Boiler output 'P' =70 °C Mean water kW8.814.714.723.4
temperatureBtu/h30 00050 00050 00080 000
Seasonal efficiency (SEDBUK) *Band D [ 78.8 ]%Band D [ 78.6 ]%
Nox classificationclass 4
* The value is used in the UK Government's Standard Assessment Procedure (SAP) for energy rating of dwellings.
The test data from which it has been calculated have been certified by a notified body.
Note.
Gas consumption is calculated using a calorific value of 38.7
MJ/m3 (1038 Btu/ft3) gross or 34.9 MJ/m3 (935 Btu/ft3) nett. To
obtain the gas consumption at a different calorific value:-
a. For l/s - divide the gross heat input (kW) by the gross C.V.
of the gas (MJ/m3)
3
b. For ft
/h - divide the gross heat input (Btu/h) by the gross
C.V. of the gas (Btu/ft3)
Key to symbols
GB = United Kingdom IE = Ireland
PMS = Maximum operating pressure of water
C13C33C53 = A room sealed appliance designed for connection
via ducts to a horizontal terminal which admits
fresh air to the burner and discharges the
products of combustion to the outside through
orifices which, in this case, are concentric. The
fan is up stream of the combustion chamber.
= An appliance designed for use on 2nd Family gas,
I
2H
Group H only.
(Countries of destination)
CAUTION.
this appliance, care should be taken when handling edges of sheet steel components.
To avoid the possibility of injury during the installation, servicing or cleaning of
The boiler flow and return pipes are supplied fitted to the
boiler ready for top connection
Notes.
a. For the heating loads in excess of 60, 000 Btu/hr boilers,
28mm (1") flow and return pipes should be used to and
from the boiler.
b. This appliance is NOT suitable for use with a direct hot
water cylinder.
2
BOILER CLEARANCESall dimensions in mm (in.)
The following minimum clearances must be maintained for
operation and servicing.
Additional space will be required for installation, depending upon
site conditions.
Side and Rear Flue
a Provided that the flue hole is cut accurately, e.g. with a core
drill, the flue can be installed from inside the building where wall
thicknesses do not exceed 600mm (24"). Where the space into
which the boiler is going to be installed is less than the length of
flue required the flue must be fitted from the outside.
Installation from inside ONLY
b. If a core boring tool is to be used inside
the building the space in which the boiler
is to be installed must be at least wide
enough to accommodate the tool.
5 (1/4")
5 (1/4")
165
(6 1/2")
50 (2")
50
(2")
Ecl 1574
400 (15 3/4")
Front clearance
The minimum front clearance when built in to a cupboard is
5mm (1/4") from the cupboard door but 450mm (17 3/4")
overall clearance is still required, with the cupboard door open,
to allow for servicing.
100 (4")
Jacking
screw
Gas
30 mm
(1
1/8
")
390 (15 3/8")
50 (2")
278 (11")
50 (2")
50 (2")
Flue
terminal
582
(23")
Ecl 1575
111mm
Gas
(4
3/8
")
* Bottom clearance
Bottom clearance after installation can be reduced to 5mm.
However, 100mm must be available for servicing.
4
classic m - Installation & Servicing
GENERAL
INTRODUCTION
The classic m boiler is a fully automatically controlled, wall
mounted, low water content, fan flued, non condensing gas
boiler. It has full modulating central heating outputs of 8.8 kW
(30,000 Btu/h) to 14.7 kW (50,000 Btu/h) and 14.7Kw (50 000
Btu/h) to 23.4Kw (80 000 Btu/h)
The boiler casing is of white painted mild steel with user controls
capable of being mounted remotely from the boiler, if the option
is required.
The heat exchanger is cast iron.
Note. These boilers cannot be used on systems which include
gravity circulation.
The boilers are suitable for connection to fully pumped, open
vented or sealed water systems. Adequate arrangements for
completely draining the system by provision of drain cocks
MUST be provided in the installation pipework.
OPERATION
When there is a demand for heat, the heating system is supplied
selected temperature of between 65oC and 82oC.
