HygroMatik HY05, HY17, HY08, HY13, HY23 User Manual

...
Electrode Steam Humidifier
ÁCL.EN=È
CL.EN
Page 2
A Word about Water Quality
The mode of operation of all electrode steam humidifiers is based on the fact that water contains minerals and is therefore conductive.
"normal" tap water is ideal.
but what is "normal" tap water exactly? Users of HygroMatik units in the most diverse areas consider their tap water "normal."
HygroMatik typically defines "normal" as feed water with a conductivity between 200 and 500 µS/ cm (microSiemens per centimeter) at 15° C.
Some areas, however, are supp lied with tap water whose quality is outside the parameters spec­ified by HygroMatik. If the HygroMatik steam humidifier's control is not adjusted correctly in these areas, the unit cannot perform optimally. For example, the electrodes could wear out particularly quickly or the steam production could be too low.
The operational parameters set by HygroMatik in the factory are intended for normal tap water. However, they can very easily be reprogrammed to fit the special requirements of a particular area. In addition, it is possible to install a plastic star in the cylinder in order to increase the life span of the electrodes or to provide a flushing mechanism to extend maintenance intervals.
Because of this you should monitor your new unit during initial operation. Make sure that it has been properly installed and is operating to your satisfaction.
Consult your HygroMatik specialists. We will test the quality of your water and advise you on installation and initial operation. Your HygroMatik steam humidifier will be carefully adapted to your particular application.
Warning, Hazardous Voltage: All work to be performed by trained personnel only. All electrical installation and servicing of the electrical components of this unit to be performed by qualified electricians only. Disconnect power supply before installation and servicing!
© Copyright HygroMatik GmbH; CompactLine 30.10.2013 Information in this manual is subject to change or alteration without prior notice. Current version of this manual can be found at: www.hygromatik.co.uk
Page 3
1. Introduction ....................................................................................................................... 5
1.1 Directions for Use ..............................................................................................................5
1.2 Typographic Distinctions ...................................................................................................6
1.3 Documentation .................................................................................................................. 7
2. Safety Notes ....................................................................................................................... 8
2.1 Overview ........................................................................................................................... 8
2.2 Guidelines for Safe Operation ........................................................................................... 8
2.3 Disposal after Dismantling .................................................................................................9
3. Transport ............................................................................................................................ 10
3.1 Overview ........................................................................................................................... 10
3.2 Carton outer Size and Weight ...........................................................................................10
3.3 Packing ..............................................................................................................................11
3.4 Interim Storage ..................................................................................................................11
3.5 Check for Complete and Correct Delivery of Goods .........................................................11
3.6 Included in the Delivery .....................................................................................................11
4. Operation and Installation ................................................................................................ 12
4.1 Mode of Operation .............................................................................................................12
4.2 Installation and Operation .................................................................................................12
5. Installation ......................................................................................................................... 15
5.1 Steam Humidifier Operating Environment ......................................................................... 15
5.1.1 Fitting measures .............................................................................................................16
5.1.2 Equipment Dimensions C01 - C58 ................................................................................. 17
5.2 Fan Unit (optional) ............................................................................................................. 18
5.2.1 Fan Unit Type VG ...........................................................................................................18
5.3 Absorption Distance BN ....................................................................................................19
5.3.1 Determining the Absorption Distance ............................................................................. 19
5.3.2 Absorption Distance Nomogram .................................................................................... 21
5.4 Steam Manifold .................................................................................................................22
5.4.1 Notes on Installation ....................................................................................................... 22
5.5 Steam Line ........................................................................................................................ 26
5.6 Cover Plate ........................................................................................................................ 27
5.7 Drill Pattern ........................................................................................................................ 28
5.8 Condensate Hose .............................................................................................................. 30
5.9 Types of Installation ..........................................................................................................30
5.10 Steam Solenoid Valves ...................................................................................................32
