Wire-in supply, emergency test (Standard emergency test, supply disconnect)
For KLCM how-to guides please see hager.co.uk or our YouTube channel
ZD0782ZD0782
Technical Characteristics
Number of channels4
Number of outputs per channel3 (hard wired LCM has 4 outputs on channel A)
Number of sensor inputs4 (KLCM-OS range)
Number of switch inputs4
Supply Voltage230V AC 50Hz
Maximum Number of Devices64 DALI, 16 per output.
Rated current10A (total load)
Rated current each connector10A
Complies withBS 5733:2010,
IP protectionIP20
Connection for commissioningBluetooth Smart (Bluetooth 4) (only available for apple iPad)
DimensionsHeightWidthDepthWeight
Hager hereby declares that this KLCM**** is in compliance with the essential requirements and other relevant provisions of Directive 1999/5/EC.
A copy of the original declaration of conformity may be obtained from technical@hager.co.uk.
youtube.com/user/hageruktv.
Search ‘Hager Klik LCM’ for our video quick start guide.
EN60669-2-5
F
pr
BS EN 61535:2009 - (Excluding clauses 10.1 and 10.3 due to Aluminium enclosure)
145mm440mm58mm1.9kg
Search KlikLink in the iPad app store.
Hager Ltd.
Hortonwood 50
Telford
Shropshire
TF1 7FT
Sales Service Centre: 01952 675 675
Mounting Options
Drop RodsDirect: e.g. nail gun or screw xing
Trunking
(Use slider along spring channel nuts.)
(not possible for hard-wire KLCM413W)
Supply Connection
Hard wired - KLCM413W & WIET
Neutral
Line
CPC
Do not use
Do not use
Emergency connection to be
used for KLCM413WIET only.
Pluggable - KLCM412P
Plug in supply & Klik 7 Lead Connection
16A
LOCK
E
D
16A
LOCKED
PRES
S
16A
LOCKED
16A
LOCKED
16A
LOCKED
E
S
A
E
L
RE
16A
PRESS
LOCKED
R
E
LE
A
S
E
R
E
L
EA
S
E
• Connecting the supply lead: plug
in and push down
• Disconnecting the supply lead:
press button and push up.
16A
LOCK
E
D
PRES
16A
S
Plug colour coding
White: Luminaire Lead
Red: Luminaire & Emergency
Black: Link Lead
LOCKED
16A
LOCKED
1
ZD0782 - Issue 3 10-17
Supply input connection
Klik LCM Control Connection
Klik LCM
Installation Instructions
RJ45 Link LeadRJ45 Link Lead
KLCM-OS 1 Head Sensor (inc 10m RJ11)
KLCM-3OS 3 Head Sensor (corridor sensor, inc 10m RJ11)
KLCM-5OS 5 Head Sensor (wide area sensor, inc 10m RJ11)
KLO*RJ45G RJ45 Switch Drop (plug-to-plug), Grey
KLO*RJ45R RJ45 Link lead (plug-to-plug), Red
KLORJ45CON RJ45 Splitter
*5, 10, 15, 20, 30, 40, 50
Hager strongly recommends the use of Hager
supplied RJ54 cables for all installations. All
Hager leads are tested prior to shipment. If
other manufacturers RJ45 cables are used
we recommend that each lead is tested with
a dedicated RJ45 tester prior to installation.
Should Hager be called to site to support the
installation and a fault is found with the RJ45 cables, then a
charge for site support will be incurred.
Partition switching
For partition switching please use switch input 1 only.
x4 Max
x4 Max
Sollysta Wiring Accessories for use with Klik
WMGS13R 2 way & centre off retractive switch module, on/off, dim up/down
WMGS12 20A, 2 way, single pole switch
WMGKS 20A, double pole keyswitch for emergency override
WMGP*(1, 2, 3, 4, 6, 8) White moulded, grid switch cover plates
WMGP*(1, 2, 3, 4, 6, 8)G Grey moulded (Part M), grid switch cover plates
WMGF*(1, 2 & 34) Grid frames, 1, 2 and 3/4 gang
Decorative nishes also available for grid products, see Hager catalogue.
