Maximum Installation Weightkg (lb)46.6 (103)46.7 (103)46.9 (103)
Boiler Casing SizeHeightmm (in)687 (27)
Widthmm (in)390 (15 3/8)
Depthmm (in)278 (11)
*Required for maximum flow rate. Boiler operates down to 0.2bar with reduced DHW delivery
** In areas of low water pressure the DHW restrictor can be removed
DHW Flow Ratel/min9.612.014.4
at 35°C temp. rise.(gpm)(2.1)2.6(3.2)
DHW Specific Ratel/min11.214.016.8
NOx ClassificationClass 5
C-10g/s74oC - 12 g/s82oC-14g/s
Nett CVkW24.330.236.0
(Btu/h) (82 900) (103 000) (122 800)
Gross CVkW27.033.539.9
(Btu/h) (92 100) (114 400) (136 200)
3
(ft
/h)(89.0)(110)(131)
(gpm)(2.5)(3.1)(3.7)
* The value is used in the UK Government's Standard Assessment Procedure (SAP) for energy rating of dwellings. The test data from which
it has been calculated have been certified by a notified body.
Note. Gas consumption is calculated using a
calorific value of 38.7 MJ/m
3
(1038 Btu/ft3) gross
or 34.9 MJ/m3 (935 Btu/ft3) nett
To obtain the gas consumption at a different
calorific value:
a. For l/s- divide the gross heat input (kW) by
the gross C.V. of the gas (MJ/m
b. For ft
3
/h - divide the gross heat input (Btu/h)
3
)
by the gross C.V. of the gas (Btu/ft3)
CAUTION.
To avoid the possibility of injury during the installation, servicing or cleaning of
Key to symbols
GB = United KingdomIE = Ireland(Countries of destination)
PMS = Maximum operating pressure of water
C
13 C33 C53
= A room sealed appliance designed for connection via ducts to a
horizontal or vertical terminal, which admits fresh air to the burner
and discharges the products of combustion to the outside through
orifices which, in this case, are concentric. The fan is up stream
of the combustion chamber.
I
= An appliance designed for use on 2nd Family gas, Group H only.
2H
this appliance care should be taken when handling edges of sheet steel components
4
evo HE C - Installation and Servicing
GENERAL
evo HE
Natural Gas only
Boiler sizeG.C. Appliance No.PI No.
(Benchmark No.)
C22/2447 348 3287 BP 34
C22/3047 348 3387 BP 34
C22/3547 348 3487 BP 34
Destination Country: GB, IE
CONTENTS
Air Supply ....................................................................... 8
For GB, to comply with Building Regulations Part L1 (Part 6 in Scotland) the boiler should be fitted in accordance with the
manufacturer's instructions. Self-certification that the boiler has been installed to comply with Building Regulations can be
demonstrated by completing and signing the Benchmark Commissioning Checklist.
Before installing this boiler, read the Code of Practice sheet at the rear of this book.
BENCHMARK COMMISSIONING CHECKLIST DETAILS
BoilerPage
Make and model .......................................................5
Appliance serial no. on data badge ....... Front Cover
For all boilers: complete, sign & hand over to customer
For assistance see Technical Helpline on the back page
Page
NOTE TO THE INSTALLER:
COMPLETE
THE BENCHMARK COMMISSIONING
CHECKLIST AND LEAVE THESE
INSTRUCTIONS WITH APPLIANCE
5evo HE C - Installation and Servicing
GENERAL
INTRODUCTION
The evo HE range of boilers are wall mounted, full sequence, automatic spark
ignition, low water content, fanned flue, high efficiency, condensing,
combination gas boilers.
Note.Due to the high efficiency of the boiler a plume of water vapour will form
at the terminal during operation.
Central heating (CH) output is fully modulating with a range of 8.8 to 22 kW
(30,000 to 75,000 Btu/h)
Instantaneous domestic hot water (DHW) output is also fully modulating with
a maximum of :
C22/2423.4kW (80,000 Btu/h)
C22/3029.3kW (100,000 Btu/h)
C22/3535.2kW (120,000 Btu/h)
The boiler is supplied fully assembled with DHW plate heat exchanger,
Variable CH and DHW temperature controls are fitted on the user control and
the boiler features a DHW preheat facility.
The boiler casing is of white painted mild steel with the user controls capable
of being mounted remotely from the boiler if the option is required.
The boiler temperature controls are visible at the bottom RHS of the front
panel.
The heat exchanger is of cast aluminium.
The boiler is suitable for connection to fully pumped, sealed water systems
ONLY. Adequate arrangements for completely draining the system by
provision of drain cocks MUST be provided in the installation pipework.
Pipework from the boiler is routed downwards as standard, but may be routed
upwards behind the boiler using the stand-off frame (supplied in a separate
kit).
1
BOILER WATER
CIRCUIT DIAGRAMS
OPERATION
With no demand for CH, the boiler fires only when DHW is drawn off, or
periodically for a few seconds without any DHW draw-off, in order to maintain
the DHW calorifier in a heated condition.
When there is a demand for CH, the heating system is supplied at the
selected temperature of between 30 oC and 82oC, until DHW is drawn off.
The full output from the boiler is then directed via the diverter valve to the
plate heat exchanger to supply a nominal DHW draw-off of
C22/249.6 l/min at 35
C22/3012 l/min at 35 oC temperature rise.
C22/3514.4 l/min at 35
The DHW draw off rate specified above is the nominal that the boiler flow
regulator will give. Due to system variations and seasonal temperature
fluctuations DHW flow rates/temperature rise will vary, requiring adjustment at
the draw off tap.
At low DHW draw-off rate the maximum temperature is limited to 65
modulating gas control.
Refer also to Frame 1 - 'Boiler Water Circuit Diagrams'
The boiler features a comprehensive diagnostic system which gives detailed
information on the boiler status when operating, and performance of key
components to aid commissioning and fault finding.
o
C temperature rise.
o
C temperature rise.
o
C by the
SAFE HANDLING
This boiler may require 2 or more operatives to move it to its installation site,
remove it from its packaging base and during movement into its installation
location. Manoeuvring the boiler may include the use of a sack truck and
involve lifting, pushing and pulling.
Caution should be exercised during these operations.
Operatives should be knowledgeable in handling techniques when performing
these tasks and the following precautions should be considered:
•Grip the boiler at the base.
•Be physically capable.
•Use PPE as appropriate, e.g. gloves, safety footwear.
During all manoeuvres and handling actions, every
attempt should be made to ensure the following
unless unavoidable and/or the weight is light.
•Keep back straight.
•Avoid twisting at the waist.
•Avoid upper body/top heavy bending.
•Always grip with the palm of the hand.
•Use designated hand holds.
•Keep load as close to the body as possible.
•Always use assistance if required.
6
evo HE C - Installation and Servicing
GENERAL
OPTIONAL EXTRA KITS
•Flue Extension Ducts (1000mm long).
C22/24 & 30-up to 6m
C22/35-up to 3m
•Flue Finishing Kit
o
•90
Elbow Kit (maximum per installation).
C22/24 & 30-up to 4 elbows
C22/35-up to 2 elbows
o
•45
Elbow Kit (maximum per installation).
C22/24 & 30-up to 4 elbows
C22/35-up to 2 elbows
•Concentric Flue Screw Retaining Kit
•Roof Flue Kit (to a maximum of 7.5m).
•Powered Vertical Flue Kit (5m primary and 17m secondary
is a typical maximum length. For alternative details refer to
Powered Vertical Instructions).
•High Level Flue Outlet Kits
•Flue Deflector Kit
•Weather Collar
•Horizontal Flue Terminal 600mm long
•Remote User Controls Kit
•Boiler Stand-off Kit
•Siphon Kit
•Valve Cover Kit
•Condensate Pump Kit
•Pre-piping Frame
•Adjustable flue support bracket
SAFETY
Current Gas Safety (installation and use) regulations or rules
in force:
The appliance is suitable only for installation in GB and IE and
should be installed in accordance with the rules in force.
In GB, the installation must be carried out by a Gas Safe
Registered Engineer. It must be carried out in accordance with
the relevant requirements of the:
•Gas Safety (Installation and Use) Regulations
•The appropriate Building Regulations either The Building
Regulations, The Building Regulations (Scotland), Building
Regulations (northern Ireland).
•The Water Fittings Regulations or Water byelaws in
Scotland.
•The Current I.E.E. Wiring Regulations.
Where no specific instructions are given, reference should be
made to the relevant British Standard Code of Practice.
In IE, the installation must be carried out by a Registered Gas
Installer (RGII) and installed in accordance with the current
edition of I.S.813 "Domestic Gas Installations", the current
Building Regulations and reference should be made to the
current ETCI rules for electrical installation.
Detailed recommendations are contained in the following British
Standard Codes of Practice:
BS. 5440:1Flues (for gas appliances of rated input not
exceeding 70 kW).
BS. 5440:2Ventilation (for gas appliances of rated input not
exceeding 70 kW).
BS. 5449Forced circulation hot water systems.
BS. 5546Installation of gas hot water supplies for
domestic purposes (2nd Family Gases)
BS. 6798Installation of gas fired hot water boilers of rated
input not exceeding 70 kW.
BS. 6891Low pressure installation pipes.
Health & Safety Document No. 635.
The Electricity at Work Regulations, 1989.
The manufacturer’s notes must NOT be taken, in any way, as
overriding statutory obligations.
IMPORTANT. These appliances are CE certificated for safety
and performance. It is, therefore, important that no external
control devices, e.g. flue dampers, economisers etc., are
directly connected to these appliances unless covered by these
Installation and Servicing Instructions or as otherwise
recommended by Wolseley Centers Ltd. in writing. If in doubt
please enquire.
Any direct connection of a control device not approved by
Wolseley Centers Ltd. could invalidate the certification and the
normal appliance warranty. It could also infringe the Gas Safety
Regulations and the above regulations.
SAFE HANDLING OF SUBSTANCES
Care should be taken when handling the boiler insulation panels,
which can cause irritation to the skin. No asbestos, mercury or
CFCs are included in any part of the boiler or its manufacture.
LOCATION OF BOILER
The boiler must be installed on a flat and vertical wall, capable
of adequately supporting the weight of the boiler and any
ancillary equipment.
The boiler may be fitted on a combustible wall and insulation
between the wall and the boiler is not necessary, unless
required by the local authority.
For electrical safety reasons there must be no access available
from the back of the boiler.
The boiler must not be fitted outside.
Timber Framed Buildings
If the boiler is to be fitted in a timber framed building it should be
fitted in accordance with the Institute of Gas Engineering
document IGE/UP/7:1998.
Bathroom Installations
This appliance is rated IP20.
The boiler may be installed in any room or internal space,
although particular attention is drawn to the requirements of the
current IEE (BS.7671) Wiring Regulations and, in Scotland, the
electrical provisions of the building regulations applicable in
Scotland, with respect to the installation of the boiler in a room
or internal space containing a bath or shower. For IE reference
should be made to the current ETCI rules for electrical
installations and I.S. 813:2002.
If the appliance is to be installed in a room containing a bath or
shower then, providing water jets are not going to be used for
cleaning purposes (as in communal baths/showers), the
appliance must be installed in Zone 2, as detailed in BS.7671.
Compartment Installations
A compartment used to enclose the boiler should be designed
and constructed specially for this purpose.
An existing cupboard or compartment may be used, provided
that it is modified for the purpose.
In both cases, details of essential features of cupboard /
compartment design, including airing cupboard installation, are
to conform to the following:
z BS 6798 (No cupboard ventilation is required - see ‘Air
Supply’ for details).
z The position selected for installation MUST allow adequate
space for servicing in front of the boiler.
z For the minimum clearances required for safety and
subsequent service, see the wall mounting template and
Frame 2. In addition, sufficient space may be required to
allow lifting access to the wall mounting plate.
7evo HE C - Installation and Servicing
GENERAL
GAS SUPPLY
The local gas supplier should be consulted, at the installation
planning stage, in order to establish the availability of an
adequate supply of gas. An existing service pipe must NOT be
used without prior consultation with the local gas supplier.
The boiler MUST be installed on a gas supply with a governed
meter only.
A gas meter can only be connected by the local gas supplier or
by a Gas Safe Registered Engineer. In IE by a Registered Gas
Installer (RGII).
An existing meter should be checked, preferably by the gas
supplier, to ensure that the meter is adequate to deal with the
rate of gas supply required.
It is the responsibility of the Gas Installer to size the gas
installation pipework in accordance with BS6891:2005. Whilst
the principle of the 1:1 gas valve ensures the evo C range is
able to deliver it’s full output at inlet pressures as low as 14mb,
other gas appliances in the property may not be as tolerant.
