Grasso RC6, RCU6 Installation And Maintenance Manual

RC(U)6 Installation and Maintenance Manual
00.89.238 v004.00.02.en
Refrigeration Division
Grasso
All rights reserved. No part of this publication may be copied or published by means of printing, photocopying, microfilm or otherwise without prior written consent of Grasso. This restriction also applies to the corresponding drawings and diagrams.
For extra information as to adjustments, maintenance and repair, contact the Technical Departmentof your supplier.
This publication has been written with great care. However, Grasso cannot be held responsible, neither for any errors occurring in this publication nor for their consequences.
Installation and Maintenance Manual RC(U)6 v001.99.01.en
1. Document Information
This ’lnstallation and Maintenance manual’ will
be supplied together with the compressor.
This manual is suitable for both end-user and
contractor and will provide information on how to transport, install, start-up and maintain the compressor (package). It also contains a number of "Engineering Data Sheets" and the current "Parts List".
2. Additional Documentation
In addition to the above the following is available for this series compressor:
Engineering Data Sheets Book;
This book contains all engineering data for this series compressor and the corresponding recommended accessories. It is meant to be a guide to the selection of these components.
Parts book;
This book contains all current parts of the compressor and accessories together with the design changes applicable to earlier supplied components ("History").
Mounting and Installation Instructions for
Accessories;
If compressor is supplied with accessories, all the relevant mounting and installation instructions and spare parts information for those accessories will be supplied together with the compressor.
Refrigeration Division
Grasso
PREFACE
v001.99.01.en Installation and Maintenance Manual RC(U)6 V
Refrigeration Division
Grasso
PREFACE
VI Installation and Maintenance Manual RC(U)6 v001.99.01.en
This manual must be carefully read and understood prior to installing the compressor (package)
Installer-oriented information The compressor (package) is filled with nitrogen to prevent penetration of moisture. Therefore, keep the compressor closed until the compressor (package) is being installed. The compressor is not filled with oil. How to charge the compressor package with oil is discussed in Section A, §A2.3, "Initial oil charge". After the succesful initial run of the compressor (package) the warranty chart must be filled in and returned to Grasso. A warranty chart is attached to each compressor.
Safety
This manual is written with great care, but the contractor/installer is held responsible to examine this information and to care of possible additional and/ or deviated safety measures.
Safety instructions
It is the task of the contractor/installer to inform and explain his client about the operation of the compressor (Package). Do respect all federal, state or local safety regulations/legislations during installing, connecting and operating this compressor (package).
Typographic signs:
Indicates a caution, note or procedure to which you should pay special attention. Read it carefully!
Values Between [ ]
Values between [ ] are read-outs of Grasso’s electronic control device Monitron.
Refrigeration Division
Grasso
GENERAL SAFETY INSTRUCTIONS
v001.99.01.en Installation and Maintenance Manual RC(U)6 VII
Refrigeration Division
Grasso
GENERAL SAFETY INSTRUCTIONS
VIII Installation and Maintenance Manual RC(U)6 v001.99.01.en
General information
Refrigeration Division
Grasso
Subject Feature refer to chapter:
Oil viscosity
10 cSt during operation at location of bearings
Direction of rotation of compressor drive shaft Counterclockwise when facing shaft end A2.6
Operating limits and switch settings
(for values between [ ] brackets refer to the Instruction Manual of the Monitron)
Timers Time interval refer to chapter:
Switching frequency max. 6 starts per hour A2.10.1
Time interval between stopping and re-starting min. 2 minutes A2.10.2
Time interval between starting and re-starting min. 10 minutes A2.10.2
Time interval between unloading and loading min. 3 minutes B1.2
Oil system limits Value
Oil level 25 - 75% crankcase sight glass B4
Min. oil temperature
warmer than surroundings and 20 °C (68 °F) for NH
3 and 30 °C (86 °F) for halocarbons
A2.8
Max. oil temperature [max. Toil] see oil selection table in the appendix section B1.2
Lubricating oil pressure difference [min dOil] between 1.5 and 2.5 bar
Setting approx. 1.8 bar
A2.5.2
Temperature and pressure limits Value
Max. discharge temperature [max Tdis] 155 °C (311 °F) B1.2
Pdischarge - Psuction
< 24.0 bar
Superheat [dTo]
5 K
Cooling water inlet temperature of cylinder head cooling system
Tcond + 10 K
Pressure safety limits A2.5.2
GENERAL INFORMATION AND SURVEY
OF SETTINGS AND LIMITS
v001.99.01.en Installation and Maintenance Manual RC(U)6 IX
Refrigeration Division
Grasso
GENERAL INFORMATION AND SURVEY
OF SETTINGS AND LIMITS
X Installation and Maintenance Manual RC(U)6 v001.99.01.en
SUBJECT Page no.:
PREFACE ............................................................................................................................... V
GENERAL SAFETY INSTRUCTIONS ................................................................................................. VII
GENERAL INFORMATION AND SURVEY OF SETTINGS AND LIMITS .......................................... IX