The boiler features a comprehensive diagnostic system which
gives detailed information on the boiler status when operating
and performance of key components to aid commissioning and
fault finding.
BS. 5440:2 Ventilation (for gas appliances of rated input not
exceeding 70 kW).
BS. 5449Forced circulation hot water systems.
BS. 5546Installation of gas hot water supplies for domestic
purposes (2nd Family Gases).
BS. 6798Installation of gas fired hot water boilers of rated
input not exceeding 60 kW.
BS. 6891Low pressure installation pipes.
Health & Safety Document No. 635
The Electricity at Work Regulations, 1989.
The manufacturer’s notes must NOT be taken, in any way, as
overriding statutory obligations.
IMPORTANT. These appliances are CE certificated for safety
and performance. It is, therefore, important that no external
control devices, e.g. flue dampers, economisers etc., are directly
connected to these appliances unless covered by these
Installation and Servicing Instructions or as otherwise
recommended by Caradon Plumbing Limited in writing. If in
doubt please enquire.
Any direct connection of a control device not approved by
Caradon Plumbing Ltd. could invalidate the certification and
the normal appliance warranty. It could also infringe the Gas
Safety Regulations and the above regulations.
OPTIONAL EXTRA KITS
z D Pack Flue Extension Ducts (1000mm long)
z Flue Finishing Kit
o
Elbow Kit (Maximum 2 per installation)
z 90
o
Elbow Kit (Maximum 2 per installation)
z 45
z Roof flue Kit
z Powered Vertical Flue Kit
z Remote User Controls Kit
z Boiler Stand-off Kit
SAFETY
Current Gas Safety (Installation and Use) Regulations or rules
in force.
It is law that all gas appliances are installed and serviced by a
CORGI registered installer in accordance with the above
regulations. Failure to install appliances correctly could lead to
prosecution. It is in your own interest, and that of safety, to
ensure the law is complied with.
The installation of the boiler MUST also be in accordance with
the latest I.E.E (BS 7671) Wiring Regulations, local building
regulations, bye-laws of the local water authority, the building
regulations and the Building Standards (Scotland) and any
relevant requirements of the local authority.
SAFE HANDLING OF SUBSTANCES
Care should be taken when handling the boiler insulation
panels, which can cause irritation to the skin. No asbestos,
mercury or CFCs are included in any part of the boiler or its
manufacture.
LOCATION OF BOILER
The boiler must be installed on a flat and vertical wall, capable
of adequately supporting the weight of the boiler and any
ancillary equipment.
The boiler may be fitted on a combustible wall and insulation
between the wall and the boiler is not necessary, unless
required by the local authority.
For electrical safety reasons there must be no access from the
back of the boiler.
The boiler must not be fitted outside.
Detailed recommendations are contained in the following British
Standard Codes of Practice:
BS. 5440:1Flues (for gas appliances of rated input not
exceeding 70 kW).
classic m - Installation & Servicing
Timber Framed Buildings
If the boiler is to be fitted in a timber framed building it should be
fitted in accordance with the British Gas publication 'Guide for
Gas Installations in Timber Frame Housing', reference IGE/UP/
7:1998.
5
GENERAL
Compartment Installations
A compartment used to enclose the boiler should be designed
and constructed specially for this purpose.
An existing cupboard or compartment may be used, provided
that it is modified for the purpose.
In both cases details of essential features of cupboard /
compartment design, including airing cupboard installation, are
to conform to the following:
z BS. 6798. (No cupboard ventilation is required - see “Air
Supply” for details).
z The position selected for installation MUST allow adequate
space for servicing in front of the boiler.
z For the minimum clearances required for safety and
subsequent service, see the wall mounting template and
Frame 2. In addition, sufficient space may be required to
allow lifting access to the wall mounting plate.
GAS SUPPLY
The local gas supplier should be consulted, at the installation
planning stage, in order to establish the availability of an
adequate supply of gas. An existing service pipe must NOT be
used without prior consultation with the local gas supplier. The
boiler must installed on a gas supply with a governed meter
only.
A gas meter can only be connected by the local gas supplier or
by a registered CORGI engineer.