When operating pressures are found to be below the minimum
meter outlet of 19mb these should be checked to ensure this is
adequate for correct and safe operation.
Allowing for the acceptable pressure loss of 1mb across the
installation pipework, it can be assumed that a minimum
permitted operating pressure of 18mb will be delivered to the
inlet of the appliance. (Reference BS 6400-1 Clause 6.2
Pressure Absorption).
The integral appliance isolation valve and boiler pipework
could further reduce the operating pressure by up to 1.5mb
when measured at the inlet test point on the appliance gas
valve. Therefore it has been identified that an operating
pressure as low as 16.5mbar could be measured at the
appliance inlet pressure test point on the gas valve.
IMPORTANT.
Installation pipes must be fitted in accordance with BS.6891. In
IE refer to IS.813:2002. Pipework from the meter to the boiler
MUST be of an adequate size.
Table 4 - Balanced Flue Terminal Position
Flue Terminal Positions
1. Directly below, above or alongside an opening
window, air vent or other ventilation opening.300mm (12")
2. Below guttering, drain pipes or soil pipes.25mm ( 1")*
BS5440-1 200075mm (3")
3. Below eaves.25mm (1")*
BS5440-1 2000200mm (8")
4. Below balconies or a car port roof.25mm (1")*
BS5440-1 2000200mm (8")
5. From vertical drain pipes or soil pipes.25mm (1")*
BS5440-1 2000150mm (6")
6. From an internal or external corner or to a25mm (1")*
boundary along side the terminal.BS5440-1 2000300mm (12")
7. Above adjacent ground, roof or balcony level.300mm (12")
8. From a surface or a boundary facing the terminal. 600mm (24")
9. From a terminal facing a terminal.1,200mm (48")
10. From an opening in a car port
(e.g. door or window) into dwelling.1,200mm (48")
11. Vertically from a terminal on the same wall.1,500mm (60")
12. Horizontally from a terminal on the wall.300mm (12")
Vertical Terminals
13. Above the roof pitch with roof slope of all angles. 300mm (12")
Above flat roof.300mm (12")
14. From a single wall face.300mm (12")
From corner walls.300mm (12")
* Only one reduction down to 25mm is allowable per installation
otherwise BS5440-1 2000 dimensions must be followed.
Min. Spacing*
8
The complete installation MUST be tested for gas tightness and
purged as described in the above code.
FLUE INSTALLATION
Pluming will occur at the terminal so terminal positions where
this could cause a nuisance should be avoided.
The flue must be installed in accordance with the
recommendations of BS. 5440-1: 2000.
In IE refer to I.S. 813:2002.
The following notes are intended for general guidance:
1. The boiler MUST be installed so that the terminal is exposed
to external air.
2. It is important that the position of the terminal allows the free
passage of air across it at all times.
3. Minimum acceptable spacing from the terminal to
obstructions and ventilation openings are specified in
Table 4.
4. Where the lowest part of the terminal is fitted less than 2m
(6'6") above a balcony, above ground or above a flat roof to
which people have access then the terminal MUST be
protected by a purpose designed guard.
Terminal guards are available from boiler suppliers. (Ask for
TFC flue guard model no. K6 - round, plastic coated). In case
of difficulty contact:
5. The flue assembly shall be so placed or shielded as to
prevent ignition or damage to any part of any building.
6. The air inlet/products outlet duct and the terminal of the boiler
MUST NOT be closer than 25mm (1") to combustible
material. Detailed recommendations on the protection of
combustible material are given in BS. 5440-1:2000.
IMPORTANT. It is absolutely essential to ensure, in practice,
that products of combustion discharging from the terminal
cannot re-enter the building or any other adjacent building
through ventilators, windows, doors, other sources of natural air
infiltration, or forced ventilation / air conditioning.
If this should occur the appliance MUST be turned OFF, labelled
as 'unsafe' until corrective action can be taken.
TERMINAL
The terminal assembly can be adapted to accommodate various
wall thicknesses. Refer to Frame 12 .
AIR SUPPLY
It is NOT necessary to have a purpose-provided air vent in the
room or internal space in which the boiler is installed. Neither is
it necessary to ventilate a cupboard or compartment in which
the boiler is installed, due to the low surface temperatures of
the boiler casing during operation; therefore the requirements of
BS 6798, Clause 12, and BS 5440:2 may be disregarded.
WATER CIRCULATION SYSTEM
IMPORTANT.
A minimum length of 1 metre of copper pipe MUST be fitted to
both flow and return connections from the boiler before
connection to any plastic piping.
The central heating system should be in accordance with
BS.6798 and, in addition, for smallbore and microbore
systems, BS.5449.
WATER TREATMENT - see Frame 6
evo HE C - Installation and Servicing
GENERAL
6065557965
95
evfu9802
2
BOILER DIMENSIONS, SERVICES & CLEARANCES
The boiler connections are made on the boiler connection tails.
Refer to Frames 32-35.
The following minimum clearances must be maintained for
operation and servicing.
Additional space will be required for installation, depending
upon site conditions.
Side and Rear Flue
a. Provided that the flue hole is cut accurately, e.g. with a
core drill, the flue can be installed from inside the building
where wall thicknesses do not exceed 600mm (24"). Where
all dimensions in mm (in)
the space into which the boiler is going to be installed is
less than the length of flue required the flue must be fitted
from the outside.
Installation from inside ONLY
b. If a core boring tool is to be used inside the building the
space in which the boiler is to be installed must be at least
wide enough to accommodate the tool.
Front clearance
The minimum front clearance when built in to a cupboard is 5mm (1/
4") from the cupboard door but 450mm (17 3/4") overall clearance is
still required, with the cupboard door open, to allow for servicing.
N.B. The boiler will not fit into a standard depth wall unit. In order for
it to do so the plastic fascia should be removed. See Frame 44.
* Bottom clearance
Bottom clearance after installation can be reduced to 5mm.
However, 100mm must be available for servicing.
SIDE FLUE ONLY
Horizontal length of flueTop clearance
from centre line of boilerrequired (MIN.)
to outside wallDim. A
C22/24 C22/30 C22/35
0.5 m0.5 m0.5 m160 mm (6
1.0 m1.0 m1.0 m170 mm (6
1.5 m1.5 m1.5 m185 mm (7 1/4")
1.5 m1.5 m1.5 m200 mm ( 7
2.5 m2.5 m2.5 m210 mm (8 1/4")
3.0 m3.0 m3.0 m225 mm (8
3.5 m3.5 mN/A250 mm (9 7/8")
4.0 m4.0 mN/A260 mm (10
4.5 m4.5 mN/A265 mm (10 7/16")
5.0 m5.0 mN/A275 mm (10
5.5 m5.5 mN/A290 mm (11 3/8")
6.0 m6.0 mN/A300 mm (11
REAR FLUE ONLY
MIN. Top clearance required = 145 mm (5
5/16")
11/16)
7/8")
7/8")
1/4")
13/16")
13/16")
3/4")
9evo HE C - Installation and Servicing
GENERAL
BOILER CONTROL INTERLOCKS
Wolseley Centres Ltd. recommend that heating systems
utilising full thermostatic radiator valve control of
temperature in individual rooms should also be fitted with a
room thermostat controlling the temperature in a space
served by radiators not fitted with such a valve as stated in
BS. 5449.
Central heating systems controls should be installed to
ensure the boiler is switched off when there is no demand
for heating or hot water.
When thermostatic radiator valves are used, the space
heating temperature control over a living / dining area or
hallway having a heating requirement of at least 10% of the
boiler heat output should be achieved using a room
thermostat, whilst other rooms are individually controlled by
thermostatic radiator valves. However, if the system
employs thermostatic radiator valves on all radiators, or two
port valves, then a bypass circuit must be fitted with an
automatic bypass valve to ensure a flow of water should
all valves be in the closed position.
3
SYSTEM REQUIREMENTS - Central Heating
Notes
a. The method of filling, refilling, topping up or flushing sealed
primary hot water circuits from the mains via a temporary hose
connection is only allowed if acceptable to the local water
authority.
b. Antifreeze fluid, corrosion and scale inhibitor fluids suitable
for use with boilers having aluminium heat exchangers may
be used in the central heating system.
Advice should be sought from a local water treatment company.
General
1. The installation must comply with all relevant national and
local regulations.
2. The installation should be designed to work with flow
temperatures of up to 82
3. All components of the system must be suitable for a working
pressure of 3 bar and temperature of 110
should be taken in making all connections so that the risk of
leakage is minimised.
The following components are incorporated within the
appliance:
a. Circulating pump.
b. Safety valve, with a non-adjustable preset lift pressure of
3 bar.
c. Pressure gauge, covering a range of 0 to 6 bar.
d. An 8-litre expansion vessel, with an initial charge pressure
of 0.75 bar.
4. 'Make-up' Water. Provision must be made for replacing water
loss from the system, either :
a. From a manually filled 'make-up' vessel with a readily
visible water level. The vessel should be mounted at
least 150mm above the highest point of the system and
be connected through a non-return valve to the system,
fitted at least 150mm below the 'make-up' vessel on the
return side of the radiators.
o
C.
o
C. Extra care
ELECTRICAL SUPPLY
WARNING.
This appliance must be earthed.
Wiring external to the appliance MUST be in accordance with the
current I.E.E. (BS.7671) Wiring Regulations and any local
regulations which apply. For IE reference should be made to the
current ETCI rules for electrical installations.
The point of connection to the mains should be readily accessible
and adjacent to the boiler.
Note. The fan voltage is 325V DC
CONDENSATE DRAIN Refer to Frames 22 & 54.
A condensate drain is provided on the boiler. This drain must be
connected to a drainage point on site. All pipework and fittings in the
condensate drainage system MUST be made of plastic - no other
materials may be used.
IMPORTANT.
Any external runs must be insulated
The drain outlet on the boiler is standard 21.5mm (3/4”) overflow pipe.
Safety valve settingbar3.0
Vessel charge pressurebar0.5 to 0.75
System pre-charge pressure barNone1.0
System volumeExpansion vessel
(litres)volume (litres)
251.61.8
503.13.7
754.75.5
1006.37.4
1257.89.2
1509.411.0
17510.912.9
19011.914.0
20012.514.7
25015.618.4
30018.822.1
For other system volumes
multiply by the factor across0.0630.074
or
b. Where access to a 'make-up' vessel would be difficult,
by pre-pressurisation of the system.
The maximum cold water capacity of the system
should not exceed 143 litres, if not pressurized.
However, if the system is to be pressurized, the
efficiency of the expansion vessel will be reduced and
a larger vessel (or smaller system volume) may be
necessary. If the capacity of the vessel is not
considered sufficient for this, or for any other reason,
10
evo HE C - Installation and Servicing
GENERAL
CH Return
Ecl 6053
Hose unions
Mains
water supply
Temporary hose
(disconnect after filling)
Additional
stop valve
Double check valve
assembly
(
note direction of flow
)
4
SYSTEM REQUIREMENTS - CH (continued) and Hot Water
an additional vessel MUST be installed on the return to
the boiler.
Guidance on vessel sizing is given in Frame 3.
5. Filling. The system may be filled by the following method:
a. Through a temporary hose connection from a 'draw-off'
tap, supplied from a service pipe under mains pressure.
Where the mains pressure is excessive a pressure
reducing valve must be used to facilitate filling.
When installing the filling device it must be connected as
shown below, to fully comply with the water regulations.
This may involve the fitting of an additional WRAS
approved isolator valve to the mains supply.
i. Thoroughly flush out the whole system with
cold water.
ii. Fill and vent the system until the pressure
gauge registers 1bar and examine for leaks.
iii. Release water from the system until the
minimum system design pressure is reached;
1.0 bar if the system is to be pre-pressurised.
Water Flow Rate and Pressure Loss
Max CH OutputkW23.4
(Btu/h)(80 000)
Water flow ratel/sec0.37
(gal/min)4.8
o
Temperature Differential
C15
o
F)(27)
(
Head available form.w.g.2.3
system pump.(ft.w.g.)7.5
DOMESTIC HOT WATER
1. The domestic hot water service must be in accordance with
BS 5546 and BS 6700.
2. Refer to Table 1 for minimum and maximum working
pressures.
3. The boilers are suitable for connection to most types of
washing machine and dishwasher appliances.
4. When connecting to suitable showers, ensure that:
a. The cold inlet to the boiler is fitted with an approved
anti-vacuum or syphon non-return valve.
b. Hot and cold water supplies to the shower are of equal
pressure.
