Jandy Deck Jet Installation Manual

Installation Instructions
Jandy® Sheer Descent
Installation Manual
THIS UNIT MUST BE INSTALLED ACCORDING TO THE MANUFACTURER'S INSTALLATION
INSTRUCTIONS. PLEASE READ AND FOLLOW ALL INSTRUCTIONS. PLEASE SAVE THESE
INSTRUCTIONS.
This manual provides easy reference illustrations to help you identify each part of the Sheer Descent Waterfall. Use this manual to guide you through the routine procedures and adjustments for a trouble free installation. These instructions were developed with the aid of experienced contractors and has proven to be a simple, yet consistent and trouble free, method of installation.
During all phases of the installation, care should be taken not to damage the Sheer Descent Waterfall. Keep the unit in the original packaging until the site is prepared for permanent installation.
The Sheer Descent Waterfall is available in standard sizes from eight inches to eight feet in length and is shipped complete with safety tongue installed in the opening of the waterfall. See figure 1. The protective tongue keeps the spillway opening clean and damage free. DO NOT REMOVE THE TONGUE until the start up of the pool equipment. The safety tongue must be left in the opening during the entire installation, or damage to the unit, which would effect its ability to perform, may occur.
Tongue (Do not remove prior to start-up)
Figure 1
EXCAVATION & STEEL MODIFICATIONS
It is recommended that the area designated for the Sheer Descent Waterfall be marked off with colored stakes, yellow construction ribbon, or similar material during the framing process, prior to excavation. In preparation for the installation of the steel rebar, mark the EXACT area designated for the Sheer Descent Waterfall. To allow room for notching the bond beam and installing the unit, offset the steel pattern by 3 inches below the original form and 1 inch on both ends of the Sheer Descent Waterfall. For example, if the Sheer Descent Waterfall is 4 feet in length, offset the steel pattern to measure 3 inches down from the top of the frame and 50 inches in length (this allows 1 inch of space on each side of the Sheer Descent unit). See figure 2.
Steel off set
Figure 2
Note: Notching of the bond beam is the next step in the process. The change to the steel will make the notch a simple procedure.
3½" wide x 3½"
deep notch
Finished notch in beam
2½"
Top of raised bond beam
Page 2
Feet of Elevation
Feet of Projection
Gallons per minute per foot
Guideline is for 1ft. to 4ft models
7
1
2
3
12
9101215 20
Manifold
Rock trap
Sheer Descent Waterfall back feed plumbing for 6, 7, & 8 ft. lengths.
Beam
Center
CONCRETE INSTALLATION AND MODIFICATIONS
As the concrete installation (or similar process) nears completion, a notch must be cut into the inner edge of bond beam in the same area at which the steel was offset to allow for the installation of the Sheer Descent Waterfall. See figure 3.
CUTTING THE BOND BEAM
FOR SHEER DESCENT WATERFALL SIZES 8" THROUGH 5'
Select the EXACT location for the Sheer Descent Waterfall. The notch in the bond beam should be cut 3½" deep by 2½" wide and 2" longer than the length of the proposed Sheer Descent Waterfall (1" per side). For example, if a
Tile
4' model is to be installed, the notch length should be 50" (48" + 1"+ 1" = 50"). In addition, mark a single slot on the top of the beam in the center of the proposed notch
Tongue
3½" wide by 3½" deep. The notch will be used to plumb 1½" pipe to the Sheer Descent Waterfall. Mark the bond beam and proceed with cutting the beam.
FOR SHEER DESCENT SIZES 6', 7', AND 8'
Mark and cut the beam as instructed previously, with the exception that two notches are required on the top of the beam for piping. Longer waterfalls require more water; consequently, two plumbing lines are required. The top of the beam should be marked for these units as follows: NOTE: These measurements are from the center of the Sheer Descent
Waterfall unit.
3½" wide x 3½" deep notch
2½"
3½"
Figure 3
Length Plumbing Location 6 foot 1 foot 6 inches to the right and to the left from the center line 7 foot 1 foot 9 inches to the right and to the left from the center line 8 foot 2 feet to the right and to the left from the center line
The notches should be 3½" wide by 3½" deep. See figure 4.
MAKE SURE THE CUTS IN THE BEAM ARE PROPERLY COMPLETED BEFORE PROCEEDING.
