with the operating conditions of the pump concerned.
Fig. 49
Part No. Designation
1 Bottom half of body 2 Top half of body 3 Valve cone 6 Guide shank 8 Slide valve head 9 Nozzle 10 Throttle 11 Rotary slide valve
12
Page 14
WK
12 Lever 13 Taper grooved dowel pin 14 Bottom spider 15 Top spider 16 Cylindrical helical spring 17 Socket head cap screws 18 Socket head cap 19 Taper grooved dowel pin 20 O-ring 21*) O-ring 22 Valve 23 Cylindrical helical spring 24 Manual operation nozzle 25 Multistage throttle
0
*) Not applicable for temperature above 130 pressure rating above PN 100 (Metal to metal sealing provided).
Parts 8-13 (Complete leak-off nozzle) can be replaced individually.
9.4 Final Coupling Check
After completion of the piping assembly, the coupling alignment should be checked once more (See Section 8.3 ‘‘Aligning the Coupling’’). It must be possible to rotate the pump rotor without effort by hand at the coupling, when the stuffing boxes are not packed. If the alignment is satisfactory (no misalignment having taken place), the driver can be dowelled with cylindrical dowel pins.
9.5 Measuring Instruments
Each pump should be equipped with two pressure gauges, one at suction nozzle and the other at the discharge nozzle; their measuring range should be suitable for the prevalent pressure conditions, and they should be provided with a stop cock or stop valve. If the suction conditions demand it (e.g. suction lift operation), the gauge on the suction nozzle should be pressure vacuum gauge (measuring instruments can be supplied by us on request see Fig. 50).
C and valve
Even a relatively short start up run in reverse rotation may result in damage to the pump. The overspeed trip check of the turbine or turbine driven pumps should also be carried out with the turbine disconnected from the pump.
2. Check correct coupling alignment again.
3. Dismantle pump bearings, clean them and reassemble them (as described in section 11, ‘‘Dismantling the Pump’’).
4. Fill-in oil, or check grease fill respectively.
5. Pack the stuffing boxes (see section 1.5.1 ‘‘Stuffing Boxes’’).
10.2 Start-up
1. Check oil level in pump bearings, if necessary top up the oil fill until oil starts pouring out of the over flow hole.
2. Check condition of stuffing boxes (451.1 / 451/2). The stuffing box gland should penetrate deep enough in the stuffing box to ensure positive guidance, and must not be tightened askew (see section 1.5.1 ‘‘Stuffing Boxes’’).
3. In the case of a mechanical seal with internal circulation, open flow controller fully (only applies to the initial start­up).
4. Turn on cooling liquid supply and check that it flows away freely.
5. Open suction valve fully.
6. Leave isolating valve in discharge line closed for the time being.
7. The pump must be completely primed with the product pumped. Before it is started up for the first time, the pump should be vented through the connection on the discharge pressure gauge, or through the vent valves, if provided. The discharge line should also be vented through valves situated at the apex of the line.
Fig. 50 Arrangement of measuring instruments
10. Commissioning
10.1 Preliminary Remarks regarding Commissioning
If the initial start up does not take place immediately after the erection of the pumping set, but only weeks or even months later, it will be necessary to carry out the following checks once again before start up :
1. Renewed direction of rotation check of driver with pump disconnected from the driver.
8. Open the shut off valve on the minimum flow line of the automatic recirculation valve and lock it open, to prevent unintentional closure. If the automatic recirculation valve is equipped with a manual operation line, open the valve in this line.
If the pump is only equipped with a manually controlled minimum flow (by pass) line, open the isolating valve in this line.
If a check valve or non return valve is incorporated and if the pump is to be started up against an open discharge valve, make sure that the non return valve is closed as a result of the back pressure (e.g. the boiler pressure). If the full back pressure does not reign at the time of start up the pump should only be started up against a closed discharge valve.
9. Check suction pressure and temperature. Check whether the saturation condition of the fluid pumped reigns inside the pump with the aid of the saturation curve. No vapour formation must be allowed to take place inside the pump.
10. When starting up for the first time, and also after a prolonged plant shutdown, start up the driver with the pump coupled to it, then switch off the driver again immediagely. Check that the rotor runs down to a standstill
13
Page 15
WK
smoothly and lightly, and check that the pump bearings are being supplied with oil. The pump rotor must not stop with a sudden jerk.
11. In the case of a turbine driven pump, run the pump up to full sped rapidly.
12. Watch the discharge pressure, to make such the pump attains the prescribed discharge pressure.
13. If applicable, close the manually operated minimum flow line when the operating rotational speed has been attained. Check whether minimum flow line becomes warm.
14. Adjust rate of flow of cooling liquid for the mechanical seal by means of the flow controller. The temperature at the mechanical seals should not exceed 70
0
C.
15. Open isolating valve in the discharge line.
Caution : If the pump is commissioned on hot fluid, the casing will heat up more rapidly than the connection rods (905) because of its direct contact with the fluid pumped. The casing will become longer as a result of thermal expansion. The pre­stressing of the connection rods will increase and the surface pressure (contact pressure) on the flat gaskets will attain a maximum value. Under such stress conditions, the gaskets which are still new will bed themselves down. When the pump has warmed up all over, the connection rods (905) may suffer such a reduction in prestressing that the pump may start leaking at the stage casings, especially in the case of pumps with a large number of stages. In order to avoid such leakage, the connection rods (905) should be tightened up after the first few ‘‘hot’’ starts on a new or reconditioned pump.
10.3 Operation and Supervision of Pump
1. Pumps operating at constant speed may usually be operated at the point of optimum efficiency, at total heads up to 90% of design head providing that suction head and the motor horsepower are adequate.
2. Pumps operating at constant speed may usually be operated within the range indicated in the pump operating diagram below. It should be noted that the throughout which can be achieved decreases with decreasing speed and pressure (see Fig. 51).
3. When filling the boiler, the operating limits specified in 1 and 2 above should not be exceeded i.e. the discharge valve should be partially closed to ensure that the pressure does not fall below the minimum discharge pressure corresponding to the particular speed or capacity at which the pump is operated at the time. If the rate of flow drops below the minimum flow, the minimum flow device starts operating. Any prolonged operation within the response range of the minimum flow device should be avoided as far as possible, because this will cause premature wear on the control and throttling organs.
10.4 Shutting the pump down
1. Close isolating valve (gate valve or globe valve) in the discharge line. If applicable, check the opening point of the minimum flow device from time to time.
2. Switch off driver and watch the pump run down smoothly to a standstill. The pump rotor should not stop with a sudden jerk.
3. If applicable, turn off the sealing, circulation or flushing liquid.
4. The cooling liquid supply can be partially throttled, but it should only be turned off completely when the temperature inside the pump measured at the pump nozzle, has dropped below 80
0
C. The suction valve should remain open unless the pump is being taken out of service of a prolonged period and it being drained.
10.5 Preserving the Pump
If the pump is taken out of service for a prolonged period, it is advisable to dismantle it completely. Proceed as described in section 11 ‘‘Dismantling’’. All components should be thoroughly cleaned, dried and all bright parts coated with grease. Thereafter the pump should be reassembled. All apertures on the pump should be plugged with wooden stoppers soaked in oil or blanked off with wooden cover plates fitted with O-rings. A sachet filled with silicagel (silicagel absorbs moisture) should be attached to the inside faces of the oil soaked wooden cover plates on the suction and discharge nozzles (i.e. inside the nozzles).
