Hitachi RAC-35NH5, RAC-50NH5, RAC-25NH5 Installation Manual

CONDENSED WATER DISPOSAL OF OUTDOOR UNIT
There are holes on the base of Outdoor unit for condensed
water to exhaust.
In order to flow condensed water to the drain, the unit is installed on
a stand or a block so that the unit is 100mm above the ground as shown figure. Join the drain pipe to one hole.
At first insert one portion of the hook to the base (Portion A), then
pull the drain pipe in the direction shown by the arrow while inserting the hook into the base. After installation, check whether the drain pipe cling to the base firmly.
When Using and Installing In Cold Areas
When the air conditioner is used in low temperature and in snowy conditions, water from the heat exchanger may freeze on the base surface to cause poor drainage. When using the air conditioner in such areas, do not install the bushings. Keep a minimum of 250mm between the drain hole and the ground. When using the drain pipe, consult your sales agent.
For more details, refer to the installation Manual for Cold Areas.
Maximum pipe length 20m
above 200mm
above 700mm
above 200mm
above 50mm when installed on the ceiling of balcony
(
)
above 100mm
above 100mm
give clearance as wide as possible
SPLIT UNIT AIR CONDITIONER
INSTALLATION MANUAL
RAC-25NH5
Outdoor Unit RAC-35NH5
RAC-50NH5
+
– Screwdriver●Measuring Tape●Knife
Saw●ø 65mm Power Drill●Hexagonal Wrench
Key ( 4mm)
Wrench (14, 17, 22, 26, 27mm)
Gas Leakage Detector●Pipe Cutter●Putty
Vinyl Tape●Pliers●Flare Tool
Carefully read through the procedures of proper installation before starting installation work.
The sales agent should inform customers regarding the correct operation of installation.
Tools Needed For Installation Work
SAFETY PRECAUTION
Read the safety precautions carefully before operating the unit.
The contents of this section are vital to ensure safety. Please pay special attention to the following sign.
WARNING ........ Incorrect methods of installation may cause death or serious injury.
CAUTION ......... Improper installation may result in serious consequence.
Be sure that the unit operates in proper condition after installation. Explain to customer the proper way of operating the unit as described in the user’s guide.
!
!
WARNING
!
CAUTION
!
A circuit breaker or fuse (16A time delay) must be installed. Without a circuit breaker or fuse the danger of electric shock exists. A main switch with a contact gap of more than 3mm has to be installed in the power supply line to the outdoor unit.
Do not install the unit near a location where there is flammable gas. The outdoor unit may catch fire if flammable gas leaks around it.
Please ensure smooth flow of water when installing the drain hose.
Piping shall be suitable supported with a maximum spacing of 1m between the supports.
Please request your sales agent or qualified technician to install your unit. Water leakage, short circuit or fire may occur if you do the installation work yourself.
Please observe the instructions stated in the installation manual during the process of installation. Improper installation may cause water leakage, electric shock and fire.
Make sure that the units are mounted at locations which are able to provide full support to the weight of the units. If not, the units may collapse and impose danger.
Observe the rules and regulations of the electrical installation and the methods described in the installation manual when dealing with the electrical work. Use power cables approved by the authorities of your country.
Be sure to use the specified wire for connecting the indoor and outdoor units. Please ensure that the connections are tight after the conductors of the wire are inserted into the terminals. Improper insertion and loose contact may cause over-heating and fire.
Please use the specified components for installation work. Otherwise, the units may collapse or water leakage, electric shock and fire may occur.
Be sure to use the specified piping set for R-410A. Otherwise, this may result in broken copper pipes or faults.
When installing or removing an air conditioner, only specified refrigerant (R410A) shall be allowed, do not allow air or moisture to remain in the refrigeration cycle. Otherwise, pressure in the refrigeration cycle may become abnormally high so that a rupture may be caused.
Be sure to ventilate fully if a refrigerant gas leak while at work. If the refrigerant gas comes into contact with fire, a poisonous gas may occur.
After completion of installation work, check to make sure that there is no refrigeration gas leakage. If the refrigerant gas leaks into the room, coming into contact with fire in the fan-driven heater, space heater, etc., a poisonous gas may occur.
Unauthorized modifications to the air conditioner may be dangerous. If a breakdown occurs please call a qualified air conditioner technician or electrician. Improper repairs may result in water leakage, electric shock and fire, etc.
FOR SERVICE PERSONNEL ONLY
THE CHOICE OF MOUNTING SITE (Please note the following matters and obtain permission from customer before installation).
