LAG BOLTS OR
SCREWS (10 REQ’D)
(NOT PROVIDED)
HOOK RODS (2)
P/N 101567443730
WOOD SCREWS
(NOT PROVIDED)
SJ8 MOUNTING FRAME INSTRUCTIONS
WOOD FOR STEEL FRAME
(NOT PROVIDED)
CHILLER SHELF
P/N 401567343730
ELECTRICAL INLET
LOCATION ON CHILLER
FLOOR LINE
1. Cut a rectangular wall opening 18 3/4" (476mm) W x 23 3/8" (594mm) H and 4 1/2" (min.)
(1 14mm) above the floor line.
NOTE: Building construction must allow for adequate air flow on both sides and top of remote chiller
unit. Minimum of 4" (102mm) is required.
2. Install plumbing and electrical rough-ins. A junction box for a (3) wire, 10 amp branch circuit is
provided on the inside of the chiller. (S t andard 120 V olts, 60 Hz and single phase)
3. Remove frame and related hardware from packaging. Remove tape holding hook rods to shelf.
Install the frame squarely in wall opening with frames upright edges flush with the finished wall face.
Place shelf inside frame and line up the (2) holes on each. Insert loose ends of rods into holes on
sides of shelf panel. Using appropriately sized wood screws (not provided), fasten the shelf and
frame to bottom of wall opening. Secure the frame sides and top to the wall using appropriately
sized lag bolts or screws (not provided).
NOTE: Be sure that frame is squared in location. Do not use less than the required screw quantity .