5.11 Unit Installation Check ..................................................................................................... 32
6. Water Installation ..............................................................................................................33
6.1 Operation with Softened Water .........................................................................................33
6.2 Water Supply .....................................................................................................................34
6.3 Water discharge ................................................................................................................ 35
6.4 Water Installation Check ...................................................................................................36
7. Electrical Connection ........................................................................................................ 37
7.1 Electrical Installation .......................................................................................................... 37
Page 4
7.2 Cable Connections ............................................................................................................ 39
7.3 Fan Unit .............................................................................................................................40
7.4 Safety Interlock .................................................................................................................. 41
7.5 Wiring Diagram .................................................................................................................. 41
7.6 Electrical Installation Checklist ..........................................................................................41
8. Commissioning ................................................................................................................. 42
9. Maintenance ....................................................................................................................... 43
9.1 Maintenance Work ............................................................................................................43
9.2 Access Electrical Enclosure .............................................................................................. 44
9.3 Removing and Cleaning the Steam Cylinder .................................................................... 45
9.4 Electrode wear ..................................................................................................................50
9.4.1 Original Electrode Lengths .............................................................................................51
9.4.2 Uneven Electrode Lengths ............................................................................................. 51
9.5 Replacing Electrodes ........................................................................................................51
9.6 Cleaning the Blow- Down Pump ........................................................................................53
9.7 Cleaning the Water Inlet Solenoid Valve ........................................................................... 54
9.8 Chekking Cable Connections and Electrode Cables .........................................................54
9.9 Checking Hoses ................................................................................................................ 55
9.10 Checking Operation ......................................................................................................... 55
9.11 Dismantling ......................................................................................................................55
10. EC-Declaration of Conformity ........................................................................................ 56
11. Spare Parts ...................................................................................................................... 57
12. Fax Form - Order for spare parts ................................................................................... 62
13. Technical Data .................................................................................................................63
14. Exploded View ................................................................................................................. 64
15. View of housing ............................................................................................................... 65
Page 5
1. Introduction
Dear Customer,
Thank you for choosing a steam humidifier. HygroMatik steam humidifiers represent the latest in humidifica-
tion technology. They will impress you with their safety, ease of use and econom-
ical operation. In order to operate your HygroMatik steam humidifier safely,
properly and efficiently, please read these operating instructions. Employ your steam humidifier only in sound condition and as
directed. Consider potential hazards and safety issues and fol­low all the recommendations in these instructions.
If you have additional questions, please contact us:
Tel.: +49-(0)4193 / 895-0 (Main Number) Tel.: +49-(0)4193 / 895-293 (Technical Support Hotline) Fax: +49-(0)4193 / 895-33 e-mail: hot1@HygroMatik.de
For all technical questions or spare parts orders, please be pre­pared to provide unit type and serial number (see name plate on the unit).
1.1 Directions for Use
The HygroMatik steam humidifier is intended for steam produc­tion.
Proper usage also entails following HygroMatik's instructions for installation, dismantling, reassembly, initial operation and opera­tion and maintenance, as well as disposal procedures.
Only qualified, authorized personnel may operate or service the unit. Workers who transport or service the unit must have read and understood the relevant sections of the operating instruc­tions, especially the section "Safety Notes." In addition, staff must receive safety training about potential hazards from the operator. Place a copy of the operating instructions at the loca­tion where the unit is operated.
Page 6
Use feed water with a conductivity between 125 and 1250 µS/ cm only
D1: Lower threshold C1: Range of reduced conductivity (adjustments recommended) A: Normal tap water B: Range of heightened conductivity C2: Range of high conductivity (adjustments recommended) D2: Upper threshold
Warning: HygroMatik steam humidifiers emit steam with a tem­perature of 100° C. The steam may not be inhaled directly.
The HygroMatik Steam Humidifier is not designed for out door fit­ting
1.2 Typographic Distinctions
preceded by a bullet: general specifications. » preceded by an arrow: Procedures for servicing or
maintenance which should or must be performed in the
indicated order. Installation step which must be checked off. italics Terms used with graphics or drawings..