5
SYSTEM BALANCING
The boiler does not normally need a bypass but at least some
radiators on the heating circuit, of load of at least 10% of the
minimum boiler output, must be provided with twin lockshield
valves so that this minimum heating load is always available.
See note regarding thermostatic radiator valves on page 10.
Note. Systems incorporating zone valves which could
completely cut off the flow through the system must also
include a bypass.
BALANCING
1. Set the programmer to ON.
Close the manual or thermostatic valves on all radiators,
leaving the twin lockshield valves (on the radiators referred
to above) in the OPEN position.
5. Hard Water Areas
Where the water hardness exceeds 200mg/litre, it is
recommended that a proprietary scale reducing device is
fitted into the boiler cold supply within the requirements of
the local water company.
IMPORTANT
Provision MUST be made to accommodate the expansion of
DHW contained within the appliance, if a non-return valve is
fitted to the DHW inlet.
Turn up the room thermostat and adjust these lockshield
valves to give boiler flow and return temperatures not
more than 20 oC differential.
These valves should now be left as set.
2. Open all manual or thermostatic radiator valves and
adjust the lockshield valves on the remaining radiators,
to give around 15
3. Adjust the room thermostat and programmer to
NORMAL settings.
o
C temperature drop at each radiator.
11evo HE C - Installation and Servicing
INSTALLATION
6
WATER TREATMENT
CENTRAL HEATING
The evo HE range of boilers have an ALUMINIUM alloy
heat exchanger.
IMPORTANT.
The application of any other treatment to this product
may render invalid the guarantee of Wolseley Centres
Ltd.
Wolseley Centres Ltd. recommend Water Treatment in
accordance with the Benchmark Guidance Notes on
Water Treatment in Central Heating Systems.
If water treatment is used Wolseley Centres Ltd.
recommend only the use of FERNOX-COPAL, MB1, GE BETZ or
SENTINEL X100 inhibitors and associated water treatment
products, which must be used in accordance with the
manufacturers' instructions.
Notes.
1. It is most important that the correct concentration of the
water treatment products is maintained in accordance with
the manufacturers' instructions.
DOMESTIC HOT WATER
In hard water areas where main water can exceed 200ppm
Total Hardness (as defined by BS 7593:2006 Table 2) a
scale reducing device should be fitted into the boiler cold
supply within the requirements of the local water company.
The use of artificially softened water, however, is not
permitted.
Wolseley Centres Ltd. recommend the use of Fernox
Qantomat, GE Betz Sentinel Combiguard and Calmag
CalPhos I scale reducing devices, which must be used in
accordance with the manufacturers' instructions.
For further information contact:
Fernox Manufacturing Co. Ltd
Cookson Electronics
Forsyth Road
Sheerwater
Woking
Surrey GU21 5RZ
+44 (0) 1799 521133
Sentinel Performance Solutions
The Heath Business & Technical Park
Runcorn
Cheshire WA7 4QX
Tel: 0800 389 4670
www.sentinel-solutions.net
2. If the boiler is installed in an existing system any unsuitable
additives MUST be removed by thorough cleansing. BS
7593:2006 details the steps necessary to clean a domestic
heating system.
3. In hard water areas, treatment to prevent lime scale may be
necessary - however the use of artificially softened water is
NOT permitted.
4. Under no circumstances should the boiler be fired before
the system has been thoroughly flushed.
7
BOILER ASSEMBLY - Exploded View Legend
Note that item numbers are linked to the spares list
1.Front casing panel.
2.Boiler sealing panel.
3.Sump cover.
4.Bottom casing panel.
5.Flue sensing nipple.
6.Return pipe.
8.Flue manifold.
10.Interpanel.
11.Burner.
12.Combustion chamber insulation.
13.Heat exchanger.
14.Injector and housing.
15.Venturi assembly.
16.Fan assembly.
17.Automatic air vent (Heat Exchanger)
18.Gas service cock.
19.Gas control valve.
20.Fan bracket.
21.Orifice plate.
23.Control thermistor (flow/return)
24.Overheat thermostat.
25.Ignition electrode.
26.Flame detection electrode.
32.Kit - Trap and seal.
35.User control.
36.Primary controls (PCB).
39.Mains switch.
40.Spark generator.
44.Wall mounting plate
51.Mains connector.
53.Turret gasket kit.
57.CH stub pipe.
Salamander Engineering Ltd
The Heath Business & Technical Park
Runcorn
Cheshire WA7 4QX
Tel: 0800 389 4670
Calmag Ltd.
Unit 4-6, Crown Works
Bradford Road
Sandbeds, Keighley
West Yorkshire BD20 5LN
Tel: +44 (0) 1535 210 320
59.Flow restrictor.
60.DHW inlet/outlet pipe.
61.Pressure relief valve.
62.Expansion vessel.
64.Pressure gauge.
66.Diverter valve head.
67.Diverter valve.
68.Diverter valve manifold.
69.Pump
70.Pump manifold.
71.DHW plate heat exchanger.
75.Control box clamp.
94.Ignition lead.
98.Air Vent (Pump)
103. Dry fire thermistor.
12
evo HE C - Installation and Servicing
8
62
44
5
4
10
25
17
103
8
11
26
12
13
3
23
32
19
36
39
35
24
71
98
69
74
57
60
18
60
68
67
66
6
51
64
57
75
59
61
40
94
53
14
15
21
16
20
2
1
evfu9803
BOILER ASSEMBLY - Exploded View
INSTALLATION
INSTALLATION
evo HE C - Installation and Servicing
13
INSTALLATION
9
UNPACKING
The boiler is supplied fully assembled in one Pack A, together with a telescopic flue
assembly for lengths up to 595mm, rear or side flue outlet, in Pack B.
Unpack and check the contents.
Pack A Contents
ABoiler
BHardware Pack Box
CWall Mounting Plate
DThese Installation/Users
Instructions
INSTALLATION
EWall Mounting Template
(located on internal
protective packaging)
F1 Year Guarantee
A
C
E
B
D
F
evfu9804
Hardware Pack Contents
A Support Bracket - 1 off
B Accessory Pack
C CH Flow Valve & Gauge Pack
D DHW Pack
Pack B Contents
ATelescopic flue terminal
BFlue turret
CRubber Terminal Wall Seal
DScrew
ESealing tape
14
E Gas Valve Pack
F CH Return Valve Pack
G “S” Trap Hose Moulding
B
A
D
E
C
isfu8751d
evo HE C - Installation and Servicing
10
PACKAGING REMOVAL
1. Ensure the boiler is on a sound flat
surface.
2. Carefully remove the strapping.
3. Fold back the top flaps to gain access to:
z Instructions
z 1 year guarantee
z Wall mounting plate
z Wall mounting template.
(located under pre-piping frame on
protective packaging).
4. Remove the instructions and read
thoroughly before unpacking the product.
5. When ready for installation lift off the
cardboard carton.
INSTALLATION
Wall Mounting template/
protective packaging
INSTALLATION
Hardware
pack box
11
BOTTOM AND FRONT PANEL REMOVAL
1. Remove the screw from the
underside of the boiler’s bottom
panel.
2. Pull the right-hand side of the panel
down, slide it to the right and
withdraw.
3. Remove the screws from bottom of
the front panel.
4. Lift panel up and off top pegs.
3
Boiler
1
evfu9805
evfu
9806
evo HE C - Installation and Servicing
2
15
INSTALLATION
Wall Thickness X
160 mm
160 + S = 193mm
nm8943
195mm
195mm
Wall Thickness X
Sideflue length L
12
DETERMINING THE FLUE LENGTH AND FLUE PACKS REQUIRED
IMPORTANT. The boiler MUST be installed in a vertical position
(Centre Line of turret to outside of wall terminal)- ONE PIECE TERMINAL = 285MM
FLUE KITS
Pack B - supplied as standard
Pack D - optional extension kit for side flue or rear flue outlet.
Screw Kit - Optional kit for mechanical fixing of flue joints
Finishing Kit - Supplied as an optional extra.
Refer to 'Flue Extension Ducts'
SIDE FLUE
REAR FLUE
FLUE OUTLET
16
evo HE C - Installation and Servicing
INSTALLATION
12A
Notes.
1. It is recommended that a support bracket is
fitted for every 1 meter of extension pipe used
and a bracket should be used at every joint,
to ensure pipes are held at the correct angle.
If a slip joint coupling is to be used then a
bracket should be used to secure the collar.
2. When extension ‘D’ packs are used the flue
duct MUST be inclined at 1.5 degrees to the
horizontal to allow condensate to drain back
into the boiler and out through the
condensate drain.
3. If the telescopic ‘B’ pack, or horizontal flue
terminal (600 long) only are used, they may
be mounted horizontally. The 1.5 degrees is
taken care of by the inclination of the flue
within the air pipe.
4. If the boiler is to be installed with upward
piping routed behind the boiler then the
optional stand-off kit should be used. Care
must be taken when cutting the ducts and
marking the wall to suit this condition.
5. Only use water as a lubricant during
assembly. Do not use mineral based oils.
CONT’D DETERMINING THE FLUE LENGTH AND FLUE PACKS REQUIRED
Total Flue length dimensionFlue
(measuring from CL of turret to outside wall)
Rear flueSide flueExtra packsBoiler
dim. X+160 dim. L+195requiredSize
Up to 595 mmUp to 595 mmnoneC22/24,30 & 35
Up to 1545 mm Up to 1545 mmPack D - 1 offC22/24,30 & 35
Up to 2495 mm Up to 2495 mmPack D - 2 offC22/24,30 & 35
Up to 3445 mm Up to 3445 mmPack D - 3 off C22/24,30 & 35*
Up to 4395 mm Up to 4395 mmPack D - 4 offC22/24 & 30
Up to 5345 mm Up to 5345 mmPack D - 5 offC22/24 & 30
Up to 6000 mm Up to 6000 mmPack D - 6 offC22/24 & 30
*evo HE C22/35 is capable of 3m flue only
13
FLUE ASSEMBLY - Exploded View
An optional flue duct extension kit is
required for wall thicknesses greater
than :
Side 395mm
Rear 435mm
LEGEND
1. Duct assembly.
2. Flue turret.
3. Turret gasket.
4. M5 x 10 pozi screw.
5. Turret clamp.
Rear flue arrangement shown
TOP
1
The flue terminal MUST be
fitted with the ‘TOP’
uppermost to allow the
correct fit and use of the
plume management system.
nm8760
FLUE OUTLET
evo HE C - Installation and Servicing
17
INSTALLATION
nm8772
C22/35
C22/24 & C22/30
14
WALL MOUNTING TEMPLATE
The wall mounting template is located on the internal
protective packaging.
Note.
The template shows the positions of the fixing holes and
the rear flue hole centre for standard installation. Care
MUST be taken to ensure the correct holes are drilled.
1. Tape template into the selected position. Ensure
squareness by hanging a plumbline as shown.
2. If fitting a side flue extend the flue centre line onto the side
wall and measure in 155mm for standard installation.
Note. If using stand-off kit distance increases to 188mm.
3. Mark onto the wall the following:
a The wall mounting plate screw positions (choose one
from each group).
b. The position of the flue duct hole (see diagram below).
Note. Mark the centre of the hole as well as the
circumference.
4. Remove the template from the wall.
Extendedcentre line
155
V - See Diagram Below
nm9279
15
PREPARING THE WALL
IMPORTANT.
Ensure that, during the cutting operation, masonry
falling outside of the building does not cause damage
or personal injury.
1. Cut the flue hole (preferably with a 5" core boring
tool), ensuring that the hole is square to the wall.
Both wall faces immediately around the cut hole
should be flat.
2. Drill 4 holes with a 7.5mm / 8mm masonry drill
and insert the plastic plugs, provided, for the
piping frame.
3. Locate 4 No.14 x 50mm screws in the piping
frame (one at each side, in any of the 3 holes
provided at each side) and screw home.
FLUE OUTLET
18
X
Section
through wall
Rear flue only
5" diameter hole
Note. Check all of the hole
positions before drilling.
evo HE C - Installation and Servicing
Side flue only
5" diameter hole
2011
INSTALLATION
var9784
Rubber
Terminal
Wall Seal
nm8944
X + 75
Drill hole
Adhere sealing tape
Measurement to be
taken from this point
16
TERMINAL WALL SEAL ASSEMBLY / POSITIONING
Prior to fitting the flue, the rubber terminal wall seal provided
in the flue pack MUST be fitted to the flue terminal as shown
below in Figure 1.
FIGURE 1FIGURE 2
Once the flue is installed it is IMPORTANT that the rubber
terminal wall seal is pressed against the outside wall to
create an adequate seal between the flue and wall as
shown in Figure 2.