The packing should be removed from the stuffing box compartments and these should be sealed by oil-soaked wooden half tubes, each provided with two O-rings, in order to prevent the penetration of moisture (not applicable to pumps fitted with mechanical seals).
Fig. 51 Pump operating diagram
Caution : Only use acid free oils and greases when preserving the pump.
Fig. 52 Transport frame, Pump feet at shaft centreline heigh
14
Page 16
10.6 Sending the Pump back to our Works
If the pump is sent back to our Works for repairs or overhaul, it should be despatched completely assembled in order to prevent any possible damage to the sealing faces during transport. All pipe connections and flanges should be plugged or blanked off, after the pump has been drained. The pump should be securely mounted on a transport frame for despatch (see Figs. 52 and 53).
WK
Fig. 55 Pulling off the coupling hub
2. Remove bearing cover (360).
3. Bend back tab washer between ring nut of adaptor sleeve and cylindrical roller bearing (322) (see Fig. 56).
Fig. 53 Transport frame, Pump feet at bottom
11. Dismantling the Pump
11.1 Preparations prior to Dismantling
1. Close all isolating valves in the suction and discharge lines, and also, if applicable, in the cooling liquid, sealing liquid or flushing liquid lines, and drain the pump via the drain apertures (6B) in the suction and discharge casings (106 and 107).
2. Dismantle and remove cooling liquid, sealing liquid or flushing liquid lines.
3. Pull out stuffing box gland (452) and remove stuffing box packing (461.1).
4. Disconnect coupling (see section 1.6 ‘‘Couplings’’). Check pump alignment at the coupling and make a note of the measurements (see section 8.3 ‘‘Alignment’’).
5. If the pump is to be dismantled completely, unscrew the fixing bolts on the suction and discharge lines and on the pump feet, and remove the pump from the baseplate.
6. Drain off the oil fill in the bearing housing by unscrewing drain plug (903.4/.5).
11.2 Dismantling the Bearings
Fig. 56 Bending back the locking washer
4. Slacken withdrawal nut of adaptor sleeve (52.1) by a few turns (see Fig. 57).
11.2.1 Dismantling the Drive End Bearing
1. Pull off the half coupling with the aid of an extractor (see Figs. 54 and 55).
Fig. 54 Wheel puller
Fig. 57 Pulling off the coupling hub
5. Loosen adaptor sleeve (52.1) on shaft (210) by gentle taps on the end face of the withdrawal nut.
15
Page 17
Fig. 58 Forcing out the inner components of the cylindrical roller bearing
6. Pull out inner race of cylindrical roller bearing (322) together with adaptor sleeve (52.1) from bearing housing (350) (see Figs. 58 and 59)
WK
Fig. 61 Removing the bearing housing (350) together with outer race of cylindrical roller bearing (322)
Fig. 59 Dismantled inner components of cylindrical roller bearing
7. Unscrew and remove hex. nuts (920.2) from studs bolts (902.1) in the suction casing (106) in order to dismantle the bearing housing and stuffing box housing (see Figs. 60 and 61).
Fig. 60 Forcing off the bearing housing
Fig. 62 Stripping off the splash ring
8. On pump size 150 which is fitted with a cylindrical roller bearing without adaptor sleeve, the bearing housing (350), including the outer race of the bearing and the other distance ring (543) are removed after unscrewing the hex. nuts (920.4), then the inner race of the bearing and the inner distance ring (525.4) are pulled off the shaft, and the circlip (932) removed.
11.2.2 Dismantling the End side Bearing
11.2.2.1 Standard Bearing Construction
1. Remove bearing end cover (361) together with gasket (400.4).
2. Unscrew hex. shaft nut (920.4) and remove it from the shaft.
3. Unscrew and remove hex. nuts (920.2) from studs (902.1) in discharge casing (107), in order to dismantle the bearing housing and stuffing box housing.
4. Force off bearing housing together with deep groove ball
16
Page 18
bearing (321) by means of loan forcing screws until the bearing housing and bearing can be pulled off the shaft without effort.
5. Inspect condition of deep groove ball bearing (321) and if necessary remove it form bearing housing (350).
6. Strip splash ring (507) off the shaft.
11.2.2.2 Heavy Duty Bearing Construction
1. Remove bearing end cover (361) including O-ring (412.7).
2. Unscrew shaft nut (923) and remove it from the shaft together with lubricating ring (644).
3. Unscrew hex. nuts (920.2) from studs (920.3) in outlet cover (107), in order to dismantle bearing housing (350).
4. Force off (with the aid of forcing screws) bearing housing (350.2) together with angular contact ball bearing (320), inner distance ring (525.8), outer distance ring (543), guide bush (508) and lubrication ring (644), and pull the bearing assembly off the shaft with the aid of an extractor.
5. Remove distance bush (525.5), circlip (932) and splash ring (507) from the shaft.
6. Inspect condition of angular contact ball bearing (320) and if necessary remove it form bearing housing (350.2).
11.3 Removing the Shaft Seal
11.3.1 Soft-packed Stuffing Box Construction
WK
Fig. 64 Slackening shaft protection sleeve (524.2)
11.4 Dismantling the Pump Body
1. The stage casings (108) should be numbered consecutively in respect of their positions in relation to one another before dismantling, to ensure that the suction casing (106), the stage casing (108) and the discharge casing (107) are all reassembled in the correct sequence in relation to one another during reassembly (see Fig.
68).
1. Pull stuffing box gland (452) off the shaft.
2. Force off and remove stuffing box housing (451). On pumps equipped with cooled stuffing boxes, force off and remove the stuffing box housing (451) including cooling cover (165) (see Fig. 63).
Fig. 63 Removing the stuffing box housing (451)
3. Slacken shaft protection sleeve (524.2) and remove it from shaft (210) (see Fig. 64)
Fig. 68 Identification of casing components and removal of tie rods
2. Unscrew nuts (920.1) at discharge end or connection rods (905) and pull the connection rods out of the suction and discharge casing (see Fig. 68).
3. Underpin the pump at the stage casing (108) with wooden blocks or an erection trestle, so as to free the component which is to be dismanntled next.
4. Force discharge casing (107) together with diffuser/last stage (171.2) off stage casing (108) and lift it off (see Fig. 69 and 70).
17
Page 19
WK
Fig. 69 Forcing off the stage casing
Fig. 70 Lifting off the stage casing
5. Dismantle in sequence impellers (230), stage casings (108) together with diffusers (171.1), keys and stage sleeve (521) (see Figs. 71 and 72)
Fig. 72 Slackening and removing the stage casing
6. When the last stage casing (108) has been dismantled, pull shaft (210) together with last impeller (230), spacer sleeves (525.1) and shaft protection sleeve (524.1) out of the suction casing (see Fig. 73).
Fig. 73 Removing the shaft together with first stage impeller
7. Pull impeller (230), spacer sleeve (525.1) and shaft protection sleeve (524.1) off the shaft (see Fig. 74).
Fig. 71 Forcing off the impeller
Fig. 74 Dismantled shaft with impeller spacer sleeve and shaft protection sleeve.