An existing meter should be checked, preferably by the gas
supplier, to ensure that the meter is adequate to deal with the
rate of gas supply required. A working gas pressure of
20 mbar should be available at the boiler inlet.
IMPORTANT.
Installation pipes MUST be fitted in accordance with BS. 6891.
Pipework from the meter to the boiler MUST be of an adequate
size, i.e. not less than 15mm O.D.
The complete installation MUST be tested for gas soundness
and purged as described in the above code.
Table 3 - Balanced flue terminal position
Terminal Position
1. Directly below or alongside an
opening window, air vent or other300 mm (12")
ventilation opening
2. Below guttering, drain pipes or soil
pipes75 mm ( 3")
3. Below eaves200 mm ( 8")
4. Below balconies or a car port roof200 mm ( 8")
5. From vertical drain pipes or soil pipes75 mm ( 3")
6. From internal or external corners300mm (12")
7. Above adjacent ground, roof or
balcony level300 mm (12")
8. From a surface facing the terminal600 mm (24")
9. From a terminal facing a terminal1200 mm (48")
10. From an opening in a car port
(e.g. door or window) into dwelling1200 mm (48")
11. Vertically from a terminal on the
same wall1500 mm (60")
12. Horizontally from a terminal on the wall300 mm (12")
boiler MUST NOT be closer than 25mm (1") to combustible
material. Detailed recommendations on the protection of
combustible material are given in BS. 5440: 2000.
Minimum Spacing
IMPORTANT. It is absolutely ESSENTIAL to ensure, in
practice, that products of combustion discharging from the
terminal cannot re-enter the building or any other adjacent
building through ventilators, windows, doors, other sources of
natural air infiltration, or forced ventilation / air conditioning.
If this should occur the appliance MUST be turned OFF, labelled
as 'unsafe' until corrective action taken.
TERMINAL
The terminal assembly can be adapted to accommodate various
wall thicknesses. Refer to Frame 11 - Unpacking.
FLUE INSTALLATION
The flue must be installed in accordance with the
recommendations of BS. 5440: Part 1.
The following notes are intended for general guidance.
1. The boiler MUST be installed so that the terminal is exposed
to external air.
2. It is important that the position of the terminal allows the free
passage of air across it at all times.
3. Minimum acceptable spacing from the terminal to
obstructions and ventilation openings are specified in
Table 3.
4. Where the lowest part of the terminal is fitted less than 2m
(6'6") above a balcony, above ground or above a flat roof to
which people have access, then the terminal MUST be
protected by a purpose designed guard.
Ensure that the guard is fitted centrally.
5. Where the terminal is fitted within 850mm (34") of a plastic or
painted gutter or 450mm (18") of painted eaves then an
aluminium shield at least 750mm (30") long should be fitted
centrally to the underside of the gutter or painted surface.
6. The air inlet/products outlet duct and the terminal of the
AIR SUPPLY
It is NOT necessary to have a purpose-provided air vent in the
room or internal space in which the boiler is installed. Neither is
it necessary to ventilate a cupboard or compartment in which the
boiler is installed, due to the low surface temperatures of the
boiler casing during operation; therefore the requirements of BS
6798, Clause 12, and BS 5440:2 may be disregarded.
WATER CIRCULATION SYSTEM
For the types of system and correct piping procedure see
Frames 1, and 3 to 8.
The central heating system should be in accordance with
BS. 6798 and, in addition, for smallbore and microbore systems,
BS. 5449.
WATER TREATMENT - see Frame 9
The hot water storage cylinder MUST be of the indirect type and
should preferably be manufactured of copper.
Single feed, indirect cylinders are not recommended and MUST
NOT be used on sealed systems.
The appliances are NOT suitable for gravity central heating nor
are they suitable for the provision of gravity domestic hot water.
6
classic m - Installation & Servicing
GENERAL
The hot water cylinder and ancillary pipework, not forming part
of the useful heating surface, should be lagged to prevent heat
loss and any possible freezing - particularly where pipes run
through roof spaces and ventilated underfloor spaces.
The boiler must be vented.
The hydraulic resistance of the boilers, at MAXIMUM OUTPUT,
with an 11 oC (20 oF) temperature differential, is shown in
Graph 1.