Wall Seal Lip
Step
Ensure lipofwall seal ispositionedoversteponplasticnoseofflueterminal
(note, sealis cut away forclarity)
isfu9783
17A
SETTING THE FLUE - REAR Wall thicknesses of 210 to 435mm
Notes.
a. If using the extension ducts go to Frame 18.
b. If the stand-off frame is used it is essential to add 33mm
to dimension X.
c. For shorter flue requirements less than 210mm, use non
telescopic B Pack.
1. Measure and note wall thickness X. Refer to Frame 12.
2. Add 75mm to dimension X and set telescopic flue length
as indicated in drawing.
3. Using a 3.5mm drill bit, drill one hole in outer air duct
taking care not to pierce plastic inner flue.
4. Fix to length using self tappers provided.
5. Seal outer air duct using the tape provided.
17B
SETTING THE FLUE - SIDEWall thicknesses of 170 to 395mm
Notes.
a. If using the extension ducts go to Frame 18.
b. For shorter flue requirements use non telescopic B
Pack.
1. Measure and note wall thickness X. Refer to Frame 12.
2. Measure distance from side of boiler to inside of wall
and add to wall thickness X=L. Refer to Frame 12.
3. Add 115mm to dimension L and set telescopic flue
length as indicated in drawing.
4. Using a 3.5mm drill bit, drill one hole in outer air duct
taking care not to pierce plastic inner flue.
5. Fix to length using self tappers provided.
6. Seal outer air duct using the tape provided.
evo HE C - Installation and Servicing
Drill hole
nm8945
Adhere sealing tape
L + 115
Measurement to be
taken from this point
FLUE OUTLET
19
INSTALLATION
nm8762
Boiler
Standardflue
Terminal grille
Flue length
Extensionflue
18
FLUE EXTENSION DUCTS - For total flue lengths greater than 595mm
Pack D Flue extension duct kit contents
Extension duct & clamp
1.0m (39") long
nm8732
19
FLUE EXTENSION DUCTS - continued
Use a maximum of 6m extended flue ONLY (C22/24 &
30)
Use a maximum of 3m extended flue ONLY (C22/35)
Flue duct support
General arrangement
1. A maximum of 6 extension ducts for the C22/24
and C22/30 and a maximum of 3 extension ducts
for the C22/35 (one suitably cut) plus the
standard flue duct may be used together.
2. Flue extensions of greater length than 1m (39")
should be supported with the bracket provided,
suitably adjusted. Refer to Frames 18 and 26.
3. Only use water as a lubricant during assembly.
Do not use mineral based oils.
Flue support cutting aid
(shown folded up)
Wall plugs - 4 off
No. 10 x2" wood screw - 4 off
Note. Side flue shown
20
FITTING THE KIT
Because of the flexibility of the telescopic flue terminal it is not
always necessary to cut an extension pack.
1. Measure the total flue length from the centre of the boiler
outlet to the outside wall.
2. Subtract 70mm from this dimension.
3. Subtract 950mm for each ‘D’ pack to be used.
4. If the remainder Y is 300mm -
525mm this can be taken up by
the adjustment in the
telescopic flue.
5. If the remainder Y is 525mm 950mm it will be necessary to
cut a ‘D’ pack to 400mm.
70
FLUE OUTLET
esp8940
20
6. if the remainder Y is less than 300mm, shorten the
previous ‘D’ pack to 400mm and adjust the telescopic
terminal.
7. Measure and mark the length on the flue, to ensure a
square cut mark the flue all the way around and cut to
length.
L
950
Y
525
300
evo HE C - Installation and Servicing
INSTALLATION
21
FITTING THE WALL MOUNTING PLATE (Rear Flue outlet shown)
TO FIT THE WALL MOUNTING PLATE DIRECTLY TO THE WALL
•Insert wall plugs.
•Put the screws into the wall plugs and leave 10mm proud
•Hang the plate onto the screws (take care to use the same
hole position from each group as previously chosen with
the wall template) and tighten up.
•Locate the support bracket on the mounting plate.
TO FIT THE WALL MOUNTING PLATE USING THE STAND-OFF
FRAME OPTION KIT (To allow pipework to be taken
upwards)
•Put the screws into the wall plugs and leave 10mm
proud.
•Hang the stand-off frame onto the screws and tighten up.
•Fasten the wall mounting plate to the stand-off frame with
the 6mm screws provided.
•Locate the support bracket on the mounting plate.
Note.
If the clearances above and below the boiler are less than
the length of the pipes it will be necessary to position the
pipes behind the wall mounting plate BEFORE the plate is
screwed to the wall.
evo HE C - Installation and Servicing
FLUE OUTLET
21
22
CONDENSATE DRAIN
Before mounting the boiler on the wall, the condensate
drain (provided in the h/ware pack) must be connected
from the boiler ‘S’ trap to a drainage point, preferably
within the building.
Ensure that the condensate trap is full of water before
commissioning the boiler . Refer to Frame 26.
The routing of the drain must be made to allow a
minimum fall of 1 in 20 away from the boiler, throughout
its length.
The drainage pipework must be arranged so that
obstruction (e.g. through freezing) of external drainage
pipe does not give rise to spillage within the dwelling.
INSTALLATION
IMPORTANT.
If excessive external pipework cannot be avoided an
additional siphon kit and insulation are recommended to
prevent possible freezing.
All pipework and fittings in the condensate drain system
must be made of plastic. No other materials may be
used.
The drain outlet on the boiler is standard 21.5mm
overflow pipe. This size must not be reduced in any part
of its length.
If external condensate pipe run is greater than 3m then
pipe must be 32mm nominal diameter.
Consideration must be given to insulating external
condensate pipe runs.
INSTALLATION
23
CONDENSATE PIPE TERMINATION CONFIGURATIONS
Notes: ALL PIPE RUNS MUST BE IN ACCORDANCE WITH BS6798
1. INTERNAL TO SINK WASTE
UPSTREAM OF SINK WASTE
TRAP
2. INTERNAL TO SINK WASTE
BOILER
cla7771b
BOILER
Sink constitutes
air break
DOWNSTREAM OF SINK
WASTE TRAP (PREFERRED
METHOD)
Air Break
cla9252
75mm trap
Open end of pipe
direct into gulley
below grating but
above water level
Ground Level
DRAIN
Sink
Open end of pipe
direct into gulley
below grating but
above water level
Ground Level
DRAIN
22
continued . . . .
evo HE C - Installation and Servicing
INSTALLATION
BOILER
External
wall
Ground Level
Termination
to Soak away
cla7774
minimum
500mm
24
CONDENSATE PIPE TERMINATION CONFIGURATIONS . . . continued
3. INTERNAL CONNECTION TO SOIL AND VENT STACK
Termination into a down pipe can take place providing it can be confirmed that
the down pipe is part of a combined waste and rain water system.
* Make connection to SVP using a solvent welded saddle
4. TERMINATION TO SOAK AWAY
BOILER
Air Break
INSTALLATION
cla9253
5. TERMINATION TO DRAIN / GULLEY
evo HE C - Installation and Servicing
BOILER
External
wall
Open end of pipe
direct into gulley
below grating but
above water level
cla7775
Ground Level
DRAIN
23
INSTALLATION
25
MOUNTING THE BOILER
1. Before mounting the boiler on the wall place it on its left hand
side and fit ‘S’ trap hose, supplied in the hardware pack.
2. Locate position of 15mm copper safety drain discharge pipe.
Ensure this pipe is not strained or damaged when mounting the
boiler.
3. Ensure that the plastic blanking plugs are removed from all of
the boiler service connections before mounting. Note that some
spillage of water may occur when mounting the boiler to the
frame.
4. Lift the boiler onto the wall mounting frame, locating it
over the tabs at the top of the frame. When handling
the boiler take care not to place strain on safety valve
discharge pipe.
5. Lower the boiler into position, engaging it onto the
support bracket.
INSTALLATION
1
2
IMPORTANT: When handling the boiler take
care not to place strain on the safety valve
discharge pipe.
26
CONNECTING THE FLUE TO THE BOILER
Note. Before fitting the flue turret fill the condensate trap within the
boiler by pouring a cupful of water into the flue outlet A.
Take care to ensure that the water is only poured into the flue
outlet, and does not spill into the boiler casing.
2
1. Locate the flue into the turret.
2. Insert the flue assembly through the
prepared hole in the wall. Push
through and pull back to seal against
outside wall face.
3. Locate the flue turret on the top of
the boiler, ensuring that the turret
gasket is in place. Also ensure the
turret is located concentric with the
flue aperture on the boiler top panel.
Check that the flue seal ‘A’ located in
the top of the flue manifold is secure
and giving an effective seal.
4. Secure the flue turret on top of the boiler
by inserting the open ends of the turret
clamp under the 2 studs and fixing it in the
middle with the single M5 x 10mm pozi-hex
screw provided.
5. Flues over 1 metre long.
Fix the flue support bracket to the wall, using the 4 wall
plugs and wood screws.
NB. The space bracket will utilise one fixing hole only whilst
used in conjunction with the stand-off option.
24
3
1
nm8764
evo HE C - Installation and Servicing
INSTALLATION
27
FITTING THE OPTIONAL ROOF FLUE KIT (Flat or Pitched)
Note.
A flat or pitched roof flashing plate (not supplied) is required before
proceeding with the installation of this kit.
This kit is suitable for both flat and pitched roof terminations, using a
concentric flue to run vertically from the top of the boiler and terminating
above roof level.
Connection to the top of the boiler is made using both a separately supplied
vertical connector and a 80/125 adaptor.
WEATHER PROOFING
Where the flue passes through the roof line an
adequate seal must be made. This is achieved
by using either:
-Flat roof weather collar
or
-Universal weather collar.
ACCESSORIES
Flue Duct Extension Kits are available for
flue lengths extending beyond 1m. These
packs contain 1m extension ducts and may
be cut to the desired length.
If the offset vertical option is used an elbow
Kit is required. For a full accessories list
refer to page 7, Optional Extras and Frame
31, Flue Arrangement.
nm8736
28
ROOF FLUE KIT CONTENTS / OPTIONS
Flue Terminal
UIN 203132
Flue
duct
support
Flue Seal Collar - Flat Roof
UIN 152259
Flue Seal Collar - Tile Roof
UIN 152258
Vertical connector
UIN 203135
o
45
elbow
UIN 203131
Roof Flue Extension Duct
UIN 203129
o
90
elbow
UIN 203130
evo HE C - Installation and Servicing
nm8735
FLUE OUTLET
25
INSTALLATION
rf8394-1
690mm
Fixed
300mm
min
rf8393-1
300mm
min
300mm
min
625mm
Fixed
Flat roof - with structure
29
FLUE TERMINAL POSITION
The terminal should be positioned so that products of
combustion can safely disperse at all times.
Pluming may occur at the termination so, where
possible, terminal positions where this could cause
a nuisance should be avoided.
Minimum dimensions are shown below
rf8392
FLUE OUTLET
26
Terminal PositionMinimum Dimension
Directly below an opening,
air brick, windows, etc.300 mm
Below plastic / painted gutters300 mm
Below eaves or balcony500 mm
Painted surface300 mm
evo HE C - Installation and Servicing
INSTALLATION
rf8737
rf8738
30
FLUE ARRANGEMENT
Note.
The equivalent flue length resistance of the elbow kits are:
o
90
elbow kit = 1m
o
45
elbow kit = 0.6m
evo HE C - Installation and Servicing
FLUE OUTLET
27
INSTALLATION
nm8740
Flue Terminal
Pitchedrooftile
weathercollar
Flatrooftile
weathercollar
1
nm8741
2
Extension
Duct
Vertical
connector
Turret
clamp
3
31
ASSEMBLING THE ROOF FLUE KIT
Determine the correct height that the flue should terminate
above the roof. If after calculating or measuring the overall flue
height from the top of the boiler, it is necessary to cut both pipes
of assembly A, then ensure they are cut equally leaving the inner
flue tube longer than the outer air tube as supplied.
Ensure the cut pipe ends are free from any burrs.
1. Position the roof flashing plate (supplied separately) over the
hole cut in the roof and insert flue terminal from the roof end.
MAX LENGTH:
7.5m
o
o
min 16
max 41
BOILER
2. Fit the vertical connector (supplied seperately) in accordance
with the in the instructions provided with the vertical connector
kit. ENSURE THE GASKETS IN THE BOILER FLUE OUTLET
ARE CORRECTLY FITTED.