Page 7
1.3 Documentation
Retention
Please retain these operating instructions in a secure, always accessible location. If the product is resold, turn the documenta­tion over to the new operator . If the document ation is lost, please contact HygroMatik.
Versions in Other Languages
These operating instructions are available in several languages. If interested, please contact HygroMatik or your HygroMatik dealer.
Page 8
2. Safety Notes
2.1 Overview
These safety notes are required by law. They promote work­place safety and accident prevention.
Warnings and Safety Symbols
The safety symbols below identify sections containing warnings about hazards or potential dangers. Please familiarize yourself with these symbols.
Warning: Failure to observe this warning may result in serious injury or death and/or damage to the unit.
Danger, Hazardous Voltage: Hazardous electrical current! Failure to observe this warning may result in injury or even seri-
ous injury or death. Warning: Failure to follow these instructions may result in dam-
age to the unit due to electrostatic discharge. The electronic components of the humidifier control are very sensitive to elec­trostatic discharges. In order to safeguard these components during installation and servicing, steps must be taken to protect against ESD.
Reminder: Materials and consumables must be handled and/or disposed of as required by law.
Note: Appears before explanations or cross-references which refer to other sections of the operating instructions.
2.2 Guidelines for Safe Operation
Overview
Obey all safety notes and warnings present on the unit. In case of a malfunction, switch off the unit immediately and prevent a restart. Repair malfunctions promptly. After any repair work, have qualified personnel check the safe operation of the unit.
Use original spare parts only. Additional national safety regula­tions also fully apply to the operation of this unit.
This unit is not designed for the use by persons (also children) with limited physical, sensory and mental abilities - or without knowledge and experience. Unless they are supervised or trai­ned by a person, who is responsible for their safety. Supervise children in order to ensure that they will not play with the unit.
The unit is only allowed to work with connected steam hose that safely leads the steam.
Page 9
Accident Prevention Regulations Attention: In the event of leaky or faulty components uncon-
trolled hot steam may flow. HygroMatik steam humidifiers are IP20-protected. Make sure
that the unit is protected from drips in its installed location. Installing a humidifier in a room without water discharge requires
safety devices to protect against water leakages.
Accident Prevention Regulations
Comply with the Accident Prevention Regulation Electrical Sys­tems and Equipment to prevent injury to yourself and others.
Operation of the Unit:
Do not perform any work which compromises the safety of the unit. Regularly check that all safety and monitoring devices are functioning normally. Do not remove or disable safety devices.
Installation, Dismantling, Maintenance and Repair of the Unit:
Disconnect unit components from power supply prior to mainte­nance or repair work.
Attaching or installing additional components is permitted only with the written consent of the manufacturer.
Electrical
Work on the electrical system must be performed by qualified personnel.
Disconnect unit components from power supply prior to work. It is not allowed to connect the unit to DC voltage supply. In case of a malfunction in the electrical power supply, switch off
the unit immediately. Use only original fuses with the appropriate amperage rating. Regularly check the unit's electrical equip­ment. Promptly repair any damage, such as loose connections, burned wiring or defective electrical insulation. After proper elec­trical installation or repair, test all safety mechanisms (such as grounding resistance).
2.3 Disposal after Dismantling
Note: The operator is responsible for the disposal of unit compo-
nents as required by law.
Page 10
3. Transport
3.1 Overview
Note: Proceed carefully when transporting the steam humidifier
in order to prevent damage due to stress or careless loading and unloading.
3.2 Carton outer Size and Weight
HyLine:
CompactLine:
MiniSteam:
* Dimensions and weights may vary slightly.
