GOK BC-1 Series, BC-1-2, BC-1-1, BC-1-3, BC-1-4 Assembly And Operating Manual

Assembly and operating manual
Overfill prevention device type BC-1
for monitoring tanks with liquid media as an alarm equipment during filling
CONTENTS
GENERAL PRODUCT INFORMATIO
APPROVAL ................................
SAFETY ADVICE ................................
PRODUCT-RELATED SAF
ETY ADVICE ................................................................................................. 3
INTENDED USE ................................
INAPPROPRIATE USE ................................
USER QUALIFICATION ................................
ADVANTAGES AND EQUIPMENT ...............................
INFORMATION FOR THE PLANT OPERATOR ...............................
DESIGN ................................
ASSEMBLY ................................
CALCULATION OPTION FOR THE ADJ
ELECTRIC CONNECTION ................................
START-UP ................................
OPERATION ...............................
FUNCTION CHECK ................................
ERROR MESSAGE/MEANING .........................
RESTORATION ...............................
MAINTENANCE ...............................
DISPOSAL ................................
TECHNICAL DATA ...............................
WARRANTY ...............................
TECHNICAL CHANGES ...............................
N .................................................................................................... 2
.............................................................................................................. 2
..................................................................................................... 2
...................................................................................................... 3
............................................................................................ 4
........................................................................................... 4
........................................................................... 4
........................................................ 4
................................................................................................................... 4
.............................................................................................................. 4
USTING DIMENSION X ............................................................ 7
....................................................................................... 8
............................................................................................................. 11
........................................................................................................... 12
............................................................................................... 12
..................................................................................... 12
...................................................................................................... 13
...................................................................................................... 13
............................................................................................................. 13
................................................................................................. 14
........................................................................................................... 14
......................................................................................... 14
Translation of the original operating instructions / part no. 308 393 _15 700 71 a
Version 06.2016
Overfill prevention divice type BC-1
2 / 16
installation guidelines.
Your safety and the safety of others are very important to us. We have provided many important safety messages in this assembly and operating manual.
Always read and obey all safety messages.
This is the safety alert symbol.
“DANGER”, “WARNING”, or “CAUTION”. These words mean:
May result in death or serious injury.
May result in death or serious injury.
May result in minor or moderate injury.
Has an effect on ongoing operation.
ABOUT THE MANUAL
This manual is part of the product.
This manual must be observed and handed over to the operator to ensure that
the component operates as intended and to comply with the warranty terms.
Keep it in a safe place while you are using the product.
In addition to this manual, please also observe national regulations, laws and
GENERAL PRODUCT INFORMATION
The BC-1 overfill prevention divice corresponds to the Zulassungsgrundsätze für Überfüllsicherungen (ZG-ÜS) requirements of a overfill prevention divice as a safety equipment, e.g. according to DWA-A 791-1 (TRwS). The BC-1 overfill prevention divice consists of an indicator and probe and is used to monitor the filling procedure of a tank for water-endangering operating media. Before the maximum permissible filling level in the tank is reached, acoustic and optical alarms activate so that the filling procedure can end on time. The BC-1 represents a safety overflow switch as an object within the meaning of the general building approval which serves, as part of an overfill prevention divice, to prevent overfilling of tanks. The plant
components and the signal amplifier required for the signalling and control device are not part of the BC-1 overfill prevention divice.
APPROVAL
general building approval no. Z-65.11-428
Belgium: AIB-VINCOTTE with prototype no. 99/H031/09030901
Switzerland: SVTI certificate with no. 302.006.15
SAFETY ADVICE
of the Deutsches Institut für Bautechnik (DIBt) as well as the
This symbol alerts you to potential hazards that can kill or hurt you and others. All safety messages will follow the safety alert symbol and either the word
describes a personal hazard with a high degree of risk.
describes a personal hazard with a medium degree of risk.
describes a personal hazard with a low degree of risk.
describes material damage.
describes a piece of information describes a call to action
part no. 308 393 _15 700 71 a
3 / 16
Overfill prevention divice type BC-1
PRODUCT-RELATED SAFETY ADVICE
May not be used in potentially explosive areas!
