International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
2
www.iec-okc.com
Page 3
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
Table of Contents
4 SECTION 1 – Introduction
4 Safety
5 SECTION 2 – Pre-Installation
Unpacking and Inspection
5 Prepare Jobsite for Unit Installation
5 Identify and Prepare Units
5 Protect Units from Damage
7 SECTION 3 – Installation
7 Place Units In Position
8 Cooling/Heating Pipe Connections
9 Field Piping Connections
10 Steam Drain Connections
10 Leak Testing
10 Refrigerant Coil Testing
10 Piping Insulation
10 Condensate Drain
11 Electrical Connections
12 Factory Installed Options
12 Condensate Overow switch
12 Standard Wiring Packages
15 Connecting Ductwork
16Exposed Unit Finish Touch-up and Repaint
16Make Final Preparations
16 SECTION 4 – Startup
17 Cooling/Heating System
17 Air Balance System
17 Water Balancing System
18 Water Treatment
18 Eco-telligent® Motor
19 Controls Operation
19 SECTION 5 – Service/Maintenance
General
19 Motor/Blower Assembly
20 Coil
20 Electric Resistance Heater Assembly
20 Electrical Wiring and Controls
21 Valves and Piping
21 Filters, Throwaway
21 Filters, Permanent
21 Drain
21Replacement Parts
23SECTION 6 – Equipment Startup Check List
23Receiving and Inspection
23Handling and Installation
23Cooling/Heating Connections
23Ductwork Connections
23Electrical Conditions
23Unit Startup
International Environmental Corporation (IEC) works continually
to improve its products. As a result, the design and specications
of each product may be changed without notice and may not be
as described herein. Please contact IEC for information regarding
current design and product specications. Statements and other
information contained herein are not express warranties and do not
form the basis of anybargainbetween the parties butare merely IEC’s
opinion or commendation of its products. Manufacturer’s standard
limited warranty applies.
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
23 Motor
24Appendix A
25Appendix B
www.iec-okc.com
Adjustment of ICM AW4105
Adjustment of EVO/ECM-4SPD
3
Page 4
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
SECTION 1 – Introduction
International Environmental Corporation (IEC) fan coil
units represent a prudent investment oering troublefree operation and long service with proper installation,
operation, and regular maintenance. The equipment
covered by this manual is available with a variety of
options and accessories. Always consult the approved unit
submittals, order acknowledgement, and other manuals
for specic details on unit options and accessories. Always
follow proper procedures related to safety, handling,
installation, operation, and servicing of mechanical
equipment as the manufacturer assumes no responsibility
for personal injury or property damage resulting from
improper or unsafe practices during the handling,
installation, service, or operation of any equipment.
Safety
IEC equipment is initially protected under the
manufacturer’s standard warranty; however, this
warranty is provided under the condition that the
steps outlined in this manual for initial inspection,
proper installation, commissioning, regular periodic
maintenance, and everyday operation of the
equipment be followed in detail. This manual should
be fully reviewed and understood in advance of initial
installation, startup, and any maintenance. Should
any questions arise, please contact your local Sales
Representative or the factory BEFORE proceeding.
Install approved Lock-Out/Tag-Out protection devices
on ALL incoming power sources to equipment being
installed or serviced prior to beginning any work. Always
verify all incoming power sources are de-energized
using an electrical multi-meter.
CAUTION: Never wear bulky or loose tting
clothing when working on any mechanical
equipment. Gloves should always be worn for
protection against sharp sheet metal edges, heat, and
other possible injuries. Safety glasses or goggles should
always be worn, especially when drilling, cutting, or
working with refrigerants, lubricants or cleaning chemicals.
WARNING: Never pressurize any equipment beyond
specied test pressures listed on the unit rating plate.
Always pressure test with an inert uid or gas such as clear
water or dry nitrogen to avoid possible damage or injury
in the event of a leak or component failure during testing.
CAUTION: Always protect adjacent ammable
material when welding or soldering. Use a
suitable heat shield material to contain sparks or
drops of solder. Have a re extinguisher readily available.
CAUTION: Always protect chilled and hot water
valve bodies, strainers, ball valves, and other
ow control related devices from heat caused
by soldering or brazing processes by wrapping these
devices in cold or damp rags.
WARNING:NO ATTEMPT SHOULD BE MADE TO
HANDLE, INSTALL, OR SERVICE ANY UNIT WITHOUT
FOLLOWING SAFE PRACTICES REGARDING
MECHANICAL EQUIPMENT.
The equipment must always be properly supported. Temporary supports used during installation or service must be adequate to hold the equipment securely.
CAUTION: All power must be disconnected before any installation or service is attempted.
More than one power source may be supplied to a unit. Power to remote mounted control devices may not be supplied through the unit.
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
4
Safety should always be the rst priority when handling,
installing, operating or servicing mechanical equipment.Always follow all safety codes, procedures and protocols.
Consult applicable local building codes and National Electrical Codes (NEC) for special requirements. Be alert to safety information: symbols, words such as DANGER, WARNING and CAUTION.
Improper installation, adjustment, service, maintenance, or use can cause explosion, re, electrical shock, or other conditions, which may result in personal injury or property damage. This product must be installed only by personnel with the training, experience, skills, and applicable licensing that makes him/her “a qualied professional HVACR installer.”
www.iec-okc.com
Page 5
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
SECTION 2 – Pre-Installation
Unpacking and Inspection
All units are carefully inspected at the factory throughout
the manufacturing process under a strict detailed quality
assurance program. All major components and subassemblies are carefully tested for proper operation
and veried for full compliance with factory standards.
Operational testing of some customer-furnished
components such as DDC controls, pneumatic control valves
and switches may be a possible exception.
Each unit is carefully packaged for shipment to avoid
damage during normal transit and handling. Equipment
should always be stored in a dry and covered place, and in
the proper orientation as marked on the carton.
All shipments are made F.O.B. ex-factory and it is the
responsibility of the receiving party to inspect the
equipment upon arrival. Any obvious damage to the
packaging and/or its contents should be recorded on the bill
of lading and a claim led with the freight carrier.
Where local repairs or alterations can be accomplished, the
factory must be fully informed of the extent and expected
cost of those repairs before work is begun. Where factory
operations are required, the factory must be contacted
for authorization to return equipment and a Return
Authorization Number will be issued. Unauthorized return
shipments of equipment and shipments not marked with
an authorization number will be refused. In addition, any
claims for unauthorized expenses will not be accepted by
the manufacturer.
Prepare Jobsite for Unit Installation
To save time and to reduce the possibility of costly errors,
set up a complete sample installation in a typical room at
the jobsite. Check all the critical dimensions such as eld
piping, wiring, and duct connection to ensure they agree
with job requirements. Refer to job drawings and product
dimension drawings as required (See Figure 1 for sample
drawing). Instruct all trades in their part of the installation.
Should any discrepancies be discovered, contact your local
representative before continuing with unit installations.
After determining the condition of the packaging exterior,
carefully remove each unit from the carton and inspect
for hidden damage. At this time, check to make sure that
“furnished only” items such as switches, valves, thermostats,
etc. are accounted for. Any hidden damage or missing
components should be recorded and immediately reported
to the carrier and a claim led. In the event a claim for
shipping damage is led, the unit, shipping carton, and
all packing must be retained for physical inspection by
the freight carrier. All equipment shall be stored in the factory shipping carton with internal packing in place until installation.
At the time of receipt, the equipment type and arrangement shall be veried against the order documents. Should any discrepancy be found, the local Sales Representative shall be notied immediately so that proper action may be taken.
Should any questions arise concerning eld warranty repairs, the factory must be notied BEFORE any corrective action is taken.
Identify and Prepare Units
For each unit, conrm incoming and control power
requirements match available power source. Refer to unit
nameplate and wiring diagram.
1. Check all tags on unit to determine if shipping screws
are to be removed. Remove screws as directed.
2. Rotate the fan wheel by hand to ensure that the fan is
unrestricted and can rotate freely. Check forshipping
damage and fan obstructions. Adjust blower wheel as
required.
3. Perform “Dry Fit” of valve assembly that may be shipped unattached to unit coil assembly. Should anyquestions arise on fit up please contact your local representative immediately.
Protect Units from Damage
All equipment is designed and fabricated with robust materials and present a rugged appearance. Still, great care must be taken to assure that no force or pressure is applied to the coil, piping or drain stub-outs during handling.