8. Stack the stage casings on top of one another in correct order. The contact faces should be protected by wooden strips or thick cardboard during stacking, to avoid any damage. (see Fig. 75)
18
Page 20
Fig. 75 Stacking the stage casings on top of one another
WK
Fig. 76 Inserting the outer race of the roller bearing
Observe the greatest cleanliness when mounting the bearings (322). If the existing bearings are to be used again, they should be cleaned with petrol gasoline or benzol. After washing, they should immediately be sparyed with oil.
11.5 Inspection of individual Pump Components
1. Shaft (210)
Check true running (out-of-round) between centres on a lathe. Max. permissible out-of-round (shaft whip) : 0.03 mm. In principle, a bent shaft should never be straightened out, either warm or cold, but replaced by a new shaft if the permissible shaft whip is exceeded.
Caution : Make sure the shaft is accurately centred on the lathe as otherwise erroneous measurement results will be obtained.
2. Stage Casings (108)
Examine al contact faces for flawless condition. The plane parallelism of the contact faces must be checked at 4 points around the circumference. The deviation should not exceed 0.05 mm. Touch up any damage contact faces on a lathe. The surface roughness must not exceed Ra = 1.6 m.
3. Bearings (322)
The bearings should be replaced by new ones even if there are only slight discolorations or rust specks, or signs of damage on the contact faces tracks and ball or rollers. The outer race of the cylindrical roller bearing should be inserted as illustrated in Fig. 76.
4. Impellers (230) spacer sleeve suction/discharge (525), stage sleeve (521), Casing Wearing Rings (502) and Diffusers (171).
Inspect the impellers (230) for signs of damage by solids entrained with the fluid pumped.
540.2 503 171.2 400.2 541 521 106 210 107
412.2 230 108 171.1 502 540.3
525.2
525.1
Fig. 77 Alternative material construction in chrome steel throughout (e.g. CA6NM)
The impeller necks -- in the case of material construction CA6NM (chrome steel construction throughout) these are provided with impeller wearing rings (503) -- and the casing wearing rings (502, stage sleeve diffusers in the
As new clearance Max. permissible clearance
for material alternative value for material alternative
Chrome steel Chrome steel
C.I. Bz throughout C.I. Bz throughout
and bronze and bronze
mm on dia. mm on dia. mm on dia. mm. on dia.
Casing Wearing ring Impeller neck 0.30 0.40 1.0 1.0
Diffuser -- stage sleeve 0.30 0.35 1.0 1.0
Discharge casing -- spacer sleeves 0.30 0.35 1.0 1.0
Suction head
Shaft -- Suction casing 1.0 1.0 2.0 2.0
operation
19
Page 21
WK
case of chrome steel construction throughout the latter and provided with inter stage bushes (541) should all be examined for signs of radial galling (seizure). The spacer sleeve (525.1) should be examined for signs of galling in the suction casing (see Fig. 77). If any galling has been ascertained, and if it can be eliminated by touching up on a lathe, the increase in clearance which results must not exceed the max. permissible values listed in Fig. 78 ‘‘Rotor Clearances’’. If the touching up work on the components results in a clearance in excess of the max. permissible value, new components should be fitted, and the ‘‘as new’’ clearances listed in Fig. 78 should be re-established.
The increase in clearance must be adjusted to the same valve at all the throttling gaps on the pump, in principle if the clearances have been exceeded at one or more places inside the pump body, and new wear parts have to be fitted at those places, it is advisable to fit new parts at all the other places as well.
Assembly from Drive End
Slip shaft protection sleeve (524.1) onto the shaft without O­ring (421.3) and pull it tight against the shaft shoulder. Mount coupling half with the aid of a pusher device.
Assembly from End Side
Mount spacer sleeve (521), keys and impellers (230) of the remaining stages onto the shaft in their correct sequence.
Caution : Remember to mount the impellers in accordance with their correct stage sequence.
Slip spacer sleeve (525.2) shaft protection sleeve (524) respectively onto shaft (921) without O-ring (412.3), and pull them tight against the hub of the last stage impeller (230).
5. Shaft Protection Sleeves (524.1/.2)
These may only be touched up very slightly, if the damage is more than superficial, new shaft protection sleeves should be fitted.
6. Cooling Compartments of Stuffing Box Housings (451)
If applicable, and if a cooling liquid supply is connected to them, inspect the compartments and clean them.
reverse sequence to the assembly described above.
Fig. 79 Rotor assembly for dynamic balancing
12. Assembly of Pump
12.1 Preparations prior to Reassembly
Before reassembly of ring section pumps, the axial face-to­face length ‘‘E’’ of each stage casing (108) and of the corresponding impeller (230) with stage sleeve (521) must be measured. Any discrepancy in lengths must be compensated by machining the stage sleeve (521) only, and the end result must be E1 = E2 taking the thickness of glat gasket (400.2) into account (see Fig. 80).
If machining of the stage sleeve is required, it should be shortened at both end faces in one and the same clamping on the machine too. The permissible end face wobble (deviation from plane parallelism) is 5 m. Make sure not to damage the contact faces on the casing components, diffusers impellers, spacer sleeves and stage sleeves before and during assembly. All pump components, particularly the end contact faces, should be thoroughly cleaned. If new impellers are fitted, or if the old ones are touched up, the rotor must be balanced dynamically.
12.2 Assembling the Pump Body
1. Before assembly of the rotor components, coat the shaft (120) with molybdenum disulphide.
E
1
7. Coupling
If the flexible elements show signs of wear after a prolonged period of operation, replace same by new ones in good time.
11.6 Dynamic Balancing of Pump Rotor
If certain rotor components are replaced by new ones or are touched up, or if a new shaft is fitted, the pump rotor of pump sizes 40 to 100 must be subjected to an out-of-round check, and in addition, the pump rotor of pump sizes 125 and 150 must be dynamically balanced, if possible at max. operatings speed, but in any event at 1000 1/min. The max. permissible residual eccentricity should not exceed 5 m.
For the dynamic balancing test, the rotor should be assembled as follows :
Before dynamic balancing, the pump rotor should be checked for out-of-round in the region of the impeller necks (230), of the spacer sleeves and distance stage sleeve (525.1 and 521) and of the bearings (see Fig. 79). The measured out-of-round value at any of these places should not exceed 0.03 mm. Before final assembly in pump, the rotor must be dismantled again, in
E
2
Fig. 80 Measuring the stages
2. Slip the shaft protection sleeve (524.1) onto shaft (210) after inserting O-ring (412.3) and pull it tight against the shaft shoulder. Mount spacer sleeve (525.1), key and first stage impeller (230) onto shaft (210) (see Fig. 81).
20
Page 22
Fig. 81 Shaft with first stage impeller
3. Insert shaft (210) together with spacer sleeve (525.1) and impeller (230) into discharge casing (106) (see Fig. 82).
WK
Fig. 84 Mounting the stage casings
6. After assembly of each individual stage, check the total axial clearance ‘‘Sa 1 + Sa 2’’ of the pump rotor (approx. 6 mm. see Fig. 85).
Fig. 82 Shaft with first stage impeller inserted into suction casing
Fig. 83 Mounting the impeller
4. Mount stage casing (108) together with inserted diffuser (171.1) and flat gasket (400.2), and slip stage sleeve (521) onto the shaft (see Fig. 84).