Can cause an explosion or serious injuries.
Must be installed by a specialised company in accordance with local industrial health and safety regulations! Installation outside the defined EX protection zone!
are hazardous for water
are inflammable
can ignite and cause burning
can cause injury through people falling or slipping
Capture fuels during maintenance work!
INTENDED USE
Operating media
Diesel fuel Fuel oil Water or oil-water mixtures
Petrol Heavy heating oil Liquid fertiliser (AHL, ASL, HAS)
FAME Industrial oil JGS (liquid manure, semi-liquid manure
Urea solution Vegetable oil
You will find a list of operating media with descriptions, the relevant standards and the country in which they are used in the Internet at
www.gok-online.de/de/downloads/technische-dokumentation.
Place of operation
May not be used in potentially explosive areas!
Can cause an explosion or serious injuries.
Indicator:
type BC-1-1, type BC-1-3, type BC-1-4, with protection type IP30, in dry and protected rooms
type BC-1-2, with protection type IP65, indoors and outdoors, if protected against the
weather
Probe:
if the probe is used outdoors, it must be protected with suitable means against penetrating humidity (e.g. with shrinking tube attached)
pull the protection over the cable and approx. 1cm over the probe and shrink it. The marking line and the value for Z must be visible
Use in areas prone to flooding and risk areas
Escaping, liquid fuels:
and silage effluent)
Damage to the product from flooding
Suitable for installation in areas at risk of flooding only to 10 m water height! Replace the product after flooding!
INFORMATION FOR THE PLANT OPERATOR
Please ask your specialised company to confirm the proper installation of the overfill prevention divice on the installation certificate of the specialised company (see the last two pages).
part no. 308 393 _15 700 71 a
4 / 16
Screw-in unit
Overfill prevention divice type BC-1
INAPPROPRIATE USE
All uses exceeding the concept of intended use:
e.g. operation with different operating media
operation with inflammable operating media of categories 1, 2 or 3 with
a flash point
use in the weatherproof outdoor area without protection type IP65
changes to the product or parts of the product
installation in a potentially explosive area
installation in pressurised tanks and containers
USER QUALIFICATION
This product may be installed only by qualified experts. These are personnel who are familiar with setting up, installing, starting up, operating and maintaining this product. Equipment and systems requiring supervision may be operated only by persons aged at least 18, who are physically capable and who have the necessary specialist knowledge or who have been instructed by a competent person. Instruction at regular intervals, but at least once per year, is recommended.
IDESIGN
< 55°C
Probe protective pipe Sensor
Connection cable LED Betrieb [Operation] Button Alarmton Quittieren
[Reset Alarm Sound]
LED Alarm Button Prüfen [Test] Indicator
ADVANTAGES AND EQUIPMENT
optical and acoustic alarm when touching the sensor of the probe with operating media in a tank
acknowledgement button for the acoustic alarm (optical alarm cannot be acknowledged, according to the principles for DIBt approval for overfill prevention divice prior to replacement/withdrawal)
potential-free relay contacts:
- Alarm 1: permanently switched in case of an alarm
- Alarm 2: like Alarm 1, but can be acknowledged for installation, e.g. a warning light or an
acoustic signal generator
- Betrieb [Operation]: for the connection of an external operation indicator
tank port with insert
part no. 308 393 _15 700 71 a
5 / 16
The permits, approvals, and certificates legally required for the execution of building
operating manual.
The specialist installer must enter and confirm that the safety device was installed in accordance with the assembly and operating manual and the guidelines in the general building-authority approval in the printed installation certificate.
The indicator (with IP 30 type of protection) should be installed on the wall of a
protection must be used.
If the indicator is installed in a closed housing (e.g. control cabinet), the connection of
(alarm horn or lamp, operating light, acknowledgement button, test key).