Type* Height
[cm]
Width
[cm]
Depth
[cm]
Weight
[kg]
HY05- 08 58 56 32 16 HY13- 17 75 63 37 24 HY23 75 63 37 25 HY30 81 67 41 33 HY45 88 76 48 46 HY60 80 104 41 54 HY90- 116 90 117 48 77
Type* Height [cm] Width [cm] Depth [cm] Weight [kg]
C01 46 45 26 11 C02 48 44 31 12 C06 52 50 28 13 C10 58 51 31 14 C17 75 54 37 22 C22 75 54 37 22 C30 75 58 37 23 C45 81 63 41 25 C58 90 72 48 36
Type**Height [cm] Width [cm] Depth [cm] Weight[kg]
MS 5 59 48 28 13
MS 10 68 51 31 15
Page 11
3.3 Packing
Note: Notice the symbols affixed to the packing box.
3.4 Interim Storage
Store the unit in a dry place and protect from frost.
3.5 Check for Complete and Correct Delivery of
Goods
Upon receipt of the unit, confirm that:
the type and serial number on the name plate match
those specified in the order and delivery documents
and
the equipment is complete and all parts are in perfect
condition Note: In case of damage during shipment or missing parts,
immediately notify the carrier or supplier in writing. Time limits for filing freight claims with shipping companies are*:
* Time limits for some services subject to change.
3.6 Included in the Delivery
The delivery includes:
Unit of the selected humidifier type including selected
control.
Water installation hose 0,6m, 3/4".
Mounting set with anchors and screws. For HyLine
types HY45 to HY116, extra mounting bar.
Operating Instructions for the unit and the control.
Ordered accessories (steam manifold, steam hose,
condensate hose, etc.).
Maintenance o-ring set for steam cylinder.
Shipping Companies After Receipt of Goods
Mail no later than 24 hours Rail no later than 7 days
Truck and Rail Carriers no later than 4 days
Parcel Service immediately
Page 12
4. Operation and Installation
4.1 Mode of Operation
The HygroMatik steam humidifier utilizes the conductivity nor­mally present in tap water for steam production. Electrodes inside an enclosed steam cylinder are immersed directly into the tap water. They are connected to the alternating current.
The conductivity of the water generates an electric current between the electrodes. In this way, the electric power supplied is converted directly into heat without energy loss.
The amperage is a function of the available voltage, the immersed electrode surface area, the average distance between the electrodes and the water conductivity. The steam output of the humidifier is determined by electric power usage, which is regulated by increasing or decreasing the immersed surface area of the electrodes.
Concurrently, a self-regulating control keeps conductivity within a specified range.
The steam produced has a temperature of about 100°C with minimal excess pressure ("pressureless steam"). It is largely free of minerals and germ-free. Mineral deposits typically remain behind in the cylinder.
4.2 Installation and Operation
By pressing the control switch („Pos. I”) the humidifier is turned on. When the controller specifies an increase in humidity, the main contactor is switched on and the electrodes (48) are sup­plied with power. The water inlet solenoid valve (25) feeds water into the steam cylinder (16+19).
As soon as the electrodes are immersed, the current begins to flow. The water is now heated. When the pre-selected output is reached, the control turns off the solenoid valve and interrupts the water supply.
After a short heating up period, the water between the elec­trodes begins to boil and vaporize. The vaporization lowers the water level in the steam cylinder, reducing the output provided. The inlet solenoid valve, equipped with a fine mesh filter, inter­mittently admits fresh water.
Humidifier power usage is continuously monitored. With a cold start-up, the nominal current increases to 125% in order to achieve quick-start output parameters. This activates the elec­tronic overflow limiter which causes a partial draining of the cyl­inder. This reduces the immersed surface area of the electrodes, lowering power usage.
Page 13
Please also see Section „Exploded View“.
Location Designation
1 adapter
6 vent pipe 10 max. water level sensor electrode 14 water drain, discharge 16 top part of steam cylinder 17 o-ring cylinder flange 18 cylinder flange and o-ring 19 lower part of cylinder 25 solenoid valve water inlet 32 blow-down pump 35 o-ring 37 cylinder base 48 electrodes
Page 14
The concentration of dissolved salts increases over time, which can lead to a rise in the conductivity of the water. If this contin­ues, conductivity may increase until a short circuit occurs. This could damage the unit, but in any case would significantly reduce the life span of the electrodes.