SECTION A: INSTALLATION AND PREPARATIONS FOR USE ....................................................... A1.1
A1 INSTALLATION .......................................................................................................................... A1.1
A1.1 Moving instructions and storage ................................................................................. A1.1
A1.1.1 Hoisting and moving instructions ...................................................................... A1.1
A1.1.2 Storage ............................................................................................................... A1.2
A1.2 Required free space ....................................................................................................... A1.2
A1.3 Foundation requirements .............................................................................................. A1.2
A1.3.1 Concrete structure ............................................................................................. A1.3
A1.3.2 Anchoring ........................................................................................................... A1.4
A1.4 Concrete block mounting instructions .......................................................................... A1.4
A1.4.1 Mounting bare compressor on a concrete block ............................................. A1.4
A1.4.2 Mounting the base frame on a concrete block ................................................ A1.4
A1.5 Connecting to refrigerating system pipework ............................................................. A1.5
A1.6 Connecting the power supply ....................................................................................... A1.6
A1.7 Earthing connections ..................................................................................................... A1.6
A1.8 Separately delivered components .................................................................................. A1.6
A2 PREPARATIONS FOR USE ......................................................................................................... A2.1
A2.1 Leak test of compressor and system ............................................................................. A2.1
A2.2 Evacuation/drying the refrigerating system ................................................................. A2.1
A2.3 Initial oil charge .............................................................................................................. A2.1
A2.4 Initial refrigerant charge ................................................................................................ A2.2
A2.5 Adjustment of instruments and safety devices ............................................................ A2.2
A2.5.1 Monitron ............................................................................................................. A2.2
A2.5.2 Pressure safety switches ..................................................................................... A2.2
A2.5.3 Re-adjustment of oil pressure regulator ........................................................... A2.3
A2.6 Checking direction of rotation of motor shaft ............................................................. A2.4
A2.7 Installing the (drive) guards .......................................................................................... A2.4
A2.8 Initial oil warm-up .......................................................................................................... A2.4
A2.9 Initial start-up ................................................................................................................. A2.4
A2.9.1 Limitations part load operation and start-up .................................................... A2.4
A2.9.2 Pre-start check list .............................................................................................. A2.4
A2.10 Starting and stopping procedures ................................................................................ A2.4
A2.10.1 Starting for the very first time ......................................................................... A2.4
A2.10.2 Restart .............................................................................................................. A2.5
A2.10.3 Starting after a seasonal (1 till 6 months) standstill or maintenance operations A2.5
A2.10.4 Starting after a long standstill periode of time (more than 6 months) ........ A2.5
A2.10.5 Stopping the compressor ................................................................................. A2.5
SECTION B: INSPECTION, MAINTENANCE AND TROUBLE SHOOTING: .Table of contents ....... B.I
SECTION C: APPENDIX <Instructions & collection of data sheets>: .......Table of contents ...... C.I
SECTION D: STANDARD ILLUSTRATED SPARE PARTS LIST: ....................Table of contents ....... D.I
For oil selection table refer to "Engineering Data"
Refrigeration Division
Grasso
TABLE OF CONTENTS
v001.99.01.en Installation and Maintenance Manual RC(U)6 III
Refrigeration Division
Grasso
TABLE OF CONTENTS
IV Installation and Maintenance Manual RC(U)6 v001.99.01.en
The compressor is not charged with oil, therefore, DO NOT start the compressor before it has been installed and prepared according to the sections A1 and A2.
A1 INSTALLATION
This section contains instructions for the proper installation of a Grasso compressor (package). Before the compressor (package) is ready for the initial start up, the installation instructions in the following paragraphs must be followed:
1. The Compressor (Package) should be levelled and
securely anchored to the foundation (see §A1.4).