Scene control plates, brushed steel, are available on request, 4 scenes, on/dim up, off/dim down.
RJ45 Link Lead
Standard Switch Drop
Switch inputs - 1 to 4 on KLCMEmergency test, override, corridor hold, in & out.
COM
Brown/WhiteOn
Blue/WhiteOff
Brown0V (Common)
WMGS13R - 20A, 2 way, centre off retractive grid switch - white
L1 L2
LOOP
N
(KLCM413WIET, emergency test not applicable)
Orange/White
Orange
Green/White
Blue
Blue/White
Green
Brown
Brown/White
Override - All Outputs On
Override - All Outputs Off
Corridor Hold Line
Emergency Test (Timer 1)
Emergency Test (Timer 2)
Emergency Test (Timer 3)
Common
Not Used.
Default operation on power up (pre-commissioning)
The default settings on power up of the LCM is Presence with a 20 minute time out. Therefore any lights connected will not come on (to prevent a building being
lit 24/7).
To enable any light plugged in to the LCM to come on prior to nal commissioning (i.e. during other building works) we recommend temporarily connecting a
KLCM-OS. This will enable all lights to come on for 20 minutes when the sensor is triggered, this also reduces the requirement to power off LCM at night and
could also aid building security during construction or renovation works.
For the latest range information or assistance call our sales service centre on 01952 675 675 or technical service centre on 01952 675 689 or hager.co.uk
ZD0782ZD0782
2
ZD0782 - Issue 3 10-17
Klik LCM
Sensor Control Conguration
GB
Hortonwood 50
KLCM Sensing Options
Sales Service Centre: 01952 675 675
Technical Service Centre: 01952 675 689
ZD0782ZD0782
Sensor Control (Standard, Corridor, Large Area)
Using one of the KLCM range of sensors allows maximum energy savings to be achieved whilst retaining the required amount of lighting when occupation is detected.
Connect to the LCM using the RJ11 lead supplied
KLCM-OS
Single head SELV Sensor, these can be used for all applications and come with a 10m RJ11 Lead. If used for a corridor application ensure sensors are spaced equally
and cover all doors on to the corridor.
KLCM-3OS
3 Head SELV Sensors for use in corridors or narrow rooms, sensor heads should be orientated along the corridor.
KLCM-5OS
5 Head SELV Sensors give more wide area coverage of approx 15m
Other Hager Sensors are available for both special applications or for part of a standard Klik or other lighting control installation. Please see the latest catalogue on
www.hager.co.uk
To congure in the App, Select “Channel” then “Absence/presence” and “Input Mapping” to allocate to a Channel.
2
.
Hager Ltd.
Telford
Shropshire
TF1 7FT
KLCM-OSKLCM-3OS
5m
15m
5m
KLCM-5OS
7.5m
7.5m
7.5m
7.5m
Daylight Dimming including Sensor Offset
This conguration will provide a constant regulated light level which is monitored by the digital lux sensor integrated within the KLCM-OS range of sensors.
The sensor should be positioned within the area to be controlled mid-way between lights for best performance. Connect into a sensor input using the RJ11 lead
supplied.
This technique can also be used to regulate lights when natural light does not exist to allow for over lighting when new and under lighting as lamps age. This can be of
particular use where LED lights are installed that may be prone to light output degradation.
To congure in the App, Select “Input Mapping” to allocate the sensor followed by “Sync”. A sensor can be mapped to multiple outputs and also to different
levels.
Do not activate “Daylight Dimming” during this process. Once desired level is achieved, switch on “Daylight Dimming” and “Sync”.
Absence & Presence
The most common scenarios we see our customers use are based on Presence Detection (People entering an area and moving around switches lights on) or Absence
Detection (Manual switch on and then switches off when no movement detected). Connecting switches and occupancy sensors to the LCM will be the same be it is
absence or presence. (Please see schematic on page 2).