3. "Push" fit extension duct (if required (supplied separately)) into
vertical connector.
nm8739
nm8743
FLUE OUTLET
28
'X'
4. If the last extension duct requires cutting, measure ‘X’, the distance
(outer ducts), between the duct and the terminal and add 100 mm to
this dimension. This gives the length of the last extension duct.
4
Note. Check the position of the inner flue duct relative to the outer duct
on the assembled extension duct(s) and ensure the terminal flue duct is
cut longer than the air duct to ensure engagement in the final flue duct
seal.
5. Finally ensure the roof flashing plate is correctly sealed to the roof.
evo HE C - Installation and Servicing
INSTALLATION
32
WATER CONNECTIONS - CH
1. Connect boiler service valves and copper tails provided in the hardware pack to the threaded boss connections
provided at the lower rear of the boiler. Ensure all boss blanking plugs are removed before connecting hardware. Each
valve must be fitted to the correct boss as shown in the picture. Guidance to correct connection location is also provided
on the wall-mounting template. Ensure each union is fitted with fibre seals provided.
2. If connecting the boiler to heating loads in excess of 60,000 Btu/h, connecting flow and return heating system
pipework must be sized in 28mm diameter at the point of pipe connection to the boiler tails. Use 22mm x 28mm pipe
adaptors as appropriate.
3. Do not subject any of the isolating valves to heat as the seals may be damaged.
33
WATER CONNECTIONS - DHW
1. The DHW inlet isolating valve incorporates a flow regulator / filter pre-fitted in the valve body Inspect it to ensure no
blockage is evident. Fit it to the DHW inlet ball valve, ensuring the seal provided is correctly located.
2. Fit DHW outlet pipe tail to DHW outlet connection, ensuring the seal provided is correctly located.
evo HE C - Installation and Servicing
FLUE OUTLET
29
INSTALLATION
34
GAS CONNECTION
IMPORTANT. The gas service cock is sealed with a non-metallic blue fibre washer, which must not be overheated when
making capillary connections. Refer to Frame 2 for details of the position of the gas connection.
A boiler gas supply pipe length of 20m and not less than 15mm O.D. can be connected to the boiler via the gas service
cock union.
Ensure that the gas supply pipe does not foul the boiler casing.
For additional gas supply information refer to “Gas Supply” on page 8.
INSTALLATION
35
SAFETY VALVE DRAIN
The safety valve connection, located at the bottom right-hand side of the boiler, comprises a 15mm diameter stub pipe.
The discharge pipe should be positioned so that the discharge of water or steam cannot create a hazard to the occupants
of the premises or damage the electrical components and wiring. A 15mm compression fitting is supplied with the
Hardware Pack to connect it to the stub pipe.
30
evo HE C - Installation and Servicing
INSTALLATION
36
IMPORTANT - when filling:
A. Ensure the dust cap on air vent located at the rear of
B. When filling, there may be a slight water leak from
Central Heating
1. Remove the front panel. Refer to Frame 49.
2. Ensure that the CH isolating valves are open.
3. Fill and vent the system. Check for water tightness.
4. Pressurise the system to 1 bar.
Domestic Hot Water
1. Fully open all DHW taps and ensure that water flows
the air vent therefore electrical connections should be
protected.
freely from them.
INSTALLATION
evo HE C - Installation and Servicing
31
37
ELECTRICAL CONNECTIONS
INSTALLATION
WARNING. This appliance MUST be earthed.
A mains supply of 230 V ~ 50 Hz is required.
The fuse rating should be 3A. All external controls and wiring
must be suitable for mains voltage.
Wiring external to the boiler MUST be in accordance with the
current I.E.E. (BS.7671) Wiring Regulations and any local
regulations.
INSTALLATION
38
INTERNAL WIRING
A pictorial wiring diagram is shown in Frame 40.
This photo shows an external programmer lead (on
the left) and the mains cable (on the right).
1. Route the mains cable from bottom left-hand rear of
boiler casing to plug & socket connection.
2. Wire the permanent live supply into the 5-way remote
plug terminals, L3, N & .
IMPORTANT.
A permanent live is ESSENTIAL in order for the
advanced diagnostic controls to function correctly.
Ensure that the lengths of the live and neutral wires
are shorter than the earth wires so that if the cable
slips in its anchorage the current carrying wire
become taut before the earth wires.
Wiring should be 3 core PVC insulated cable, not less than
0.75 mm2 (24 x 0.2mm), and to BS 6500 Table 16. For IE
reference should be made to the current ETCI rules for
electrical installations.
Connection must be made in a way that allows complete
isolation of the electrical supply such as a double pole switch
having a 3mm (1/8") contact separation in both poles, or a
plug and socket, serving only the boiler and system controls.
The means of isolation must be accessible to the user after
installation.
3. Wire any switched live supply into L2 or connect L1
and L2 via external control switching as shown in
Frame 39. In either case remove the wire link fitted
to L1 to L2.
4. Secure the mains lead with the cable clamp.
5. Connect the mains lead connector. Ensure it is fully
located into the socket.
6. Support the incoming cable(s) with the clips provided.
32
evo HE C - Installation and Servicing
INSTALLATION
39
EXTERNAL ELECTRICAL CONTROLS
Wiring External to the Boiler
The fuse rating should be 3A.
Wiring external to the boiler MUST be in accordance with the
current I.E.E. (BS.7671) Wiring Regulations and any local
regulations.
Room Thermostat
If the thermostat has a neutral connection, use it (it provides
for more energy efficient operation by reducing switching
temperature differentials).
Frost Protection
If parts of the pipework run outside the house or if the boiler
will be left off for more than a day or so then a frost thermostat
should be wired into the system.
This is usually done at the programmer, in which case the
programmer selector switches are set to OFF and all the other
controls MUST be left in the running position.
The frost thermostat should be sited in a cold place but where
it can sense heat from the system.
Note. If the boiler is installed in a garage it may be necessary
to fit a pipe thermostat, preferably on the return pipework.
Wiring should be as shown, with minimal disturbance to other
wiring of the programmer.
Designation of the terminals will vary but the programmer and
thermostat manufacturers' leaflets will give full details.
A
L3
Mains in
Optional
Frost 'stat
L1
Room 'stat
System
controls
N
if required
l 6069
Ec
INSTALLATION
Diagram A
Shows an application to boilers fitted with a room thermostat
only.
Diagrams B & C
show applications to boilers fitted with alternative time
controls.
Earths are not shown for clarity but must never be
omitted.
evo HE C - Installation and Servicing
33
nm9323
Dry fire
thermistor
Diverter
Valve
Permanent
black
link
br
br
pk
y/g
b
bk
gy rv
123
y/g
y/g
40
INSTALLATION
PICTORIAL WIRING DIAGRAM
LEGEND
b-blue
bk - black
br - brown
gy - grey
or - orange
pk - pink
r-red
v-violet
w-white
y-yellow
y/g- yellow/green
INSTALLATION
34
evo HE C - Installation and Servicing
41
FUNCTIONAL FLOW WIRING DIAGRAM
INSTALLATION
INSTALLATION
LEGEND
b-blue
bk - black
br - brown
gy - grey
42
COMMISSIONING AND TESTING
A. Electrical Installation
1. Checks to ensure electrical safety should be carried out by
a competent person.
2. ALWAYS carry out the preliminary electrical system checks,
i.e. earth continuity, polarity, resistance to earth and short
circuit, using a suitable test meter.
or - orange
pk - pink
r-red
v-violet
w-white
y-yellow
y/g - yellow/green
B. Gas Installation
1. The whole of the gas installation, including the meter,
should be inspected and tested for tightness and
purged in accordance with the recommendations of BS.
6891.
In IE refer to IS.813:2002.
2. Purge air from the gas installation by the approved
methods only.
WARNING. Whilst effecting the required gas tightness test and purging air from the gas installation,
open all windows and doors, extinguish naked lights and DO NOT SMOKE.
evo HE C - Installation and Servicing
35
43
INITIAL LIGHTING
INSTALLATION
INSTALLATION
LEGEND
A. Boiler On/Off switch.
B. CH thermostat knob.
D. Burner On neon.
E. Reset button.
F. Injector pressure test
point.
G. Inlet pressure test point.
H. Gas service cock.
J. Casing pressure test point.
K. Overheat thermostat.
1. Check that the system has been filled and that the boiler is
not airlocked. Ensure the automatic air vent cap (N) is open.
Note.
It is important the burner is not operated before the system is
fully vented of air. If it is necessary to operate the appliance
pump to assist venting of the air this must be done with the
gas service cock turned off.
2. Refit the boiler sealing panel. Refer to Frame 50.
3. Check that the drain cock is closed and that the CH and DHW
isolating valves (T, W and S) are OPEN.
4. Check that the electrical supply is OFF.
5. Check that the boiler on/off switch (A) is off.
6. Check that the gas service cock (H) is OPEN.
7. Slacken the screw in the inlet pressure test point (G) and
connect a gas pressure gauge via a flexible tube.
8. Switch the electricity supply ON and check all external controls
are calling for heat.
CENTRAL HEATING
9. Set the boiler thermostat knob (B) to position 6 and switch
the boiler on/off switch (A) to ON. The boiler control should
now go through its ignition sequence until the burner is
established.
10. If the boiler does not light after 3 attempts the fault code
will be displayed, Press the reset button (E) and the boiler
will repeat its ignition sequence.
When the burner is established the WHITE 'Burner On' neon
(D) will be illuminated, the LED display will show status
M. Control thermistor (flow).
N. Automatic air vent.
R. Pressure gauge.
S. CH Flow isolating valve.
T. CH Return isolating valve.
U. DHW outlet.
W. DHW inlet
Y. DHW thermostat knob.
Z. Spark generator.
Control Box Servicing Position. See Frame 51.
THE DISPLAY
The user control has one neon and one display to inform the
user about the status. The display will show the status of the
boiler. The neon will show the status of the flame. If no flame
is detected the neon is blinking. When the flame is detected
the neon will be lit permanently.
Below is a list with display function in normal operation.
Standby, no demand for heat present.
Boiler is active for central heating.
Boiler is active for domestic hot water.
Boiler is heating up the plate heat exchanger.
Note: Boiler frost protection is activated as follows:
1 Pump runs if temperature is below 5 degrees C
2 Boiler fires if temperature is below 3 degrees C
Boiler is in lockout for a specific error. Display will be
blinking, alternating with a number or letter to show which
error is detected.
Boiler is in lockout for a specific error. Display will be
blinking,
which error is detected.
alternating with a number or letter to show
36
evo HE C - Installation and Servicing
INSTALLATION
44
INITIAL LIGHTING - continued
DOMESTIC HOT WATER
11. With the boiler firing, set the DHW thermostat knob (Y) to
maximum and fully open a DHW tap.
The boiler should continue to run and the LED display
should show status
12. Ensure that with the boiler operating the dynamic gas
pressure is able to obtain maximum output. Refer to
Table 2.
For additional gas supply information refer to “Gas Supply”
on page 8.
IMPORTANT
The gas input to the burner is regulated by the gas valve
according to the air flow produced by the fan. It is NOT
user-adjustable. Any interference to sealed settings on
the gas valve will adversely affect operation and render
our warranty void.
13. Turn off the DHW tap.
14. Set the boiler on/off switch (A) to OFF.
15. Swing the control box into the servicing position. Refer to
Frame 51.
16. Remove the pressure gauge and tube. Tighten the sealing
screw in the pressure test point. Ensure a gas tight seal is
made.
17. Swing the control box back into its working position and
secure. Reconnect the ignition lead.
18. Refit the user control.
19. Fit the boiler front and bottom panels.
INSTALLATION
45
GENERAL CHECKS
Make the following checks for correct operation in:
DOMESTIC HOT WATER (DHW) MODE
1. With no call for CH or DHW the boiler should fire for a
short period to preheat the DHW plate heat exchanger.
The display should read
returning to
when the burner switches off.
Notes.
a. If no DHW is drawn off, the boiler will fire periodically
for a short time, to maintain the plate heat exchanger
temperature.
b. The DHW preheat operates 24 hours a day .
2. Fully open all DHW taps in turn and ensure that water flows
freely from them.
The display should read:
neon flashing
then:
neon steady when the burner lights.
3. Close all taps except the furthest one from the boiler and
check that the boiler is firing at maximum rate.
This is factory set to give a DHW temperature rise of
approximately 35
“operation”.