Graph 1 - Water flow rate and pressure loss
1.0
0.5
THERMOSTATIC RADIATOR VALVES (TRV)
Caradon Plumbing Ltd. recommend that heating systems
utilising full thermostatic radiator valve control of temperature in
individual rooms should also be fitted with a room thermostat
controlling the temperature in a space served by radiators not
fitted with such a valve as stated in BS. 5449.
For further information refer to the 'Good Practice Guide 143',
publication of the Energy Efficiency Office, available from the
Building Research Establishment, Garston, Watford WD2 7JR.
Tel: 01923 664 258
ELECTRICAL SUPPLY
Wiring external to the appliance MUST be in accordance with
the current I.E.E. (BS.7671) Wiring Regulations and any local
regulations which apply.
The point of connection to the mains should be readily
accessible and adjacent to the boiler.
Pressure Drop Across Boiler
(metres water)
8.811.714.717.620.523.4
Boiler Output (kW)
Ecl 1603
classic m - Installation & Servicing
7
GENERAL
3
OPEN VENT SYSTEM REQUIREMENTS
The system should be vented directly off the boiler flow pipe, as close to the
boiler as possible. The cold feed entry should be inverted and MUST be
positioned between the pump and the vent, and not more than 150mm (6")
away from the vent connection.
Note.Combined feed and vent pipes may also be fitted.
There should be a minimum height, 450mm (18"), of open vent above the
cistern water level. If this is not possible refer to
Frame 5. The vertical distance between the highest point of the system and
the feed/expansion cistern water level MUST not be less than 450 mm (18").
The pump must be fitted on the flow side of the boiler.
A suitable pump is a domestic circulator capable of providing a maximum
o
C (20oF) temperature differential across the boiler with the whole of the
11
heating circuit open (e.g. Grundfos UPS 15/50, 15/60 or equivalent). With the
minimum flow circuit allowed by the controls the differential must not exceed
25 oC.
The vertical distance between the pump and feed/expansion cistern MUST
comply with the pump manufacturer's minimum requirements, to avoid
cavitation. Should these conditions not apply either lower the pump position
or raise the cistern above the minimum requirement specified by CaradonPlumbing Ltd. The isolation valves should be fitted as close to the pump as
possible.
Ecl 1604
4
SCHEMATIC PIPEWORK AND SYSTEM BALANCING
The boiler does not normally need a
bypass but at least some radiators on the
heating circuit, of load at least 10% of the
minimum boiler output, must be provided
with twin lockshield valves so that this
minimum heating load is always available
(see footnote re. thermostatic radiator
valves).
Balancing
1. Set the programmer to ON for both
CH and HW. Turn the cylinder
thermostat down. Close the manual
or thermostatic valves on all radiators,
leaving the twin lockshield valves (on
the radiators referred to above) in the
open position. Turn up the room
thermostat and adjust these lockshield
valves to give boiler flow and return
temperatures not more than 20
apart. These valves should now be left
as set.
2. Open all manual or thermostatic
radiator valves and adjust the
lockshield valves on remaining
radiators to give around 11
temperature drop at each radiator.
3. Turn up the cylinder thermostat and
adjust the cylinder balancing valve so
that the cylinder achieves a maximum
flow consistent with adequate flow to
the radiators. Check that with only the
domestic hot water loop in circuit a
differential temperature of 20
across the boiler is not exceeded.
4. Adjust room and cylinder thermostats
and programmer to NORMAL settings.
o
C
o
C
o
C
Ecl 1605
Note.
Systems incorporating zone valves which
could completely shut off the flow through
the system, must be wired such that the
boiler will not fire or continue to fire when
this occurs.
8
classic m - Installation & Servicing
GENERAL
5
LOW HEAD AND LARGE SYSTEMS WITH EXTENSIVE PIPE RUNS - OPEN VENT
This arrangement is useful for large systems where
radiators at the extremities are difficult to vent. This can
lead to pumping over with conventional feed and vent
arrangements.
The following conditions MUST be observed:
1. The top of the automatic air vent must be below the
cold water level.