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
www.iec-okc.com
5
Page 6
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
STANDARD STAMPED
SUPPLY GRILLE
5
E
(127)
2
(DIMENSION FROM MOUNTING HOLE)
(51)
2-1/2
(64)
9
(229)
9-1/2
(241)
3-3/4
25
(635)
1/2" (13) MTG. HOLES
(TYP. OF 4)
(102)
9-1/4
11-3/4
4
(235)
(298)
3-3/4
5
E
(95)
(127)
D
TOP VIEW
(229)
9-1/2
(241)
OPTIONAL
CONTROL BOX SHOWN
(STD BOX IS 2X4)
RETURN AIR OPENING
9
C
MOUNTINGHOLES
B
A
REMOVABLE FRONT
ACCESS PANEL
FRONT VIEW
CONTROL ACCESS
DOOR STD. (2)
(OPTIONS AVAILABLE)
(95)
1/4 TURN PANEL
FASTENER TYP.
SUPPLY & RETURN
WATER CONNECTIONS
DRAIN TROUGH
PLASTIC AUXILIARY 7X7
DRAIN PAN WITH
3/4" (19) MPT CONNECTION
4
(102)
(DIMENSION FROM INSIDE CASE LEG)
1" (25) FILTER
RETURN
AIR VENT
AIR
1-1/2
(38)
2-7/8
(73)
3/4
(19)
RIGHT SIDE VIEW
5-3/4
(146)
SUPPLY
AIR
8-1/4
(229)
(210)
9
REVISION HISTORY
REV
04/29/13
-13-0801
05/22/13
A13-0958
B13-0981
05/24/13
06/05/13
C13-1073
D13-1843
09/03/13
09/11/14
E14-1984
1-3/4
(45)
SEE TECHNICAL
CATALOG FOR
DIMENSIONAL DETAILS
16-1/8
(410)
14-1/2
(368)
4-1/2
(114)
ECNDATE
NOTES:
1. R.H. SHOWN, L.H. OPPOSITE.
2. ALL DIMENSIONS ± 1/4" (6).
3. PRODUCT SPECIFICATIONS ARE SUBJECT TO
CHANGES WITHOUT NOTICE.
Depending on the options and accessories, some units
may contain delicate components that may be damaged
by improper handling. Whenever possible, all units shall
be maintained in an upright position, and handled by the chassis or as close as possible to the unit mounting-point locations. In the case of a full cabinet unit, the unit must be handled by the exterior casing. This is acceptable provided the unit is again maintained in an upright position, and no force is applied that may damage internal components or painted surfaces.
The equipment covered in this manual IS NOT suitable for outdoor installations. The equipment is never to be stored or
CLASSIC
TITLE
MODEL
FXC
CABINET
E
SHEETREVISION
OF
1
1
3-3/4 (95)
2-1/4 (57)3-1/4 (83)3-5/8 (92)3-1/4 (83)
QUANTITY/UNIT
BLWRMOTOR
112
2244
111
1122
JOB NUMBER
JOB NAME
DRAWN BY
B. CHILDS
DRAWING NUMBER
I100-90017694
installed where it may be subjected to a hostile environment
such as rain, snow, or extreme temperatures.
Before, during, and after installation, take specic care to prevent foreign material such as paint, plaster, and drywall dust from being deposited in the drain pan, on the motor or blower wheels and cooling/heating coils. Failure to do so may have serious adverse eects on unit operation, and in the case of the motor and blower assembly, may result in immediate or premature failure. All manufacturers’warranties are void if foreign material is allowed to be deposited in the drain pan or on the motor or blower wheels of any unit. Some units and/or job conditions may require some form of temporary covering during construction.
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
6
www.iec-okc.com
Page 7
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
While the manufacturer is not involved in the design and
selection of support methods and components, it shall be
noted that unacceptable system operating characteristics
and/or performance may result from improper or
inadequate unit structural support. In addition, adequate
clearance must be provided for service and removal of the
equipment and its accessory components, consult local
codes. See Figure 2 for minimum recommendation for
clearances by manufacturer. Anchoring the equipment
in place is accomplished by using the mounting points
provided, and positioning the unit to maintain the drain pan
on a LEVEL plane. Care must be taken to insure that the unit
drain pan does not slope away from the outlet connection.
Vertical unit models FHC, FXC, FVC are designed to be oor
mounted or otherwise supported from below, and bolted
to the wall or oor structure through the mounting holes
provided in the chassis. These units may be wall hung only
when originally ordered from the factory for wall-mount
applications.
The type of mounting device is a matter of choice; however,
the mounting point shall always be that provided in the
chassis or cabinet. Refer to the unit product drawings for
hole mounting locations and sizes.
After mounting, the unit is then ready for the various service
connections such as water, drain and electrical. At this time,
verify that the proper types of service are actually provided
to the unit. On units requiring chilled water and/or hot
water, verify the proper line size and water temperature are
available to the unit.
SECTION 3 – Installation
Place Units In Position
F*C UNITS
1. Select the unit location. Allow adequate space for free air circulation, service clearances, piping andelectrical connections, and any necessary ductwork.For specific unit dimensions, refer to the submittal drawing for your model. Allow clearances according to local and national electric codes. See Figure 2 for basic minimum clearance recommendations.
2. Make sure the floor is able to support the weight of
the unit. See Table 1 for nominal unit weight.
3. Ensure wall behind unit is smooth and plumb; if
necessary, install furring strips on walls with irregular
surfaces or mullions. Furring strips must be positioned
behind mounting holes in unit (FHC, FXC, FVC units).
Fasteners, furring strips, and other seals (if required)
must be field-supplied.
4. Remove all wall and floor moldings from behind the
unit.
5. Ensure FHC top panel (under window application)
and FXC, FVC front panel has been removed from unit
to obtain access to the four 0.75-in. mounting holes.
Fasteners and other required hardware must be fieldsupplied.
6. Move unit into position. Ensure unit is level or slightly
pitched towards drain to ensure proper drainage and
operation.
Unit Size F*C0203040506081012
Nominal Air
Flow (cfm)
FHC424757607779108127
FXC6368828599101133154
FVC64698386100102135156
Coil Weight w/Water (Approx. lbs per row of coil)
FHC/FXC/FVC0.40.50.60.81.01.11.82.1
Coils5.77.47.611.6 14.5 15.1 24.5 27.7
FPI12 FPI
Coil Face Area
(sq ft)
Motor (Qty)
FHC/FXC/FVC
Blower (Qty)
FHC/FXC/FVC
FHC/FXC/FVC
Qty11111111
Supply Air
Duct Collar
Coil Supply and Return
Drain
Connection
Table 1: Nominal Unit Weight
200300400500600800 1000 1200
Shipping Weight (lb)
0.81.01.11.62.02.13.64.2
11111122
11222244
Filters (Nominal Size (in.) (1-in. thick)
7¾ x
7¾ x
7¾ x
7¾ x
7¾ x
7¾ x
7¾ x
21¾
21¾
31¾
31¾
41¾
43¾
57¾
1-inch
Piping Connections (Sweat) (in.)
5/8” OD, 7/8” OD
3/4 MPT
7¾ x
65¾
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
www.iec-okc.com
7
Page 8
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
7. Adjust FHC, FXC, FVC units leveling legs so unit is
level. See Figure 2. Unit must be level for proper
operation and condensate drainage. (See Figure 5 for
recommended connection methods/trapping)
8. Mounting unit: Reach into unit and attach unit
to the wall using the 0.375-in. mounting holes (4)
Level Unit
12”
30” Minimum
per building code
±1/4”
1/2”
Minimum
in top panel; do not use any other locations. The
four mounting holes and hanger slots with rubber
grommets are NOT for balancing unit.
NOTE: For any unit without a return-air duct connection,
applicable installation codes may limit unit to installation
in single story applications only.
1/2”
Minimum
Side ViewFront View
Figure 2: Clearance recommendations.
valve packages may be shipped loose with the equipment.
Cooling/Heating Pipe Connections
CAUTION: Residues and loose particles resulting from manufacturing and eld piping
In these cases, perform a dry t of the assemblies to ensure
proper alignment and access to the assembly components
can be utilized for maintenance and service.
techniques such as joint compounds, soldering ux, and
metal shavings may be present in the unit and the piping
system. Give special consideration to system cleanliness when connecting to solar, domestic or potable water systems.
If coil and valve package connections are made with a “sweat” or solder joint, verify that no components in the valve package are subjected to a high temperature which may damage seals or other materials. Do not allow valve bodies to exceed 300°F. Protect all valve and water control
Thoroughly review submittals and product literature detailing unit operation, controls, and connections BEFORE
assemblies with wet or damp rag wrapped around the body during the soldering/brazing process.
beginning the connection of the various cooling and/or heating mediums to the unit.