4. Reduce the DHW draw-off rate to about 3 l/min (0.7gpm)
and check that the boiler modulates to deliver DHW at
approximately 65
5. Close the DHW tap and check that the main burner
extinguishes. The pump should overrun for a few seconds
and the display sequence should read:
When the pump stops the display sequence should read:
Note. On systems in excess of 2 bar inlet pressure a water
pressure governor may be required to prevent water noise.
o
C at the flow rate stated on page 6 under
o
C.
evo HE C - Installation and Servicing
37
INSTALLATION
46
GENERAL CHECKS - continued
CENTRAL HEATING (CH)
& DOMESTIC HOT WATER (DHW) MODE.
1. Ensure that the CH external controls are calling for heat.
The display should read:
after first satisfying DHW preheat if necessary. ( )
2. Fully open a DHW tap and check that hot water is
delivered.
The display should read:
flashing
INSTALLATION
3. Gas Rate
Check the boiler gas rate when the boiler is at full DHW
output.
Check at the gas meter, with no other appliance in use.
Refer to Table 3 for gas rates.
4. Close the DHW tap. The burner should go off and the
pump continue to run.
The display should read:
flashing
then
flashing
After 15 seconds the burner should relight, to supply
central heating.The display should read:
5. Set the central heating external controls to OFF. The
burner should go off and the pump continue to run for five
minutes
The display should read:
returning to
when the pump stops.
6. Check the correct operation of the programmer (if fitted)
and all other system controls. Operate each control
separately and check that the main burner responds.
WATER CIRCULATION SYSTEM
1. With the system COLD, check that the initial pressure is
correct to the system design requirements.
For pre-pressurised systems, this should be 1.0 bar.
2. With the system HOT, examine all water connections for
soundness. The system pressure will increase with
temperature rise but should not exceed 2.5 bar.
3. With the system still hot, turn off the gas, water and
electricity supplies to the boiler and drain down to
complete the flushing process.
Note: A flushing solution should be used during the flushing
procedure. Flushing solutions: Fernox Superfloc,
Sentinel X300 (new systems) or X400 (existing
systems). Refer to Frame 6.
4. Refill and vent the system, add inhibitor (see Frame 6),
clear all air locks and again check for water soundness.
Affix the water treatment warning label, supplied in the
hardware pack, in a prominent position on the system, to
prevent the use of incorrect water treatment additives.
5. Reset the system initial pressure to the design
requirement.
6. Balance the system. Refer to Frame 5.
7. Check the condensate drain for leaks and check that it is
discharging correctly.
8. Finally, set the controls to the User's requirements.
Note: The pump will operate briefly as a self-check once
every 24 hours in the absence of any system demand.
38
WATER TEMPERATURES
Temperatures can be selected using the CH and DHW thermostats.
Knob SettingCH FlowDHW Outlet
TempTemp
o
C (oF)
Max82 (180)65 (150)
Min30 (86)42 (110)
o
C (oF)
evo HE C - Installation and Servicing
INSTALLATION
47
HANDING OVER
After completing the installation and commissioning of the system the installer should hand over to the householder by
the following actions:
1. Hand the User Instructions to the householder and
explain his/her responsibilities under the relevant
national regulations.
2. Explain and demonstrate the lighting and shutting
down procedures.
3. The operation of the boiler and the use and adjustment
of all system controls should be fully explained to the
householder, to ensure the greatest possible fuel
economy consistent with the household requirements
of both heating and hot water consumption.
Advise the User of the precautions necessary to prevent
damage to the system and to the building, in the event
of the system remaining inoperative during frosty
conditions.
4. Explain the function and the use of the boiler heating
and domestic hot water controls.
Explain that due to system variations and seasonal
temperature fluctuations DHW flow rates/temperature
rise will vary, requiring adjustment at the draw off tap. It
is therefore necessary to draw the users attention to the
section in the Users Instructions titled “Control of Water
Temperature” and the following statement:
“Additionally, the temperature can be controlled by
the user via the draw-off tap: the lower the rate the
higher the temperature, and vice versa”.
5. Explain the function of the boiler fault mode.
Emphasise that if a fault is indicated, the boiler should
be turned off and a Gas Safe Registered Installer
consulted. In IE contact a Registered Gas Installer
(RGII).
6. Explain and demonstrate the function of time and
temperature controls, radiator valves etc., for the economic
use of the system.
7. If a programmer is fitted draw attention to the Programmer
Users Instructions and hand them to the householder.
8. Loss of system water pressure
Explain that the dial underneath the boiler indicates the
central heating system pressure and that if the normal COLD
pressure of the system is seen to decrease over a period of
time then a water leak is indicated. Explain the repressurising procedure and if unable to repressurise or if the
pressure continues to drop a registered local heating
installer should be consulted.
WARNING. Do not fire the boiler if the system pressure is less
than 0.5 bar.
9.
After installation and commissioning please complete the
Commissioning Checklist before handover to the customer.
For IE, its is necessary to complete a “Declaration of
Conformity” to indicate compliance to I.S. 813:2002.
IMPORTANT
10. A comprehensive service should be carried out ANNUALLY.
Stress the importance of regular servicing by a Gas Safe
Registered Installer. In IE servicing work must be carried out
by a Registered Gas Installer (RGII).
11. As the installer you may wish to undertake the service
contract yourself or alternatively offer to the customer the
benefits of the Ideal Care Scheme, details of which are
outlined in the householder pack supplied with this boiler.
INSTALLATION
evo HE C - Installation and Servicing
39
SERVICING
48
SERVICING SCHEDULE
For the very latest copy of literature for specification and maintenance practices visit our website www.idealboilers.com, where
you will be able to download relevant information. N.B. Technical Bulletins are also available on our website.
WARNING. Always turn OFF the gas supply at the gas service cock, and switch OFF and disconnect the electricity
supply to the appliance before servicing.
To ensure the continued safe and efficient operation of the
appliance it is recommended that it is checked at regular
intervals and serviced as necessary. The frequency of
servicing will depend upon the installation condition and
usage but should be carried out at least annually.
It is the law that any service work must be carried out by a
Gas Safe Registered Installer. In IE service work must be
carried out by a Registered Gas Installer (RGII).
1. Light the boiler and carry out a pre-service check, noting
any operational faults.
2. Clean the main burner.
3. Clean the heat exchanger & ‘S’ trap.
4. Check the condition of the combustion chamber insulation.
Any cracked, damaged or displaced pieces should be replaced.
Ionisation probes are a servicable component and requires
inspecting annually. Replace if distorted.
SERVICING
5. Check the main injector for blockage or damage.
6. Wherever possible remove and clean the condensate ‘S’
trap (refer to Frame 54) and check the drain for blockage.
7. Check that the flue terminal is unobstructed and that the
flue system is sealed correctly.
8. Check the DHW filter for blockage. Refer to Frame 33.
The servicing procedures are covered more fully in Frames
49 -56 and MUST be carried out in sequence.
Note. In order to carry out either servicing or replacement of
components the boiler front panel and sealing panel
must be removed. Refer to Frames 49 and 50.
IMPORTANT.
9. After completing the servicing or exchange of components
always test for gas tightness.
10. When work is complete the sealing panel MUST be
correctly refitted, ensuring that a good seal is made.
Do NOT OPERATE the boiler if the sealing
panel is not fitted.
11. If, for any reason, the condensate ‘S’ trap has been
removed ensure the trap is refilled with water before
reassembling.
12. Check the gas consumption.
13. Connect a suitable gas analyser to the sampling point on
the top of the boiler (refer to Frame 49) or into the flue
terminal if access is possible (optional test).
For correct boiler operation, the CO/CO
gas should not be greater than 0.004 ratio.
14. Complete the service section in the Benchmark
Commissioning Checklist.
content of the flue
2
40
evo HE C - Installation and Servicing
49
BOILER FRONT PANEL REMOVAL
1. Remove the 2 screws from the
underside of the boiler.
2. Pull the panel forward at the bottom and
lift to disengage it from the top lugs.
SERVICING
50
BOILER SEALING PANEL / BOTTOM PANEL REMOVAL
1. To remove the sealing panel remove
the 4 screws.
2. Remove the panel.
3. To remove the bottom panel first
remove the screw.
4. Pull the right hand side of the panel
down. Slide it to the right and
withdraw.
SERVICING
evo HE C - Installation and Servicing
41
SERVICING
51
MOVING CONTROL BOX TO THE SERVICING POSITION
1. Remove the 2 screws and withdraw the user
control.
2. Unplug the low voltage electrical lead from the
back of the user control.
3. Release the clamp,
4. Swing the control box down
5. Pull the control box slightly forward.
SERVICING
42
evo HE C - Installation and Servicing
SERVICING
52
FAN AND VENTURI ASSEMBLY REMOVAL AND CLEANING
1. Disconnect the electrical leads from the
fan.
2. Undo the gas pipe union connection to the
injector housing.
3. Undo the screw on the fan mounting
bracket.
4. Lift off fan and venturi assembly.
5. Inspect the injector for blockage or
damage.
53
BURNER REMOVAL AND CLEANING
1. Remove the 6 screws securing the
burner (the 3 screws at the rear are
extended to ease access).
2. Lift off the burner from the combustion
chamber.
IMPORTANT
The burner head is a ceramic plaque
construction. Care must be taken to
ensure that the burner is not placeddown upon its face as this may cause
damage to the ceramic.
3. Brush off any deposits that may be on
the ceramic with a SOFT brush.
4. Inspect the sealing gasket around the
burner and combustion chamber
insulation for any signs of damage.
Replace as necessary.
Note.
Take care not to disturb the ionisation
probes at the front and rear of the
combustion chamber.
SERVICING
1
2
4
Ionisation
Probes
nm7400
evo HE C - Installation and Servicing
43
54
nm7401
2
Sumpcover
3
Ionisation
probes
Heat exchanger
CLEANING THE CONDENSATE 'S' TRAP
Note: Ensure the condensate trap is
fully drained before removal.
1. Swing the control box down into the
servicing position. Refer to Frame 51.
2. Disconnect the condensate drain pipe.
3. Remove the 2 screws and pull the trap
down and forward to remove.
4. Flush out any deposits with clean
water.
SERVICING
55
CLEANING THE HEAT EXCHANGER
Note: Ensure the sump is fully drained before removal.
1. Remove ignition and flame detection electrodes. Refer to
Frames 63 & 64.
2. Remove the 3 screws retaining the sump cover and
remove.
SERVICING
3. Using a suitable tool as supplied in the standardBritish
Gas Flue brush kit, clean between the heat exchanger
fins from the top of the heat exchanger.
4. Access to the base of the heat exchanger is now possible.
Brush clean any deposits from the base of the heat
exchanger and remove any loose deposits from the sump.
5. Inspect the ignition and detection electrodes. Ensure that
they are clean and in good condition - replace if necessary.
6. Check the condition of the combustion chamber insulation.
Any cracked or damaged pieces must be replaced.
Note. Take care not to disturb the ionisation probes at the
front and rear of the combustion chamber.
7. Check that the ignition and detection gaps are correct.
Refer to Frames 63 & 64.
56
Reassemble the boiler in the following order:
1. Refit the condensate ‘S’ trap, ensuring that it is full of water.
2. Refit the sump cover.
3. Refit the electrodes. (Check dimensions; Frames 63 & 64).
4. Refit the burner.
5. Refit the fan / venturi assembly.
6. Reconnect the fan electrical lead.
44
REASSEMBLY
7. Refit the boiler sealing panel.
IMPORTANT.
Ensure that the boiler sealing panel is correctly fitted and
that a good seal is made.
8. Swing the control box back into its working position and
secure.
9. Refit the display unit.
10. Refit the boiler front and bottom panels.
11. Turn on the gas supply at the gas service cock.
12. Reconnect the electrical supply.
evo HE C - Installation and Servicing
ispfu9797
57
REPLACEMENT OF COMPONENTS
SERVICING
GENERAL
When replacing ANY component
1. Isolate the electricity supply.
2. Turn off the gas supply.
3. Remove the boiler front panel. Refer to Frame 49.
After replacing ANY component check operation of the boiler,
including gas tightness, gas rate and combustion test.
THE BOILER MUST NOT BE OPERATED WITHOUT THE SEALING PANEL FITTED
58
DRY FIRE THERMISTOR REPLACEMENT
1. Refer to Frame 57.
2. Remove the boiler front and sealing panels. Refer to
Frames 49 & 50.
3. Drain down the boiler. Refer to Frame 77.
4. Unplug the electrical lead.
5. Unscrew the thermistor.
6. Fit the new thermistor using the sealing washer
provided.
7. Reassemble in the reverse order.
8. Check the operation of the boiler. Refer to Frames 45
& 46.
IMPORTANT.
When work is complete, the sealing panel, if removed, must
be correctly refitted - ensuring that a good seal is made.
