Global AcuDrill User Manual

Page 1
USER MANUAL
DRILLING MACHINE
FOR UNDER PRESSURE MAINS
MODEL
AcuDrill
Revision No. 4 - June 2016
Publication: MU-41-14E
Page 2
DATOS DEL FABRICANTE
MANUFACTURER DATA
ACUSTER GLOBAL, S.L.
Ctra. Montcada, 608
08223 Terrassa (Barcelona) - SPAIN
Tel. (+34) 93 736 18 80
e-mail: info@acusterglobal.com
DATOS DEL DISTRIBUIDOR Y SAT
DISTRIBUTOR AND SERVICE DATA
STP Acuster Internacional
Crta. Montcada, 608
08223 Terrassa (Barcelona) - SPAIN
hello @stpacuster.com
+34937361880
STP Acuster North Europe
Ind. terrein de Wildeman, hof 4
Bossekamp 12
5301 LZ Zaltbommel - The Netherlands
info@iwmc.be
+31418840003
STP Acuster Central Europe
2, Kvetna 685, Areal Salvia
736 61 Napajedla - Czech Republic
info@stp-fittings.cz
+420577913065
STP Acuster Baltics
Bullu str. 45
Riga, LV1067 - Latvia
riga@stpfittings.lv
+37167815281
STP Acuster South Africa
54 Richard Road, Industria North
PO BOX 2203 Wilro Park
1731 Roodepoort - South Africa
shawn.pretorius@stp-sa.com
+27315397451
Agru Acuster Chile
Lo Echevers 891,
Bodegas 11 y 12, Quilicura,
Santiago - Chile
info@agrusa.cl
+56229493910
Agru Acuster Brasil
Rua Saburo Sumiya, 211
Aldeia, Barueri, SP
CEP: 06440-110 – Brasil
daniel@agru.com.br
+55114138088
NOTES ! The modifications carried out against the previous revision of this
publication are indicated with
2 on the right margin.
Page 3
USER MANUAL
AcuDrill DRILLING MACHINE
Edition: June 2016 Revision: No. 4
GENERAL CONTENTS - 3
CONTENTS:
Page:
CHAPTER 1: INTRODUCTION............................................................................ 5
1.1 Introduction........................................................................ 5
1.2 General information............................................................. 5
1.3 “CE” declaration of conformity............................................... 6
1.4 Guarantee.......................................................................... 7
CHAPTER 2: MACHINE DESCRIPTION................................................................. 8
2.1 Components of the drilling machine....................................... 8
2.2 Machine accessories............................................................ 10
2.3 Hole saws diameters and characteristics................................. 11
CHAPTER 3: MODE OF OPERATION.................................................................... 12
3.1 Drilling under pressure over AcuStop-R branch connections..... 12
3.1.1 Initial operations....................................................... 12
3.1.2 Branch connection installation..................................... 12
3.1.3 Assembly of the drilling machine................................. 12
3.1.4 Pressure test............................................................ 13
3.1.5 Drilling the mains...................................................... 14
3.1.6 Plugging the branch connection................................... 15
3.1.7 Disassembly of the machine and accessories................. 15
3.1.8 Connecting the branch connection............................... 16
3.2 Pressureless drilling over CA-R branch connections................. 17
3.2.1 Initial operations....................................................... 17
3.2.2 Branch connection installation..................................... 17
3.2.3 Assembly of the drilling machine................................. 17
3.2.4 Drilling the mains...................................................... 18
3.2.5 Disassembly of the machine and accessories................. 19
3.2.6 Connecting the branch connection............................... 19
3.3 Drilling under pressure over CA-R branch connections............. 20
3.3.1 Initial operations....................................................... 20
3.3.2 Branch connection installation..................................... 20
3.3.3 Assembly of the cutoff valve....................................... 20
3.3.4 Assembly of the drilling machine................................. 21
3.3.5 Pressure test............................................................ 22
3.3.6 Drilling the mains...................................................... 22
3.3.7 Disassembly of the machine and accessories................. 23
3.3.8 Connecting the branch connection............................... 23
3.4 Pressureless drilling over
ACUFLEX/BH525 branch connections. 24
3.4.1 Initial operations....................................................... 24
