A. Introduction
1
Heat Controller, Inc., Air Handlers come in a variety of models and
sizes for upow or horizontal use and when combined with cool-
ing coils, are ready for air conditioning and heat pump applications. These instructions are primarily to assist qualied individuals trained and experienced in the proper installation of this type of equipment.
B. Rules for Safe Installation and Operation
1. Read these rules and the instructions carefully. Failure
to follow the rules and the instructions could cause a malfunction of the unit, and a possible safety hazard. Keep these instructions nearby the unit for future
reference.
2. This unit has been designed and manufactured to comply
with National Codes; however, it is the installer’s responsibility to install this unit to comply with
prevailing codes and regulations. Heat Controller, Inc.,
assumes no responsibility for units installed in violation
of any code or regulation.
3. Before servicing, ALWAYS SHUT OFF ELECTRICITY TO THE UNIT. This will prevent any
electrical shocks.
4. Ground the unit to prevent electric shock. All electrical
wiring should be in accordance with the National
Electrical Code.
5. Duct work must be installed in accordance with the
0.2 inches of static pressure. See National Environmental
Systems Contractors Association Manual K for duct
sizing recommendations. Ductwork in non-conditioned spaces must be insulated to prevent formation of condensate and for maximum operating efciency.
6. The safety testing agency label appearing on the unit
covers the unit and factory installed coil(s) only. It does not cover any other equipment.
7. Exterior surface of cabinet may sweat when unit is installed
in non-conditioned space such as attic or garage. Installer must provide protection such as full size auxiliary drain pan on all units installed in non-conditioned space such as
attic or garage type installations to prevent damage from
condensation. It is recommended that units installed in non-conditioned space be insulated on the outside with 1” thick berglass with the vapor barrier on the outside.
8. While designed to operate quietly when properly installed,
several steps should be taken to insure this. Use of isolation pads when mounting unit, exible duct collars for discharge, and use of acoustical duct liners are all good installation practices that promote quiet operation.
9. Cabinet insulation is rated for R=4.2 (standard). Some
jurisdictions require R=6.0 on installations in non­conditioned space. Add insulation 1” thick to exterior of air handler to comply in these jurisdictions, putting the vapor barrier on the outside.
C. Unpacking the Unit
The unit should be unpacked on receipt and if damage is found, a claim should be made immediately to the shipping carrier. This is the responsibility of the entity receiving the equipment. The air
handler is completely assembled, as received. Electric power, ther-
mostat wiring, refrigerant piping and duct connections are needed to complete an installation. Additionally, a drain connection will be needed. Check the rating plate for unit size, voltage, phase etc. to make sure unit meets your requirements.
D. Physical Installation
MINIMUM CLEARANCES
These units have a 0” minimum clearance to combustible materi-
als rating from all cabinet surfaces. The unit should be installed with serviceability clearance of 30” from the front of the unit. The unit can be serviced entirely from the front, including replacing the lter. Be sure and route primary and secondary drain connections so as not to obstruct lter replacement.
ARRANGEMENT
Unit is shipped from the factory arranged to be installed in a verti-
cal upow or horizontal right to left airow position (standard) or eld convertible to a horizontal left to right airow position.
Upow Application
In an upow installation the discharge outlet is at the top. Care should be taken to ensure unit is level to permit proper condensate
drainage. Normal upow installation will be in a basement or clos-
et. If installed in a closet, the closet should have a platform framed in, with an opening on top of the platform centered in the closet.
Connect the supply air outlet to a discharge air plenum. Install re-
turn air grilles from outside the closet to space below the platform. Platform must be at least 10” above the oor. Run all supply and return ductwork in accordance with local codes.
Horizontal application
Horizontal application will normally be used in an attic or crawl space. This type installation requires a return air duct be attached to the air handler inlet. The opposite end of the return air duct is attached to a return air lter grille through the ceiling or wall. Remove lter from unit if lter grill is used. The unit is shipped in right to left conguration.
CAUTION
A “P” trap must be installed in the coil
drain line! Cap unused drain ttings.
WARNING
To ensure unit will not interfere with drains and
refrigerant lines, modication must be made
prior to installing these lines..
FOR LEFT TO RIGHT APPLICATIONS.
