Water Coils
• Chilled Water
• Hot Water
Steam Coils
• Standard Steam
• Steam Distribution (Non-Freeze)
Refrigerant Coils
• Condenser Coils
• DX Coils (Evaporator)
• Heat Reclaim
Maintenance
P.O. Box 410
Schofield, WI 54476
Phone: 715.359.6171
www.greenheck.com
Installation, Operation & Maintenance Manual
Water Coil Installation Recommendations
1. Piping should be in accordance with accepted industry standards. Always use a back up wrench on
the coil connections when attaching the piping to the coil if pipe thread connections are utilized.
2. When drainable coils are desired, tubes should be installed in a horizontal position. Use a spirit level.
If the tubes cannot be installed level, special drain headers are available on request.
3. Connect the water supply to the bottom connection on the air leaving side and the water return to the
top connection on the air entering side.
4. When four connections are provided the extra bottom connection can be used for an auxiliary manual
drain connection, and the extra top connection can be used for an automatic air vent or the extra
connections can be capped. Connecting the supply and/or return in any other manner will result in
very poor performance.
5. Water coils are not normally recommended for use with entering air temperatures below 40°F. Glycol
solutions or brines are the only freeze-safe media for operation of water coils for low entering air
conditions.
6. When fresh and return air are to be heated or cooled by a water coil, care should be used in the
design of the ductwork to insure thorough mixing before the air enters the coil. The return ai r should
always enter the bottom of the duct. Fresh air should enter the top of the duct. The greater the
distance between the points of mixing and entrance to the coil, the better the application.
7. Two position control valves, modulating valves, three way valves or a combination of these controls
can accomplish control of water coils. Follow the recommendations of the control manufacturer
regarding types, sizing and locations. Face and bypass dampers may also be used, but do not close
off tightly. Air leakage in cooling applications has no appreciable effect. In heating applications,
however, the air temperature may rise several degrees and should be considered in system design.
Low leakage dampers may be required.
8. Pipe sizes for the system must be selected on the basis of the head [pressure] available from the
circulating pump. It is recommended that the velocity should not generally exceed 8 feet per second
and that the friction loss should be approximately 3 feet per 100 feet of pipe.
9. When cooling coils are banked two or three high, an intermediate drain pan with plastic drain tubes
extending into the main drain pan should be installed on the air leaving side of each coil. On high
latent installations, the condensate draining from top coils may load the lower coils with condensate,
resulting in reduced air flow and performance or condensate being blown downstream into the
ductwork. All individually installed water cooling coils and the bottom of all cooling coil banks should
be mounted in drain pans extending at least ten inches from the leaving air edge of the coil. A drain
line trap must be installed to allow condensate to drain freely. The drain line trap depth must be twice
the negative static pressure of the operating system for the unit to drain correctly. Incorrect trapping
can cause the drain pan to overflow.
Note: Vent and Drain connections are provided on Greenheck Coils water coils unless otherwise
specified. This allows the coils to be drained. Keep in mind that when draining the coils, all water may
not drain from the coil. In order to completely drain the coil to prevent the possibility of freezing during
cold ambient temperatures, air or nitrogen pressure must be utilized to blow any remaining water from
the coil.
Page 2 of 7 IOM, Rev. 2, November 2007
Copyright © Greenheck Fan Corporation
Steam Coil Installation Recommendations
A. General
1. Provide separate supports and hangers for the coil and for the piping. Always use a back up wrench
on coil connections when attaching piping to the coil. Coils not designed with pitched casing or fin
pack must be pitched ¼" per foot towards the return connection at installation.
2. Be certain that adequate piping flexibility is provided. Stresses resulting from expansion of closely
coupled piping and coil arrangement can cause serious damage.
3. Do not reduce pipe size at the coil return connection. Carry the return connection size throu gh the dirt
pocket, making the reduction at the branch leading to the trap.
4. Vacuum breakers and air vents must be installed on all applications to prevent ret aining condensate
or air in the coil. Generally the vacuum breaker is to be connected between the coil inlet and the trap.
For a system with a flooded return main, the vacuum breaker should be open to the atmosphere and
the trap design should allow venting of large quantities of air.
5. Do not drip steam mains through coils.
6. Insure steam pressure and condensate line pressure differential is sufficient to allow efficient
condensate removal from the steam coil, especially when using modulating steam control valves to
control the leaving air temperature of the coil.
7. Do not attempt to lift condensate without the assistance of a condensate pump. The pressure
required to lift condensate must also be considered for sufficient pressure differential. Check valves
are also required to prevent reverse flow of condensate back into the coil.
8. Entering air temperatures should not be below 40° F to insure freezing doesn't occur.
B. Traps
1. Size traps in accordance with the manufacturer’s recommendations. Be certain that the required
pressure differential will always be available. Do not undersize.
2. Float and thermostatic traps are recommended for high or low-pressure steam systems, but bucket
traps may be used. Float and thermostatic traps should be used when air venting is necessary.
Bucket traps are recommended for use with on-off control only. It is recommended that traps be
located at least 12 inches below the coil return connection. When traps without air venting capabilities
are used, air vents are required in the system.
3. Multiple coil installations:
a. Each coil or group of coils that is individually controlled must be individually trapped.
b. Coils in series; separate traps are required for each coil, or bank of coils, in series.
c. Coils in parallel; a single trap may be used but an individual trap for each coil is preferred.
Page 3 of 7 IOM, Rev. 2, November 2007
Copyright © Greenheck Fan Corporation