Many two position electric control valves, depending on valve operation, are provided with a manual opening lever.
All accessory valve packages shall be installed as required, and check all service valves for proper operation. At times,
Place this lever in the “open” position during all soldering or brazing operations.
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
8
www.iec-okc.com
Page 9
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
Mating
Hole
Step 1: Rotate
actuator counter
clockwise
approximately
30 degrees.
Manual Operating
Lever
General Close-O (G)
Taco Line Voltage
Locking Post
Schneider Erie
Release Button
Stem
B
A
Release
Button
High Close-O (H)
Step 2: Move actuator
upward 3/4” to disengage.
Manual
Operating Lever
Mating
Hole
The supply and return connections are marked on the coil
stub outs and the valve package, with an “S” meaning supply
or inlet and “R” meaning return or outlet indicating uid ow
direction to and into the coil. Blue letters mark the chilled
water connections and Red letters mark the hot water or
steam connections.
In the case of eld-installed valves and piping, install the
chilled water valve cluster (or expansion valve on DX units)
in such a way that any dripping or sweating caused from
condensation is contained in the drain pan or other device
such as an optional extended drain pan or factory drip lip.
Factory drip lips are eld installed and may be packaged
separately from the unit. Factory supplied cooling coil valve
packages will be arranged to locate as much of the package
as possible over a standard drip lip. Some eld congurations
may require additional insulation be applied to the exposed
water piping to prevent condensation from dripping into
areas not directly above the auxiliary drain pans.
If none of the above factory accessories are provided with
the units, simple ashing may be used to carry moisture into
the unit drain pan.
Field Piping Connections
Taco Zone Sentry
Step 1: Push in and hold release clip at the front of the actuator.
Figure 3: Valve and Lever–Pop-Top Installation
If the valve package connection at the coil is a union, the coil side of the union must be prevented from twisting (“backed up”) during tightening to prevent damage to the coil tubing. Do not over tighten the union preventing distorting (“egg shaping”) of the union seal surface and destroying the union.
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
Step 2: Move actuator away from the valve body approximately 3/4” to disengage locking posts and stem.
Locking Post
www.iec-okc.com
To chilled water coil: IEC’s innovative design incorporates
3/8” copper tubing inside and stubbing out of the coil. To
facilitate ease of connecting to eld supplied ½” hydronic
tubing, there is a 3/8” to 1/2” swedge adaptor installed on
both the supply and return water tube connections to the
coil. Care must be taken when soldering the eld supplied
tubing to this connection.
The use of solder with a ow or initial melting point below
500°F is recommended to make these connections. Local codes and/or building specications should always be consulted to ensure solder being used is compliant with current building standards. When making soldering connections, use a wet rag as a heat sink around the factory adaptor to prevent overheating of this joint. See Figure 4. After soldering, use the wet rag to quench the eld and factory connections at this tting.
9
Page 10
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
Supply
or
Torch
Field
Tubing
Figure 4: Field Piping Connections:
Return
Adaptor
(Factory Installed)
Wet Rag
Stub
From Coil
CAUTION: Piping must be adequately
supported or equipment damage could result.
NOTE: The installing contractor is responsible for adequately
supporting field mounted or field supplied valve packages
or components. Once installed the valve package
components must not impede or block condensate run off
path from the drain trough to the drain pan.
NOTE: Copper connections should only be made with commonly
available solder that melts (flows) below 500°F. Excessive
overheating of connections may damage IEC equipment,
valves, pipe integrity, etc.
Steam Drain Connections
Verify units with steam-heating coils have the proper line
sizing and routing, and the maximum steam pressures
applied never exceed 10 psig. The drain piping and
steam trap are to be sized and routed to allow for proper
condensate ow.
Leak Testing
After completing the connections, test the system for any
leaks. Always test hydronic systems with water as some components are not designed to be inert gas pressurized.
Field pressure testing for leaks should not exceed 300 psi for hydronic coil and valve package components. Consult factory if higher limits are required.
CAUTION: Protect all water coils from freezing after initial lling with water. Even if the
system is drained, unit coils may still hold enough water
to cause damage when exposed to temperatures below
freezing.
Refrigerant Coil Testing
Test refrigerant systems with dry nitrogen rather than air to
prevent the introduction of moisture into the system. In the
event that leaking or defective components are discovered,
notify the Sales Representative BEFORE any repairs are
attempted. All leaks must be repaired before proceeding
with the installation.
Piping Insulation
After system integrity has been established, insulate the
piping in accordance with the project specications. This is
the responsibility of the installing or insulation contractor.
All chilled water piping and valves or refrigerant suction
piping not located over drain pans or drip lips must be
insulated to prevent damage from sweating. This includes
factory and eld piping inside the unit cabinet.
Condensate Drain
The condensate drain shall always be connected and piped
to an acceptable disposal point. For proper moisture carry
o, the drain piping shall be sloped away from the unit at
least 1/8” per foot. A drain trap may be required by local
codes and it is strongly recommended for odor containment.
A minimum drain P-Trap of 2” is required to be connected
to the primary drain outlet of the condensate pan. This
connection must be serviceable during preventativemaintenance. See Figure 5 below.
Note: Field
Drain Pan
Drain
“P” Trap
Figure 5: “P”Trap Minimum Conguration
trim “P” trap as required
to prevent kinking.
Clamp
2” Minimum
Drain
Clamp
Unit Wall
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
10
www.iec-okc.com
Page 11
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
Electrical Connections
The unit serial plate lists the unit electrical characteristics
such as the required supply voltage, fan and heater
amperage and required circuit ampacity. The unit wiring
diagram shows all unit and eld wiring. Since each project
is dierent and each unit on a project may be dierent, the
installer must be familiar with the wiring diagram and serial
plate on the unit BEFORE beginning any wiring.
Incoming Power
Option 1
Figure 6: High Voltage Wiring Service Switch (Side Location)
Incoming Power
Incoming Power
Option 3
Figure 8: High Voltage Wiring Service Switch (Bottom Location)
Make sure all eld electrical connections are in accordance
with unit wiring diagram and all applicable national and
local codes. The type and sizing of all wiring and other
electrical components such as circuit breakers, disconnect
switches, etc. shall be determined by the individual job
requirements. Verify conductor size is suitable for the
distance to the equipment connection and will support
the equipment electrical load. All installations including
eld wiring shall be made in compliance with all governing
codes and ordinances. Compliance with all codes is the
responsibility of the installing contractor.
Option 2
Figure 7: High Voltage Power Connection (Unit Without Service Switch)
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
All components furnished for eld installation by either
the factory or the controls contractor shall be located and
checked for proper function and compatibility. Check
all internal components for shipping damage. Check all
electrical connections within the unit control box and
accessories and tighten if necessary.
Any devices such as fan switches or thermostats that have
been furnished from the factory for eld installation must be wired in strict accordance with the wiring diagram that appears on the unit. Failure to do so could result in personal injury or damage to components, and will void all manufacturer warranties.
Never control fan motor(s) by any wiring or device other than the factory-supplied switch or thermostat/switch combination unless prior factory authorization is obtained. Fan motor(s) may be temporarily wired for use during
www.iec-okc.com
11
Page 12
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
construction only with prior factory approval and only in
strict accordance with the instructions issued at that time.
Factory Installed Options
Aquastats: Units with optional factory-furnished and
installed aquastats may be shipped with the aquastats
mounted on a coil stub out. In this circumstance, remove
the aquastat before installation of a valve package. Consult
the factory piping diagram in the approved submittals for
proper location when reinstalling the aquastats. If the valve
package is eld-furnished, the aquastat must be installed
in a location where it will sense the water temperature
regardless of control valve position. A bleed bypass may
be required to guarantee proper aquastat operation. The
aquastat bypass line allows a small amount of water to ow
from the supply to the return piping when the control valve
is closed for loop temperature sensing.
NOTE: The aquastat must be able to sense whether the flowing
water is being chilled or heated and switches a contact
closed to provide automatic summer or winter changeover
for the system.
Condensate Overow switch
The condensate overow switch is used to detect a clogged
or restricted condensate pan drain. The condensate switch
uses a Normally Closed contact to allow the system control
power to pass through the switch energizing the water
valves and fans allowing normal operation. When an
overow condition is detected by the switch, it opens the
NC contacts and de-energizes the water valves and fans.