Sa2
Sa1
Fig. 85 Checking the total axial clearance.
7. Mount discharge casing (107) with inserted last stage diffuser (171.2) and O-ring (412.2) (see Fig. 86).
5. Mount all the following stages in similar fashion each stage consists of stage casing 9108), diffuser (171.1), casing wearing ring (502), flat gasket (400.2), impeller (230), key and stage sleeve (521). Underpin the stage casings (108) in turn after assembly (see Fig. 84).
Fig. 86 Inserting the diffuser in the discharge casing
21
Page 23
WK
Size Number Torque Number Torque
of stages of stages
40 1-10 7.5 kpm 11-16 8.0 kpm
50 1-10 8.5 kpm 11-15 10.0 kpm
65 1-10 12.0 kpm 11-14 15.0 kpm
80 1-8 20.0 kpm 9-12 23.0 kpm
100 1-8 25.0 kpm 9-11 27.0 kpm
125 1-6 30.0 kpm 7-10 32.0 kpm
150 1-6 35.0 kpm 7-8 37.0 kpm
Fig. 87 Tightening torque for the connection rods
1kgm = 1 kpm
8. Insert tie rods (905) with nuts (920.1) and washers (550) from the suction end.
9. At the suction end, screw on at the hex. nuts (920.1) on connection rods (905) and screw them down to median position. Insert the tie rods (905) from the suction end, after having slipped on the washers.
9a. PUmps which operate under conditions of extreme
temperature fluctuations (in excess of 50
0
C within a 30 minute interval) can be subjected to unequal thermal expansion at the casings and tie rods, which can result in leakage. In order to compensate these expansions, a stack of cup springs should be inserted between the nut and suction casing on each connection rod. The number of cup springs in the stack will depend on the compression pressure required, and is determined by the pump manufacturer (see Fig. 88).
by hand with a standard short spanner to ensure intimate contact of the stage casings (108) at their sealing faces.
11. Slip the spacer sleeve onto the shaft until it abuts against the hub of the last stage impeller.
12. Place the pump on the baseplate. The pump feet must seat flush on the baseplate. Tighten hex. nuts (920.1) on the tie rods at the discharge end evenly on the cross.
13. Tighten nuts (920.1) on the tie rods (905) at the discharge end. Then slacken the nuts at the discharge end again until the seating is loose, and tighten them again by hand with the aid of a short hammering spanner until contact is established. Then tighten the nuts firmly with the aid of a torque spanner (see Fig. 87).
12.3 Assembly of Shaft Seal
12.3.1 Pump construction with Soft packed Stuffing Box
1. Slip shaft protecting sleeve (524.2) onto shaft (210) after insertion of O-ring (412.3), and pull it tight against spacer sleeve (525.2) (see Fig. 89).
483 520.1 550.1
Part No. Designation 106 Suction casing 483 Spring cage
520.1 Sleeve
550.1 Washer 905 Tie rod
920.1 Hex. nut 950 Stack of cup springs
920.1 950 106 905
Fig. 88 Stack of cup springs.
9b. The washer (550.1), sleeve (520.1), stack of cup springs
(950) and spring cage (483) are all mounted on the tie rods (905) between the suction casing (106) and the hex. nut (920.1). The cup springs should be lightly coated with oil before insertion. The hex. nut (920.1) should be screwed on by hand. The tie rods (905) should be fitted as described under point 10 below. The hex. nut (920.1) at the suction end should be tightened until abbutment is achieved.
Fig. 89 Mounting the shaft protection sleeve
2. Mount stuffing box housing (451) with flat gasket (400.3). In the case of pumps equipped with cooled stuffing boxes, mount the stuffing box housing (451) together with cooling cover (165) (see Fig. 90).
If the pump should become slightly distorted by uneven tightening, the hex. nuts (920.1) at the suction end should be slackened slightly.
10. At the discharge end, the screw threads of the tie rods and the washers should be coated with molybdenum disulphide. The hex. nuts (920.1) should bbe tightened
Fig. 90 Mounting the stuffing box housing
22
Page 24
WK
3. Slip the stuffing box gland (452) loosely on shaft (210) but do not insert it in the stuffing box compartment.
4. Slip splash ring (507) onto the shaft.
12.4 Assembly of Bearings
12.4.1 Assembly of End Side Bearing
Standard Bearing Construction 1
1. Mount splash ring (507) onto shaft (210).
2. Slip bearing housing (350) onto the shaft and onto the studs on discharge casing (107), and fasten it with the nuts (920.2) (see Fig. 107).
920.4 321 350 903.12 400.4 920.4 350 525.4
361
3. Slip spacer sleeve (525.5) onto the shaft until it abuts against circlip (932).
4. Slip inner guide bush (508) and lubricating (644) onto the shaft.
901.3 361 913 350.2 412.7 507
903.5
412.7
(13B)
400.5
644
160
543
525.8
901.4
720.3
644
(8B)
360.2
210350508320320923
525.5
902.3
Fig. 109 Heavy duty bearing bracket construction on pump size 150.
400.4
903.4 (13B)
507
932321543361
507
Fig. 107 Bearing construction, pump sizes 40 to 125
Fig. 108 Bearing construction, pump size 150
3. Mount deep groove ball bearing (321).
4. Screw hx. shaft nut (920.4) onto the shaft and tighten it.
5. Mount bearing end cover (361) and gasket (400.4).
6. Seal the oil drain apertures (13B) by means of threaded plug (903.4).
7. In the case of pump size 150, assembly should proceed as follows :
Mount splash ring (507), circlip (932) and inner spacer sleeve (525.4) on the shaft.
Insert deep groove ball bearing (321) and outer spacer sleeve (543) into the bearing bracket (see Fig. 108).
Mount bearing bracket (350) together with inserted components.
Caution : The angular contact ball bearings must be mounted in ‘‘X’’ arrangement. To facilitate mounting, it is advisabble to pre-heat the angular contact ball bearings in an oil bath before they are slipped onto the shaft.
5. Mount inner angular contact ball bearing (320), inner distance ring (525.*0, outer spacer sleeve (543) and outer angular contact ball bearing (320) onto shaft (210).
6. Screw shaft nut (923) onto shaft, and pull it tight. Insert lubricating ring (644).
7. Mount bearing end cover (361) with O-ring (412.7) and pull it tight with the aid of hex. bolts (901.3).
12.4.2 Assembly of Drive End Bearing
1. Mount splash ring (507) on shaft (210).
2. If necessary, insert outer race of cylindrical roller bearing (322) in the bearing housing (see Fig. 76).
731.2 322 400.4 901.2
350
Mount lock washer and hex. shaft nut (920.4) on the shaft.
Pull the nut tight and lock it with the aid of the lock washer.
Mount bearing end cover (361) with gasket (400.4).
Heavy Duty Bearing Construction (see Fig. 109).
1. Mount splash ring (507) and circlip (932) on the shaft.
2. Slip bearing housing (350.2) together with cover (160) and bearing cover (360.2) onto the shaft and studs (902.3) on the discharge casing and fasten it with the nuts (920.2).
507 52-1 360 210
Fig. 110 Bearing construction, pump sizes 40 to 125
23
Page 25
WK
3. Mount bearing housing (350) together with outer race of cylindrical roller bearing (322) and tighten hex. nuts (920.2) evenly (see Fig. 111).