2. All piping should be completed as in §A1.5.
3. The system and the compressor are to be pressure
tested for leaks (see §A2.1).
4. The system should be evacuated to remove air and
moisture (see §A2.2).
5. The electric wiring should be completed as per
wiring diagrams. Do not energize the main power control cabinet until oil is added and the direction of rotation has been checked.
6. The compressor is to be filled with the correct type
and amount of lubricating oil (see §A2.3).
7. The drive coupling or V-belt drive system should be
installed.
8. The system should be charged with the correct
amount of refrigerant.
9. The oil should be warmed up above minimum start
up oil temperature (see "Engineering Data").
10. The control cabinet or Monitron CR should be
energized to check the package control (see §A2.5).
A1.1 Moving instructions and storage
For loose component or compressor package weights, refer either to the relevant component type plate or package lay-out or to the suppliers document. For bare compressor weights, see "Engineering Data".
Every precaution must be taken while moving the package to its final location. Pushing, pulling or climbing on any package component or piping, can easily create damage.
A1.1.1 Hoisting and moving instructions
Packaged base frame:
The only places that can be used for safe hoisting of the package are the four hoisting eyes on the steel base frame as shown in the above figure. Prior to hoisting a compressor package with a V-belt drive arrangement, the factory mounted drive guard has to be removed. Attach spreader bars to the slings so as to prevent damage to piping and components.
DO NOT use the component hoisting eyes to move the package! These hoisting eyes are intended for lifting loose components only and not for the entire package!
Fig. A1.1 Hoisting a compressor-package
Refrigeration Division
Grasso
A: INSTALLATION AND PREPARATION FOR USE
v001.99.01.en Installation and Maintenance Manual RC(U)6 A1.1
Bare compressor or loose components: Determine the dead weight of the par­ticular component (see "Engineering Data"), prior to moving a bare compres­sor or loose component. Use the hoist­ing eyes only to lift so, DO NOT sling from other compressor parts (see figure A1.1A).
Moving by fork-lift truck
The bare compressor or package can be transported with a fork-lift truck with the forks spread as much as possible between the skids. To simplify moving, the 2 wooden transport beams must still be mounted underneath the base frame and stored in this way, untill the package is positioned above its approximate location.
A1.1.2 Storage
The compressor (package) is filled with dry nitrogen. Keep the system closed until the package is installed. If the compressor (package) is stored, it should be kept at all times in a dry location to prevent corrosion damage. If the compressor (package) is to be stored for a prolonged period of time, it should be checked weekly to ensure that the holding charge of dry nitrogen remains above atmospheric pressure.
A1.2 Required free space
For easy operating, servicing and maintenance access, the compressor (package) should be at least installed with sufficient free space around it.
A1.3 Foundation requirements
This paragraph covers measures to be taken for a compressor (package) on a concrete floor.
Two foundation arrangements are described:
Compressor package with steel base frame
mounted on a concrete block.
Bare compressor direct mounted on a concrete
block via grouted machined anchors (see "Engineering Data"). The mounting surfaces of these machined anchors must be level without any deviation and projecting at least 10 mm above the concrete base.
COMPRESSOR AND COMPRESSOR PACKAGE TO BE MOUNTED ON A CONCRETE BLOCK On request, Grasso can calculate the exact dimensions of the concrete block, based on the compressor size and operating conditions.
Fig. A1.1A Hoisting angle bare shaft compressor
Refrigeration Division
Grasso
A: INSTALLATION AND PREPARATION FOR USE
A1.2 Installation and Maintenance Manual RC(U)6 v001.99.01.en
A1.3.1 Concrete structure
The concrete block for compressor and motor or compressor package should have a profile as illustrated in fig. A1.2 and made according to the following recommendations:
The concrete block should be set on firm
footings or on a floor capable of carrying the weight of the concrete block and capable to absorb the free forces and gas forces of the compressor during operation. The ground under the concrete block should be horizontal and flat (refer to fig. A1.2).
The top surface of the block should be level and
even.
There should be sufficient free space around the
block to install corkboard (or similar).
The block should be provided with anchor bolt
recesses or holes (fig A1.3.) according to the anchor bolt spacing as per package lay out drawing.
It is recommended to consult a concrete specialist/ constructor for the following items:
The compounding of the concrete with/without
reinforcement.