NOTE: All field wiring must be in accordance with governing
codes and ordinances. Any modification of unit wiring without factory authorization will invalidate all factory warranties and nullify any agency listings. The manufacturer assumes no responsibility for any damages and/or injuries resulting from improper field installation and/or wiring. Units may be equipped with line voltage controls or 24 V AC control systems. Some adjustment may be required for proper operation.
Standard Wiring Packages
Manual Fan Control — On vertical cabinet units, a 3-speed
fan switch may be furnished unit-mounted and wired.
See Figure 9. On vertical furred-in units, the switch may
be shipped separately on a decorative wall plate for eld
mounting and wiring. See Figure 10. The standard fan switch
has LOW, MEDIUM, HIGH and OFF positions plus an auxiliary
contact to energize thermostats, valves, dampers, etc.
NOTE: Wiring diagrams are for typical applications. If other
voltages for heaters or controls are specified, wiring may
differ from that shown. Refer to wiring diagram on unit
blower housing or inside control box cover for unit specific
wiring.
Thermostatic Electric Valve Control, 2-Pipe — A
thermostatically controlled 2-position valve provides
superior control to fan cycling. With this control, the fan
runs continuously unless it is manually switched to the OFF
or AUTO position. The fan must be on before the valve can
be opened to supply water to the coil. This system can be
used for normal 2-pipe changeover systems and can also be
furnished for cooling-only or heating-only applications by
omitting the changeover and specifying which application
is intended. See Figure 11 for line voltage control and
Figure 12 for 24 V control. Wiring diagrams show typical
applications. Refer to the wiring diagram on each unit
blower housing for unit specic wiring.
Thermostatic 2-Pipe Auxiliary Electric Heat with Valve
Control — This system, also called twilight or intermediate
season electric heat, goes a long way towards solving the
spring and fall control problems of 2-pipe systems. Chilled
water can be run late into the fall, turned on early in the spring and electric heat will still be available to all units whenever required. In winter, the system is switched over to hot water. Two changeover devices are required for this. One device switches the action of the thermostat and the other locks out the electric heat when hot water is in the coil.
The following descriptions are for typical control sequences only. For detailed control operating sequence, refer to thermostat operating instructions.
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
12
With this system, the fan runs continuously unless manually switched to OFF or AUTO position. Fan must be on before thermostat can send signal to open chilled water valve or turn on electric heater.
www.iec-okc.com
Page 13
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
Two control methods are available:
1. Use the standard automatic changeover thermostat
with a dead band between heating and cooling.
2. Use a manual changeover thermostat. With this
method only one changeover is required. Be sure
to include a 2-way or 3-way electric valve with this
system.
Thermostat 2-Pipe Total Electric Heat with Valve
Control— With this system type, the complete heating
requirement for the space is provided by the electric heater;
the water system is never changed over for heating. It is
therefore possible to have heating or cooling at any time of
the year. The fan may run continuously unless it is manually
switched to OFF or AUTO position. Fan must be on before
thermostat can send signal to open chilled water valve or
turn on electric heater.
Normally, an automatic changeover thermostat with a dead
band between heating and cooling is used, but a manual
changeover thermostat is also suitable. A 2-way or 3-way
valve must also be used so that the chilled water is o
whenever the heater is on. No changeover device to sense
water temperature is necessary.
Thermostatic Electric Valve Control, 4-Pipe — This system
conguration provides the complete heating requirement
for the space by the hydronic heating coil. It is therefore
possible to have heating or cooling at any time of the year.
The fan may run continuously unless it is manually switched
to OFF or AUTO position. Fan must be on before thermostat
can send signal to open chilled water valve or the hot water
valve.
Normally, an automatic changeover thermostat with a dead
band between heating and cooling is used, but a manual
changeover thermostat is also suitable. A 2-way or 3-way
valves must also be used so that the chilled water valve is
closed whenever the heating valve is open. No changeover
device to sense water temperature is necessary.
NOTE: Wiring diagrams are for typical applications. If other
voltages for heaters or controls are specified, wiring may
differ from that shown. See Figure 11 for line voltage
control. See Figure 12 for 24 V control. Refer to wiring
diagram on unit blower housing for unit specific wiring.
Incoming
Power
Figure 9: Standard Fan Switch
To Motor Speeds
L
M
H
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
www.iec-okc.com
13
Page 14
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
L1
L2 OR N
L2 OR N
WHT*
1
BLK
2
BLU
3
RED
4
WHT*
1
BLK
2
BLU
3
RED
4
SSIPF
BM2
BM1
GND
GND
WHT*
BLK
BLU
RED
WHT*
BLK
BLU
RED
Figure 10: Switch with Decorative Wall Plate
BLK
WHT* SEE NOTES
WHT*
1
BLK
2
BLU
3
RED
4
WHT*
1
BLK
2
BLU
3
RED
4
L1
L2 OR N
L2 OR N
GND
GND
BLK
2
WHT*
1
BLK
BLU
RED
SSIPF
1
2
3
4
BLK
WHT* SEE NOTES
BLU
RED
LOWMED HIGH
AUX CIRC
BRN
BLK
OFF
HOT LINE YEL
Figure 11: Line Voltage Control
BM2
BM1
WHT*BLKBLURED
WHT*BLKBLURED
WHT*
1
BLK
2
BLU
3
RED
4
WHT*
1
BLK
2
BLU
3
RED
4
WHT*
1
BLK
2
BLU
3
RED
4
WHT*
1
BLK
2
BLU
3
RED
4
WHT*
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
14
www.iec-okc.com
Page 15
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
Figure 12: 24 V Control
BM2
BM1
WHT*
BLK
BLU
RED
WHT*
BLK
BLU
RED
L1
L2 OR N
GND
WHT*
1
BLK
2
BLU
3
RED
4
WHT*
1
BLK
2
BLU
3
RED
4
VALVES FACTORY/FIELD INSTALLED
1
2
3
4
1
2
3
4
VALVE
VALVE
WHT*
BLK
BLU
RED
WHT*
BLK
BLU
RED
SS
BLK
BLK
BLK
BLK
FUSE
1
2
3
4
1
2
3
4
BLK
WHT* SEE NOTES
BLK
WHT*
L2(IN) L1
LINE VOLTAGE
L2
MED
LO
HI
L2
MED
LO
HI
PUR
YEL
ORG
BRN
YEL
ORG
TRANS
24VCOM
SECPRIAUX
24+
COM
YEL
GND
1 2
213
5
6
8
9
11
12
15
BLK BLK
4
7
10
1314
COM
1
2
HI
MED
LOW
PRI
SEC
AUX
RM SEN
RM COM
PIPE SEN
PIPE COM
COND OVFL
COND OVFL
R 24V
C COM
R 24V
C COM
NC
NO
COS
BLU
BLU
ORG
ORG
1
2
COM
ORG
YEL
1
2
NC
NO
1
COM
NO
NC
CO
RAS
Connecting Ductwork
All ductwork and/or supply and return grilles shall
be installed in accordance with the project plans and
specications. If not included on the unit or furnished from
the factory, supply and return grilles shall be provided as
recommended in the product catalog.
NOTE:When installing units with plenums that attach to branch
duct piping, use industry approved duct standards and configuration such as those published by Air Conditioning Contractors of America or American Society of Heating, Refrigeration and Air Conditioning Engineers. The standards provide necessary information on sizing, layout and installing supply and return air duct systems. Following these guidelines will ensure a quiet, low static system that has uniform air distribution.
For units with no return-air ductwork, check local code requirements for possible application restrictions. All units must be installed in areas that are noncombustible.
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
Some models are designed to be connected to ductwork
with a MINIMUM amount of external static pressure. These
units may be damaged by operation without the proper
ductwork connected. Consult the approved submittals
and the product catalog for unit external static pressure
limitations.
NOTE:None of these methods will adequately protect a coil in
Flexible duct connections should be used on all air handling equipment. All ductwork and insulation shall be installed to allow proper access to all components for service and repair such as lters, motor/blower assemblies, etc.
The manufacturer assumes no responsibility for undesirable system operation due to improper design, equipment
www.iec-okc.com
the event of power failure. The safest method of freeze protection is to use glycol in the proper percent solution for the coldest expected air temperature.
15
Page 16
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
or component selection, and/or installation of base unit,
ductwork, grilles, and other related components.