For this reason, regular, periodic blow-downs of some of the concentrated water are very important. Following this procedure as recommended provides stable cylinder water conductivity as well as minimal water loss for the expected service life of the cyl­inder.
Water blow-down is performed by a blow-down pump (32). The functioning of the blow-down pump is continuously monitored during operation. If the pump is damaged, the steam humidifier shuts down.
With normal water quality, the blow-down loss rate is between 7% and 15% of the amount of steam produced. The steam cylin­der requires complete drainage every 3-8 days, regardless of the water quality.
Mineral deposits settle in the open area below the electrodes and are removed through periodic maintenance. The blow-down pump itself has wide openings and can flush out smaller pieces of mineral deposit. This extends the service life of the unit and reduces the required maintenance interval.
During blow-downs, water flows from the pump into the drainage system.
A sensor electrode (10) monitors the maximum
water capacity
of the cylinder. When the water level reaches the sensor elec­trode, the water supply is interrupted. This can occur when the water has low conductivity or when the electrodes are worn out. In the case of low water conductivity, however, this state usually lasts only a short time. The built-in control and the large area electrodes combine to produce a rapid rise in conductivity by increasing the concentration of the water.
The steam cylinder consists of a top (16) and lower (19) part joined with a cylinder flange. The seal between the cylinder and cylinder base (37), as well as between the top and lower part of the cylinder, is maintained using an o-ring (35+17).
For maintenance the cylinder can be drained by pressing the control switch „Pos.II”.
Page 15
5. Installation
Warning: Installation of this unit to be attempted only by quali-
fied personnel. We accept no liability for damage due to faulty installation.
Obey all safety notes and warnings present on the unit. During installation the unit must be disconnected from its power
supply. Attaching or installing additional components is permitted only
with the written consent of the manufacturer, or else the war­ranty is void.
Warning: If the installation of this unit is attempted by only one person there is a risk that the unit drops down. We propose to carry out the installation by two persons.
5.1 Steam Humidifier Operating Environment
Note: When selecting the installation site for the steam humidi-
fier, note that:
Ambient temperature must be between +5° and +40° C. Relative humidity must not exceed 80% RH.
An Installation in a closed room requires aeration and if neccessary temperature conditioning in order to reach the above mentioned environmental conditions.
The minimum clearances indicated in the diagram below must be observed; these are necessary to ensure adequate ventilation for the housing.
HygroMatik humidifiers are not suitable for direct out­door installation.
The steam humidifier should be installed as close as possible to the steam manifold. Optimal performance is guaranteed only with short lengths of steam and con­densate hose
.
Hoses must be laid at a consistent 5-10% incline to pre­vent sagging and kinking
.
The rear panel of the steam humidifier heats up during operation (to a maximum of 60°C).
Take care that the
construction on which the unit is mounted is not made of temperature-sensitive material.
Place the steam humidifier so that the unit is easily accessible with sufficient space to perform mainte­nance.
The steam humidifier is not qualified for exterior appli­cations.
Page 16
5.1.1 Fitting measures
Clearances
Note: When choosing the site for the steam humidifier, consider
the location of existing water installations (feed and drain lines).
Page 17
5.1.2 Equipment Dimensions C01 - C58
C01 C02 C06 C10 C17/
C22/ C30
C45 C58
a 370 350 438 480 653 707 790 b 355 392 401 414 480 527 615 c 171 221 187 217 283 325 392 d 280 317 351 369 435 482 564 e 293 273 394 436 609 657 740
f31313434383838 g 130 130 130 119 210 250 300 h40404343635861
i45453035355050
j 105 125 102 119 152 175 202 k 105 105 102 100 133 155 199
l------328
m 135 178 145 173 233 255 343
n 105 74 77 68 86 108 181 o------215 p27 27 26 42
r18,5
View from below
Rear view
Viem from top
Cable entries
Waste water connection
Steam outlet
Water inlet
Page 18
5.2 Fan Unit (optional)
Note: The fan unit should be positioned to avoid drafts . In gen-
eral, a minimum height of 2 m is sufficient. Install the fan unit directly on a wall.