Notes.
1. In order to assist fault finding, the control panel has an
LED diagnostic display. The key to boiler fault conditions
is shown in Frame 84.
2. In order to replace components in Frames 74-82 it is
necessary to drain the boiler. Refer to Frame 77.
SERVICING
59
FAN REPLACEMENT
1. Refer to Frame 57.
2. Remove the boiler front and sealing panels. Refer to Frames
49 & 50.
3. Disconnect the electrical leads from the fan.
4. Undo the gas pipe union connection to the injector housing.
5. Remove the screw retaining the fan mounting bracket.
6. Remove the fan and venturi assembly. Refer to Frame 52.
7. Unscrew the 3 screws and remove the venturi assembly,
noting the orientation of the venturi in relation to the fan body.
8. Transfer the venturi assembly to the new fan, replacing the
gasket if evidence of damage or deterioration is visible.
9. Fit the new fan / venturi assembly.
10. Reassemble the boiler in reverse order, taking care not to
overtighten the screw on the fan mounting bracket.
11. Check the operation of the boiler. Refer to Frames 45 & 46.
evo HE C - Installation and Servicing
45
SERVICING
nm7402
Ionisation
Probes
4
5
6
60
BURNER INJECTOR REPLACEMENT
1. Refer to Frame 57.
2. Remove the boiler front and sealing panels. Refer to Frames
49 & 50.
3. Disconnect the electrical leads from the fan.
4. Undo the gas pipe union connection to the injector housing.
5. Remove the screw retaining the fan mounting bracket.
6. Remove the fan and venturi assembly
7. Remove the 2 injector housing screws.
8. Withdraw the injector housing.
9. Fit the new injector housing complete with injector.
10. Reassemble in reverse order, ensuring that the new gas seal
supplied is located correctly in the injector housing.
11. Check operation of the boiler. Refer to Frames 45 & 46.
61
BURNER REPLACEMENT
1. Refer to Frame 57.
2. Remove the boiler front and sealing panels. Refer to
Frames 49 & 50.
3. Remove the fan assembly. Refer to Frame 59.
4. Remove the 6 screws securing the burner (the 3 screws at
the rear are extended to ease access).
5. Lift off the burner from the combustion chamber.
6. Fit the new burner, replacing any damaged or deteriorating
SERVICING
sealing gasket.
7. Reassemble in reverse order.
8. Check the operation of the boiler. Refer to Frames 45 & 46.
Note. Take care not to disturb the ionisation probes at the
front and rear of the combustion chamber.
Fan
Injector
Gas pipe union
Mounting bracket
7
5
Ecl 2400
62
CONTROL THERMISTOR, RETURN THERMISTOR & OVERHEAT ‘STAT RENEWAL
1. Refer to Frame 57.
2. Remove the boiler front and sealing panels.
Refer to Frames 49 & 50.
3. Unclip the thermistor A and thermostat B from the flow pipe
C and withdraw it from the controls compartment.
4. Unclip the thermistor D from the return pipe E and withdraw
it from the controls compartment.
5. Disconnect the electrical leads from the thermistors or
thermostat.
6. Reconnect the electrical leads and reassemble in reverse
order, ensuring that the spring clips are securely on the
pipes.
7. Check the operation of the boiler. Refer to Frames 45 & 46.
46
evo HE C - Installation and Servicing
SERVICING
63
IGNITION ELECTRODE REPLACEMENT
1. Refer to Frame 57.
2. Remove the boiler front and sealing panels. Refer to
Frames 49 & 50.
3. Unplug the ignition lead from the electrode.
4. Remove the earth lead from the ignition electrode.
5. Remove the remaining screw holding the ignition electrode
to the combustion chamber.
6. Remove the electrode.
7. Fit the new ignition electrode, using the new gasket
supplied. Check dimensions as shown.
8. Reassemble in reverse order, and check that no damage
to the combustion chamber insulation has occurred during
the electrode replacement.
9. Check the operation of the boiler. Refer to Frames 45 &
46.
5
64
FLAME DETECTION ELECTRODE REPLACEMENT
1. Refer to Frame 57.
2. Remove the boiler front and sealing panels. Refer to
Frames 49 & 50.
3. Unplug the flame detection lead from the electrode.
4. Remove the 2 screws holding the flame detection
electrode to the combustion chamber.
5. Remove the electrode.
4
ispfu9788
6. Fit the new flame detection electrode, using the new gasket
supplied. Check dimensions as shown.
7. Reassemble in reverse order, and check that no damage to
the combustion chamber insulation has occurred during the
electrode replacement.
8. Check the operation of the boiler. Refer to Frames 45 & 46.
SERVICING
65
SPARK GENERATOR REPLACEMENT
1. Refer to Frame 57.
2. Disconnect the leads from the spark generator.
3. Remove the M4 screws securing the spark
generator to the boiler chassis.
4. Fit the new spark generator and re-assemble in
reverse order.
5. Check operation of the boiler. Refer to Frames 45 &
46.
evo HE C - Installation and Servicing
ispfu9801
47
66
GAS CONTROL VALVE REPLACEMENT
1. Refer to Frame 57.
2. Swing the control box down into the
servicing position. Refer to Frame
51.
3. Unplug the electrical lead connection
from the gas control valve and
disconnect the earth wire.
4. Undo the gas inlet pipe union at the
gas service cock.
5. Undo the union nut on the outlet of
the gas control valve.
6. Disconnect the white tube from the
valve.
7. Remove the back nut retaining the
valve to the bottom panel and
withdraw the valve upwards.
8. Fit the new gas control valve and
reconnect gas and electrical
connections.
9. Re-connect the white tube to the
valve.
10. Check operation of the boiler. Refer
to Frames 45 & 46.
SERVICING
SERVICING
67
DIVERTER VALVE ACTUATOR REPLACEMENT
1. Refer to Frame 57.
2. Swing the control box down into the
servicing position. Refer to Frame 51.
3. Remove the electrical connections.
4. Using a suitable tool pull out the retaining
clip and lift the diverter head from the
brass body.
5. Fit new actuator head and reassemble in
reverse order Ensure the electrical
connections are fitted correctly (left to right
GREY - RED - PURPLE)
6. Check operation of the boiler. Refer to
Frames 45 & 46.
48
evo HE C - Installation and Servicing
SERVICING
68
COMBUSTION CHAMBER INSULATION REPLACEMENT
Ideal Stelrad Group recommends that, for your own comfort
and safety and to comply with good working practice, the
procedure described below is followed:
1. Refer to 'Replacement of Components' Frame.
2. Remove the boiler front and sealing panels. Refer to
'Boiler Front Panel Removal' and 'Boiler Sealing Panel
Removal' Frame.
3. Remove the fan / venturi assembly. Refer to 'Fan and
Venturi Assembly removal and cleaning' Frame.
4. Remove the burner. Refer to 'Burner removal and
cleaning' Frame.
5. Remove the ignition electrode. Refer to 'Ignition Electrode
replacement' Frame.
6. Remove the flame detection electrode. Refer to 'Flame
Detection electrode replacement' Frame.
7. Remove the front and rear ionisation probes and discard.
Prior to removal of the insulation piece the following
protective equipment should be worn:
- Face mask supplied with the spare part.
- Gloves supplied with the spare part.
8. Damp down the combustion chamber area containing
the insulation piece.
9. Remove the insulation piece. The replacement one piece
insulation is supplied in a plastic bag, this bag should be
retained and the discarded insulation should now be
placed into it.
10. Sweep any dampened particles and place in the plastic
bag.
11. Fit new insulation piece -
(a) Locate and align the insulation with the electrode
holes and position the insulation into the combustion
chamber.
(b) Push the flexible material into the corners of the
combustion chamber ensuring it is flat and flush
against the combustion chamber wall.
(c) Interlock the insulation piece along the back wall of
the combustion chamber.
(d) Again push the flexible material into the corners of the
combustion chamber ensuring it is flat and flush
against the combustion chamber wall.
(e) Secure the insulation by replacing the ionisation
probes with those supplied in the kit. Note that
ionisation probes are a serviceable component and
require inspecting annually.
Note. The insulation is designed to be interlocking and
should be fitted as shown.
12. Remove the gloves and face mask and place them in the
plastic bag.
13. Wash your hands and any areas of skin which may have
come into contact with any of the particles from the
insulation piece.
Note. Seal the plastic bag and dispose of it and its contents
into a commercial tip.
14. Reassemble in reverse order.
15. Check operation of the boiler. Refer to 'General Checks'
Frames.
SERVICING
7
9
Insulation
Combustion
chamber
6
5
evo HE C - Installation and Servicing
isfu9570
49
69
CONDENSATE 'S' TRAP REPLACEMENT
1. Refer to Frame 57.
Note: Ensure condensate trap is fully drained before
removal.
2. Remove the casing front & bottom panel.
Refer to Frames 49 & 50.
3. Swing the control box down into the servicing
position. Refer to Frame 51.
4. Disconnect the condensate drain pipe.
5. Remove the 2 securing screws and pull the trap
down and forward to remove.
6. Transfer the drain pipe to the new trap and
reassemble in reverse order.
7. When reassembling ensure the trap is full of water.
SERVICING
8. Check operation of the boiler. Refer to Frames 45 &
46.
70
DHW THERMISTOR REPLACEMENT
1. Refer to Frame 77 for draining the appliance.
2. Swing the control box into the servicing position. Refer
to Frame 51.
SERVICING
3. Drain the DHW circuit. Refer to Frame 77.
4. Unscrew the knurled retaining nut.
5. Disconnect the in line electrical connection and withdraw
the thermistor.
6. Reassemble in reverse order.
7. Check operation of the boiler. Refer to Frames 45 & 46.
50
evo HE C - Installation and Servicing
SERVICING
71
CONTROL BOX REPLACEMENT
1. Refer to Frame 57.
2. Remove the casing front & bottom panel.
Refer to Frames 49 & 50.
3. Swing the control box down into the servicing position.
Refer to Frame 51.
4. Unplug the user control electrical lead and low voltage
lead from the control box and remove the control. Refer
to diagram A.
5. Return the control box to the working position and
secure with the clamp. Unscrew the mounting bracket
screws to remove the bracket. Refer to diagram B.
6. Release the clamp and carefully remove the control box
from the hinge arms. Refer to diagram C.
7. Unplug all the electrical wiring from the control box and
remove.
8. Transfer mounting bracket and hinge arms to the new
control box.
9. Reassemble in reverse order, ensuring that the control box
is located correctly in the housing before reconnecting the
electrical wiring.
10. Check operation of the boiler. Refer to Frames 45 & 46.
72
MAINS SWITCH REPLACEMENT
1. Refer to Frame 57.
2. Remove the casing front & bottom panel.
Refer to Frames 49 & 50.
3. Remove the 2 screws and allow the user control to lower.
4. Push out the mains switch from the rear, as shown.
5. Fit the new switch, ensuring that the electrical leads are
replaced on the correct terminals (refer to Frame 41) and
the key on the switch is correctly aligned with the slot in the
plastic moulding.
SERVICING
6. Reassemble in reverse order.
7. Check operation of the boiler. Refer to Frames 45 & 46.
evo HE C - Installation and Servicing
51
SERVICING
73
USER CONTROL REPLACEMENT
Note. Only the display unit is replaced.
1. Refer to Frame 57.
2. Loosen the screw on the underside of the user control.
3. Pull the display unit forward to remove.
4. Push the new display unit into position.
5. Reassemble in reverse order.
6. Check operation of the boiler. Refer to Frames 45 & 46.
Ecl 2044
Display
unit
2
74
PRESSURE GAUGE RENEWAL
1. Refer to Frame 57.
2. Drain the boiler. Refer to Frame 77.
3. Unscrew the pressure gauge and discard.
SERVICING
4. Fit the new pressure gauge, using a suitable jointing compound.
5. Refill the boiler. Refer to Frame 36.
6. Check operation of the boiler. Refer to Framea 45 & 46.
75
SAFETY RELIEF VALVE RENEWAL
1. Refer to Frame 57.
2. Drain the boiler CH circuit. Refer to Frame 77.
3. Undo the 15mm compression fitting from the pressure
relief outlet pipe.
4. Remove self tapping screw located on chassis adjacent
to outlet pipe.
5. Withdraw expansion vessel flexi hose clip and lift away
from pump housing to improve access to the safety valve.
6. Withdraw the clip securing the safety valve.
7. Lift safety valve complete with its outlet pipe and support
bracket upwards. Note outlet pipe bracket is supported
by key-hole fastener. Withdraw assembly from boiler.
8. Fit the new safety valve to the pipe and reassemble in
reverse order.