Exposed Unit Finish Touch-up and Repaint
Exposed cabinet units may be furnished with a baked
enamel nish. Repair small scratches in this nish with touch
up paint available from the factory. Some colors of touch
up paint are available in aerosol containers and all touch up
paint is available in pint, quart, and gallon cans. Contact the
factory for availability.
Follow proper safety procedures regarding ventilation and
safety equipment. Follow the manufacturer’s directions for
the products being used.
To repaint the factory-baked enamel, prepare the nish
surface by light sanding with #280 grit sand paper, or #000
or #0000 ne steel wool. The surface may also be wiped with
a liquid surface etch cleaning product such as “No Sand” or
“Pasceo.” These items are available at most paint product
stores. Note that the more conscientiously this preparation is
done, the more eective it will be.
After this preparation is accomplished, the factory nish
should provide excellent adhesion for a variety of air-dried
top coats. Enamel will give a more durable, higher gloss
nish, while latex will not adhere as well and will give a
dull, softer nish. Avoid top coats involving an exothermic
chemical process between two components, such as epoxies
and urethanes.
Factory aerosol touch up paint may require a number of
light “dust coats” to isolate the factory-baked enamel nish
from the quick drying touch up paint.
Make Final Preparations
1. Turn off power to the unit (open unit electrical disconnect) and install lockout tags on all power supplies to unit.
2. Install thermostats and perform any other final wiring as applicable. Ensure all electrical connections aretight.
3. Perform a final visual inspection. All equipment, plenums, ductwork, and piping should be inspected
to verify that all systems are complete and properly
installed and mounted, and that no debris or foreign
articles such as paper or drink cans are left in the units
or other areas. Clean dirt, dust, and other construction
debris from unit interior. Be sure to check fan wheel
and housing and clean if necessary.
4. Rotate fan wheel by hand to be sure it is free and does
not rub housing. Check that wing nuts securing fan
assembly to fan deck are tight. Adjust if necessary.
5. Install filter in frame at front of coil. If field-supplied
filters are used, be sure size is as specified in Table 2.
6. Ensure all panels and filters are installed before
checking fan operation. Turn on power to the unit.
7. Check the fan and motor operation.
8. Verify drain line is properly and securely positioned
and that the line is clear. Pour water into drain to check
operation.
Before beginning any startup operation, the startup personnel shall familiarize themselves with the unit, options
and accessories, and control sequence to understand the proper system operation. All personnel shall have a good working knowledge of general startup procedures and have the appropriate startup and balancing guides available for consultation.
The building must be completely nished including doors, windows, and insulation. All internal walls and doors should be in place and in the normal position. In some cases, the interior decorations and furniture may inuence overall system performance. The entire building should be as complete as possible before beginning any system balancing.
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
16
www.iec-okc.com
Page 17
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
The initial step in any startup operation shall be a nal visual
inspection. All equipment, plenums, ductwork, and piping
shall be inspected to verify that all systems are complete
and properly installed and mounted, and that no debris or
foreign articles such as paper or drink cans are left in the
units or other areas.
Check each unit for loose wires, free blower wheel operation,
and loose or missing access panels or doors. Except as
required during startup and balancing operations, no fan
coil units shall be operated without all the proper ductwork
attached, supply and return grilles in place, and all access
doors and panels in place and secure. A clean lter of the
proper size and type must also be installed. Failure to do
so may result in damage to the equipment or building and
furnishings, and/or void all manufacturer warranties.
Cooling/Heating System
Prior to the water system startup and balancing, ush the
chilled/hot water systems to clean out dirt and debris which
may have collected in the piping during construction.
During this procedure, all unit service valves must be in the
closed position to prevent foreign matter from entering the
unit and clogging the valves and metering devices. Strainers
shall be installed in the piping mains to prevent such
material from entering units during normal operation.
During system lling, air venting from the unit is
accomplished by the use of the standard, manual air vent
tting, or the optional, automatic air vent tting installed
on the coil. Manual air vents are basically Schrader valves.
To vent the air from the coil, depress the valve until the air
has vented the coil. When water begins to escape through the valve, release the valve. Automatic air vents may be unscrewed one turn counterclockwise to speed initial venting, but should be screwed in for automatic venting after startup operations.
CAUTION: The air vent provided on the unit is
not intended to replace the main system air
vents and may not release air trapped in other
parts of the system. Independently inspect the entire
system for potential air traps and vent those areas as
required. In addition, some systems may require
repeated venting over a period of time to properly
eliminate air from the system.
Air Balance System
All ductwork must be complete and connected. All grilles,
lters, and access doors and panels must be properly
installed to establish actual system operating conditions
BEFORE beginning air balancing operations.
Each individual unit and the attached ductwork is a
unique system with its own operating characteristics. For
this reason, air balancing is normally done by balance
specialists who are familiar with all procedures required to
properly establish air distribution and fan-system operating
conditions. These procedures shall not be attempted by
unqualied personnel.
Exposed units without ductwork do not require air
balancing other than selecting the desired fan speed.
After proper system operation is established, the actual
unit air delivery and the actual fan motor amperage draw
for each unit should be recorded in a convenient place for
future reference.
Water Balancing System
A complete knowledge of the hydronic system, along with
its components and controls, is essential to proper water system balancing. This procedure shall not be attempted by unqualied personnel. The system must be complete, and all components must be in operating condition BEFORE beginning water system balancing operations.
Figure 13: Manual Air Vent
Figure 14: Automatic Air Vent
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
Each hydronic system has dierent operating characteristics depending on the devices and controls used in the system. The actual balancing technique may vary from one system to another.
www.iec-okc.com
17
Page 18
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
After the proper system operation is established, record the
appropriate system operating conditions such as various
water temperatures and ow rates in a convenient place for
future reference.
Before, and during water system balancing, conditions may
exist due to incorrect system pressures which may result in
noticeable water noise or undesired valve operation. After
the entire system is balanced, these conditions will not exist
on properly designed systems.
Water Treatment
Proper water treatment is a specialized industry. IEC
recommends consulting an expert in this eld to analyze
the water for compliance with the water quality parameters
listed below, and to specify the appropriate water treatment
regimen. The expert may recommend typical additives such
as rust inhibitors, scaling preventative, antimicrobial growth
agents, or algae preventatives. Anti-freeze solutions may
also be used to lower the freezing point.
IEC water coil tubes and headers are constructed of pure
copper. Multiple brass alloys may be present in the valve
package, depending on unit conguration. It is the user’s
responsibility to ensure the tube and piping materials
furnished by IEC, are compatible with the treated water.
Failure to provide proper water quality will void the fan coil
unit’s warranty.
Water ContainingRequired Concentration
SulphateLess than 200 ppm
pH7.0 – 8.5
ChloridesLess than 200 ppm
NitrateLess than 100 ppm
IronLess than 4.5 mg/l
AmmoniaLess than 2.0 mg/l
ManganeseLess than 0.1 mg/l
Dissolved SolidsLess than 1000 mg/l
CaCO3 Hardness300 - 500 ppm
CaCO3 Alkalinity300 - 500 ppm
Particulate QuantityLess than 10 ppm
Particulate Size800 micron max
Table 3: Water Quality Concentrations
Eco-telligent® Motor
If the unit is equipped with an ECM blower, additional steps
may be required during the air balancing process. Review
project submittals or order acknowledgement to determine
which ECM control scheme the unit has. Alternatively, match
the control board to the illustrations.
CAUTION: Both of the procedures described
below require the control box to be powered
while adjustments are made. Line voltage
components are concealed behind a secondary cover.
However, installer should still take all reasonable
precautions to prevent electrical shock or arching.
3-Speed, Potentiometer Adjustment (Eco 2 Only)
Figure 15: Potentiometer Board
The unit has been factory congured to produce PSC
equivalent airow on high speed, with medium and low
speed set at 80% and 60% of high, respectively. If these
settings are acceptable, then no further conguring isrequired.
If alternative airows are desired, use board mounted potentiometers to adjust the airow associated with each input. Each speed output can be adjusted from 0 to 100% of the motor’s factory programmed operating range. Use voltmeter and airow chart (on control box cover) to set values. Refer to Appendix A for adjustment procedure.
4-Speed, Solid State with Potentiometer
See photo in Appendix B. The unit has been factory congured to produce PSC equivalent airow on high speed, with medium and low speed set at 80% and 60% of
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
18
www.iec-okc.com
Page 19
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
high, respectively. If these settings are acceptable, then no
further conguring is required.
Board mounted potentiometers are provided to adjust
the airow pertaining to each output. Each output can be
adjusted from 0 to 100% of the motor’s factory programmed
operating range. Use voltmeter and airow chart (on control
box cover) to set values. Refer to Appendix B for adjustment
procedure.