Fig. 111 Mounting the bearing housing
4. Slip adaptor sleeve (52-1) together with bearing inner race, lock washer and withdrawal nut onto shaft (210) until the rear end face of the inner bearing race lies in the same plane as the outer end face of the oter race of cylindrical roller bearing (322). Then tighten the withdrawal nut and make sure that the components of the cylindrical roller bearing do not slide out of position in relation to each outer whilst the nut is being tightened (see Figs. 112 and
113).
5. Bend down the tabs on the locking washer (see Fig. 114).
6. Mount bearing cover (360) and flat gasket (400.4) (see Fig. 115).
Fig. 112 Mounting the inner race of the cylindrical roller bearing with adaptor sleeve
Fig. 113 Tightening the withdrawal nut
7. On pump size 150, assembly should proceed as follows (see Fig. 116).
507
525.4 350 360
932 322 543
Fig. 116 Bearing construction, pump size 150
Mount splash ring (507) and circlip (932) on the shaft. Insert outer race of cylindrical roller bearing (322) and outer distance ring (543) in the bearing housing. Mount bearing housing (350).
Slip inner distance ring (525.4) and bearing inner race (322) onto the shaft.
Mount locking washer and shaft nut (920.4) on the shaft.
Pull nut tight and lock it with the locking washer.
Mount bearing cover (360) and gasket (400.4).
24
Page 26
WK
8. Mount coupling hub on the shaft with the aid of a pusher device.
9. Align pump at the coupling (see section 8.3, ‘‘Coupling Alignment’’).
10. Pull fixing bolts tight on pump feet (see section 8.5, ‘‘Final Alignment’’).
11. Pack the stuffing boxes in accordance with section 12.3.1 ‘‘Assembly of Shaft Seal’’.
12. Connect all the pipelines to the pump.
13. Carry out a final coupling alignment check in accordance with section 8.5 ‘‘Final Alignment’’.
14. Fill the bearing housing (350) with oil (see sections 1.3 ‘‘Bearings’’ and 1.4 ‘‘Lubrication’’).
15. Open isolating valve in suction line fully.
16. Start up the pump (see section 10 ‘‘Commissioning’’).
13. Operating Troubles, Causes and
Remedies
Caution : Before remedying operating troubles, check all measuring instruments used for reliability and accuracy.
13.1 Operating Troubles Cause and suggested remedy see
section 13.2 & 13.3
1. Pump fails to deliver liquid 1, 2, 3, 4, 5, 6, 8, 12,
13
2. Pump delivers insufficient 1, 2, 3, 4, 5, 8, 12, 13, liquid 19, 20, 21
3. Total head is too low 3, 4, 5, 7, 8, 10, 12, 19,
20, 21
4. Sudden interruption of 1, 2, 3, 4, 9, 11, 13 delivery shortly after start-up
5. Absorbed power is 6, 7, 9, 10, 17, 19 excessively high
6. Excessive leakage at 14, 16, 18, 22, 23, 24, stuffing box 28, 29
7. Life of packing is too short 14, 16, 18, 22, 23, 24,
25, 26, 27, 28, 29
8. Pump vibrates or runs noisily 2, 3, 4, 11, 13, 14, 15,
16, 17, 18, 20, 24, 32, 33
9. Life of bearing is too short 14, 16, 17, 25, 31, 32,
33, 34
10. Excessively high temperature 1, 3, 4, 7, 9, 11, 13, 14, inside the pump. 16, Rotor fouls the casing or 18, 19, 20, 24, 30, 32 seizes
11. Too high a rate of leakage 14, 16, 18, 24, 25, 35, liquid at the mechanical seal 36, 37, 38, 39, 40 or too short a mechanical seal life
13.2 Cause of Damage (the numbers listed below
correspond with the code numbers of section 13.1).
Faults at the Suction End
1. Pump not properly vented, air pocket in suction line, vapour bubble at suction end, lines not properly vented.
2. Pump or suction line incompletely primed with fluid.
3. Insufficient pressure differential between suction pressure and vapour pressure, NPSH required is not attained (observe rate of pressure decrease).
4. Mouth of suction line too close to surface of liquid level in the suction vessel, or liquid level in vessel too low.
General Faults in the Installation
5. Rotational speed to low, or rate or minimum flow through by-pass excessive.
6. Rotational speed too high.
7. Reverse rotation.
8. Total head required for the system is higher than total head generated by the pump at duty point (back pressure too high).
9. Total head required for the system is lower than total head generated by the pump (pump operates beyond the performance limit curve).
10. Specific gravity of fluid pumped is different from figure specified originally (different operating temperature).
11. Operation at very low rate of flow (fault in minimum flow device, rate of minimum flow is too low).
12. Pumps cannot possibly operate in parallel under these conditions.
Mechanical Faults
13. Foreign bodies lodged in impeller.
14. Pump misaligned or incorrectly aligned, or shifting of foundation.
15. Resonance, or interference by other machines via the foundation.
16. Shaft is bent.
17. Rotating elements foul the stationary elements, pump runs very rough.
18. Bearings badly worn.
19. Casing wearing rings badly worn.
20. Impeller damaged or disintegrated.
21. Fault casing seal (excessive internal loss at throttling gap, rotor clearances exceeded due to wear), so that an excessive loss arises or water leaks through the casing partition. Water leaks out of metallic sealing face to atmosphere.
22. Shaft or shaft protection sleeves worn or scored, O-ring damaged.
23. Stuffing box badly packed. Packing material of unsuitable quality.
24. Shaft chatters because bearings are worn or because shaft is misaligned.
25. Rotor vibrates.
26. Stuffing box gland is tightened excessively, no fluid available to lubricate the packing.
27. Defect in cooling liquid supply to water-cooled stuffing box gland.
28. Excessive clearance gap between stuffing box gland and shaft protection sleeve. Packing is squeezed into gap beneath the gland.
25
Page 27
WK
29. Dirt or sand in cooling liquid fed to stuffing box gland causes scoring of shaft protection sleeve.
30. Excessively high axial thrust.
31. Insufficient quantity of oil in bearing housing, unsuitable oil quality, dirty oil, water in the oil.
32. Faulty bearing assembly (damage during assembly, wrong, assembly).
33. Dirt in the bearings.
34. Ingress of water into bearing housing.
35. Rubbing faces of mechanical seal worn or scored. O-rings damaged.
36. Seal incorrectly assembled. Materials unsuitable.
37. Surface pressure in sealing gap too high, no fluid available for lubrication and cooling.
38. Fault in cooling liquid supply system to mechanical seal.
39. Excessively large gap between cooling housing and spacer sleeve. Temperature in the cooling circuit rises excessively.
40. Dirt in cooling circuit of mechanical seal leads to scoring of mechanical seal rubbing faces.
13.3 Suggested Remedies
If, after a breakdown has occurred, one of the cause listed in section 13.2 has been established as the cause, and the matter has been put right or the cause of the trouble eliminated, it is recommended, prior to recommissioning the set, to check the effortless rotation of the pump rotor by hand, with the driver disconnected (unless the pump had to be dismantled in any case, because of the damage). Check that the pump runs smoothly and quietly after recommissioning.
Cause 1. Open vent valves or pressure gauge vent screws,
open isolating valves in minimum flow device circuit. Check layout of pipelines to ensure that fluid flows smoothly.