9. Refill boiler. Refer to Frame 36. Check operation of boiler.
Refer to Frames 45 & 46.
7
6
4
3
5
Viewed from back of boiler
52
evo HE C - Installation and Servicing
SERVICING
76
AUTOMATIC AIR VENT REPLACEMENT
HEAT EXCHANGER AIR VENT
1. Refer to Frame 57.
2. Remove the boiler front and sealing panels. Refer to
frames 49 & 50.
3. Drain the boiler. Refer to frame 77.
4. Remove the turret from the boiler. Refer to frame 26.
5. Release the silicon tubing from the sample point.
6. Release the electrical connections from the dry fire
thermistor.
7. Release the electrical connections from the spark
generator.
8. Remove the M5 x 10 screw retaining the top flue
manifold casting.
9. Remove the casting.
10. Remove the fan from the boiler. Refer to Frame 52.
11. Remove the burner from the heat exchanger. Refer to
Frame 53.
12. Unscrew the air vent from its heat exchanger mount
and renew.
13. Re assemble the boiler in reverse order.
14. Refill the boiler. Refer to frame 36. Check for leaks
around the new air vent joint.
15. Check the operation of the boiler. Refer to Frames 45
& 46.
PUMP AIR VENT
1. Refer to Frame 57.
2. Swing the control box down into the servicing
position - refer to frame 51
3. Drain the boiler. Refer to frame 77.
4. Remove the circulating pump head - refer to frame
80
5. Locate the automatic air vent head located at the
rear of the of pump chamber plastic housing. If
increased access is required disconnect the 22mm
pipe connection at top a pump chamber and swing
pipe outwards.
6. The automatic air vent head is retained in the pump
body with a bayonet connection. The air vent head
and float assembly is removed by turning the head
anti-clockwise (viewed from above) and pulling
upwards.
7. Reassembly is the reverse of the above. Ensure the
air vent head 0 ring seal is in place when refitting.
8. Refill the boiler. Refer to frame 36. Check for leaks
around the new air vent joint.
9. Check the operation of the boiler. Refer to Frames 45
& 46.
SERVICING
5
Viewed from back of boiler
evo HE C - Installation and Servicing
53
SERVICING
77
DRAINING THE BOILER
1. Refer to frame 57.
2. Close all the water isolating (CH and DHW) valves on the boiler inlet.
3. To drain the central heating circuit: Attach a length of hose to the CH drain point and open the drain valve.
4. To drain the domestic hot water circuit. As there is no direct drain for the domestic hot water circuit, depending on
the location of the boiler, opening the lowest hot water tap may drain this circuit. However it must be noted that some
residual water will be experienced during replacement of components.
5. After replacing any component on the boiler, close the drain valve, remove the hose and open all system
isolating valves (re-pressurise as appropriate with filling loop) before proceeding to check operation of the
boiler.
6. Check operation of the boiler. Refer to Frames 45 & 46.
SERVICING
78
DIVERTER VALVE INTERNAL PARTS REPLACEMENT
1. Refer to Frame 57.
2. Swing the control box down into the
servicing position. Refer to Frame 51.
3. Drain the boiler. Refer to Frame 77.
4. Remove the divertor valve actuator head.
Refer to Frame 67.
5. Unscrew the top connection to access the
internal parts.
6. To allow residual water within the waterset
to drain, slacken CH isolation valve union
nut connecting isolation valve to waterset.
NOTE. Failure to do this may result in
compression of trapped residual water
during diverter valve reassembly, resulting
in damage to the pressure gauge located
on the CH isolation valve.
7. Fit the new valve cartridge mechanism
ensuring correct fit of the pin.
8. Reassemble in reverse order ensuring CH
isolation valve union is reconnected.
9. Refill the boiler. Refer to Frame 36.
10. Check operation of the boiler. Refer to
Frames 45 & 46.
Cartridge Mechanism
Part No. 175 411
5
7
6
Important:
Slacken isolation valve union to drain
residual water contained within
waterset.
54
evo HE C - Installation and Servicing
SERVICING
79
DHW PLATE HEAT EXCHANGER REPLACEMENT
1. Refer to Frame 57.
2. Swing the control box down into the servicing
position. Refer to Frame 51.
3. Drain the boiler. Refer to Frame 77.
4. Remove divertor valve actuator. Refer to Frame
67.
5. Remove condensate “S” trap. Refer to Frame 54.
6. Remove the 2 allen screws securing the plate heat
exchanger to the brass housings.
7. Manoeuvre the plate heat exchanger out of the top
left-hand side of the controls area.
8. Fit the new plate heat exchanger, using the new orings supplied.
9. Reassemble in reverse order.
10. Refill the boiler. Refer to Frame 36.
11. Check operation of the boiler. Refer to Frames 45
& 46.
80
PUMP HEAD REPLACEMENT
1. Refer to Frame 57.
2. Drain the boiler CH circuit. Refer to Frame 77.
3. Swing the control box down into the servicing
position. Refer to Frame 51.
4. Disconnect the electrical lead from the pump.
5. Remove the 4 Allen screws retaining the pump
head.
6. Remove the pump head.
7. Fit the new pump head.
8. Reassemble in reverse order.
9. Refill the boiler. Refer to Frame 36.
10. Check operation of the boiler. Refer to Frames 45
& 46.
SERVICING
evo HE C - Installation and Servicing
55
SERVICING
81
HEAT ENGINE RENEWAL
Refer also to Frame 8 - 'Boiler Exploded View'.
IMPORTANT
Before starting the removal procedure, protect the gas and
electrical controls with a waterproof sheet or plastic bag.
1. Refer to Frame 57.
2. Remove the boiler front, bottom and sealing panels. Refer
to Frames 49 & 50.
3. Drain the boiler. Refer to Frame 77.
4. Remove the control box and place on one side. Refer to
Frame 71.
5. Remove the fan / venturi assembly and place on one side.
Refer to Frame 52.
6. Remove the burner and place on one side. Refer to Frame
53.
7. Remove the ignition and detection electrodes. Refer to
Frames 63 & 64.
8. Remove the spark generator. Refer to Frame 65.
9. Release the flue from the turret. Refer to Frame 26.
10. Remove the turret from the boiler. Refer to Frame 26.
11. Release the silicone tubing from the sampling point.
12. Release the electrical connection to the dry fire thermistor.
13. Remove the M5 x 10 screw retaining the top flue manifold
casting.
14. Remove the top casting of the flue manifold from the
appliance.
15. Remove the automatic air vent. Refer to Frame 76.
16. Undo the 4 M x 10 screws securing the bottom flue
SERVICING
manifold casting and remove.
17. Remove the edge clip securing the dry fire thermistor
wiring.
18. Remove the clip securing the return pipe.
19. Remove the overheat thermostat and the control
thermistor. Refer to Frame 62.
20. Remove the clip to release the flow pipe.
21. Remove the condensate ‘S’ trap. Refer to Frame 69.
22. Remove the 2 M5 screws securing the interpanel to the
back panel.
23. Slide the heat exchanger and interpanel assembly upward
to disengage and remove from the casing, complete with
the flow pipe.
24. Remove the 2 M6 countersunk screws, remove the
interpanel and transfer to the new heat exchanger.
25. Remove the M5 screw and remove the flow pipe securing
bracket.
26. Remove the flow pipe and transfer to the new heat
exchanger.
27. Reassemble in reverse order, replacing gaskets or seals if
any sign of damage is evident. When replacing the spring
clips located on both the flow and return pipe connections,
ensure clip is oriented to correctly match connecting pipe
diameters.
Note.The heat exchanger is supplied with new combustion
chamber insulation boards. These should be fitted (refer
to Frame 68 before the burner and fan / venturi assembly
and before the ignition and detection electrodes are
replaced).
28. Refill the boiler. Refer to Frame 36.
29. Check operation of the boiler. Refer to Frames 45 & 46.
56
evo HE C - Installation and Servicing
SERVICING
82
EXPANSION VESSEL REPLACEMENT
1. Refer to Frame 57.
2. Drain the boiler. Refer to Frame 77.
3. Unscrew all the gas and water connection unions on the boiler side of the valves.
4. Remove the screw from the turret clamp and remove.
5. Remove the turret.
6. Lift the complete boiler from the wall mounting frame and place on a flat surface, face down, to expose the
expansion vessel.
7. Unscrew the union nut on the vessel water connection pipe.
8. Unscrew the 2 screws from the securing clamp and remove.
9. Remove the expansion vessel.
10. Fit the new expansion vessel.
11. Reassemble in reverse order.
12. Refill the boiler. Refer to Frame 36.
13. Check operation of the boiler. Refer to Frames 45 & 46.
Note.
If preferred, and for convenience, a new expansion vessel may be installed elsewhere in the heating system,
providing it ensures equivalent system protection.
83
BOILER SEALING PANEL SEAL REPLACEMENT
1. Refer to Frame 57.
2. Remove the boiler front and sealing
panels. Refer to Frames 49 & 50.
3. Remove the old seal from the casing
and thoroughly clean the casing
surfaces.
4. Fit the new adhesive seals, note that
they are supplied to the correct length
for the relevant sides.
5. Reassemble in reverse order.
6. Check operation of the boiler. Refer to
Frames 45 & 46.
Note. Ensure that the boiler sealing
panel is correctly sealed,
compressing the seal to make an
airtight joint.
SERVICING
evo HE C - Installation and Servicing
57
FAULT FINDING
84
FAULT FINDING CHART MAIN MENU
In order to assist fault finding the boiler has an LED diagnostic display. The key to the display codes is as follows:
Check the ignition electrode and associated harness
for: continuity, visual condition, position
(Refer to Frame 63).
Are these functioning correctly ?
NO
Replace ignition electrode and associated
harness as necessary
Note. Due to the wave form of the rectified voltage, the reading will vary depending on the type of meter used to
measure the value (some may measure the possible peak voltage of 339V). In general terms a reading greater
than 150V indicates that the correct voltage is supplied to the gas valve.
Check for an excess voltage between
neutral and earth. Is the value below 50V?
YES
LE ONLY
Is continuity of OH thermostat correct?
YES
HE ONLY
Is earth wire connected to detection
lead correctly?
YES
Have all earths been
checked for continuity?
NO
NO
NO
NO
Check earth connection to the boiler. If it is
still in excess of 50 V consult a qualified
electrician to check the household electrical
supply and circuitry.
Is water system correctly filled and vented with a
system pressure of approximately 1bar
YES
FAULT FINDING
H9/L9(HEAT EXCHANGER OVERHEAT)
Is the system filled and vented and all isolation
valves open, including TRV's & Bypass?
Check the pump is operating correctly in
Heating & DHW and check temp diffs across
Flow & Return.
Can the fault condition be reset by switching off
the mains supply to the boiler ?
NO
Check wiring for continuity from the
PCB to the dry fire thermistor
Check resistance using a suitable multimeter
connected across the thermistor’s terminal pins
o
C expect9,700 - 10,300Ohms
At 25
o
C expect2,400 - 2,600Ohms
At 60
o
C expect1,000 - 1,100Ohms
At 85
Are thermistor values correct ?
YES
Replace PCB
Replace thermistor
NO
YESNO
Check Flow
fitted - making contact
with pipe
Check resistance, using a suitable multimeter
At 25 oC expect9,700 - 10,300 Ohms
At 60
At 85 oC expect1,000 - 1,100 Ohms
Check that a permanently open
bypass circuit is available during
the pump over-run period after
boiler shutdown. This can be
provided by either an automatic
bypass valve or a heat leak radiator
(no TRV) of at least 10% of the
minimum boiler output.
Note.
With V9 Primary Control PCB, overheat LA/HA or H9/L9 when
reset will display 3 horizontal lines and will not attempt to refire
until the temperature in the heat exchanger drops below 50oC.
stat is
YES
connected across the dry fire thermistor
terminal pins.
o
C expect2,400 - 2,600 Ohms
Are thermistor values correct ?
YES
Fill and vent the
system and open all
isolating valves
NO
Replace
thermistor
93
H......F..... (FLAME DETECTION ERROR)
Remove flame detection electrode terminal from PCB
The following are parts commonly required due to damage or
expendability. Their failure or absence is likely to affect safety or
performance of this appliance.
The list is extracted from the British Gas List of Parts, which
contains all available spare parts.
The full list is held by British Gas Services, Wolseley Centers Ltd.
distributors and merchants.
When replacing any part on this appliance use only spare parts that you can be assured conform to the safety and performance specification
that we require. Do not use reconditioned or copy parts that have not been clearly authorised by Wolseley Centers Ltd.