To congure in the App, Select the required channel i.e. channel A and select the PIR function as required, here you can also set the required time-out and
staged time-out to dim level.
Input Mapping is used to associate the required Sensors and Switches to the outputs.
3
ZD0782 - Issue 3 10-17
Supply input connection
Klik LCM
Sensor Control Conguration
GB
Hager RJ45 Pin Out
1. White Orange
2. Orange
3. White Green
4. Blue
1 2 3 4 5 6 7 8
5. White Blue
6. Green
7. White Brown
8. Brown
KLCM Switching Options
Partition Switching
Partition Switch functionality provides the facility to accommodate a removable
partition switch and remap the light switches accordingly. This is achieved using
Proles 1 & 2.
Wire the partition switch as below and plug in to Switch Input 1 ONLY. When
switch is open, Prole 1 is active, switch closed, Prole 2 Active.
To congure in the app, select ‘global settings’ and then ‘Partition Switch
Enable’
Scene Setting
Scene setting allows for up to four scenes which can utilise all four outputs.
Scenes are created in the Kliklink App. Standard volt free connections are
available at the switch inputs allowing any suitable volt free switch to be used.
All four of the switch inputs can be used for Scene switch inputs. They are all
connected in Parallel internally. An On/Off switch will be required to switch off
in this instance as time out function will be inoperative. Please see the Sollysta
Wiring Accessory Range, White, Decorative and Part M available for use with Klik.
A dedicated scene plate is also available, please call for further information.
To congure the app, select ‘Scene Setting’.
Hortonwood 50
Sales Service Centre: 01952 675 675
Technical Service Centre: 01952 675 689
Brown/WhiteOn
L1 L2
Brown0V (Common)
WMGS12 - 20A, 2 way grid switch - white
Orange/WhiteScene 1
L1 L2
OrangeScene 2
Green/WhiteScene 3
L1 L2
BlueScene 4
Brown/WhiteOn/Dim Up
L1 L2
Blue/WhiteOff/Dim Down
Brown0V (Common)
Green12V (Not Used, must not be connected.)
Hager Ltd.
Telford
Shropshire
TF1 7FT
COM
LOOP
N
COM
LOOP
N
COM
LOOP
N
COM
LOOP
N
WMGS13R - 20A, 2 way, centre off, retractive grid switch - white
Classroom Control
Classrooms tend to have specic requirements where lights are controlled by
absence detection and also daylight dimming along window rows. Override
switches are often used for whiteboard and screens.
The Absence Switch and Board/Screen switches are wired the same using
separate switch inputs. The switches have to be wired as shown above and
Brown/WhiteOn
Blue/WhiteOff
Brown0V (Common)
connected to the Switch inputs congured in the Kliklink App. Switches must be
two way retractive.
WMGS13R - 20A, 2 way, centre off retractive grid switch - white
To congure in the App, Select “Input Mapping” and then select the switch
input used (1-4) on the channel required (A-D), then “Sync”
KLO*RJ45G RJ45 Switch Drop (plug-to-plug), Grey
KLO*RJ45R RJ45 Link lead (plug-to-plug), Red
KLORJ45CON RJ45 Splitter
*5, 10, 15, 20, 30, 40, 50
Hager strongly recommends the use of Hager supplied RJ54 cables for all installations. All Hager leads are tested prior to shipment. If other manufacturers
RJ45 cables are used we recommend that each lead is tested with a dedicated RJ45 tester prior to installation. Should Hager be called to site to support the
installation and a fault is found with the RJ45 cables, then a charge for site support will be incurred.
COM
L1 L2
LOOP
Hager Pre-Installed Scenarios - KlikLink for iPad
The above are a selection of scenarios that typical of those used by our customers. To make things even easier we have already saved a number of scenarios in the
App. These may be perfect for your installation or act as a starting point that you can modify to suit and then save and call your own.
N
ZD0782ZD0782
4
ZD0782 - Issue 3 10-17