Indeeco ZCA Series, XCA Series, TFZCA Series, TFXCA Series, ZCBA Series Installation, Operating And Maintenance Instructions

...
INSTALLATION, OPERATING AND MAINTENANCE INSTRUCTIONS FOR INDEECO ELECTRIC DUCT HEATERS
APPLICATION INFORMATION
1. Follow the procedure given on the reverse side of this sheet to find the minimum air velocity for safe operation. At least this minimum velocity must be provided at all points over the heater face area. Failure to meet this requirement may result in serious damage or nuisance thermal cutout tripping.
2. The maximum air inlet temperature for open coil heaters is 100F (37.8C), and for finned tubular heaters, 80F (26.7C).
3. The heater must be located at least 4’ (1220mm) from any grills, registers, filters, abrupt duct size changes, humidifiers, air conditioning or air handling units, or any other change or obstructions in the duct which may result in nonuniform airflow,
and not less than 30” (762mm) from the end of the warm air duct. Duct elbows or turns must be located at least 4’ (1220mm) from the inlet of the heater and 2’ (610mm) from the outlet of the heater.
Sufficient working space must be provided per paragraph 2-308 of the Canadian Electrical Code.
4. These duct heaters are not intended for installation in series in the airstream; the heaters are designed for use only as a single unit within a duct with the exception of Series ZCA, XCA, ZCBA, XCBA, TFZCA, TFXCA which are designed for stacked installation for use as a single unit within a duct. (See Fig. No. 3)
MECHANICAL INSTALLATION
1. Heater terminal outlet box should not be enclosed. Heaters with expanded metal terminal box covers must be installed in a position where air passing out of the terminal box does not enter into confined areas of the building structure (such as a space behind a false ceiling, a hollow space in a wall, etc.)
2. All heaters are suitable for installation with zero spacing between the duct and combustible surfaces.
3. The heater must be installed in the correct position as shown by the arrows in the terminal box.
4. Sufficient clearance for convection cooling must be allowed for all heaters with built-in SCR Power Controllers. Provide at least
5” (127mm) of free air space above and below cooling fins
extending from heater terminal box.
5. For proper operation of heaters equipped with a built-in airflow switch, a minimum of .07” (1.8mm) WC of static pressure is required in the duct system, and the velocity pickup tube for the airflow switch must be pointed in the proper direction. When the heater is installed on the downstream or positive pressure side of the air moving fan, the arrow on the mounting flange of the pickup tube must point in the same direction as the airflow. When the heater is installed on the upstream or negative pressure side of the air moving fan, the arrow must point in the direction opposite to the airflow. If incorrectly installed, remove the two screws holding the pickup tube in place, rotate 180 and reinstall. See separate instruction sheet for installation of heaters supplied with a remote pickup tube.
FOR FLANGE TYPE HEATERS ONLY: (See Fig. No. 1)
6. Provide flanges on the duct to match the heater flanges, both on the entering and leaving air sides.
7. Attach the duct flanges to the heater flanges with bolts, sheet metal screws or slip and drive connectors when the heater has matching connectors for this purpose.
FOR SLIP-IN TYPE HEATERS ONLY: (See Fig. No. 2)
8. Cut a hole in the side of the duct to accommodate the body of
the heater (excluding terminal box). This hole should be 1/8”
(3.175mm) larger than the heater frame.
9. Slip the heater into the duct and attach the back of the terminal box to the duct with sheet metal screws.
10. If heater has built-in PE switches they must be calibrated to field control system. Calibrate the PE switch marked No. 1 to come on first.
FOR STACKED TYPE HEATERS ONLY: (See Fig. No. 3)
11. The heaters with catalog prefix ZCA, XCA, ZCBA, XCBA, TFZCA and TFXCA must be stacked as indicated in Fig. No. 3.
FOR HEATERS TO BE INSTALLED IN FIBERGLASS DUCTS:
12. Write factory for special instructions. Note that the fiberglass duct material itself must be CSA approved.
FOR HEATERS TO BE INSTALLED IN INTERIOR INSULATED DUCTS:
13. All slip-in type heaters are suitable for installation in ducts with up to
1” (25.4mm) of interior insulation as long as they have been sized for the
dimensions inside the insulation. The heaters are not suitable for
insulation depths of greater than 1” (25.4mm) unless a special construction
has been ordered. Flange type heaters are only suitable for installation in insulated ducts if specially ordered for this application.