The exact grouting depth (dependent on the
soil conditions).
Installing foundation onto an existing floor, with
sealing corkboard or vibration isolators.
Fig. A1.2
Fig. A1.3
1 Corkboard
2 Concrete base
3 Basement floor
A Chemical anchor B Grouted anchor, grounded to reinforcing steel
Refrigeration Division
Grasso
A: INSTALLATION AND PREPARATION FOR USE
v001.99.01.en Installation and Maintenance Manual RC(U)6 A1.3
A1.3.2 Anchoring
After the concrete block has cured the anchors should be installed as shown in figs. A1.3 and/or A1.4 and in case of a package in accordance with the package lay out drawing. Templates should be made to locate the anchor bolts or chemical anchors to match the holes in the bottom flange of the base frame.
Grout the mortar as given by the supplier instructions. Install chemical anchors as illustrated in figure A1.4 and according the instructions of the anchor supplier.
A1.4 Concrete block mounting instructions
A1.4.1 Mounting bare compressor on a concrete
block
If no base frame is applied the compressor and motor should be installed as discussed in §A1.3 and "Engineering Data".
A1.4.2 Mounting the base frame on a concrete
block
General
After the space between base frame and concrete base is filled-up with a filling grout, the package base frame must be secured tightly to the foundation block or floor (refer to fig. A1.3).
Fig. A1.4 Anchoring details
A Drilled chemical anchor (thread size M16) B Grouted anchor recesses (thread size M16)
1 Installed chemical anchor before placing the base frame 2 Installing chemical anchor after placing the base frame (base
frame cannot removed easily) 3 Drilling angle
Refrigeration Division
Grasso
A: INSTALLATION AND PREPARATION FOR USE
A1.4 Installation and Maintenance Manual RC(U)6 v001.99.01.en
Levelling the base frame
After the anchor filling mortar is completely cured the frame should be levelled with a space between block and lower frame flange of 3 - 5 mm. This space largely depends on the sort of grout or mortar used. Determine this space as given in the instructions of the grout or mortar supplier. This space is necessary for levelling using the base frame adjusting bolts with metal washers (supplied separately). The base frame should be levelled on each frame side. Adjust the frame on each adjusting place until all frame sides are horizontal.
Finishing with a self-levelling grout (See figure A1.5)
After levelling is completed the adjusting bolt ends must be greased to avoid bonding to the self-levelling grout. The space between concrete block and frame must be completely filled with the self-levelling grout to ensure that the complete bottom surface of the base frame will
be supported. Therefore, it is not allowed to use shims between concrete base and base frame.
Grouting must be carried out in accordance with the instructions provided by the grouting supplier. After complete de-aeration of the grouted layer, secure the base frame by tightening the anchor bolt nuts and remove all adjusting bolts. At this stage the drive system can be installed. These (accessories) installation instructions can be found in the order manual.
A1.5 Connecting to refrigerating system pipe-
work
After the compressor (package) has been levelled and secured to the foundation, the system piping may be connected. The suction line(s) and discharge line(s) should be installed and supported such that there is no load exerted on the compressor. The size and location of the suction and discharge connections, can be found in the "Engineering Data" (bare compressor) and in case of a package, the package lay out drawing.
Fig. A1.5 Grouting details
1 Self-levelling grout 2 Adjusting bolt (4x) 3 Washer 4 Temporary barrier strip around and inside frame 5 Complete cured concrete block 6 Grout layer
Refrigeration Division
Grasso
A: INSTALLATION AND PREPARATION FOR USE
v001.99.01.en Installation and Maintenance Manual RC(U)6 A1.5
If an oil rectifier system is applied in the re­frigeration system, the oil return line must be connected to the oil return con­nection.
Never connect the oil rectifier return line to
the suction line or to the suction gas filter.
DO NOT ground through the compressor when arc welding
Suspension of system pipework To eliminate vibration transmission to the system
piping, the following is recommended:
Install all piping free of tension.
Secure the piping by clips or suspenders in two
directions.
Install (stop) valves, piping and accessories such,
that there is no load exerted on the compressor.
A1.6 Connecting the power supply
Before leaving the factory the compressor package is completely wired*. The connection to be made by the installer is between main power source and the Monitron CR (if ordered). Information about further electrical connections to be made (e.g. crankcase heater, drive motor starting equipment, thermal protection of drive motor, automatic start/ stop, motor current transducer and other external electrical devices) can be found in the order manual.
