1
. GENERAL INFORMATION…………………………………………………………………..3
1.1 Introduction………………………………………………………………………………........3
1.2 Warranty……………………………………………………………………………………….3
2. BOX DESCRIPTION AND TECHNICAL SHEET…………………………………………..4
2.1 General description……………………………………………………………………………4
2.2 Components……………………………………………………………………………………5
2.3 Fabric’s characteristics………………………………………………………………………..7
3. INSTALLATION…………………………………………………………………………..........8
3.1 Handling and transport…………………………………………….......................................8
3.2 Place and requirements for the installation………………………………………….….…..8
3.3 Installation………………………………………………………………………………..…….9
3.3.1 Package opening……………………………………………………………………..….….9
3.3.2 Box installation…………………………………………………………………………… ...9
4. BOX UTILIZATION……………………………………………………………………………11
5. CHECKS AND MAINTENANCE……………………………………………………….........12
6. DISASSEMBLY………………………………………………………………………………..12
3
1. GENERAL INFORMATION
1.1. Introduction
This manual is an integral part of the product; it is addressed to the installer and to the final user of t
he box, and enables a correct installation and use. For this reason it must be hold with the box until proper disposal. In this manual you will find the instructions to:
correctly install the box
understand the functions of the box and of every of the whole thereof
correctly do the box scheduled maintenance processes
take care of the basic safety rules
ATTENTION: the installer and the final user must read the whole manual, and store it together with the box. Before using the box, please read carefully the technical information contained in this manual and follow them strictly. Keep this manual in a safe and accessible place.
1.2. Warranty
INTENDA S.r.l. gives a 5 years warranty. D
uring this period INTENDA S.r.l. will remove in an appropriate time all vices and defects of the
materials and/or of the building process, only if the box:
has been installed by qualified workers
has been used correctly, following the conduct and maintenance indications contained in
this manual
has not been subjected to natural disasters
To remove the defects found out during the warranty time:
the costs of working time and transport are at the expense of the dealer
the costs of spare parts are at the expense of INTENDA S.r.l.
Warranty is meant to be ex works Legnago (VR). All the tools and optional parts eventually supplied by the dealer are not subject to the warranty. In the box building process INTENDA S.r.l. uses materials and mechanisms of suitable type, state and quality, at its own discretion; even after the receipt of the order, INTENDA S.r.l. can make substantial changes or appropriate improvements at its own discretion. Slight colour differences, folds or “partridge’s eyes” in the PVC clothes should not be considered defects, but features of the article.
4
2. BOX DESCRIPTION AND TECHNICAL SHEET
2.1. General description
T
he box must be used only as an ordinary protection cover, for purely temporary use. In case of bad weather conditions (wind, snow), the box must be removed. Given that the box cannot be fixed to the ground - but only bound to it - its use in these conditions can cause damages to people and things. It is particularly important for safety not to hang or apply any type of load at the structure or at the top cover of the box. In particular, children must not handle the snails. The failure to respect the conditions of use and warnings immediately voids the warranty.
BOX TUNNEL / BOX TUNNEL €CO
STADIO BOX
A
(cm)
:
412/515/618/721/824/…
B (cm): 250/280/300
C (cm): 185/200/205
A (cm)
:
412/515/618/721/824/…
B (cm): da 150 a 300
D (cm): da 180 a 240
5
NB. Starting from the length (A) of cm 700 (only for mobile version): eyelets placed on the lateral profile for ground-fixation through straps and stakes/ballasts (not supplied by Intenda)
2.2. Components
N
. DESCRIPTION
1 ALUMINIUM PROFILE MM 40x35
2 PVC LG 550/STARPOL ECO TOP COVER
3** WINDOW IN MICRO-PERFORATED MATERIAL
4** PVC GABLE END WITH WINDOW IN MICRO-PERFORATED MATERIAL
5* PVC BUCKLE
6* STRING FASTENER HANDLE IN PVC
7* NYLON STRING DIAM. MM 5
8* GROUND-FIXING BRACKETS (base v.), CARABINER (mobile v.)
9 CROSSES CM 120X120 (in the mobile v. includes also tension bar)
10* TENSION BARS
11* PVC SLIDING CURTAIN
12* PVC WALL WITH WINDOW IN MICRO-PERFORATED MATERIAL
13* ALUMINIUM CROSSBEAM
14* GROUND-FIXING BRACKETS* (base v.), NYLON WHEELS (mobile v.)
*Only for Box Tunnel and Box Tunnel Eco *Only for Box Tunnel
7
2.3. Fabric’s characteristics
P
OLY LG 550/LAC 2L FLAME-RETARDANT
BOX TUNNEL – STADIO BOX
Yarn W
arp: 100% PES 1100 Dtex
Weft: 100% PES 1100 Dtex
Fabric’s weight 550 gr/m2
C
haracteristics ABUV
Finishing gloss lacquered
Breaking strength Warp: ca 250 DaN/5 cm (DIN 53354) Weft: ca 180 DaN/5 cm
Tear strength Warp: 25 DaN (DIN 53363) Weft: 20 DaN
Grip (IVK/PKT 14) 10 DaN/5 cm
Temperature resistance +70° C/- 30° C
Light resistance (DIN 53388) Level: 7/8
Fire-proofing ADR cl. II
8
STARPOL ECO
BOX TUNNEL ECO
Yarn W
arp:100% PES/1100 Dtex
Weft:100% PES/1100 Dtex
Fabric’s weight Ca 610 gr/m2
F
inishing PVC coated
Breaking strength Warp: ca. 235 DaN/5 cm (DIN 53354) Weft: ca. 220 DaN/5 cm
Tear strength Warp: ca. 23 DaN (DIN 53363) Weft: ca. 22 DaN
Grip (DIN 53357) 9 DaN/5 cm
Temperature resistance +70° C /- 30° C
3. INSTALLATION
3.1. Handling and transport
The box installation should only be done by qualified staff. T
he products must be unloaded through appropriate lifting equipment, which must be used only by authorized staff. If the unloading operation is made by hand, it is important to consider that the weight limit that each male person can handle is 25 Kg; moreover, the operators should be equipped with gloves and safety shoes.
3.2. Place and requirements for the installation
Before the arrival of the installers the user must arrange:
any permits required by local regulations
appropriate ground
12
5. CHECKS AND MANTAINANCE
It is necessary to periodically check the general status of the structure, of the links between co
mponents, of the hinges and the top cover. In case of holes or tears in the fabric, damages or
cracks of metal components, it is necessary to contact the d
ealer.
The top cover can be washed with neutral detergent and then rinsed with water. After cleaning, the
fabric must be dried before being folded, in order to prevent mold.