When using electrical equipment, basic safety precautions
should always be followed, including the following:
THIS PRODUCT MUST BE INSTALLED IN ACCORDANCE WITH THE
APPLICABLE INSTALLATION CODE BY A PERSON FAMILIAR WITH
THE CONSTRUCTION AND OPERATION OF THE PRODUCT AND
THE HAZARDS INVOLVED. DISCONNECT POWER TO ALL CIRCUITS
BEFORE WIRING FIXTURE. INSTALL IN ACCORDANCE WITH
ALL NATIONAL, STATE, AND LOCAL CODES. DO NOT CONNECT
TO AN UNGROUNDED SUPPLY. READ ALL FIXTURE MARKINGS
AND LABELS TO ENSURE CORRECT INSTALLATION OF FIXTURE.
SUPPLEMENTAL INSTRUCTIONS MAY BE LOCATED ON THE
FIXTURE, IN ADDITION TO THIS INSTRUCTION SHEET, REGARDING
ORIENTATION, OR MOUNTING RESTRICTIONS.
SAVE THESE INSTRUCTIONS
1
INSTALLATION INSTRUCTIONS
Install in compliance with the National Electric Code, any applicable local codes and any specic instructions given
on the luminaire labels. If installing in conjunction with any additional options and/or accessories, also refer to the
respective instruction sheets. For installation only by a qualied electrician.
NOTE: To maintain the ratings and approvals noted on the xture nameplate, any ttings or mounting hardware
supplied with this xture, must be used with this xture.
SURFACE MOUNTED FIXTURES
1. Use mounting hardware (if provided) to secure the xture to its location. If no hardware is supplied, any
appropriate hardware can be used.
2. Fixtures with external mounting tabs must be mounted using all tabs.
www.kenall.com | P: 800-4-Kenall | F: 262-891-9701 | 10200 55th Street Kenosha, Wisconsin 53144, USA
1. To ensure an adequate seal between the ange
and the ceiling system, it is important to have a
square opening and a at ceiling surface. When
gypsum is used as the base material it should
have adequate thickness to resist bowing.
See appropriate specication sheet or contact
Kenall directly for recommended ceiling cutout
dimension. The cutout opening should be
accurate to within a 1/16 of an inch.
2. Framing around the entire opening is
recommended and should start at the rough opening. Typically, “C” shaped 16 gauge galvanized cold rolled
channel used to frame the opening because of its straightness.
3. Gypsum board shall be secured to the framing material around the opening. The ceiling surface around the
opening shall be at and smooth and not run (deviate from a straight edge) more than 1/32 inch over 2 feet.
The opening should always be cut into whole pieces of gypsum. Ceiling seams and joints shall be outside of
xture cutouts. Framing members running under the gypsum shall be whole pieces around the cutouts and run
the length of the cutout, not just under the yoke bracket.
2
4. After creating the rough opening, frame the opening on the plenum side of the ceiling.
5. The yoke will span the width of the rough cutout and must be secured to C channel or framing material. Fasten
the carriage bolt to the yoke with the nut in the hardware bag. Then, locate and secure the yoke bracket to
the “C” channel, located so that the carriage bolts will engage the holes in the housing when the xture is
installed.
6. Connect the appropriate exible raceway system to the wiring access hole and raise the xture into
the opening.
7. Apply a bead of caulk to the ceiling side of the housing ange, to seal the xture housing to the ceiling. All 4
bolts will pass into the housing. Attach neoprene washer (if supplied), nylon washer and nut to the bolt to hold
the housing in place.
8. Tighten all 4 nuts until xture is rmly seated in the cutout.
RECESSED GRID FIXTURES
1. Fixture is designed for use with 1.00"/1.50" T bar grid systems with vertical grid T thickness’ of less than ¼"
with a maximum height of 2". Grid systems can be installed with standard 12, 24 or 48 inch center line spacing
of grid.
2. Fixture housing lays into grid.
www.kenall.com | P: 800-4-Kenall | F: 262-891-9701 | 10200 55th Street Kenosha, Wisconsin 53144, USA
1. Line up ceiling support channels (by others), with inside surface of ceiling cutout then secure.
2. Dimensions shown in view indicate center point location of yoke assembly in relation to ceiling opening.
Fastening device used will determine if and what size holes are needed. (By others).
www.kenall.com | P: 800-4-Kenall | F: 262-891-9701 | 10200 55th Street Kenosha, Wisconsin 53144, USA
1. After carriage bolts have been set to proper height dimensions, and center points have been located in ceiling
supports, attach yoke assembly (yoke/support attach hardware by others.
2. Refer to the chart below and locate the appropriate “A” dimension. This dimension is the amount of the
threaded bolt required to secure the xture.
WIRING INSTRUCTIONS
1. Read all xture markings and labels to insure correct installation of the xture. Additional information may be
located on the xture, separate from this instruction sheet, regarding orientation and mounting restrictions.
2. Disconnect power to main circuits before wiring xture.
3. Undo center reector and wire way cover to gain access to the inside of the xture (also refer to next page for
diffuser operation).
4. Attach conduit to wiring hole.
5. Connect xture leads to power supply leads using connectors suitable for the gage and number of wires being
used (not included). Connections are to be made in the junction box, not the xture. Black and other colored
wires connect to the supply conductor, white xture lead connects to the neutral supply conductor, and the
grounding wire must be connected to a suitable ground.
6. Fasten wire way cover and center reector.
www.kenall.com | P: 800-4-Kenall | F: 262-891-9701 | 10200 55th Street Kenosha, Wisconsin 53144, USA