Overfill prevention divice type BC-1
ASSEMBLY
Before assembly, check that the product is complete and has not suffered any damage during transport. In Germany, the assembly of the BC-1 overfill prevention divice is to be carried out:
for water-endangering substances by a company specialised in terms of water law
for water-endangering substances by a specialised company if it is excluded from the
obligation to employ a company specialised in terms of water law according to national regulations
Electric work is always to be carried out by a trained electrician. These requirements also apply for the start-up, maintenance and repair work of the overfill prevention divice. Switzerland: The installation may only be carried out by experts with knowledge in electrical engineering as well as regarding explosion and fire protection.
projects are not replaced by the general building permit and this assembly and
The specialised company and the operator must observe, comply with and understand all of the following instructions in this assembly and operating manual. For the system to function as intended, it must be installed professionally in compliance with the technical rules applicable to the planning, construction and operation of the entire system. These regulations also include the accident prevention regulations of the employers’ liability insurance associations, the VDE regulations, and the installation and operating instructions.
regularly used, dry room. The device is to be installed at a suitable place on the wall. For assembly in the weatherproof outdoor area, the version with IP 65 type of
Installation of the display unit
1. Mount the display unit to the wall in a suitable position.
2. After loosening the four screws, open the display unit by removing the cover.
3. Mount the display unit to a smooth vertical wall by means of dowels. Mount the housing
of the display unit by the four fixing holes with the enclosed screws and anchors. Take care not to damage the housing.
4. After connecting the terminals and setting the unit up, replace the cover.
external signal generators and operating elements is required at a suitable position
part no. 308 393 _15 700 71 a
6 / 16
ASSEMBLY OF THE PROBE
The probe is height-adjustable. The probe may not be shortened under any circumstances.
Z X Y
Adjusting dimension X
The adjusting dimension X is the distance between the reference edge between the dome cover or screw-in unit and the marking ring on the protective cover of the sensor at the lower end of the probe.
Control dimension Y
The control dimension Y results from the difference between the probe dimension Z and the adjusting dimension X. It represents the distance between the upper marking line and the reference edge of the dome cover or screw-in unit. The probe is the part of the limit indicator that protrudes into the tank in a height-adjustable manner, which has a sensor (PTC thermistor as temperature-dependent PTC resistor) protected on the bottom. Probe lengths from 150 to 1000mm are possible. (Observe the tank permit!) A marking line and a number have been embossed into the top of probe tube. The marking line and the value for Z must be visible upon installation. The number indicates the distance from the marking line to the switching point (marking at the bottom of the probe) in millimetres. Probes with probe tube lengths Z = 500 to 1000mm: The probe tube protruding from the tank is to be protected from mechanical stress if necessary. Insert the probe carefully and do not damage it!
Overfill prevention divice type BC-1
The probe must be installed according to the assembly and operating manual and be set to the maximum of the permissible filling volume with permissible filling level – generally <95% (V/V) of the rated volume of the tank as well as according to the stipulations of the building’s certificate of suitability for intended use for tanks or tank systems in the case of battery tanks made of plastics. In case of tanks which are filled via an automatically closing discharge valve, the filling is to be ended when an optical and acoustic alarm of the BC-1 is given. In case of tanks/plants with installed signalling and control devices as well as signal amplifiers as an overfill prevention divice, the following must be observed: If the filler line is longer than 20m, the adjusting dimension X is to be determined according to the special conditions. If necessary, contact the tank manufacturer with a specification of the special tank shape and size, as well as the length of the filler line. The criterion in this case is the overrun volume in the filler line which may not lead to an exceeding of the maximum permissible filling volume. If no information regarding the response height is available, the adjusting dimension X can be determined by the volumetric measurement of the tank or by the calculation of the response height according to the "Zulassungsgrundsätze für Überfüllsicherungen” of the DIBt (see page 7). The connection lines between the probe and the indicator may have a total length of a max. of 200m when a suitable cable with a cross-section of 2 x 1.5mm2 (Cu) is used.