Eco 2 Variable Airow for 0-10 VDC
No control board is required and no eld adjustments are
possible. Motor uses 0-10VDC signal directly. See control box
label. Fan enable at 1.5VDC.
Controls Operation
Before proper control operation can be veried, all other
systems must be operating properly. The correct water and
air temperatures must be present for the control function
being tested. Some controls and features are designed to
not operate under certain conditions. For example, on a
2-pipe cooling/heating system with auxiliary electric heat,
the electric heater cannot be energized with hot water in the
system.
equipment on the job. A formal schedule of regular maintenance and an individual unit log should be established
and maintained. This will help to achieve the maximum
performance and service life of each unit on the job.
Information regarding safety precautions contained in the
preface at the beginning of this manual shall be followed
during any service and maintenance operations.
For more detailed information concerning service
operations consult your IEC Sales Representative or the
factory.
Motor/Blower Assembly
The type of fan operation is determined by the control
components and their method of wiring. This may vary from
unit to unit. Refer to the wiring diagram that is attached to
each unit for that unit’s individual operating characteristics.
All motors have permanently lubricated bearings. No eld
lubrication is required.
Should the assembly require service, the motor/blower
assembly may be removed from the unit to facilitate such
operations as motor or blower wheel/housing replacement, etc.
A wide range of controls, electrical options and accessories
may be used with the equipment covered in this
manual. Consult the approved unit submittals, order
acknowledgements, and other literature for detailed
information regarding each individual unit and its controls.
Since controls and features may vary from one unit to
another, care must be taken to identify the controls used on
each unit and their proper control sequence. Information provided by component manufacturers regarding installation, operation, and maintenance of their individual controls is available upon request.
SECTION 5 – Service/Maintenance
General
Each unit on a job will have its own unique operating environment and conditions which may dictate a main-te nance schedule for that unit that is dierent from other
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
Dirt and dust should not be allowed to accumulate on the
blower wheel or housing. This can result in an unbalanced
blower wheel condition which can damage a blower
wheel or motor. The wheel and housing may be cleaned
periodically using a vacuum cleaner and a brush taking care
not to dislodge the factory balancing weights on the blower
wheel blades.
www.iec-okc.com
19
Page 20
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
reset limit switches are as the name implies, they reset
automatically after the heater has cooled down.
High-limit thermal switches must be replaced once the
circuit has been broken. The high-limit thermal cutout
device is a safety device only, and is not intended for
continuous operation. This device only operates when a
problem exists, and ANY condition that causes high-limit
cutout MUST be corrected immediately. High supply voltage
also causes excessive amperage draw and may trip the
circuit breaker or blow the fuses on the incoming power
supply.
After proper airow and supply power are assured, regular
Figure 16: Motor Blower Deck Servicing
Coil
Coils may be cleaned by removing the motor/blower
assemblies and brushing the entering air face between
ns with a sti brush. Brushing shall be followed by
cleaning with a vacuum cleaner. If a compressed air source
is available, the coil may also be cleaned by blowing air
through the coil ns from the leaving air face. This shall
again be followed by vacuuming. Units provided with the
proper type of air lters, replaced regularly, will require less
frequent coil cleaning.
lter maintenance is important to provide clean air over
the heater. Dirt that is allowed to deposit on the heating
element will cause hot spots and eventual element burn
through. These hot spots will normally not be enough to
trip the high-limit thermal cut-out device, and may not be
evident until actual heater element failure.
Electrical Wiring and Controls
The electrical operation of each unit is determined by the
components and wiring of the unit. This may vary from unit
to unit. Consult the wiring diagram attached to the unit for
the actual type and number of controls provided on each
unit.
Electric Resistance Heater Assembly
Electric resistance heaters typically require no normal
periodic maintenance when unit air lters are changed
properly.The operation and service life may be aected by
other conditions and equipment in the system. The two
most important operating conditions for an electric heater
are proper airow and proper supply voltage. High supply voltage and/or poorly distributed or insucient airow over the element will result in element overheating and possible limit switch openings.
This condition may result in the heater cycling on the high limit thermal cutout. Sheath heaters have automatic reset switches only. Open-strip heaters have an automatic reset switch with a backup, high-limit thermal switch. Automatic
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
20
The integrity of all electrical connections should be veried
at least twice during the rst year of operation. Afterwards,
all controls shall be inspected periodically for proper operation. Some components may experience erratic operation or failure due to age. Wall thermostats may also become clogged with dust and lint, and shall be periodically inspected and cleaned to provide reliable operation.
When replacing any components such as fuses, contactors, or relays, use only the exact type, size and voltage component as furnished from the factory. Any deviation without factory authorization could result in personnel injury or damage to the unit. This will also void all factory warranties. Only factory supplied replacement parts
ensure that the warranty and agency status remain in eect. All repair work shall be done in such a manner as
www.iec-okc.com
Page 21
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
to maintain the equipment in compliance with governing
codes, ordinances and testing agency listings.
More specic information regarding the use and operating
characteristics of the standard controls oered by the
manufacturer are contained in other manuals.
Valves and Piping
No formal maintenance is required on the valve-package
components most commonly used with fan coil units other
than a visual inspection for possible leaks in the course of
other normal periodic maintenance. In the event that a
valve must be replaced, the same precautions taken during
the initial installation to protect the valve package from
excessive heat should also be used during replacement.
Filters, Throwaway
The type of throwaway lter most commonly used on fan
coil units shall be replaced on a regular basis. The time
interval between each replacement shall be established
based on regular inspection of the lter, and should be
recorded in the log for each unit. Refer to the product
catalog for the recommended lter size for each product
type and size. If the replacement lters are not purchased
from the factory, the lters used should be the same type
and size as those furnished from, or recommended by the
factory. Pleated media, or extended surface lters shall
not be used since the high air pressure drops encountered
with these types of lters is not compatible with the type
of fan coil unit covered in this manual. Consult the factory
for applications using lter types other than the factory
standard or optional product.
Filters, Permanent
A maintenance schedule for permanent lters shall be developed in the same manner as throwaway lters. Unlike throwaway lters, permanent lters may be cleaned and reinstalled in the unit instead of being discarded when dirty. The optional factory permanent lter may be cleaned in hot soapy water to remove any trapped dirt then set aside on edge to dry.
Before replacing the lter in the unit, it should be recharged
with some type of entrapment lm such as “Film Cor
Recharging Oil.” The lter shall be sprayed on both sides or
submerged in the lm to assure complete coverage. The
lter should not be allowed to soak in the lm, but should
be immediately removed and the excess lm drained from
the lter before reinstallation in the unit. Consult a local
lter supplier for types of available cleaning solutions and
charging lms.
Note that permanent lters normally have less static
pressure loss than throwaway lters.
Drain
The drain shall be checked before initial startup, and at the
beginning of each cooling season to assure that the drain
trap, and line are clear. If it is clogged, take steps to clear the
debris so that condensate will ow easily.
Make periodic checks of the drain during the cooling season
to maintain a free-owing condensate. Units provided with
a secondary or “tell-tale” drain connection will indicate
a clogged main-drain line by ow from the “tell-tale”
connection.
Should the growth of algae and/or bacteria be a concern,
consult an air conditioning and refrigeration supply
organization familiar with local conditions for chemicals, or
other solutions available to control these agents.
Replacement Parts (1-866-432-7278)
Use factory replacement parts wherever possible to maintain unit performance, it’s normal operating characteristics, and the testing agency listings. Replacement
parts may be purchased through a local IEC Sales Representative.
Contact the local Sales Representative or the factory before attempting any unit modications. Any modications not authorized by the factory could result in personnel injury, damage to the unit, and could void all factory warranties.
When ordering parts, the following information must be supplied to ensure proper part identication:
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
www.iec-okc.com
21
Page 22
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
1. Complete unit model number
2. Unit serial number
3. Unit hand connection (right or left hand) while facing
into the air stream
4. Complete part description including any numbers
On warranty replacements, in addition to the information
previously listed, the unit shipping code which appears on
the upper right-hand corner of the serial plate is required.
Contact the factory for authorization to return any parts
such as defective parts replaced in warranty. All shipments
returned to the factory must be marked with a Return
Authorization Number which is provided by the factory.
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
22
www.iec-okc.com
Page 23
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
SECTION 6 – Equipment Startup Check List
IMPORTANT
Fan coil units must be lled with water before operating the circulator. The circulator bearings are water lubricated and
should not be allowed to operate dry. Filling the system properly will result in immediate lubrication of the bearings.