Cause 2. Prime pumps and piping again, and vent them
thoroughly. Check layout of pipelines.
Cause 3. Check isolating valve and strainers in suction line.
The instrument readings taken must be accurate. Consult manufacturer.
Cause 4. Check water level in reservoir and examine
possibility of altering it. Raise water level, alter mouth of suction line. The nozzle should not project too high inside the reservoir, and it should be shaped so as to promote favourable flow characteristics.
Cause 5. Increase speed, if pump it turbine-driven. Refer to
manufacturer, if pump is motor-driven. Check operation of minimum flow device.
Cause 6. Decrease speed, if pump is turbine-driven. Refer
to manufacturer, if pump is motor driven.
Cause 7. Cross over two phase leads on the motor.
Cause 8. Increase rotational speed. Fit larger diameter
impellers. Increase number of stages. Refer to manufacturer.
Cause 9. Adjust pressure conditions by means of discharge
valve. Alter rotation speed, alter impeller diameter. Refer to manufacturer.
Cause 10. Check temperature of fluid pumped, take steps
outlined in 9, above.
Cause 11. Check operation of minimum flow device. Refer to
manufacturer.
Cause 12. Check condition of individual machines. Refer to
manufacturer.
Cause 13. Clean out pump, check condition of suction system
(check suction line and strainers).
Cause 14. Realign pumping set when cold.
Cause 15. Refer to manufacturer.
Cause 16. Fit a new shaft. On no account straighten outt a
bend shaft.
Cause 17. Dismantle pump.
Cause 18. Check quiet running of pumps. Check coupling
alignment (when cold). Check oil quality and cleanlines.
Cause 19. Fit new casing wearing rings, Check out-of-round
(true running of) rotor. Check presence of foreign bodies in the pump (see also item 16).
Cause 20. Fit new impeller. Check suction head (cavitation).
Check system for presence of foreign bodies (see also item 16).
Cause 21. Replace damaged components by new ones.
Cause 22. Replace damaged components by new ones.
Check shaft protection sleeves for true running (out-of-round). Check suitability of packing material used. Check that gland is not tightened askew and observe rate of leakage.
Cause 23. Carefully repack stuffing box. Check suitability of
packing material used.
Cause 24. Realign coupling (when cold). Fit new bearings.
Check rotor for signs of damage.
Cause 25. Check suction pressure (cavitation). Check
coupling alignment. Check pump internals for presence of foreign bodies.
Cause 26. Repack stuffing box. Tighten gland lightly only.
Alow slightly higher rate of gland leakage. Check suitability of packing material used.
Cause 27. Check unobstructed flow through cooling liquid
feed line.
Cause 28. Fit an end ring or a new stuffing box gland. Check
condition of shaft protection sleeve.
Cause 29. Use treated cooling liquid. Fit filters in cooling liquid
lines.
Cause 30. Check rotor clearances. Check axial adjustment
(position) of rotor.
Cause 31. Check oil quality and quantity.
Cause 32. Check bearing components for signs of damage
and assemble them correctly.
Cause 33. Throughly clean bearings, bearing housings and
check condition of bearing of seal.
Cause 34. Remove all rus t from bearings and bearing
brackets. Change the oil fill.
Cause 35. Replace damaged components by new ones.
Check rotating components for out-of-round. Check suitability of materials used. Make sure all seal components seat accurately, and lookout for leakage.
Cause 36. Carefully insert seal. Check materials for suitability.
Cause 37. Measure the seal anew. Refer to manufacturer.
26
Page 28
WK
Cause 38. Check unobstructed flow through cooling liquid
supply line.
Cause 39. Fit a new bush or a spacer sleeve in the cooling
housing.
Cause 40. Use treated cooling liquid. Incorporate filters in
cooling liquid line.
Quantity for pump
construction with
14. Spare Parts
When ordering spare parts, always please quote the item numbers, and designations of the items concerned, and the Works serial number of the pump, in order to avoid any queries and delays in delivery. The Works serial number of the pump can be obtained from the title page of the present instruction manual, or from the rating plate on the pump.
We recommend keeping the following spare parts in stock in order to be in a position to remedy rapidly any operating trouble which might arise.
Remark
Standard
Part No.
210 Shaft with keys 1 1 1 *) 230 Impeller S S S *) 320 Angular contact ball bearing 2 2 2 Only on heavy duty bearing bracket 321 Deep groove roller bearing 1 1 1 322 Cylindrical roller bearing 1 1 1
400.1 Flat gasket 1 1 1
400.2 Flat gasket S S S
400.3 Flat gasket 2 4 4
400.4 Flat gasket 2 2 2
400.5 Flat gasket 1 1 1 Only on heavy duty bearing bracket
400.6 Flat gasket - - 2
412.2 O-ring 1 1 1
412.3 O-ring 2 2 2 *)
412.4 O-ring - 2 2
412.7 O-ring 2 2 2 Only on heavy duty bearing bracket
422.1 Felt ring 3 3 3 Only on heavy duty bearing bracket
422.2 Felt ring 1 1 1 Only when bearing is sealed
461.1 Stuffing box packing (in metres) 2 2 ­472 Mechanical seal, complete - - 2 502 Casing wearing ring S S S 521 Stage sleeve S-1 S-1 S-1
523.1 Shaft protection sleeve - - 1 *)
524.1 Shaft protection sleeve 1 1 - *)
524.2 Shaft protection sleeve 1 1 - *)
525.1 Spacer sleeve 1 1 1 *)
525.2 Spacer sleeve 1 1 1 *)
540.1 Stage bush 1 1 1 Only on pump size 150
540.2 Stage bush 1 1 1 Only on material alternative chrome steel
540.3 Stage bush 1 1 1 Only on material alternative chrome steel 541 Stage bush S-1 S-1 S-1 Only on material alternative chrome steel
52.1 Adaptor sleeve, complete 1 1 1
stuffing box
Special stuffing
boxes HW
V, VSM, VSH
Mechanical seal
S = Number of stages *) Parts for complete pump rotor. The latter should be assembled and dynamically balanced, and kept in stock as a complete spare parts.
27
Page 29
WK
15. Check List
15.1 Pre-requisites for Initial Commissioning
Check direction of rotation of driver with pump disconnected. Check correct alignment of pumping set with appropriate alignment jigs and dial micrometers.
Check that the stuffing box gland seats squarely and has sufficient guidance (with the aid of a feeler gauge, check that the gap between the shaft protection sleeve and the stuffing box gland remains the same around the circumference). If mechanical seals are fitted, check that the circulation lines are vented at the apex.
Check that the system is primed with the fluid pumped, and thoroughly vented via the vent valve in the discharge line (if provided), and via the vent screws of the pressure gauge valve (suction pressure-discharge pressure).
Check that the valves in the minimum flow line are opened. Check that the valve in the manually-operated line of the minimum flow device is opened.
Check that oil has been filled in the bearing bracket and that the required oil level has been attained (by oil pouring out of the overflow holes).
Observe the start-up procedure for the driver.
0
If the operating temperature exceed 150 valve in the cooling liquid supply line is fully open, and that the fluid flows through freely, also check that the throttling valves in the cooling liquid lines are fully open.
Check that the isolating valve in the suction head line is fully open.