part no. 308 393 _15 700 71 a
7 / 16
a = dimension a= H - L1 - b b = tank wall thickness
H = height or diameter of the tank k = height bushing or threaded flange
1. Maximum volumetric flow rate of the booster pump of the road tanker
V
max
l/min
2. Switching and closing delays of the booster pump of the road tanker
Time
Level sensor according to measurement / datasheet
t1
s
Switch / relay / or similar
t2
s
Booster pump, flow time
t3
s
Shut-off fitting:
t4
s
s
Total time (t
ges
= t1 + t2 + t3 + t4):
t
ges
s 3. Overrun volumeV
4
Overrun volume from delays:
V1 = Q
max
• (t
ges
/ 60)
V1
L
Overrun volume from filler line:
LFL = length of the filler line in m
V4 = V1 + V2
V4 L 4. LevelL
1
Volume at admissible level 95% (V/V)
V3
L
Overrun volume
V4 L Volume at level L1 V5 = V3 - V4
V5
L
Then, the volume at level V5 value results, in combination with the calibration chart or by
shape:
Installation on tank ceiling:
X = H - L1 - b
= mm
Overfill prevention divice type BC-1
CALCULATION OPTION FOR THE ADJUSTING DIMENSION X
mechanical, manually operated time alarm to closing start, closing time:
electrically, pneumatically, or hydraulically operated, closing time:
V2 = (π / 4) • Di² • LFL / 1000
= internal pipe diameter in mm
D
i
V2
calculation, in the level L1. The adjusting dimension X for the GWG must be determined taking into account* the tank
* If applicable Take into account ADJUSTING DIMENSION X AND SUBSEQUENT
LEAK PROTECTION LINING.
part no. 308 393 _15 700 71 a
L
8 / 16
After having DETERMINED THE ADJUSTING DIMENSION X, the insert must be locked.
tighten the upper locking screw .
Connecting threads present on the tank larger than G1 can be brought to the
the partial increase of the fitting edge, the following is applicable: X = a + k + k
Reducer.
ironment, condensation may cause the device to malfunction or may even destroy
temperature before using it.
installation, start-up and maintenance.
a
Overfill prevention divice type BC-1
Assembly insert
The insert is used to fasten the probe within the tank. The insert has locking screws which secure the probe tube against moving. Manually screw-in and fasten the insert using a gasket or sealing materials. The installation is done from above. When adjusting the required response height of the probe (adjusting dimension X), the probe must be secured against unintentional adjustment by using the locking screw(s).
Insert G 3/4
loosen the locki
set the determined adjusting dimension X.
tighten the locking screw so that the probe tube cannot
be moved.
Insert G 1
loosen the upper locking screw .
set the determined adjusting dimension X.
tighten the locking screw a in such a way that the probe tube
cannot be moved.
screw-in the tank insert into the tank.
connecting thread G1 of the insert by using commercially available reducers. Due to
ng screw on the insert.
ELECTRIC CONNECTION
Safety precautions for electrical components
The functions and operating safety of the device are guaranteed only under the climatic conditions that are specified in TECHNICAL DATA. If the device is transported from a cold to a warm env the device. Because of this, you must ensure that the device has acclimatised to the ambient
If you have any doubts that the device can be operated safely, do not operate it. Your safety may be adversely affected by the device, if for example:
it is obviously damaged
it no longer works as specified
it has been stored in unsuitable conditions for some time.
If in doubt, send the device to the manufacturer for repair or maintenance.
Do not use this device for safety applications or emergency stop mechanisms or misuse it!
Injuries and damage to health and property through misuse.
You must observe the information contained in these instructions, especially regarding
part no. 308 393 _15 700 71 a
9 / 16
Use only a dry cloth to clean the device!
Have new insulation installed by a specialised company!
devices.
Electrical Installation
Connection Lines Between the Indicator and the Probe
Line cross-section
2 x 1mm2 (Cu)
2 x 1.5mm2 (Cu)
maximum length
100m
200m
Version
e.g. H05VV-F ; NYM or
Extension via special
connection fitting
Port
Terminals 4 and 5 - sensor
Supply voltage
Supply voltage
230V AC 50Hz
Connection to terminals L1 and N – network
Overfill prevention divice type BC-1
Unplug the device if it is not in use and when it is being cleaned!
Can result in short circuit or electric shock.
Do not open the housing when the device is connected to the power supply! Do not use cleaning agents to clean the device!
Damaged or destroyed insulation!
Can result in short circuit or electric shock.
Do not use the device if the insulation is damaged!