*
If the standard recommended Monitron CR is applied.
A1.7 Earthing connections
Grasso compressors and packages are equipped with litz-wires and earth connecting points.
To avoid leakage current flowing through the components, disconnect all litz-wires when arc­welding. After all installation functions are completed, reconnect the litz-wires and ground the package to earth.
A1.8 Separately delivered components
Mount the separately delivered set-components e.g. oil charge and drain valve, according to the instruction enclosed in each individual set.
Refrigeration Division
Grasso
A: INSTALLATION AND PREPARATION FOR USE
A1.6 Installation and Maintenance Manual RC(U)6 v001.99.01.en
A2 PREPARATIONS FOR USE
After the Compressor (Package) has been installed (excl. final connection of drive device), the following actions should be followed in the order given:
A2.1 Leak test of compressor and system
The compressor (package) has been pressure tested prior to leaving the factory. In case an additional leak test is required, this test is should be carried out with dry nitrogen under pressure up to a max. of 10 bar(a).
Do NOT add oil to the compressor prior to pressure testing.
A system leak test should be carried out over 24 hours to ensure that the system is tightly sealed. Record during the pressure test, the pressure, ambient temperature and outside temperature. During the initial 6 hours a pressure drop of 2% is permissable. With respect to temperature variations, no further pressure loss should be detected in the remaining 18 hours. If the test pressure has not decreased by more than 5% the system can be considered leak free.
A2.2 Evacuation/drying the refrigerating system
For evacuation of compressor only, refer to §B5. Procedure to evacuate and to dry a system: a) STATUS: System is filled with nitrogen (refer to
§A2.1) and no oil into the system (oil prevents any trapped moisture from boiling off).
b) Verify that all valves in that part of the system to be
evacuated are opened (refer also to the plant manual).
c) Connect vacuum pump to the evacuation/purging
valve(s) of the compressor (for location of these valves refer to the "Engineering Data" or to a connection as mentioned in the plant manual and evacuate the system to approx. 5 mm Hg (=6.6 mBar).
d) Break vacuum by charging dry nitrogen into the
system. e) Repeat step ’c’. f) Wait approx. 24 hours. g) If pressure has been increased (system still contains
moisture), repeat steps ’d’, ’e’ and ’f’, otherwise,
continue with the "Initial oil charge" procedure
§A2.3.
A2.3 Initial oil charge
Used or filtered oil should NEVER BE added to a compressor under any circumstance. Use only new oil to be selected from the oil table (see "Engineering Data").
a) STATUS: System is dried and still evacuated (refer to
§A2.2).
b) Close suction and discharge stop valves of
compressor and oil return line of oil separator
(if present). c) Fill the compressor crankcase with oil (for oil
quantity see table overleaf) via the oil charge/ drain
valve (for location of this valve refer to the
"Engineering Data"). d) Open evacuation/purging valve(s) of the
compressor (for location of these valves refer to the
"Engineering Data") to bring the compressor to
atmospheric pressure. e) Fill the following components with oil as given in
the table on the next page with/without pre-
lubrication valves (explained hereafter) :
- Shaft seal housing via the oil filling opening.
- Oil pump housing via the oil filling opening.
- Oil suction and discharge filter housings via the oil
filling openings.
Refrigeration Division
Grasso
A: INSTALLATION AND PREPARATIONS FOR USE
v001.99.01.en Installation and Maintenance Manual RC(U)6 A2.1
A2.4 Initial refrigerant charge
Refrigerant charging should be done in accordance to the plant manual by qualified refrigeration engineers.
Oil charging via the suction line of the compressor is not allowed.
A2.5 Adjustment of instruments and safety
devices
A2.5.1 Monitron
For adjustments see table overleaf.
A2.5.2 Pressure safety switches
Refer to the table overleaf. Setting procedures are described in the Safety Switch supplier instructions.
