Hydrolevel CG400 User Manual

WARNING – To prevent electrical shock or
equipment damage, power must be off during installation or servicing of the control. To pre­vent serious burns, the boiler should be thor­oughly cooled before installing or servicing con­trol. Only qualified personnel may install or ser­vice the control in accordance with local codes and ordinances. Read instructions completely before proceeding.
The probe may be installed in the boiler above the lowest safe water level established by the boiler manufacturer. Most manufacturers pro­vide a suitable opening in the side of the boiler.
Allow 1/4" clearance from the probe to any boiler surface, tube or baffle. NOTE: Excessive use of Teflon tape to seal probe piping threads may insulate the control from boiler ground. This could result in the control not operating.
Low Water Cut-Offs For Steam Boilers
24 VAC Operating Voltage Max. Pressure 15 psi
U.S. Patent No. 5,739,504
with
HOW TO INSTALL
1 2 3
5
1/4"
SAFE WATER LINE
P.O. Box 1847 New Haven, CT 06508 Phone: (203) 776-0473 FAX: (203) 773-1019
Low maintenance. No moving parts to wear stick or hang up, as in float devices.
Solid state circuitry. Designed for the highest level of perfor­mance and reliability.
Automatically shuts off burner, after delay, in a low water condition to prevent dry firing.
Time delay allows water to feed above the probe to a safe operating level.
INTERMITTENT LEVEL TEST – periodically monitors settled water level for added protection of today’s smaller steam boilers.
CG400 Series
Loosen the two control cover binding head screws and remove the cover. Assemble the chassis to the probe flange and secure with the screws provided with the probe.
Connect the ring terminal wire lead to the probe terminal stud and secure with the lock washer and wing nut provided. With the power removed, proceed with installation and wiring according to the instructions on page 2. Upon completion of wiring replace control cover.
4
REMOTE MOUNTED MODELS ONLY
A. To secure mounting plate to boiler jacket,* pre-drill two 3/32" pilot holes using the mount­ing plate as a template. Secure plate with sheet metal screws provided. Attach control to mounting plate by slipping keyholes in back of chassis over pre-mounted screws on plate. Tighten screws.
B. Using a wire nut, attach a wire (min 90°C) to the pigtail lead in the control box. Attach the other end to the probe terminal in the remote probe housing. Attach a second wire between the ground screw on the control chassis and one of the four screws in the remote probe housing. Note: Wires and wire nuts not provided.
*Or other suitable surface
BA
HOW TO WIRE
MODEL CG400
1
AP2P112
BURNER
BURNER
COMMON
POWER
SOURCE
24VAC
Connect input voltage (24 VAC, 60 HZ) to terminals 1 and 2.
FACTORY INSTALLED JUMPER.
HOT
DO NOT REMOVE
2
BURNER
AP2P112
BURNER
POWER
SOURCE
24VAC
COMMON
Connect terminal 2 to burner circuit common. Connect terminal P2 to burner Circuit in series with and before other limit controls. Consult boiler manufacturer instructions for proper terminal connections.
C
GAS
VALVE*
LIMIT
HOT
CONTROLS
+
0
H
*or Intermittent Ignition
3
BURNER
POWER
SOURCE
24VAC
Optional water feeder connection. Connect feeder N to terminal 2. Connect Feeder H to terminal 1. Connect feeder “FEED” or “W” to terminal A. For water feeders with 2 leads, connect feeder common to terminal 2 and feeder hot to ter­minal A. Note: Use of a solenoid
valve or McDonnell & Miller Model 101A water feeder may cause flooding and is not recommended for use with this low water cut-off.
MODEL CG400 — ALTERNATE WIRING METHOD USING PLUG CONNECTOR
C
VALVE*
VALVE*
4
AP2P112
AP2P112
BURNER
BURNER
POWER
SOURCE
24V
AC
LIMIT
CONTROLS
GAS
GAS
+
0
H
WATER FEEDER
C
VALVE*
LIMIT
CONTROLS
0
GAS
H
WATER FEEDER
OPTIONAL ACTIVATION
Standing pilot boilers: Connect “Burner” terminal to hot leg of 24VAC connection on gas valve.
Pilotless ignition boilers: “Burner” terminal to hot leg of 24VAC connection on intermittent
ignition (spark) module.
See boiler manufacturer’s installation instructions for correct connection to 24VAC hot.
BURNER
+
Connect
1
2
3
WATER
FEEDER
WATER FEEDER
AP2P112 BURNER
BURNER
AP2P112
BURNER
AP2P112
C H
GAS
VALVE*
Plug wire harness connector into matching end on circuit board.
IMPORTANT: Factory installed jumper must be in place between
P2
2
1
terminals 1 and P1.
Optional water feeder connection. Connect feeder N to terminal 2. Connect Feeder H to terminal 1. Connect feeder “FEED” or “W” to ter­minal A. For water feeders with 2 leads, connect feeder common to terminal 2 and feeder hot to terminal A. Note: Use of a solenoid valve
or McDonnell & Miller Model 101A water feeder may cause flooding and is not recommended for use with this low water cut-off.
OPTIONAL ACTIVATION
Standing pilot boilers: Connect “Burner” terminal to hot leg of 24VAC connection on gas valve.
Pilotless ignition boilers:
Connect “Burner” terminal to hot leg of
24VAC connection on intermittent ignition (spark) module.
See boiler manufacturer’s installation instructions for correct
*or Intermittent Ignition
connection to 24VAC hot.