Observe the safety precautions and the assembly and operating instructions of connected
Indicator Type BC-1-1 and BC-1-2 – Sectional View
similar
part no. 308 393 _15 700 71 a
accessories for cable
10 / 16
Indicator type BC-1-4 - Sectional View
The indicated test does not replace the required annual test (see paragraph MAINTENANCE).
maximum switching voltage
250V 50Hz
230V
110V
60V
24V
Type of current
AC
DC
maximum switching current
1.0A
0.1A
0.2A
0.6A
4A
maximum switching power
250VA
During connection, additionally secure the indicator using a back-up fuse.
Output
Contact closed at alarm
Contact open at
Contact closed during
service)
Alarm 1
Terminals 1 + 3
Terminals 2 + 3
Alarm 2
Terminals 6 + 8
Terminals 7 + 8
Operation
Terminals 11 + 12
Overfill prevention divice type BC-1
Connection of the Outputs and the Potential-Fr
ee Relay Contacts on the Indicator
The indicator has 3 potential-free relay contacts. The outputs Alarm 1 and Alarm 2 are intended for the actuation of external alarm units (for the connection of the signalling or control devices of the overfill prevention divice). The output Betrieb [Operation] is intended for connection of an external operation indicator (lamp). The outputs Alarm 1 and Alarm 2 are not monitored, i.e. a line disconnection or a short circuit to the connected signalling or control devices is not recognised and indicated by the measuring transducer. Therefore, either the signalling and control devices must be switched in such a way that a line disconnection is signalled (static current principle) or a functional control of the overfill prevention divice (including the connected signalling and control devices with actuator) must be carried out before each filling. This can be done by pushing the Prüfen [Test] button at the measuring transducer – this leads to an alarm signal, and possibly connected signalling and control devices are switched. After release of the Prüfen [Test] button, the alarm signal goes out.
alarm
operation (readiness for
part no. 308 393 _15 700 71 a
11 / 16
Overfill prevention divice type BC-1
Notice for Switzerland
For shut-off devices and booster pumps in Switzerland, the following must be observed: These devices are, depending on the plant, very different and may not be specifi
universally. In particular, the plant owner must install a suitable shut-off device which is automatically controlled by the special filling protector (e.g. solenoid valve). This happens within the scope of the proper approval procedure and with the approval of the responsible cantonal authority.
In case of storage plants with several containers and with a common filler line, a single automatic
ally controlled shut-off device may be sufficient if each tank has at least one manual
slide and the filling levels of all containers are the same. In case of plants with their own stationary booster pumps, the special filling protection must
shut off t
he booster pumps when reaching the maximum permissible filling level which is determined by the effective volume according to section 20 VWF – when operating the sensor at the latest and prior to closing the automatic shut-off device.
Connection of External Buttons for Alarm Deactivation
The indicator has an input for an external acknowledgement button (Terminals 9 + 10). The function corresponds with the Alarmton Quittieren [Reset Alarm Sound] button integrated into the indicator which can reset (deactivate) the acoustic alarm as well as the output Alarm 2 in case of an alarm. The indicator has an input for an external test key (Terminals 13 + 14). The function corresponds to the Prüfen [Test] button in the indicator which controls the alarm function in the monitoring mode: Display red LED Alarm and buzzer tone. After the connection of the terminals, screw on the front panel again!
START-UP
Settings on the indicator are not required. The start-up of the BC-1 overfill prevention divice is carried out after assembly is completed
by applying the supply voltage. A start-up alarm is emitted first. It is indicated via the red LED Alarm optically and via a buzzer acoustically; in this case, the Alarm 1 and Alarm 2 relay outputs together with possibly connected external signalling or control devices (e.g. solenoid valve, signal horn or lamp) are switched. After about 20 s, this alarm message disappears and only the green LED Betrieb [Operation] lights up – the operation relay output is switched on, so that a possibly connected external signal light goes on as well. The Alarm 1 and Alarm 2 relay outputs are deactivated. After that, a functional check with all components of the overfill prevention divice (including any connected signalling and control devices) should be performed. The operating manuals of the connected appliances must be respected. Pressing the Prüfen [Test] button on the indicator triggers an alarm. In the process, an alarm indication as described above must be emitted.