QUANTITY OF OIL TO BE FILLED (in dm3)
Compressor series RC6 Shaft seal housing Oil filters Oil pump Crankcase
RC46
± 0.5 ± 1.0 ± 0.5
11 RC66 12 RC86 13
Refrigeration Division
Grasso
A: INSTALLATION AND PREPARATIONS FOR USE
A2.2 Installation and Maintenance Manual RC(U)6 v001.99.01.en
A2.5.3 Re-adjustment of oil pressure regulator (re-
fer to fig. A2.1)
Re-adjustment procedure: a) Run the compressor for 15 minutes until the
crankcase oil is at its stable operating temperature [Toil].
b) Determine the oil pressure difference (difference
between the pressure gauges of the oil and suction or [dOil]).
c) After approx. 15 minutes of operatinf and an oil
temperature of 50 °C, the oil pressure difference should be approx. 2.0-2.5 bar. During these first minutes the pressure should be slightly higher.
d) Remove the cap nut (3) with alu ring (2), of the oil
pressure regulator if the pressure needs to be re-adjusted.
e) Turn the slotted pin (1) with a screwdriver clockwise
or counter clockwise for a higher or lower oil pressure respectively, until the required oil pressure differences has been achieved.
f) Replace the cap nut (3) with alu ring (2).
Settings of compulsory pressure safeties
Read-out Monitron
1
)
Description Min. value Max. value (pre)-Setting
Psuc Suction pressure 0.3 bar (4.4 psia) NH3 6.2 bar (90 Psia)
R22 6.8 bar (99 Psia) R134a 6.2 bar (90 Psia) R404A 6.0 bar (87 Psia) R507 5.8 bar (84 Psia)
5 °C (9 °F) below design evaporating temperature
Pdis Discharge pressure > Psuc 26.0 bar (377 Psia) 5 °C (9 °F) above design
condensing temperature Pdis-Psuc > 0 bar 24.0 bar (348 Psia) < 24.0 bar (348 Psia) dPoil Lubrication oil
pressure difference
1.5 bar (22 Psia) 2.5 bar (36 Psia) The oil pressure regulator is adjusted at the works, but it may occur that this setting should be corrected during the initial run (see A2.5.3)
1
)In case of Monitron the values are measured via pressure transducers, otherwise protection via switches is compulsory.
Fig. A2.1 Oil pressure regulator
1 slotted pin 2 alu ring 3 cap nut 4 return from oil separator
or oil rectifier 5 oil pressure regulator
Refrigeration Division
Grasso
A: INSTALLATION AND PREPARATIONS FOR USE
v001.99.01.en Installation and Maintenance Manual RC(U)6 A2.3
A2.6 Checking direction of rotation of motor shaft
Prior to installing the intermediate coupling element or V-belts, the direction of rotation of the motor shaft must be checked either by bumping the electrical drive motor or by measuring the rotation of the field (direction of rotation normally counter clockwise when facing compressor shaft end).
A2.7 Installing the (drive) guards (if present)
Only after the compressor is ready for the initial startup! Refer to the drive guard installing procedures included in the order documentation.
A2.8 Initial oil warm up
Prior to the initial start-up (refer to §A2.9), the crankcase heater (if present) must be energized. For the min. oil temperature (min. [Toil]) refer to page VII.
A2.9 Initial start-up
A2.9.1 Limitations of part load operation and
start-up
The capacity control serves to adapt the compressor capacity at any moment as closely as possible to the refrigerating capacity. In order to adapt the capacity, a number of cylinders can be put in or out of action either individually or collectively.
Due to start-up limitations and to limitations of part load operation it may be that not all available part load steps are allowed under certain conditions. Use of incorrect control steps can damage compressor and/or components.
In the case of a Monitron Controller, all these limitations will be checked automatically. For a detailed description about these start-up and part load limitations refer to the "Engineering Data".
A2.9.2 Pre-start check list
The following Paragraph covers only the initial start of the compressor and not the complete refrigeration plant.
Be sure that all necessary system valves are open and that the refrigeration system is ready for start up. Use the following check to guarantee that no items of importance regarding the compressor (package) have been overlooked.
a) System is charged with refrigerant. b) Monitron (if present) is properly installed (refer to
the Monitron Instruction Manual). c) Settings of safety limit switches are adjusted properly. d) Direction of rotation of compressor crankshaft is
correct. e) Oil level established in sight glass. f) Stop valves to the pressure gauges are open (if
present). g) Suction stop valve is closed (in case the evaporating
temperature is much higher than the design
evaporating temperature) and the discharge stop
valve is open. h) Stop valve in the oil return line of the oil separator
(if present) is closed.