Check that the isolating valve in the discharge line is closed.
C, check that the main
15.4 Initial Operation with Hot Fluid
When the nominal temperature of the fluid pumped has been attained, adjust the flow rate of the cooling liquid supply. This should be done by throttling the individual valves in the internal cooling liquid piping system in such a way that a temperature differential of 10
0
C max. is set up between the cooling liquid
inlet and outlet.
During operation, check the pressure drop across the strainer in the suction lift or suction head line. When the max. permissible pressure drop value has been reached, switch off the pumping set and clean the strainer.
15.5 Supervision of Operations & Maintenance
During operation, the pump should be kept under careful observation. The following measurement values should be checked at frequent intervals :
Suction pressure
Suction temperature
Pump discharge pressure
Temperature at pump discharge nozzle
Bearing temperature
Stuffing box leakage
Temperature of mechanical seals
Cooling liquid temperature at cooler outlet (Max. temperature differential 10
0
C)
Check that the pump runs smoothly and quietly at all times, and check the pressure drop across the suction head line by differential pressure measurement.
15.2 Initial Start-up with Cold Water
Switch on driver for a short instant, and switch it off again immediately. Check that rotor runs down smoothly and evenly to a standstill.
Switch driver on again. Check quiet running of pump.
Observe the stuffing boxes (they should not run too hot).
Make sure that the pump runs smoothly and quietly, and that the stuffing boxes function correctly.
On pumps fitted with mechanical seals, keep a check on the temperature in the circulation lines.
Keep a check on the pressure gauge indications (suction and discharge pressures).
If the pump is turbine driven, run up turbine to full operating speed as rapidly as possible, and make sure the pump runs quietly during this time.
15.3 Priming the Boiler
Crack the isolating valve in the discharge line open slowly (remember lag of servo-actuated valves). Run the pump within the confines of the limitation curve of the operating diagram (see section 10.3 ‘‘Pump Operation and Supervision’’).
We recommend keeping a log book on pump operation, to supervise the pumps more closely; the following data should be entered in this log book at hourly intervals : rate of flow, suction pressure, discharge pressure, temperature of fluid pumped, rotational speed and axial rotor position. The times of start-up and shutdown should also be recorded, so that the total number of hours of operation of the feed pump can be ascertained at any time.
The oil level and oil quality should be checked, respectively tested, after the first 200 hours of operation. Thereafter, the oil level and oil quality should be checked at least once a month.
28
Page 30
WK
16. Sectional Drawings and List of Components
ç
903.1
920.4
350 920.2
361
903.4
321
902.1 400.3
720.3
903.2
ç
400.3
731.2
322
901.2
350
52-1
360
210
903.2
920.3
902.2
507
412.3 451
400.4
452
461.1
550
524.2
905
920.1
Qty. Part Designation per No. pump
1 106 Suction casing 1 107 Discharge casing S-1 108 Stage casing 1 160 Cover 5) 2 165 Cooling cover S-1 171.1 Diffuser 1 171.2 Last stage 1 (210) Shaft S (230) Impeller 2 (320) Contract ball bearing 5) 1 (321) Deep groove ball bearing 1 (322) Cylindrical roller bearing 2 350 Bearing housing 1 350.2 Heavy bearing housing 1 360 Bearing cover 1 360.2 Bearing cover/End side5) 1 361 Bearing cover/End side S-1 (400.2) Flat gasket 2 (400.3) Flat gasket 2 (400.4) Flat gasket 2 (400.5) Flat gasket 5) 2 (412.2) O-ring 2 (412.3) O-ring 2 (412.4) O-ring 2 (412.7) O-ring 5) 2 (422.1 Felt ring 2)
107
525.2
171.2
412.2
108
Qty. Part Designation per No. pump
1 (422.2) Felt ring 2) 2 451 Stuffing box housing 2 452 Stuffing box gland 2 458 Lantern ring 2 (461.1) Stuffing box packing 2 500.1 End ring 2) 1 500.2 End ring 2) 2 500.4 Ring Sx2 (502) Casing wearing ring 1) Sx2 503 Impeller wearing ring 1) 2 507 Splash ring 1 508 Guide bush S-1 (521) Stage sleeve 1 (524.1) Shaft protection sleeve 1 (524.2) Shaft protection sleeve 1 (525.1) Spacer sleeve 1 (525.2) Spacer sleeve 1 525.43/.8 Spacer sleeve 1 525.5 Spacer sleeve 1 (540.2) 1) Bush 1 (540.3) 1) Bush 1 (541) 1) Stage bush S-1 550 Washer 2 (52-1) Adaptor sleeve 16 636 Grease nipple 1 638 Constant level oiler 2 2 2 644 Lubricating ring 5) 1 680 Cover sheet
171.1 521
680
500.4
230
400.2
502
524.1
525.1
106
451
412.3
507
461.1
452
400.4
Basic construction WK 40 to 125
Qty. Part Designation per No. pump
2 720.3 Double nipple 2 731.2 Plug 8 901.2 Hex. bolt 4 901.3 Hex. bolt 5) 4 901.4 Hex. bolt 16 902.1 Stud 4 902.2 Stud 8 902.3 Stud 2 903.1 Plug 2 903.2 Plug 2 903.4 Plug 1 903.5 Plug 1 903.12 Plug 8 905 Tie rod 2 913 Vent plug 16 920.1 Hex. nut 16 920.2 Hex. nut 4 920.3 Hex. nut
920.4 Shaft nut 1 923 Shaft nut 5) 1 932 Circlip 3) 5) 2 7A Cooling liquid outlet
7E Cooling liquid inlet 10A Sealing liquid outlet 10 E Sealing liquid inlet 11 E Flushing liquid inlet 13 B Oil drain
( ) Recommended spare parts S Number of stages
1) Material alternative with CA6NM (special chrome steel with emergency running characteristics, approximately 14% Cr)
2) For out door execution felt ring Part No. 422.1/2 or Oil seal 421.1/2.
3) WK 150
4) Only supplied in conjunction with Part No. 230 (Impeller)
5) For heavy duty bearing construction
29
Page 31
WK
Construction with constant level oiler and bearing housing seal
913
X
500.1
422.1
WK 150 bearing construction
903.12 361 543 920.4 321 525.4 350
Constant level oiler (viewed from X)
638
350 322 360
Grease-lubricated construcion
638
731.2
Hot water stuffing box HW.
350
165
452
412.3
412.4
Construction with bearing housing seal
422.2 500.2 932
7A/7E
400.3 4003
451
524.2 (524.1)
461.1
Front end Drive end
Bearing construction incorporatingheavy-duty bearing housing WK 40 to 150
901.3 361 913 350.2 412.7 507
903.5 (13B)
412.7 644
400.5 543 901.4 160
525.8
720.3 (8B)
644 360.2
210932508320320923
525.5
902.3
Construction with CA6NM material alternative
540.2 107
503
412.2
171.2 230
400.2 108
541
171.1
521
502
106
210
540.3
Special stuffing boxes
165
452
VSM
165
452
VSH
412.3
412.3
350
350
412.4
412.4
7A/7E
400.3 4003
461.1
10A/10E
400.3 4003
458
461.1
451
524.2 (524.1)
451
524.2 (524.1)
Impeller wear rings and bushes
11E
400.3 4003
525.1525.2
165
452
412.3
350
412.4
461.1
458
451
524.2 (524.1)
30
Page 32
WK
Balancing Liquid Piping
1. Field of Application
Balancing liquid piping is a must for WL pumps. However for WK/WKS pumps balancing liquid piping is required whenever the discharge pressure exceeds 20 bar for sizes 40 to 65 and for sizes 80 to 150 when this pressure exceeds 15 bars.