ed
part no. 308 393 _15 700 71 a
12 / 16
Operation mode
Status of
Betrieb
[Operation] *1
Alarm
Alarm
Output
Output
Normal operation
ON
OFF
OFF
OFF
OFF
Alarm
ON
ON
ON
ON
ON
Alarm acknowledged
(with button)
ON
ON
OFF
ON
OFF
Failure of the auxiliary energy
OFF
OFF
OFF
OFF
OFF
Disruption
thermistor
ON
ON
ON
ON
ON
Short circuit
thermistor
ON
ON
ON
ON
ON
The relay outputs Alarm 1 and Alarm 2 are not monitored, i.e. a line disconnection or a short
measuring transducer.
*1 Output Betrieb [Operation] only with type BC-1-1, BC-1-2 and BC-1-4
Overfill prevention divice type BC-1
OPERATION The indicator must indicate the monitoring mode constantly via the green LED Betrieb
[Operation].
During a filling of the tank, an alarm is indicated via the red LED Alarm, the integrated buzzer, and any connected external alarm units when the response level is reached (according to the adjusting dimension X of the probe) so that the filling procedure can be ended on time. An alarm is also indicated in case of a possible line disconnection or short circuit in the probe circuit. With the Alarmton Quittieren [Reset Alarm Sound] button, both the integrated acoustic alarm and the Alarm 2 output can be reset (deactivated). The LED Alarm, however, remains in operation. After the liquid level in the tank sinks (the probe is no longer submerged in liquid, e.g. due to withdrawal), the indicator switches to monitoring mode again. Operation includes MAINTENANCE.
FUNCTION CHECK
By pressing the Prüfen [Test] button, the alarm function in monitoring mode may be checked: Display red LED Alarm and buzzer tone. After the button is released, the alarm indication disappears.
ERROR MESSAGE/MEANING
[Operation]
LED
buzzer
Alarm 1 LED + Output Betrieb
(Filling level below the probe response height)
Filling level reaches probe response height when filling
of the line between the measuring transducer and the probe or of the PTC
of the line between the measuring transducer and the probe or of the PTC
circuit to the connected signalling and control devices is not recognised and indicated by the
Alarm 2
part no. 308 393 _15 700 71 a
13 / 16
Capture fuels during maintenance work.
To protect the environment, our products may not be disposed of along with
Ordinance: 20 01 35.
Overfill prevention divice type BC-1
RESTORATION
If the actions described in TROUBLESHOOTING do not lead to a proper restart and if there is no dimensioning problem, the product must be sent to the manufacturer to be checked. Our warranty does not apply in cases of unauthorised interference. In case of a constant alarm indication without the probe part coming into contact with liquid, check the connection lines and signal and probe part for disconnection or short circuit and re­assemble if necessary.
MAINTENANCE
Escaping, liquid fuels:
are hazardous for water
are inflammable
can ignite and cause burning
can cause injury through people falling or slipping
The overfill prevention divice is maintenance-free if assembled and operated properly. Once a year, al signalling or control devices with actuator and signal amplifier) must be checked. It is the responsibility of the plant owner to select the type of test and the intervals for each calendar year. The test has to be carried out to prove the perfect functioning of the overfill prevention divice acting in combination with all components. This is guaranteed when the response height is reached during a filling process. Additionally, the probe must be checked for any dirt and, if necessary, must be cleaned.
l components of the overfill prevention divice (including all connected
Malfunctions and contamination of the probe in the cover due to contaminated operating media!
Proper operation is no longer provided for.
Remove the probe from the tank! Perform a visual inspection Sensor must be free! Carefully clean the inside of the cover with a brush and cleaning agent! Install the probe into the tank and repeat CONTROL!
DISPOSAL
household waste.