When all items a) through h) are verified, the compressor (package) is ready for the start-up.
A2.10 Starting and stopping procedures
When starting the compressor a distinction should be made between:
A2.10.1 Starting for the very first time (between
brackets [ ] are Monitron units)
a) Notice §A2.9.2 "Pre-start check list", consult also the
plant manual and verify the following items:
- Check the oil temperature [Toil] (refer to the
"Engineering Data").
- Check crankcase oil level (refer to §B4.1).
b) Start the compressor and check whether the oil
pressure [Poil] increases.
Maximum 6 starts per hour and at least 2 minutes between stopping and starting and at least 10 minutes between starting and re-starting
Refrigeration Division
Grasso
A: INSTALLATION AND PREPARATIONS FOR USE
A2.4 Installation and Maintenance Manual RC(U)6 v001.99.01.en
c) Slowly open suction stop valve and watch suction
pressure [Psuc], which may not exceed the max. value as given for each refrigerant in §A2.5.2.
Refrigerant liquid hammer, will damage the compressor; Superheat is always necessary! [dTo]5 K
d) More cylinders will be energized.
Watch maximum allowable motor current [Imot] (refer to motor type plate).
e) Adjust pressure gauge stop valves, in order to avoid
vibration of the pointers (if present).
f) Open the stop valve in the oil return line from the
oil separator (if present).
Retighten the coupling bolts or check or correct the tension of the V-belts and retighten the foundation bolts (with due respect to the torque settings given by the supplier of the fasteners!) after 50 hours of operation.
A2.10.2 Restart (not within 2 minutes after a
stop, respectively starting after a short standstill period of time [les than 1 month]). If Monitron Controlled, refer to the Monitron Instruction manual)
Proceed to the starting procedure of §A2.10.1
point a), b) and d).
A2.10.3 Starting after a seasonal standstill (1 till
6 months) or maintenance operations
Check settings of control and safety equipment
(refer to §A2.5).
Proceed to the complete starting procedure of
§A2.10.1, items a) through f).
A2.10.4 Starting after a long standstill period of
time (more than 6 months)
Consult your supplier. Monitron "standby" status (ready to operate during this long period of time) is not allowed! It is recommended to proceed with the "Initial start-up" procedure of
§A2.10.1.
A2.10.5 Stopping the compressor
The compressor can be stopped at any moment, however, consult the supplier if further actions are required.
Refrigeration Division
Grasso
A: INSTALLATION AND PREPARATIONS FOR USE
v001.99.01.en Installation and Maintenance Manual RC(U)6 A2.5
Refrigeration Division
Grasso
A: INSTALLATION AND PREPARATIONS FOR USE
A2.6 Installation and Maintenance Manual RC(U)6 v001.99.01.en
SUBJECT Page no.:
SECTION B: INSPECTION, MAINTENANCE AND TROUBLE SHOOTING ....................................... B1.1
B1 INSPECTION ................................................................................................................................ B1.1
B1.1 Periodical inspection ......................................................................................................... B1.1
B1.2 Survey of periodical inspections ....................................................................................... B1.1
B2 MAINTENANCE .......................................................................................................................... B1.2
B2.1 Post start-up maintenance ............................................................................................... B1.2
B2.2 First maintenance ............................................................................................................. B1.3
B3 STEPS FOR LONGER SHUT-DOWN PERIODS (more than 6 months) ....................................... B1.4
B4 LUBRICATION DATA .................................................................................................................. B1.4
B4.1 Topping up oil with compressor operating .................................................................... B1.4
B5 EVACUATION OF THE COMPRESSOR ....................................................................................... B1.5
B6 DRAINING AND CHANGE OF OIL ............................................................................................. B1.5
B7 CLEANING OF OIL FILTERS ........................................................................................................ B1.5
B8 CLEANING OF SUCTION GAS FILTER(S) .................................................................................... B1.6
B9 DISMANTLING, INSPECTION AND RE-ASSEMBLY OF SUCTION AND DISCHARGE VALVES .. B1.6
B10 COMPRESSOR PURGING ............................................................................................................ B1.7
B11 TROUBLE SHOOTING TABLE .....................................................................................................B1.7
Refrigeration Division
Grasso
TABLE OF CONTENTS
v001.99.01.en Installation and Maintenance Manual RC(U)6 B.I
Refrigeration Division
Grasso
TABLE OF CONTENTS
B.II Installation and Maintenance Manual RC(U)6 v001.99.01.en
B1 INSPECTION
B1.1 Periodical inspection
These inspections should be made during the normal shut-down periods as much as possible, so the compressor is always ready to operate when required. If, at that time, the number of running hours slightly differs from the scheduled period below, the inspection should nevertheless be carried out.