2. Requirement and Connection
In case of WK/WKS pumps, the balancing of major portion of axial thrust is achieved by means of balancing liquid holes provided on each stage impeller. With this, the pressure equalization on either side of impeller is attained. Due to this, a certain quantity of liquid being pumped flows towards the pressure side, which ultimately enters the balancing chamber, formed between the walls of stuffing box housing and discharge casing. This balancing liquid quantity has to be drawn off from the balancing chamber, which otherwise will accumulate there only and hamper the performance of the pump. For this purpose a pipe line is provided, which connects this high pressure chamber to the low pressure region of suction casing (fig. A). By this the pressure relieving of the discharge side stuffing box housing is also achieved.
In case of WL pumps, the balancing of major portion of axial thrust is achieved by means of balancing device.
Pipe line size Valve Size Size of
Safety Valve
16 x 1.5 DN15
20 x 2 DN20 DN20 x 32
25 x 2 DN25
Accessory Purpose Pressure Rating
Pressure gauge Indication of 0-6, 0-10 kg/cm2
balancing line reading pressure
Check Valve Restrication of PN 40
back flow of balancing liquid
Globe Valve Isolation of PN 40
balancing piping for the purpose of maintenance
Safety Valve To safe guard the PN 40 x 10
balancing piping
Fig. A
Balancing piping
This also involves the flow of balancing liquid into the balancing chamber, which again has to be drawn off. In case of WL pumps, this piping is either connected back to the suction casing (fig. A) or to the feed water tank (fig. B) depending upon the temperature and differential head of the pumping liquid.
3. Size
The tapping size provided on the balancing chamber of discharge casing and the recommended pipe line sizes are given in the following table :
Pump Size Tapping on Pipeline size
Balancing Chamber mm
40, 50, 65 R 3/8’’ 16 x 1.5
80, 100 R 3/4’’ 20 x 2
125, 150 R 1’’ 25 x 2
4. Accessories
Whenever the balancing liquid piping is connected back to the suction casing, no accessories are required.
When this connection is given back to feed water tank (fig. C) then the following accessories are necessary.
Balancing piping from balancing chamber to suction casing
Fig. B
Balancing liquid in the deareator
Balancing piping in the feed water tank.
The sizes of the valves are to be considered as the corresponding size of the pipeline given in article 3 above.
31
Page 33
Feed water tank
Globe valve
Check valve
WK
Fig. C
Pressure Gauge
Z = End of KSB Supply
Safety valve
5. Illustrations
i) Balancing liquid fed back to suction casing. Fig. A
ii) Balancing liquid fed back to feed water tank. Fig. B
iii) Arrangement of valves in balancing line. Fig. C
6. Precautionary Notes
i) Connection of balancing liquid piping whether to
suction casing or to the feed water tank is indicated on the front page (Technical Data Sheet) of the order acceptance. This is to be strictly adhered to.
ii) Size of the balancing liquid piping should be exactly
as given in article 3 above.
iii) Whenever the balancing liquid line is fed back to
feed water tank, and if more than one pumps are operating in parallel, the individual balancing liquid lines should be independently connected to the feed water tank, without joining them together, or even putting them into a common header.
iv) The globe valve in the balancing liquid line back to
feed water tank should always remain in fully open condition, and on no account should it be closed even by accident.
v) The piping for safety valve has to be branched prior
to the check valve, so that all the further piping is safe guarded against the increase in pressure.
32
Page 34
NOTES
WK
Page 35
NOTES
WK
Page 36
NOTES
WK
Page 37
WK
Page 38
Operating Instructions
WK
Manufactured in technical collaboration with KSB Aktiengesellschaft., Germany by :
PUMPS LIMITED
Works : Telephone No. Telefax
Pimpri - Irrigation and Process Division, (020) 772008, 770990 (020) 776120
Chinchwad - Power Projects Division,
Coimbatore - Water Pumps & Valves Division, NSN Palayam Post, (0422) 892547 - 9, 892647 (0422) 892650
Vambori - Foundry Division, Ahmednagar - 413 704 (02426) 72528, 34, 50 (02426) 72443 Sinnar - Water Pumps Division, (02551) 30252, 53, 30255, 30256 (02551) 30254
Regd. Office :
Mumbai - 126, Maker Chamber III, Nariman Point - 400 021 (022) 2854237 - 42 (022) 2873299
Zonal Offices :
Mumbai - 126, Maker Chamber III, Nariman Point - 400 021 (022) 2854237 - 42 (022) 2873299 Calcutta - 30, Circus Avenue, 2nd Floor, 700 017 (033) 2470473, 2400117 - 8 (033) 2470588 NOIDA - KSB House, A-96, Sector IV, NOIDA (0118) 54091 - 93 (0118) 525627, 550567
Chennai - Guindy House, 2nd Floor, 95 Anna Salai, 600 032 (044) 2352571 - 2, 2300629 (044) 2352749
Branch Offices :
! Ahmedabad - (079) 7540428, 7543427 ! Aurangabad - (0240) 351440 ! Bangalore - (080) 3491806, 3493925 ! Baroda - (0265) 330532, 333226 ! Bareilly - (0581) 452748 ! Bhubaneshwar - (0674) 557031 ! Chandigarh - (0172) 544685, 549021 ! Durgapur - (0343) 545539 ! Guwahati - (0361) 569689 ! Hubli - (0836) 251057 ! Indore - (0731) 529478, 529704 ! Jaipur - (0141) 384121, 381206 ! Jamshedpur - (0657) 433461, 433471 ! Kochi - (0484) 394667 ! Lucknow - (0522) 213492, 274492 ! Nagpur - (0712) 535062 ! Pune - (020) 5536345, 5536347 ! Raipur - (0771) 426708 ! Secunderabad - (040) 7017696 ! Vijayawada - (0866) 433796, 433384
Service Stations :
Odhav - Shed 22, G.V.M. Estate, Amedabad 382 410 (079) 2870372 NOIDA - A - 96, Sector IV, 201 301 (0118) 91 - 525626, 550567 Howrah - 142, Foreshore Road, Ramkrishnapur (033) 6602909
Mumbai-Pune Road, Pune - 411 018
D-II Block, MIDC, Pune - 411 019 (020) 773882, 774213, 774389 (020) 770890
151, Mettupalayam Road - 641 031
Plot No. E - 3, MIDC Sinnar, Malegaon, Dist. Nashik - 422 103
Dist. Gautam Budh Nagar, 201 301
Technical matter subject to change without notice.
Page 39
Operating Instructions
0011.81 / 00 - 18 G3
WK
High Pressure Centrifugal Pumps
Works Order No. : ________________________________________________
Pump Type & Size : ________________________________________________
These operating instructions contain fundamental information and precautionary notes. Please read the
manual thoroughly prior to installation of unit, electrical connection and commissioning. It is imperative to comply with all other operating instructions referring to components of individuals units.
Loading...