HME SPP2 Installation Instructions Manual

Concrete Foundation
INSTALLATION INSTRUCTIONS
The SPP2 Speaker Post requires a concrete foundation with four anchor bolts and one or more conduits embedded in it. One conduit must be installed for the audio cable. Additional conduit(s) may be required for a vehicle detection cable and/or for an AC electrical cable. These instructions are for installation of the SPP2 concrete foundation at new drive-thru sites.
CAUTION: All electrical connections must be made
by a licensed electrical contractor.
If you have any questions regarding this installation, call HME Customer Support at 1-800-848-4468.
1.0 Equipment Provided
For SPP2 Speaker Post
This surface is
6" to 10" above
the drive- thru
lane surface
1 ea Template 4 ea Anchor bolt with 2 hexagonal nuts
2.0 Material Required
Concrete, 6 cubic feet
3.0 Procedure
Step 1 Position the foundation so that water
will drain away from the base of the speaker post. The top surface of the foundation must be six to ten inches above the surface of the drive-thru lane. The side of the foundation must be 2 feet or less from the side of the drive-thru lane, and parallel to the lane as shown in Figure 2.
Build a 24 x 24 inch form with its top six to ten inches above the surface of the drive-thru lane. Dig a hole in the ground to a depth 18 inches below the top of the form for pouring the concrete foundation shown in Figure 1.
Figure 1.
SPP2 Speaker Post
on concrete foundation
HM ELECTRONICS, INC. 14110 Stowe Drive, Poway, CA 92064 USA ! Phone: 1-800-848-4468 Fax: (858) 552-0172
HME# 400262
Rev C 10/29/02
Step 2 Remove one of the two hexagonal nuts
from each of the anchor bolts. Be certain the second nut is all the way
down to the bottom of the threaded area on the anchor bolt as shown in Figure 3.
Put the threaded end of each anchor bolt through one of the ½ inch holes in the template, and replace the nut on the anchor bolt until it holds the template snugly between the two nuts.
Position the "L" ends of the anchor bolts outward, away from each other. Place the anchor bolts into the hole in the ground with the template ¼" to ½" above the top of the form, as level as possible. Be certain to comply with the note on the template to place one edge of the template "TOWARD DRIVE-THRU LANE."
Figure 3.
Assembly of anchor bolts with template
Step 3 Route the conduit (one or more) so
it/they will extend through the center of the hole, and upward approximately 6 inches through the center of the template as shown in Figure 4.
NOTE: If a loop-type vehicle detector will be used, a separate conduit must be dedicated for the loop cable.
Step 4 Hold the template steady, and fill the
hole with concrete to the bottom of the template. Smooth the concrete, sloping it away from the template toward the form for proper drainage, and allow it to dry.
After the concrete has dried, remove the upper nuts and template from the anchor bolts.
Figure 4.
Template, anchor bolt and conduit
positions in hole