2. The static water level (cold) must be at least 200mm
above the top of the horizontal flow pipe, fitted as
shown. The vent connection MUST NOT be made
immediately off the top of the boiler as venting is
made less efficient.
3. The maximum practical length of 22mm cold feed pipe
should be used in order to reduce the effective
volume of hot system water expanding into the feed/
expansion cistern to a minimum.
Note.The pump manufacturers' minimum requirements must be complied with.
Ecl 1606
Ecl 1606
All dimensions in mm (in.).
NB. Imperial dimensions are approximate
6
SEALED SYSTEM REQUIREMENTS
Note. The method of filling, refilling, topping up or flushing
sealed primary hot water circuit from the mains via a
temporary hose connection is only allowed if acceptable
to the local water authority.
1. General
a. The installation must
comply with the
requirements of BS.
6798 and BS. 5449.
b. The installation
should be designed
to work with flow
temperatures of up
to 82° C.
c. All components of the
system, including the
heat exchanger of the
indirect cylinder, must
be suitable for a working pressure of 3 bar (45lb/in
) and temperature of 110°C. Care should be taken
in making all connections so that the risk of leakage
is minimised.
2. Safety Valve
A spring loaded safety valve complying with the relevant
requirements of BS. 6759 must be fitted in the flow pipe
as close to the boiler as possible and with no intervening
valve or restriction. The valve should have the following
features:
a. A non-adjustable preset lift pressure not exceeding
3bar (45lb/in
b. A manual testing device.
2
).
2
c. Provision for connection of a discharge pipe.
3. Pressure Gauge
A pressure gauge covering at least the range 0-4 bar
(0-60 lb/in
be easily seen from the filling point and should preferably be
connected at the same point as the expansion vessel.
The valve or discharge pipe should be positioned so that
the discharge of water or steam cannot create a hazard
to the occupants of the premises or cause damage to
electrical components and wiring.
2
) must be fitted to the system. The gauge should
classic m - Installation & Servicing
9
7
SEALED SYSTEM REQUIREMENTS - continued
4. Expansion Vessel
a. A diaphragm type expansion vessel must be
connected to a point close to the inlet side of the
pump, the connecting pipe being not less than 15
1/2" nominal) size and not incorporating valves
mm (
of any sort.
b. The vessel capacity must be adequate to accept the
expansion of the system water when heated to 110°
C (230° F).
c. The charge pressure must not be less than the static
water head above the vessel. The pressure attained
in the system when heated to 110° C (230° F) should
be at least 0.35 bar (5 Ib/in
2
) less than the lift
pressure of the safety valve.
For guidance on vessel sizing refer to the table in
Frame 8.
For further details refer to BS. 5449, BS. 7074:1 and
the British Gas Corporation publication 'Material and
Installation Specifications for Domestic Central
Heating and Hot Water'.
5. Cylinder
The cylinder must be either of the indirect coil type or a
direct cylinder fitted with an immersion calorifier which is
suitable for operating on a gauge pressure of 0.35 bar
2
(5 Ib/in
) in excess of the safety valve setting. Single feed
indirect cylinders are not suitable for sealed systems.
6. Make-up Water
Provision must be made for replacing water loss from the
system, either:
a. From a manually filled make-up vessel with a readily
visible water level. The vessel should be mounted at
least 150 mm (6") above the highest point of the
system, and be connected through a non-return
valve to the system, fitted at least 300 mm (12")
below the make-up vessel on the return side of the
domestic hot water cylinder or radiators.
or
b. Where access to a make-up vessel would be difficult
by pre-pressurisation of the system. Refer to 'Filling',
below.
7. Mains Connection
There must be no direct connection to the mains water
supply or to the water storage tank supplying domestic
water, even through a non-return valve, without the
approval of the local water authority.
8. Filling
The system may be filled by one of the following
methods:
a. Through a cistern, used for no other purposes, via a
ball valve permanently connected directly to a
service pipe and/or a cold water distributing pipe.