Warning:
During operation and a soon afterwards the steam nozzle is hot! If touched this can cause burns to the skin.
During operation the cross-flow fan rotates. Do not touch the fan during operation.
During operation hot steam discharges from the nozzle. In the field of the visible steam cloud contact can cause burns to the skin.
5.2.1 Fan Unit Type VG
Install the fan unit over the steam humidifier.
When employing multiple fan units, do not exceed a
maximum distance of 5 m from the steam humidifier.
Observe the clearances specified in the diagram below:
Fan Unit Type
for wall installation VG 08, 17, 30
Technical Specifications Fan Unit VG Fan Unit VG08 VG17 VG30
Quantity of Steam [kg/h] 8 17 30 Steam Inlet [mmφ]25 25 40 Condensate Outlet [mmφ]12 12 12 Airflow Capacity [cbm/h] 185 185 350 Nominal Output [W] 35 35 67 Nominal voltage [V] 230 230 230
Dimensions W [mm] 441 507 550
H [mm] 171 171 171 D [mm] 180 237 277
Weight [kg] 4,5 6 7 Sound Level (1m dis-
tance to the source of noise)
[dB(A)] 50 53,8 59
Steam
Front View Wall Installation
Side View Wall Installation
Page 19
5.3 Absorption Distance BN
The "absorption distance" (BN) is defined as the distance from the steam feed to where the steam is completely absorbed in the
treated air. Inside the absorption distance, steam is visible as mist in the air stream.
Condensation may collect on anything installed inside the absorption distance.
Although steam outside the absorption distance (B
N
) is com-
pletely absorbed, it is not yet evenly diffused in the duct. If you plan to install any parts or devices inside the absorption dis­tance, such as sensors or elbows, we recommend increasing the absorption distance using the formulae below. The absorp­tion distances required for certain installed fittings are distin­guished by separate symbols and calculated as a multiplier of the absorption distance B
N
.
The absorption distance has no fixed value, but depends on many factors. These are depicted in the absorption distance nomogram below.
5.3.1 Determining the Absorption Distance
To determine the absorption distance, the following parameters are required:
Air humidity before humidification x
1
in g/kg.
Air temperature after humidification t
2
in °C (with steam
humidifiers the change in air temperature due to humid­ification may be disregarded t
1
or t2).
Specific increase in humidity x in g/kg (can be deter­mined in the h,x diagram)
quantity of steam introduced in kg/h.
air speed w
L
in m/s in air duct
Total length l
D
of the steam manifold installed in the air
duct
Absorption Distance
B
N
for normal obstructions, such as sen­sors, ventilators, outlets
B
c
= (1,5...2) x BNfor fine filters, heat registers
B
s
= (2,5...3) x BNfor particle filters
B
d
= (2,5...3) x BNfor humidity sensors, duct humidistats
o
D
m
Page 20
Length ID of the usable steam manifold depends on the dimen­sions of the air duct. The length of the absorption distance can
be reduced by using multiple steam manifolds (also see section on the steam manifold).
Method:
Graphically determine absorption distance B
N
using the absorp-
tion distance nomogram (also see Section „Absorption Distance Nomogramm“). Enter the value of the parameters enumerated above into the respective quadrants. The resulting point of inter­section indicates the value of the desired absorption distance B
N
.
Notes:
x
1
: _______________________________[g/kg]
t
2
: _______________________________[°C]
x:_______________________________[g/kg]
:_______________________________[kg/h]
w
L
: _______________________________[m/s]
l
D
: _______________________________[mm]
Air humidity before humidification
Air temperature after humidification
Specific increase in humidity quantity of steam introduced
air speed t
Total length of the steam manifold
o
D
m
Loading...
+ 46 hidden pages