Receiving and Inspection
Unit received undamaged
Unit received complete as ordered
“Furnish only” parts accounted for
Unit arrangement/hand correct
Unit structural support complete and correct
Handling and Installation
Mounting grommets/isolators used
Unit mounted level and square
Proper access provided for unit and accessories
Proper electrical service provided
Proper overcurrent protection provided
Proper service switch/disconnect provided
Proper chilled water line size to unit
Proper hot water line size to unit
Proper piping insulation
All services to unit in code compliance All shipping screws and braces removed Unit protected from dirt and foreign matter
Cooling/Heating Connections
Protect valve package components from heat Mount valve packages Connect field piping to unitPressure test all piping for leaksInstall drain line and traps, as requiredInsulate all piping, as requiredInstall drip lip under piping, as required
Ductwork Connections
Install ductwork, fittings and grilles, as requiredFlexible duct connections at unitProper supply and return grille type and size Control outside air for freeze protectionInsulate all ductwork, as required
Electrical Conditions
Refer to unit wiring diagram
Connect incoming power service or services
Install and connect “furnish only” parts
Unit Startup
General visual unit and system inspection
Check for proper fan rotation
Record electrical supply voltage
Check all wiring for secure connections
Close all unit isolation valves
Flush water systems
Fill systems with water/refrigerant
Vent water systems, as required
All ductwork and grilles in place
All unit panels and filters in place
Start fans, pumps, chillers, etc.
Check for overload conditions of all units
Check all ductwork and units for air leaks
Balance water systems, as required
Balance air systems, as required
Record all final settings for future use
Check piping and ductwall for vibration
Check all dampers for proper operationVerify proper cooling operationVerify proper heating operation
Reinstall all covers and access panelsVerify proper condensate drainage
Motor
Voltage:
LNL
Amperage:
Low
Med
High
1
L
2
L
3
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
www.iec-okc.com
23
Page 24
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
Appendix A
Adjustment of ICM AW4105
Adjusting the Low, Medium, and High potentiometers requires the use of a Multi-meter capable of measuring 0~5 vdc.
1. Only trained and qualified individuals should attempt to adjust or service components on any electrical component.
Failure to follow safety rules could result in electrical shock or hazard.
2. Unit must be powered to perform the following procedure. If main power is not available, IEC recommends connecting
a temporary 24 V-40VA power supply in parallel with the secondary outputs of the unit’s transformer.
3. Set the electrical multimeter to Volts Direct Current (Vdc) on the 0~5 or 0~20 Vdc scale
4. Attach black (negative) lead of meter to the DC common terminal, labeled “L2” above the potentiometers and to the
left of the orange relay.
5. Attach the red (positive) lead of the meter to the red wire that bridges the 0-10VDC outputs: high, medium, and low.
6. High Speed: Close High speed relay by applying 24 V to the High terminal. Using a small screwdriver turn the VR3
potentiometer so the meter measures 4.51 Vdc. This will set the ECM speed to 90% of maximum for high speed. Open
the high speed relay.
7. Medium Speed: Close medium speed relay by applying 24 V to the medium terminal. Using a small screwdriver turn the
VR2 potentiometer so the meter measures 3.53 Vdc. This will set the ECM speed to 70% of maximum speed for medium
speed operation. Open the medium speed relay.
8. Low Speed: Close low speed relay by applying 24 V to the low terminal. Using a small screwdriver turn the VR1 potentiometer so the meter measures 2.06 Vdc. This will set the ECM speed to 40% of maximum speed for low speed operation. Open the low speed relay.
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
24
www.iec-okc.com
Page 25
(Contact Factory)
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
Appendix B
Adjustment of EVO/ECM-4SPD
Pot Adjustment
Flo 1, 2, & 3
Pot Adjustment
Flo 0 & 4
(in the Field)
Com
Flo 1, 2, & 3 Terminals
Flo 0 & 4 Terminals
Adjusting the Flo1, Flo2, Flo3 potentiometers requires the use of a Multi-meter capable of measuring 0~5 vdc.
1. Only trained and qualified individuals should attempt to adjust or service components on any electrical component.
Failure to follow safety rules could result in electrical shock or hazard.
2. 24 vac power must be supplied to ECM board to make adjustments
3. Set the electrical multimeter to Volts Direct Current (Vdc) on the 0~5 or 0~20 Vdc scale
4. Attach black (negative) lead of meter to the “Com” terminal to the left of the potentiometers and below the Status light
5. Attach the red (positive) lead of the meter to the high speed “Flo1” terminal below the Potentiometer
6. High Speed: Using a small screwdriver turn the Flo1 potentiometer so the meter measures 4.51 Vdc. This will set the ECM
speed to 90% of maximum for high speed
7. Medium Speed: Using a small screwdriver turn the Flo2 potentiometer so the meter measures 3.53 Vdc. This will set the ECM speed to 70% of maximum speed for medium speed operation
8. Low Speed: Using a small screwdriver turn the Flo3 potentiometer so the meter measures 2.06 Vdc. This will set the ECM speed to 40% of maximum speed for low speed operation
9. For setting of Flo0 and Flo4 contact IEC Service Department, otherwise these potentiometers should be set to full counter clockwise rotation.
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
www.iec-okc.com
25
Page 26
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
TERMS AND CONDITIONS
1. Orders shall not be binding upon International Environmental Corporation, an Oklahoma
corporation (hereinafter referred to as “IEC”) unless accepted by an authorized representative of
IEC at its office in Oklahoma City, Oklahoma. No distributor, sales representative or any other
person or entity (except authorized employees of IEC at its office in Oklahoma City, Oklahoma)
has any authority whatsoever to bind IEC to any representation or agreement of any kind.
2. IEC does not build items to plans and specifications. IEC agrees to furnish only the items as
described in IEC’s acknowledgment unless IEC’s office in Oklahoma Cit y, Oklahoma has
previously received and accepted, in writing, approved submittals from Purchas
3. Prices acknowledged are firm only if Purchaser releases
immediate production by IEC with in sixty (60) days from the date of Purchaser’s initial offer to
purchase and f or shipment b y IEC within IEC’s estimated shipping date, unless otherwise agreed
to in writing b y IEC at its office in Oklahoma City, Oklahoma. If Purchaser does not meet the
terms and conditions of this paragraph, the prices are subject to escalation to those prices in eff ect
at time of shipment without notice to Purchaser.
4. All prices are F.O.B. IEC’s factory, unless otherwise agreed by IEC in writing; and, all payments
and prices shall be in U.S.A. dollars.
5. If goods are released for production but IEC is preve nted b y the Purchaser from shipping upon
completion or by IEC’s estimated shippi ng date, whichever is la
addition to all other remedies, invoice Purchaser to be payable within thirty (30) days and store th e
goods at Purchaser’s sole expense.
6. Title to and risk of loss to the goods passes to the Purchas er F.O.B. IEC’s factory.
7. Disclaimer
It is expressly understood that unless a statement is specifically identified as a warranty,
statements made by IEC or its representatives relating to IEC’s products, whether oral, writ ten or
contained in any sales literature, catalog or any other agreement, are not express warranties and do
not form a part of the basis of the bargain, but are merely IEC’s opinion or commendation of
IEC’s products. EXCEPT AS SPECIFICALLY SET FORTH HEREIN, THERE IS NO
EXPRESS WARRANTY AS TO ANY OF IEC’S PRODUCTS. IEC
WARRANTY AGAINST LATENT DEFECTS. IEC MAKES NO
MERCHANTABILITY OF THE GOODS OR OF THE FITNESS OF T HE GOODS FOR
ANY PARTICULAR PURPOSE.
8. Grant of Limited Express Warranty
IEC warrants IEC prod ucts purchased and retained in the United States of America and Canada to
be free from defects in material and workmanship under normal use and maintenance as fol lows:
(1) All complete fan coil units built or sold by IEC for twelve (12) months from date of unit start
up or eighteen (18) months from date of shipment (from factory), whichever comes first.
All parts must be returned to IEC’s f actory in Oklahoma City, Oklahoma, freight prepaid, no later
than sixty (60) days after the date of the failure of the part; if IEC
defective and within IEC’s Limited Express
replaced or repaired, return such to a factory recognized contractor or service organization, F.O.B.
