Glunz & Jensen Concept 205 C Preinstallation Manual

Pre-installation Manual
CONCEPT 205 C
Pre-installation Manual
CONCEPT 205 C
Edition AC, June 2014
T11376
This manual is published by: Glunz & Jensen Degraf S.p.A.
’Il Girasole’ - Palazzo Donatello 8/03b 20084 Lacchiarella (MI) Italy Internet: www.degraf.glunz-jensen.com
Copyright © 2014 by Glunz & Jensen Degraf S.p.A.
Pre-installation Manual - CONCEPT 205 C 1425
0-2
Part 0: Introduction
Reservations
This manual was written and illustrated using the best possible information avail
-
able at the time of publication.
Any differences between this manual and the equipment reflect improvements intro
-
duced after the publication of the manual.
Changes, technical inaccuracies and typographic errors will be corrected in subse
-
quent editions.
As a part of our policy of continuous improvement, we reserve the right to alter de
-
sign and specifications without further notice.
Pre-installation instructions
The instructions in this Pre-installation Manual allow the customer and the Service Technician to prepare the installation site for the unit and for the installation itself.
Never install the unit in explosive environments.
It is the responsibility of the owner and operator/s of the unit that the installation is made in accordance with local regulations, and by engineers authorized to carry out plumbing and electrical installations.
The manufacturer cannot be held responsible for any damage caused by incorrect in­stallation of the unit.
"
Only qualified Service Technicians are allowed to unpack and install the equipment.
#
When preparing the installation site please take into consideration that this equipment is for restricted access locations only!
Notes, cautions, and warnings !
Throughout the manual warnings, cautions, and notes are written in bold like the ex
-
ample below:
#
Electrical installation must conform to local regulations and guidelines.
Symbol Meaning Explanation
"
Note
The operator should observe and/or act according to the information in order to obtain the best possible function of the equipment.
$
Caution
The operator must observe and/or act according to the information in order to avoid any mechanical or electrical damage to the equipment.
#
Warning
The operator must observe and/or act according to the information in order to avoid any personal injury.
1407 Pre-installation Manual - CONCEPT 205 C
0-3
Introduction
Table of contents
Pre-installation Manual - CONCEPT 205 C 1407
0-4
Introduction
Table of contents
Part 0: Introduction .................................... 0-3
Reservations ..................................................0-3
Pre-installation instructions ........................................0-3
Notes, cautions, and warnings ! .....................................0-3
Table of contents .................................................0-4
Part 1: Transportation .................................. 1-1
When the unit arrives ..............................................1-1
Storing the unit before installation ...................................1-1
The crate.......................................................1-1
Dimensions and weight...........................................1-1
Checking the crate for damage......................................1-2
Handling the crate ..............................................1-2
Transporting the unit...............................................1-3
Lifting the crate ................................................1-3
Available width for transport .......................................1-3
Part 2: Installation requirements ........................... 2-1
Environmental requirements .........................................2-1
Accessories to be provided by customer for connections ......................2-1
Installation kit ...................................................2-1
Space requirements ...............................................2-2
Free space around the unit ........................................2-2
Unit dimensions and connection locations..............................2-3
Electrical requirements .............................................2-5
Main power connection...........................................2-5
Main power outlet ..............................................2-5
Power supply cable .............................................2-5
Electrical specifications ...........................................2-6
Fuses .......................................................2-6
Power consumption .............................................2-6
Part 3: Pre-installation checklist ...........................3-1