The product must be disposed of via a local collection station or a recycling station. Discharged batteries should be deposited at collection stations or in shops with collection facilities. Stored data is not lost when you replace the battery. WEEE Register No.: DE 78472800. Disposal code according to the Waste Catalogue
part no. 308 393 _15 700 71 a
14 / 16
TECHNICAL DATA
Indicator
Supply voltage
230V AC; 50-60Hz
Power consumption
4.5VA
Voltage tolerance
+10% / -15%
Protection type
IP 30 or IP 65 acc. to EN 60529
Housing
Polyester or polycarbonate
Dimensions H x W x D
Type BC-1-1
200 x 120 x 58mm
Type BC-1-2
225 x 138 x 80mm
Type BC-1-4
120 x 120 x 49mm
Sound level of alarm sound:
70dB(A)
Probe
Voltage:
12V DC
Probe length
Z = 150 to 1000mm
Length of the probe connection cable
Standard Materials
1.4301 ; 1.405 ; PA (depending on the version)
Installation position:
vertically upright
Temperature of the operating media
-20°C to +60°C
Ambient temperature
-20 °C to +60 °C
We guarantee that the product will function as intended and will not leak during
Overfill prevention divice type BC-1
WARRANTY
the legally specified period. The scope of our warranty is based on Section 8 of our terms and conditions of delivery and payment.
TECHNICAL CHANGES
All the information contained in this assembly and operating manual is the result of product testing and corresponds to the level of knowledge at the time of testing and the relevant legislation and standards at the time of issue. We reserve the right to make technical changes without prior notice. Errors and omissions excepted. All figures are for illustration purposes only and may differ from actual designs.
part no. 308 393 _15 700 71 a
15 / 16

Installation certificate from specialised company

To be kept by system operator!
Important for any warranty claims!
I hereby confirm that the
installed correctly:
in accordance with the applicable assembly and operating manual. After ASSEMBLY, the
handed to the operator and is in the possession of the operator.
Specialised company is
specialised company according to water law
(electrical installation) company
Operating medium or stored material
petrol
diesel fuel
liquids
1)
More detailed description of the
operating medium
2)
Proof of test acc. to INTENDED USE
Overfill prevention divice type BC-1
following safety equipment was
Overfill prevention divice type BC-1 GOK device no.:
safety equipment underwent the start-up and a FUNCTION CHECK. Upon start-up, the safety equipment operated properly. The operator was informed about the operation, care and maintenance of the product in accordance with the assembly and operating manual. The assembly and operating manual along with a copy of the general building approval was
  FAME  aqueous urea solution
fuel oil  industrial oil vegetable oil water or oil-water mixtures liquid fertiliser (AHL, ASL, HAS) JGS (liquid manure, semi-liquid manure and
silage effluent)
other water-hazardous, non-flammable
1) + 2)
The probe (limit indicator) was installed in a tank:
Manufacturer:
Fabricate no.
Approval / test mark:
Tank acc. to construction standard
Rated volume in litres:
Maximum admissible level
Adjusting dimension X =
part no. 308 393 _15 700 71 a
% (V/V)
mm
16 / 16
Address of operator
Address of specialised company
Place, date, signature
company

Recurring FUNCTION CHECK

The safety equipment was subjected to a recurring FUNCTION CHECK and worked correctly at that time.
Place, date
Specialised company (stamp, signature)
Overfill prevention divice type BC-1
Installation certificate – page 2
The proper installation of the overfill prevention divice BC-1 in accordance with the applicable assembly and operating manual is certified. After assembly, the device underwent a FUNCTION CHECK prior to start-up. Upon start-up, the overfill prevention divice worked without malfunctions and defects. The operator was informed about the operation, care and maintenance of the overfill prevention divice BC-1 in accordance with the assembly and operating manual. The assembly and operating manual along with a copy of the general building approval was handed to the operator. The operator must have a copy of the general building approval.
Place, date, signature, stamp of the specialised
For Switzerland, the following must be observed:
The name of the inst
GENERAL BUILDING APPROVAL
DECLARATION OF CONFORMITY
allation company with on-call service and telephone number must be
attached to the indicator of the BC-1!
Self Climat
Rue des Epinettes ZI Sud 77200 TORCY 01 60 05 18 53 Fax: 01 60 17 58 39
E-Mail: info@selfclimat.com Internet: www.selfclimat.com
part no. 308 393 _15 700 71 a
Loading...