PUMP SIZING AND INSTALLATION OPTIONS
One of the advantages of the Sheer Descent Waterfall is the ability to provide a continuous sheet of water with a minimum of water flow. A standard four foot model, for example, requires only 40 gallons per minute to operate. In order to size your pump properly, refer to the Water Flow Requirement Chart. In most cases, a properly sized standard swimming pool pump will operate the Sheer Descent Waterfall and filter the pool with little loss of total water turnover. As a general rule of thumb, the Sheer Descent waterfall requires approximately 10 gallons per minute per foot with little head loss. For more a dramatic effect, more water gallonage can be applied to project the waterfall further away from the wall. NOTE: When plumbing multiple falls, add the total length of waterfalls together to determine GPM required. e.g. When plumbing two (2) 6' units, you now have 12' of waterfall, which requires 120 gallons per minute.
Figure 4
EXISTING POOL FILTER PUMP INSTALLATION
The installation of the Sheer Descent Waterfall using the main pool filter pump is the most common plumbing system, due to the unique low flow aspect of the waterfall system. Simply plumb a three way valve on the return line, after the filter, and plumb the waterfall feed line in a minimum of 1½" PVC schedule 40 pipe. Units above 5' in length need a minimum of 2" plumbing.
Page 3
SEPARATE PUMP FOR THE SHEER DESCENT WATERFALL
If multiple waterfalls are being installed, or a Sheer Descent Waterfall 6' or longer is being installed, we
Cantilever edge
recommend installing a separate pump. When plumbing a pump dedicated for use by the Sheer Descent, a separate suction line to the pool must be
Sheer Descent unit
Tile
plumbed. This should be plumbed in a minimum of 2" schedule 40 pipe.
Water line
NOTE: At least one anti-vortex safety suction cover must be installed at pool side as a safety precaution. The anti-vortex suction cover is recommended to be positioned 18 inches above
Anti vortex cover
the floor of the pool.
Next, a Sheer Descent filter/strainer (part #3456), or equivalent, must be installed on the return side of the pump, between the pump and the Sheer Descent Waterfall. A FILTER IS REQUIRED for separate pump installations, as large debris must not be allowed to enter the Sheer Descent unit. For installations requiring up to 60 gallons per minute, use one Sheer Descent filter. For higher water requirements, use two or more filters plumbed in parallel. A separate return line, with a three way valve plumbed in such a way that water can be balanced between the Sheer Descent Waterfall and return back to the pool, is also required. See figure 5.
Conventional concrete decking
Suction line
Figure 5
Rock trap
Separate return to pool
Jandy three way valve
Sheer Descent filter/strainer
Filter pump
PLUMBING THE SHEER DESCENT WATERFALL
WATERFALL RETURN LINE PLUMBING
The waterfall feed line, from either the main filter pump or a separate pump, should be plumbed in a minimum of 1½" PVC pipe. NOTE: Two inch plumbing or larger is suggested for waterfalls over 5 feet in total length. Refer to Hydraulic Guideline Chart for specifications. The feed line should end near the back of the bond beam near the center of the waterfall location.
It is important to have a valve located in a convenient location on the feed line to regulate the flow of water to the Sheer Descent Waterfall. A Jandy three-way valve is suggested to be used as the "T" from the return line of the pool to the Sheer Descent Waterfall. A properly plumbed valve in that position will allow full control of the water to the Sheer Descent, as well as to the rest of the pool. In most cases, this valve can be located after the filter near the equipment pad. See figure 6.
NOTE: All water to the Sheer Descent must be filtered. Those systems using a separate pump must use our separate filter (part #3456) to prevent debris from entering the Sheer Descent unit.
Figure 6
Return to pool
Jandy three
Filter
way valve
Pump
Suction from pool
Rock trap
Water to sheer descent
H YDRAULIC GUIDELINE CHART
•Use minimum of 1½" pipe.
•Use minimum of 2" pipe for runs in excess of 60
feet or if Sheer Descent unit is over 5 feet.
•Dedicated plumbing lines are recommended.
•Maximum recommended flow for a typical installation: 1½" pipe for 60 GPM
2" pipe for 100 GPM
2½" pipe for 140 GPM
3" pipe for 225 GPM
Typical pump performance at 50 Feet of head
½ HP = 26 GPM ¾ HP = 58 GPM
1 HP = 68 GPM
1½ HP = 93 GPM
2 HP = 106 GPM 3 HP = 140 GPM
Loading...
+ 5 hidden pages