NOTE: Be sure merchandisers
have been leveled according to the
installation instructions. Carefully
unpack and inspect the Wall/
Island Joint Kit, making sure there
is no
breakage or damage. Be
sure factory-
installed nut retainers
and alignment pins are in place.
SSTTEEPPSS
1
Apply Gaskets
——
1 and 2
as shown in Figure 1.
• Remove paper backing as
gasket is applied.
• Lap gaskets at lower corners.
• Check that there are no gaps
between gasket and merchandis
er.
• Do not stretch gasket,
especially around corners.
• Do not butt gaskets; always
overlap joints.
A. Remove Honeycomb at
end to be joined by lifting up
atbottom and pullingforward.
B. Lift out Rear Panel.
C. Remove Front Panel.
PARTS LIST
Item No. Quantity Description
L LG LN LNG LI LIG
1. 1 1 1 1 1 1 Gasket 1/2 x 1/2 x 120
2. 1 1 1 1 1 1 Donut Gasket
3. 6 5 6 4 6 4 Cap Screw5/16-18 x 1
4. 6 5 6 4 6 4 Lock Washer Split Steel 5/16
5. 6 5 6 4 6 4 Flat Washer5/16
6. 6 5 6 4 6 4 Hex Nut 5/16 - 18
7. – 1 – 2 – 2 Glass Post Joint Extrusion
8. – 1 – 1 – 1 Glass Post End Cover
9. 4 4 4 4 4 4 Screw Phillips Sheet Metal 8 x 1/
2
10. 1 – 2 1 2 1 Nosing Joint Trim
11. 1 1 – – – – Joint Trim
Wall/Island Merchandiser
(Solid and Glass Front) Joining Instruction
L, LG, LN, LNG, LI, LIG
Splashguard Brackets
MUST BE INSTALLED
Before Piping Case.
For Low Temperature Merchandisers
Figure 1. Installing Gasket for Solid and Glass
See Figures 1, 2 and 3 for gasket, hole and fastener locations for all models.
NOTE: A
PPLY GASKET TO ONE CASE ONLY.
NOTE: Refer to the
Installation Manual to
install splashguard