WARNING
!
The Outdoor unit must be mounted at a location which can support heavy weight. Otherwise, noise and vibration will increase.
CAUTION
!
Do not expose the unit under direct sunshine or rain. Besides, ventilation must be good and clear of obstruction.
The air blown out of the unit should not point directly to animals or plants.
The clearances of the unit from top, left, right and front are specified in figure below. At least 3 of the above sides must be open air.
Be sure that the hot air blown out of the unit and noise do not disturb the neighbourhood.
Do not install at a location where there is flammable gas, steam, oil and smoke.
The location must be convenient for water drainage.
Place the Outdoor unit and its connecting cord at least 1m away from the antenna or signal line of television, radio or telephone. This is to avoid noise interference.
OUTDOOR UNIT
Dimension of Mounting Stand
of the Outdoor unit
(unit: mm)
The difference in height
between the indoor and outdoor unit should be kept max 10m.
The connecting pipe, no
matter big or small, should all be insulated with insulation pipe and then wrapped with vinyl tape. (The insulator will deteriorate if it is not wrapped with tape).
The connection of insulated drain hose.
Please use insulated drain hose for the indoor piping (commercial product).
inner diameter ø 16mm
Names of Outdoor Components
Drain Pipe
1
57
12 35
124
500
320
10
20
(10)
340
mounting stand
Dimension of Mounting Stand
of the Outdoor unit
(unit: mm)
57
12 35
198
508
320
10
35
(10)
340
mounting stand
(RAC-25NH5, RAC-35NH5)
(RAC-50NH5)
Please mount the Outdoor unit on stable ground to prevent vibration and increase of noise level.
Decide the location for piping after sorting out the different types of pipe available.
When removing side cover, please pull the handle after undoing the hook by pulling it downward.
Please face this side (suction side) of the unit to the wall.
Please remove side cover when connecting the piping and connecting cord.
Pull downward
BASE
DRAIN PIPE
A
DRAIN PIPE
BUSH
100 mm ABOVE
11
10
BUSH
12
Figure showing the Installa­tion of Outdoor Unit.
2
3
Bush
QtyNo. Item
(RAC-25NH5, RAC-35NH5)
(RAC-50NH5)
HFC
R410A
<
I867: A
>
Bush
1
10
11
12
(EN) INS RAC-25/35/50NH5 20/10/05, 9:14 AM1
Removal Of Air From The Pipe And Gas Leakage Inspection
Gas Leakage Inspection
Please use gas leakage detector to check if leakage occurs at the connection of Flare nut as shown on the right.
If gas leakage occurs, further tighten the connection to stop leakage. (Use the detector provided for R410A)
3
Procedures of using Vacuum Pump for Air Removal
As shown in right figure, remove the cap of valve core. Then, connect the charge hose. Remove the cap of valve head. Connect the vacuum pump adapter to the vacuum pump and connect the charge hose to the adapter.
Fully tighten the Hi shuttle of the manifold valve and completely unscrew the Lo shuttle. Run the vacuum pump for about 10–15 minutes, then completely tighten the “Lo” shuttle and switch off the vacuum pump.
2
Completely unscrew the spindle of the service valve (at 2 places) in anti­clockwise direction to allow the flow of coolant (using Hexagonal Wrench key).
3
Remove the charge hose and tighten the cap of valve head. Check the cap’s periphery if there is any gas leakage. The task is then completed.
1
Preparation of Pipe
1
Use a pipe cutter to cut the copper pipe.
Jagged edge will cause leakage.
Point the side to be trimmed downwards during trimming to prevent copper chips from entering the pipe.
Before flaring, please put on the flare nut.
Pipe Connection
2
CAUTION
!
Outer
dia.of pipe
6.35 (1/4")
9.52 (3/8")
12.7 (1/2")
6.35 (1/4")
9.52 (3/8")
12.7 (1/2")
Valve
head cap
Torque N·m
(kgf · cm)
13.7 – 18.6 (140 – 190)
34.3 – 44.1 (350 – 450)
44.1 – 53.9 (450 – 550)
19.6 – 24.5 (200 ~ 250)
19.6 – 24.5 (200 ~ 250)
29.4 – 34.3 (300 – 350)
12.3 – 15.7 (125 ~ 160)
Outer Diameter (mm)
6.35
9.52
12.7
For R410A tool
0.0
~
0.5mm
0.0
~
0.5mm
0.0
~
0.5mm
For R22 tool
A (mm)
Small dia. side
Large dia. side
Valve core cap
AIR REMOVAL
Recommend to use R410A flaring tool.