1. Remove and set aside front panels.
2. Remove the coil support bracket (4-screws).
3. Remove horizontal drain pan retaining clip (1-screw).
2
4. Carefully remove coil assembly and bottom drain pan.
5. Move horizontal drain pan from left hand side of coil to right side.
6. Install modied coil assembly back into unit.
7. Reinstall coil support bracket and horizontal drain pan
retaining clip.
8. Determine drain holes being used and reposition knockout
caps.
9. Reinstall doors.
CAUTION
IT IS MANDATORY TO USE AN
EMERGENCY AUXILIARY DRAIN PAN
WITH ANY COIL OR AIR HANDLER
INSTALLED IN AN ATTIC OR ABOVE A
FINISHED CEIING!
E. Electric Furnace
Optional electric heating packages are available, see the unit label
for various sizes.
* See Electric Heater Kit Specications Table
F. Power Wiring
Refer to the unit’s nameplate for specic electrical data.
CAUTION
DISCONNECT POWER AT MAIN FUSE OR CIRCUIT
BREAKER DISTRIBUTION PANEL BEFORE WIRING
UNIT TO PREVENT SHOCK OR FIRE HAZARD.
Use copper conductors only. Tighten all wire connectors.
Refer to unit nameplate for minimum circuit ampacity. For correct wire size, refer to the National Electrical Code. Use 75˚C minimum wire in unit wiring compartment.
NOTE: SEE UNIT FOR COMPLETE WIRING DIAGRAM
LOCATED ON BLOWER HOUSING.
G. Control Wiring
Field connections are made to the low voltage terminal strip. Consult installation instructions provided with accessory items for specic information on control wiring. Use 18 AWG minimum copper control conductors for control wiring up to 50 feet between units. 16 AWG control conductors are recommended for lengths up to 100 feet. Class 2 wiring is acceptable. Do not short control leads. Transformer burn-out will result. Set thermostat heat anticipator at
0.15 amps for air handler.
Terminal number 4 on the (FR) fan relay is the cooling blower speed and terminal number 6 on the (FR) is the heating blower
speed.
I. Refrigerant Piping
All air handlers have DX refrigerant cooling coils installed, liquid and suction piping should be sized in accordance with condensing unit manufacturer’s recommendations. An adapter (by others) may be required to make the transition between the line set and the coil connector. The evaporator coil has sweat copper connections. The suction line is a swaged solder cup connection. The liquid line connection is made to a tail piece portion of the TXV. Remove the nut on the inlet to the expansion valve and place it on the tail piece prior to brazing the liquid line. DO NOT connect the tail piece to the TXV until the liquid line has been brazed to the tail piece. Refrigerant lines should be soldered with silver solder or other high temperature brazing alloy. Dry nitrogen must ow through the refrigerant lines during the brazing operation to prevent oxidation.
J. Refrigerant Flow Control
As shipped, the TXV installed on the A-coil is for the nominal capacity of a 13 SEER matched with Heat Controller, Inc., condensing units. The TXV is for use on an R-410A system. For other refrigerants, contact the factory. TXV has a built-in check valve for reverse ow and is suitable for heat pump operation. All are externally equalized with non-adjustable superheat and have 15% bleed. Hard start capability for outdoor units is not normally required when a 15% bleed valve is used. The external equalizer line attached to the TXV has a female are nut and is attached to the suction line at the coil. Install the TXV bulb to the suction line using the bulb clamp furnished with the kit. The bulb should be installed on a horizontal run of the suction line if possible. On a line less than 7/8” OD, the bulb may be installed on top of the line. With 7/8” OD or over, the bulb should be installed in a position of about 4 or 8 o’clock. If the bulb installation is made on a vertical run, the bulb should be located at least 6 inches from any bend and on the tubing side opposite the plane of the bend. On vertical bulb installations, the bulbs should be positioned with the bulb capillary tube at the top. The bulb must be insulated using thermal insulation to protect it from the effects of the surrounding ambient
temperature.
H. Blower Motor
Units are equipped with a three-speed blower motor. Two factory­selected motor speed leads are connected to the fan relay (FR) to provide automatic speed change for heating and cooling airow volumes. The pre-selected motor speeds would normally not have to be changed in the eld. All HAH models contain a post purge timer (TDR) that delays the blower turning off at the end of the cooling cycle, this improves energy efciency.