The static head available from the cistern should be
adequate to provide the desired initial system design
pressure. The cold feed pipe from the cistern should
GENERAL
include a non-return valve and a stop valve with an
automatic air vent connected between them, the stop
valve being located between the system and the
automatic air vent. The stop valve may remain open
during normal operation of the system if automatic
water make-up is required.
b. Through a self-contained unit comprising a cistern,
pressure booster pump (if required) and, if necessary,
an automatic pressure reducing valve and flow
restrictor. The cistern should be supplied through a
temporary connection from a service pipe or cold
water distributing pipe.
This unit may remain permanently connected to the
heating system to provide limited automatic water
make-up. Where the temporary connection is
supplied from a service pipe or distributing pipe which
also supplies other draw-off points at a lower level
then a double check valve shall be installed upstream
of the draw-off point.
c. Through a temporary hose connection from a draw-off
tap supplied from a service pipe under mains
pressure. Where the mains pressure is excessive a
pressure reducing valve shall be used to facilitate
filling.
The following fittings shall form a permanent part of
the system and shall be fitted in the order stated:
A stop valve complying with the requirements of
BS. 1010, Part 2 (the hose from the draw-off tap shall
be connected to this fitting).
A test cock.
A double check valve of an approved type.
• Thoroughly flush out the whole of the system with
cold water, without the pump in position.
• With the pump fitted, fill and vent the system until the
pressure gauge registers 1.5 bar (21.5lb/in
2
).
Examine for leaks.
• Check the operation of the safety valve by manually
raising the water pressure until the valve lifts. This
should occur within ± 0.3 bar (± 4.3lb/in
2.
) of the pre-
set lift pressure.
• Release water from the system until the initial
system design pressure is reached.
• Light the boiler and heat the system to the maximum
working temperature. Examine for leaks.
• Turn off the boiler and drain the system while still
hot.
• Refill and vent the system.
• Adjust the initial pressure to the required value.
Sizing procedure for expansion vessels: The volume of the expansion vessel (litres) fitted to a sealed system shall not be
less than that given by the table on the following page, multiplied by a factor of 0.8 (for flow temperatures of less than 83 °C).
10
classic m - Installation & Servicing
GENERAL
8
SEALED SYSTEM REQUIREMENTS - continued
Safety valve setting3.0 bar2.5 bar2.0 bar
Vessel charge and initial0.51.01.50.51.01.50.51.0
system pressurebarbarbarbarbarbarbarbar
Total water content of systemExpansion vessel volume litres
25litres2.12.73.92.33.35.92.85.0
504.25.47.84.76.711.85.610.0
756.38.211.77.010.017.78.415.0
1008.310.915.69.413.423.711.320.0
12510.413.619.511.716.729.614.125.0
15012.516.323.414.120.135.516.930.0
17514.619.127.316.423.441.419.735.0
20016.721.831.218.826.847.422.640.0
22518.724.535.121.130.153.325.445.0
25020.827.239.023.533.559.228.250.0
27522.930.042.925.836.865.131.055.0
30025.032.746.828.240.271.133.960.0
Multiplying factors for
other system volumes0.08330.1090.1560.0940.1340.2370.1130.20
9
WATER TREATMENT
The classic m boiler has a cast iron heat exchanger
IMPORTANT.
The application of any other treatment to this product may render the guarantee of Caradon Plumbing
invalid.
If water treatment is used Caradon Plumbing Ltd. recommend only the use of FERNOX or SENTINEL water treatment
products, which must be used in accordance with the manufacturers' instructions. For further information contact:
Fernox Manufacturing Co. Ltd.
Tandem House
Marlowe Way
Croydon
Surrey CRO 4XS
Tel: 0870 5601 5000
Notes.
1. It is most important that the correct concentration of the
water treatment product is maintained in accordance with
the manufacturers' instructions.
2. If the boiler is installed in an existing system any unsuitable
additives MUST be removed by thorough cleansing.
BS. 7593:1992 details the steps necessary to clean a
domestic central heating system.
3. In hard water areas, treatment to prevent lime scale
may be necessary - however, the use of artificially
softened water is NOT permitted.
4. Under no circumstances should the boiler be fired
before the system has been thoroughly flushed.
Sentinel Division
Betz Dearborn Ltd.