IEC’s factory, Oklahoma City, Oklahoma, freight prepaid. The warrantyon anyparts repaired or
replaced under warranty expires at the end ofthe originalwarrantyperiod. For information and
warranty service contact:
This warrantydoes not cover and does not applyto: (1) Air filters, fuses, fluids; (2) Products
IEC is not responsiblefor: (1) The cost ofanyfluids or other systemcomponents, or associated
International Environmental Corporation
Customer Service
5000 West I-40
Oklahoma City, OK 73128
(405) 605-5000
relocatedafter initial installation; (3) Anyportion or component ofanysystemthat is not supplied
by IEC, regardless of the cause of the failure of such portion or component; (4) Products on
the unit identificationtags or labels have been removed or defaced;
payment to IEC is or has been in default; (6) Products which have defects or damage which resultfromimproper installation, wiring, electricalimbalance characteristics or maintenance; or are caused byaccident, misuse orabuse, fire, flood, alteration or misapplicationofthe product; (7)Products which have defects or damagewhich result fromacontaminated orcorrosiveair orliquid supplyor operation at abnormal temperatures; (8) Mold, fungus or bacteria damages; (9)Products subjected to corrosion or abrasion; (10) Products manufactured or supplied byothers;(11) Products which have been subjected to misuse, negligence or accidents; (12) Products whichhave beenoperated ina manner contrarytoIEC’sprinted inhave defects, damage or insuffdesign or the improper application of IEC’s products.
labor to repair or replace the same, which isincurred asa result ofa defective partcovered byIEC’s Limited ExpressWarranty; (2) The costs oflabor, materials or service incurred in removalofthe defective part,or in obtainingandreplacing thenewor repaired part;or, (3) Transportationcosts ofthe defective part from the installation site to IECor ofthe return ofanypart not covered by IEC’s Limited Express Warranty.
Limitation:
This Limited Express Warrantyis given in lieuofall other warranties. If, notwithstanding the disclaimers contained herein, it is determined that other warranties exist, anysuch warranties, including without limitation anyexpress warrantiesor anyimplied warranties offitness for particular purpose and merchantability, shall belimited to the durationofthe LimitedExpress Warranty.
Warranty, IEC shall, when such part has beeneither
icient performance as a result ofinsufficient or incorrect system
the goods covered by this order for
structions; or(13)Productswhich
er.
ter, IEC ma y at its option, in
MAKES NO
WARRANTY OF
determines the partto be
(5) Products on which
which
9. Limitation of RemediesIn the event of a breach of the Limited Express Warranty, IEC will only be obligated at IEC’s
option to repair the failed part or unit or to furnish a new or rebuilt part or unit in exchange for the
part or unit which has failed. If after written notice to IEC’s factory in Ok lahoma City, Oklahoma
of each defect, malfunction or other failure and a reasonable number of attempts by IEC to correct
the defect, malfunction or other failure and the remedy fails of its essential purpose, IEC shall
refund the purchase price paid to IEC in exchange for the return of the sold good(s). Said refund
shall be the maximum liability of IEC. THIS REMEDY IS THE SOLE AND EXCLUSIVE
REMEDY OF THE BUYER OR THEIR PURCHASER AGAINST IEC FOR BREACH OF
CONTRACT, FOR BREACH OF ANY WARRANTY OR FOR IEC’S NEGLIGENCE OR
IN STRICT LIABILITY.
10. Limitation of LiabilityIEC shall have no liability for any damages if IEC’s performance is delayed for any reason or is
prevented to any extent by an y event such as, but not limited to: any war, civil unrest, gover nment
restrictions or restraints, strikes, or work stoppages, fire, flood, accident, shortag es of
transportation, fuel, material or labor, acts of God or any other reason beyond the sole control of
IEC. IEC EXPRESSLY DISCLAIMS AND EXCLUDES ANY LIABILITY FOR
CONSEQUENTIAL OR INCIDENTAL DAMAGE IN CONTRACT, FOR B REACH OF
ANY EXPRESS OR IMPLIED WARR
NEGLIGENCE OR AS STRICT LIABILITY.
11. IEC shall have no system design, application or maintenance responsibility or responsibility for
mold, fungus or bacteria to Purchaser or any other third party.
12. All sales, good s and services, use, excise, value added, transportation, privilege, occupational
consumption, storage, document, transaction or other taxes which may be levied by any taxing
authority as a result of this transaction shall be paid by the Purchaser.
13. Unless otherwise agreed to in writing by IEC any technical data furnished in conjunction with this
order and not obtainable from another source shall not be d uplicated, used, or disclosed in whole
or in part for any purpose other than to evaluate this order.
14. IEC shall have no liability or other obligation hereunder, if IEC’s performance is del
reason or is prevented to any extent by an y event such as, but not limited to: any act of God, strike
or work stoppage, fire, flood, accident, allocation, or other controls of Government authorities,
shortages of transportation, fuel, material or labor, or any othe r cause beyond IEC’s sole control.
Any shipping date stated by IEC is IEC’s best estimate but IEC makes no guarantee of shipment
by an y such date and shall have no liabilit y or other obligation for failure to ship on such date,
regardless of cause.
15. Payment terms are net thirty (30) days from date of shipment on approved credit. One a nd one
half percent (1 1/2%) per month (18% annual rate) may be charged on past due accounts or
highest rate permitted by applicable law, whichever is lesser. In the event the account is placed for
collection, Purchaser shall be responsible f or all reasonable attorneys f ees or costs on a solicitor
and client basis, plus all other costs and expenses incurred by IEC in securing payment.
16. Purchaser shall not cancel the contract without prior written consent of an authorized
representative ofIEC at its offices in Oklahoma City, Oklahoma. In the event Purchaser cancels
the contract with the prior written consent ofIEC after the Purchaser’s offer to purchase is
received and acknowledged in writing, IEC shall be entitled to receive from Purchaser IEC’s cost
incurred to time of cancellation plus a reasonable allowance for overhead and profit.
17. Purchaser shall not assign anyof its interest or rights under this agreement without written consent
of IEC.
18. IEC will protect all its lien rights. IEC will not furnish lien waivers or releases payment, in full, at its office in Oklahoma City,Oklahoma fromPurchaser for the goods covered
bythis order. There is no authorized retainage for any reason.
19. This Agreement shall be construed, and the rights and liabilities ofthe parties hereunder shall be
determined in accordance with the laws ofthe State ofOklahoma.Ifit shall be found that anyportion of this agreement violates anyparticular law of the United States or anystate in the UnitedStates havingjurisdiction or,ifapplicable, anylawofCanadaoranyprovinceorterritoryinCanada having jurisdiction, suchportion ofthe agreement shall be ofno force and effect in thatpolitical unit, division or sub-division in which theyare illegal or unenforceable and theagreement shallanydispute or disagreement in connection with anyorder should arise or exist between Purchaserand IEC, jurisdiction and venue for anylegalaction shall be, if IEC so elects, exclusivelyin thestate or federal courts in Oklahoma County, Oklahoma. The statute oflimitations onanyclaim ofthe Purchaser against the IEC shall be one (1) year from the date the cause of action accrues.
20. Without regard to anyother agreement, all obligations ofPurchaser to IEC shall becomeimmediatelydueand payable ifPurchaser becomes insolvent or ifPurchaser doesnotmakepayments when due or breaches anyother agreement or fails to performany obligation.
21. All orders are expresslylimited and made conditional upon acceptance band conditions set forth abovewithout change. There shall be nounderstandings, agreements, or obligations (outside these terms and conditions) unless specificallyset forth in writing andaccepted bysignature of an authorized representative of IEC in Oklahoma City, Oklahoma.
22. The parties hereto have requested that these presents and all judicial proceedings relating thereto be drafted in English.Les parties aux présentes ont demandé à ce que les présentes ettoutesprocedures judiciaires yafférentes soient rédigées en anglais
be treated as ifsuch portionor portions had not been inserted. In the event that
ANTY, OR IN TORT, WHETHER FOR IEC’s
ayed for an y
the
until IEC receives
yPurchaser ofthe terms
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
26
www.iec-okc.com
Page 27
IEC Vertical F*C Series Fan Coils
INSTALLATION, OPERATION, & MAINTENANCE MANUAL
International Environmental Corporation • Vertical F*C Series Fan Coil Installation, Operation, & Maintenance Manual
www.iec-okc.com
27
Page 28
P.O. Box 2598
Oklahoma City, OK 73101-2598
p: 405.605.5000
f: 405.605.5001
www.iec-okc.com
IEC Vertical F*C Series Fan Coils IOM Part #: I100-90013980