Small dia. side
Large dia. side
CAUTION
!
In case of removing flare nut of an Indoor unit, first remove a nut of small diameter side, or a seal cap of big diameter side will fly out. Prevent water from entering into the piping when working.
When the meter reaches - 101KPa (-76cmHg) during pumping, fully tighten the shuttle.
Meter showing pressure
Closed R410A
Manifold valve
Vacuum pump
Valve
Charge hose
Valve
Vacuum pump adapter
When pumping starts, slightly loosen the flare nut to check of air sucked in. Then tighten the flare nut.
Copper pipe
Trimming tool
A
Die
Die
Copper pipe
1.0mm
1.0mm
1.0mm
Wrench
Torque wrench
Flare nut
Lo Hi
The body of service valve
Cap of
valve core Hexagonal Wrench Key
Cap of valve head
Cap of valve head
4
WARNING
If you cannot attach the side cover due to the connecting cord, press the connecting cord in direction to the front panel to fix it.
Be sure that the hooks of the side cover is fixed in certainly. Otherwise water leakage may occur and this causes short circuit or faults.
The connecting cord should not touch to service valve and pipes. (It becomes high temperature in heating operation.)
Checking for the electric source and the voltage range
Before installation, the power source must be checked and necessary wiring work must be completed. To make the wiring capacity proper, use the wire gauges list below for the lead-in from a pole transformer and for the wiring from a switch board of fuse box to the main switch and outdoor unit in consideration of the locked rotor current.
Investigate the power supply capacity and other electrical conditions at the installation location. Depending on the model of room air conditioner to be installed, request the customer to make arrangements for the necessary electrical work etc. The electrical work includes the wiring work up the outdoor. In localities where electrical conditions are poor, use of a voltage regulation is recommended.
THIS APPLIANCE MUST BE EARTHED.
Procedures of Wiring
Wiring of The Outdoor Unit
Please remove the side cover for wire connection.
!
WARNING
!
In case that power is supplied from Outdoor Unit
Earth terminal
N
CD
Power supply shall be connected at the rated voltage, otherwise the unit will be broken or could not reach the specified capacity.
DCNLDC
Indoor Unit Outdoor Unit
Connecting Cord
Connecting Cord
AC 220 - 230V
1.6 or
2.0
2.0
L
The naked part of the wire core should be 10 mm and fix it to the terminal tightly. Then try to pull the individual wire to check if the contact is tight. Improper insertion may burn the terminal.
Be sure to use only power cables approved from the authorities in your country. For example in Germany: Cable type: NYM 3x1.5mm
2
.
Please refer to the installation manual for wire connection to the terminals of the units. The cabling must meet the standards of electrical installation.
There is a AC voltage of 230V between the L and N terminals. Therefore, before servicing, be sure to remove the plug from the AC outlet or switch off the main switch.
WARNING
!
Outdoor
Unit
GRN + YEL
Strip wires
25mm
25mm
10mm
10mm
10mm
35mm
Cable length
up to 16m
up to 15m
up to 25m
Wire cross-section
1.5mm
2
2.5mm
2
4.0mm
2
IMPORTANT
FINAL STAGE OF INSTALLATION
Insulation And Maintenance Of Pipe Connection
1
The connected terminals should be completely sealed with heat insulator and then tied up with rubber strap.
Please tie the pipe and power line together with vinyl tape as shown in the figure showing the installation of Indoor and Outdoor units. Then fix their position with holders.
To enchance the heat insulation and to prevent water condensation, please cover the outdoor part of the drain hose and pipe with insulation pipe.
Completely seal any gap with putty.
Power Source And Operation Test
2
Power Source
CAUTION
!
Please use a new socket. Accident may occur due to the use of old socket because of poor contact.
Please plug in and then remove the plug for 2 – 3 times. This is to ensure that the plug is completely plugged into the socket.
Keep additional length for the power cord and do not render the plug under external force as this may cause poor contact.
Do not fix the power cord with U-shape nail.
Sleeve of protection pipe
Putty
Putty
Insulation material for pipe connection
<
I867: A
>
Operation Test
Please ensure that the air conditioner is in normal operating condition during the operation test.
Explain to your customer the proper operation procedures as described in the users manual.
Power line Control line
Use 16A Time Delay Fuse
(EN) INS RAC-25/35/50NH5 20/10/05, 9:14 AM2
Loading...