ELECTRICAL INSTALLATION
14. Follow the wiring diagram on the inside of the terminal box.
15. Supply connections must be made with copper wiring rated 90C minimum. Use aluminum wire only when specifically called for on accompanying wiring diagram.
16. All wiring in the terminal box must be insulated for 600 volts.
17. When making line connections to heater element terminals FOR
FINNED TUBULAR DUCT HEATERS ONLY, apply a ¼” wrench to flat
section of terminal or nut immediately below threads. Otherwise damage to terminal may result.
18. Line connection should be based upon the line current and the requirements of the Canadian Electrical Code. The line current for either a single or three phase load is calculated as follows:
Single Phase Line Current=
KW x 1000
Voltage
Three Phase Line Current=
KW x 1000
Voltage x 1.73
19. Supply wiring must be suitable for 90C. Subject to local inspection authority, current carrying capacity of supply wiring should not exceed values shown in the Canadian Electrical Code Table 2, Col. 90C for not more than three conductors in a raceway, in a 30C ambient or as specified on the wiring diagram.
20. When connecting heaters with more than one stage, wire stage No. 1 so that it is the first stage on and the last stage off. Heaters with built-in PE switches must follow this rule also. The stage number will be indicated on the front of each PE switch.
continued installation etc.
21. The heater must be wired so that it cannot operate unless air is flowing over it. This can be accomplished by using a built-in airflow switch, a built-in fan relay or any of several other methods. See the accompanying wiring diagram for the method used with this heater and provide appropriate interlock wiring as illustrated.
22. The steady-state control circuit load must not exceed the thermal cutout pilot duty rating shown on the heater nameplate.
23. When heater is not supplied with built-in fusing, fuses must be installed in accordance with the requirements of the Canadian Electrical Code.
24. If not supplied as part of this heater, install a line disconnect switch or main circuit breaker in accordance with the Canadian Electrical Code.
Depending upon the heater’s location
and accessibility, a built-in disconnect switch may meet this requirement.
25. All electrical connections in the heater, including both field and factory made connections, should be checked for tightness before operating the heater. In addition, after a short period of operation, all connections should
again be checked for tightness.
26. If heater is wired to a heating­cooling thermostat, use the thermostat with isolating circuits to prevent possible inter-connection of Class 2 outputs.
27. Magnetic contactors when used in the primary limit control circuit of this heater must be CSA approved for 250,000 cycle operation. Contactors used in the secondary limit control circuit on heaters rated 30 KW and less must be CSA approved for 6,000 cycle
operation.
28. If heater frame is smaller than the
duct by more than 1” (25.4mm) in length
or width, the watts per square foot of duct area should be calculated as the heater nameplate watts divided by the area inside the sheet metal enclosure directly around the heating elements.
OPERATION & MAINTENANCE
NOTICE: ALL SOURCES OF SUPPLY MUST BE DISCONNECTED BEFORE WORKING ON THIS EQUIPMENT
To operate this heater make sure all associated control equipment is on, energize main supply disconnect and set controlling thermostat above ambient temperature. This heater is equipped with automatic and manual reset temperature limit controls. If it fails to operate, make sure manual resets are operative by pushing reset buttons.
Note: All metric conversions are approximate.
The only routine maintenance required is to check all electrical connections, including field and factory made connections, for tightness at least once each year or operating season. In addition, of course, any filters in the airstream must be kept clean so that adequate airflow is maintained.
INDUSTRIAL ENGINEERING & EQUIPMENT COMPANY
425 Hanley Industrial Court St. Louis, MO 63144 USA (314) 644-4300 FAX (314) 644-5332
ENM - 2077 – 01 / 10-1081-83-4EF
INSTALLATION DRAWINGS
AIR FLOW REQUIREMENTS
Calculate watts per square foot of duct area as:
Heater nameplate watts
(See #28)
Duct area (Sq.Ft.)
Fig. 1 – Installation drawing of flanged heater.
Fig. 2 – Installation drawing of slip-in heater.
Fig. 3 – Installation drawing of two stacked sections in a duct.
Loading...
+ 2 hidden pages