KEYSTONE OPERATING AND SAFETY INSTRUCTIONS
CheCk ValVes
Before installation, these instructions must be fully read and understood
PRECAUTIONS
WARNING
For safety reasons, it is important to take the following precautions before you start work on the valve:
1. Personnel making any adjustments to the valves should utilize suitable equipment. All required personal protection means should be worn.
2. The line must be depressurized before installing the valve. In case of dangerous pipeline fluids, the pipeline should be drained and flushed properly with an appropriate cleaning fluid.
3. Personnel trained in all aspects of manual and mechanical handling techniques must carry out handling of all valves.
4. Misuse of the valve is not allowed. For example: the valve, handles, actuators or other
Hazard potentials
• disregarding of instructions
• improper use of product
• insufficiently qualified personnel
Ensure that valve materials are compatible with the pipeline fluid.
Valve application to be within the pressure/ temperature limits indicated in the P/T diagram of the Product Manual.
parts may not be used as “climbing tools”.
5. Ensure the valve pressure/temperature specification as indicated on the identification label, is within the pressure/temperature limits of the application. A full pressure/ temperature diagram can be obtained from the Product Manual. With the use of the figure and trim number on the valve’s identification label, the correct diagram can be found.
6. Ensure that valve materials are compatible with the pipeline fluid.
If in doubt contact factory.
Check the valve’s functionality on a regular basis.
When the valve is used in an end-of-line function, PED Cat-I applications are allowed only. For other categories, contact factory.
www.valves.emerson.com © 2017 Emerson. All rights reserved.
7 m o
VCOSI-00762-EN 15/06
KEYSTONE OPERATING AND SAFETY INSTRUCTIONS
CheCk ValVes
INSTALLATION
1. Handling and lifting should be performed according the Maintenance & Installation Instructions.
2. Keystone valves are bi-directional unless fitted with a Flow Direction Arrow. If a directional arrow is fitted then the valve must be installed with the arrow pointing in the direction of the flow.
3. For detailed installation instructions refer to the Installation & Maintenance Instructions for the specific product.
4. Check valves have to be mounted in horizontal pipelines with hinge point on topside. SeeInstallation & Maintenance Instructions for alternative pipeline directions.
5. Do not use the valve to spread the flanges.
6. Do not use flange gaskets.
7. In case the valve is used as spool piece during erection of piping, do not finish weld the flanges to the pipes with the valve bolted between the flanges as this will result in serious heat-damage to the seat.
8. Valve operation should be checked for open - close positions. The disc should have enough clearance from the pipeline in all positions.
MAINTENANCE
!! Read all warning labels fitted to the valve before operation or maintenance !!
Check the valve’s functionality on a regular basis. No additional routine maintenance is required.
REPAIR
WARNING
The line must be depressurized before carrying out any repairs to the valve. In case of dangerous pipeline fluids, the pipeline should be drained and flushed with an appropriate cleaning fluid. Failure to do so may cause serious personal injury and/ or equipment damage. Before disassembling the valve ensure the valve has been decontaminated correctly from any harmful gasses or liquids and that it is within a safe temperature range for handling. Personnel making any adjustments to the valves should utilize suitable equipment. All required personal protection means should be worn. Only qualified personnel trained in all aspects of manual and mechanical handling techniques must carry out lifting and handling of valves. Use Keystone original spare parts only. For detailed information on valve (dis)assembly and part replacement, refer to the Maintenance & Installation Instructions.
TAGPLATE
Year of construction/ JOB number
Temperature
Product designation
Nominal diameter
Body material of construction
Trim number
Mass
Max. permissible working pressure
Flange
compatibility
(drilling)