In this way it will not be necessary to stop the compressor at inconvenient times. The frequency of inspections is dependent on the type of installation and operating conditions. In the case of automatically controlled plants, the periodical inspection are particularly important. The table below sums up all the points on the compressor that have to be inspected or maintained along with inspection and maintenance frequencies.
B1.2 Survey of periodical inspections ("check list")
CHECK POINTS 1) FREQUENCY REMARKS
daily
weekly
monthly
Oil level in crankcase
Between 25% and 75% height of the sight glass. For topping up oil, refer to
§B4.1.
Colour of the oil
The oil should be transparently clear. A disappearing white colour points to dissolved refrigerant. Refer to § B2.2 for oil analysis frequency.
Lubricating oil pressure differ­ence [dOil]
The indication of the oil pressure gauge should be 1.5 - 2.5 bar higher than the value shown by the suction pressure gauge.
Oil temperature max. [Toil]
Refer to the "Engineering Data".
Oil leakage of shaft seal max.
In case of more than 1 cc/hr contact supplier.
Suction pressure [Psuc]
Check against design conditions. Refer to plant manual.
Discharge pressure [Pdis]
Refer to plant manual. For the max. allowable discharge pressure refer to the technical data of compressor.
Suction superheat [dTo] Intermediate superheat [dTm]
³ 5 K
Discharge temperature max.
155 °C (311 °F)
Cooling water temperature (if present) min.
Actual condensing temperature + 10 K.
Oil temperature min. [Toil]
During compressor standstill the lower part of the crankcase must remain warmer than the surroundings: ³ 20 °C (NH
3
) and³30 °C (halocarbons).
Condition of V-belts
Check belts for:
1) Wear (fraying, cuts etc.) and ensure that they do not touch the groove bottom.
2) Tension. Too low a tension gives rise to excessive flapping or oscillation in operation. For correct tension consult the instructions given by the V-belt supplier.
Adjustment and operation of pressure safety switches
Refer to §A2.5 and to instructions of switch manufacturer.
Capacity control
The time lag between the unloading and loading of one cylinder or cylinder group should generally be at least 3 - 5 minutes.
Switching frequency of the com­pressor
The time interval between stopping and starting should be at least 2 minutes and between starting and restarting 10 minutes (see §A2.10.2).
Number of operating hours
Check the number of operating hours in view of any maintenance operations to be carried out.
Apart from the above check points, the sound produced by the compressor provides an indication or its mechanical condition. If abnormal sounds are audible, their cause should be traced and removed immediately in order to prevent serious breakdowns.
1
) During the first 50 operating hours the compressor should be checked regularly for all the points mentioned above, at least
twice every 24 hours and more frequently in cases where irregularities are found.
Refrigeration Division
Grasso
B: INSPECTION, MAINTENANCE
AND TROUBLE SHOOTING
v001.99.01.en Installation and Maintenance Manual RC(U)6 B1.1
B2 MAINTENANCE (Contractor’s level)
B2.1 Post start-up maintenance
After the compressor has run for the initial 100 operating hours:
a) Drain the oil and refill the compressor with the
correct amount of fresh oil. b) Exchange or clean the oil discharge filter element. c) Exchange or clean oil suction filter element (pos 24
of fig. 2.1) as given in §B7. d) Clean suction gas filter. e) Check the compressor shaft seal for leakage.
If excessive (more than 1 cc/hr) replace the seal. f) Check drive
f1) Retighten the coupling mounting bolts with the
torque settings as given by the coupling
manufacturer.
f2) Verify and if necessary, correct the tension of
the V-belts as given in the V-belt supplier’s
instructions. g) Verify and if necessary, correct the torque settings
of all foundation bolts as given in § 7.2 of the
Compressor Service Instruction Manual.
Refrigeration Division
Grasso
B: INSPECTION, MAINTENANCE
AND TROUBLE SHOOTING
B1.2 Installation and Maintenance Manual RC(U)6 v001.99.01.en
Loading...
+ 60 hidden pages