Widnes
Cheshire
WA8 8UD
Tel:0151 424 5351
classic m - Installation & Servicing
11
10
BOILER ASSEMBLY - Exploded view
INSTALLATION
INSTALLATION
8
53
5
44
9
10
7
23
2
24
6
13
25
1
LEGEND
1.Front casing panel.
2.Case sealing panel.
4.Bottom cover panel.
5.Flue sensing nipple.
6.Flue baffle (5080 only).
7.Flue hood.
8.Flue connection.
9.Flue hood clip.
42
26
15
16
10. Flue hood seal.
11. Burner assy.
12. C/Cham Insulation.
13. Heat engine.
14. Injector & housing.
15. Venturi assy.
16. Fan assy.
17. Gas pipe assy.
21
14
20
19
17
35
19. Gas valve assy.
20. Fan bracket assy.
21. Orifice plate.
23. Control thermistor.
24. Overheat thermostat.
25. Igniton electrode.
26. Flame sensing electrode.
35. User control.
12
11
Ecl 1628
4
51
36
36. PCB - primary controls.
42. Sightglass.
44. Wall mtg. plate.
51. Mains connector.
53. Turret gasket .
12
classic m - Installation & Servicing
INSTALLATION
11
UNPACKING
The boiler is supplied fully assembled in one Pack A,
together with a standard flue assembly for lengths up to
460mm, rear or side flue outlet, in Pack B.
Optional extras if ordered are supplied in separate boxes.
Unpack and check the contents.
Pack A Contents
Also contained in Pack A:
z Hardware Pack (listed below).
z These Installation & Servicing Instructions.
z The User's Instructions.
z The User's control.
z Benchmark log book.
Hardware Pack
z 50mm x No.10 wood screws -
3 off.
z Wall plugs (TP2B ) - 3 off.
z Turret clamp.
z M5 x 10 pozi Hex screw.
z Mains connector.
INSTALLATION
Pack B Contents
zFlue turret.
zFlue terminal.
zFlue support cutting aid.
12
PACKAGING REMOVAL
1. Ensure the boiler is stood correctly as marked on the
carton.
2. Remove the strapping.
3. Fold back the top flaps to gain access to the wall
mounting plate, instructions, user controls and
hardware pack.
Ecl 1608
Flue turret assembly
Ecl 1460
Flue terminal
4. Remove instructions and read thoroughly before
unpacking, user’s controls and hardware pack and
retain in safe place.
5. Lift off the cardboard carton.
6. Dispose of packaging.
classic m - Installation & Servicing
Ecl 1576
13
INSTALLATION
13
FRONT PANEL AND BOTTOM PANEL REMOVAL
1. Remove the 2 retaining screws.
2. Lift front panel and remove.
3. Remove the 2 bottom panel screws.
4. Allow the RHS of the bottom panel to lower slightly.
5. Withdraw the LHS of the bottom panel from the retaining
clips.
6. Place bottom and front panel to one side to avoid
damage.
Ecl 157
3
INSTALLATION
14
DETERMINING THE FLUE LENGTH AND FLUE PACKS REQUIRED
IMPORTANT.
The boiler MUST be installed in a vertical position
Dimension X - Wall thickness.
Dimension L - Wall thickness plus
boiler spacing.
Dimension S - Stand-off frame depth = 33mm
FLUE KITS
Pack B - supplied as standard
Pack D - optional extension kit for side flue
or rear flue outlet.
Refer to 'Flue Extension Ducts'
1
160 + S = 193mm
160mm
Total Flue length dimensionFlue
Rear flueSide flueExtra packs
dim. X+160flue dim. L+195required
Up to 480 mmUp to 480 mmnone
Up to 1430 mmUp to 1430 mmPack D - 1 off
Up to 2380 mmUp to 2380 mmPack D - 2 off
Up to 3000 mmUp to 3000 mmPack D - 3 off
Note.
If the boiler is to be installed with downward routing of
pipes then the optional stand-off kit can be used. Care
must taken when cutting the ducts and marking the wall
to suit this condition.
Ecl 1578
14
classic m - Installation & Servicing
Loading...
+ 30 hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.