3.4.2 Branch connection installation..................................... 24
3.4.3 Assembly of the drilling machine................................. 24
3.4.4 Drilling the mains...................................................... 25
3.4.5 Disassembly of the machine and accessories................. 26
3.4.6 Connecting the branch connection............................... 26
Page 4
USER MANUAL
AcuDrill DRILLING MACHINE
Edition: June 2016
- GENERAL CONTENTS Revision: No. 4 4
Page
:
3.5 Drilling under pressure fittings for gas: 3-Way Tees 1½”&2"..... 27
3.5.1 Initial operations....................................................... 27
3.5.2 Fitting mains installation............................................ 27
3.5.3 Sandwich valve installation......................................... 27
3.5.4 Assembly of the drilling machine................................. 27
3.5.5 Pressure test............................................................ 28
3.5.6 Drilling the mains...................................................... 29
3.5.7 Plugging the fitting.................................................... 30
3.5.8 Disassembly of the machine and accessories................. 30
3.5.9 Installation of the fitting internal plug.......................... 30
NEW ! 3.6 Drilling under pressure fittings for gas: 3-Way Tees 1"............. 32
3.6.1 Initial operations....................................................... 32
3.6.2 Fitting mains installation............................................ 32
3.6.3 Sandwich valve installation......................................... 32
3.6.4 Assembly of the drilling machine................................. 33
3.6.5 Pressure test............................................................ 33
3.6.6 Drilling the mains...................................................... 34
3.6.7 Plugging the fitting.................................................... 34
3.6.8 Disassembly of the machine and accessories................. 35
3.6.9 Installation of the fitting internal plug.......................... 35
CHAPTER 4: MAINTENANCE.............................................................................. 37
4.1 General information............................................................. 37
CHAPTER 5: TECHNICAL CHARACTERISTICS....................................................... 38
Page 5
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
Revision: No. 4
INTRODUCTION - 5
SECTION 1: INTRODUCTION
1.1 INTRODUCTION
The AcuDrill drilling machine is especially designed to drill on mains, under pressure or pressureless, on any type of material: gray-iron casting, ductile casting, PVC, PE, PP, asbestos cement, polyester, clay, steel, etc. It is especially designed to be used on branch connections or threaded accessories. The machine dome is connected to the threaded outlets of saddles through threaded adapters. The sizes of the available adapters are 3/4", 1", 1¼”, 1½” and 2" BSP. It allows holes of up to 48 mm diameter to be drilled, using standard hole saws of high-speed steel or tungsten carbide tipped hole saws with coupon retainer-equipped pilot drill. The chuckshaft can be fixed in three different positions according to the position of the accessories to be drilled. It can be operated manually by means of a ratchet wrench provided with a revolving handle, although it is designed to be used through a swivel gear with either an electric, pneumatic or hydraulic actuator. For drilling mains under pressure, the maximum allowable pressure is 16 bar (for water mains) and 5 bar (for gas mains). The machine is equipped with an absorbing mechanism that ensures a soft and regular operation system of the drill and hole saw over the pipe during drilling, absorbing excessive feed that could lead to blocking of the hole saw, allowing continuous drilling. The set includes a dome with built-in spindle, a machine body, chuckshaft, two arbor hole saws with pilot drill (with coupon retainer system), an spanner for the dome adapters, a 3 mm Allen key, a ½” ratchet wrench with revolving handle, in addition to a carrying case and User Manual. The technical information provided in this Manual is purely informative, and subject to change without prior notification. ACUSTER GLOBAL, SL. shall not be responsible for any claims derived from misuse of this publication or any errors and/or omissions that could be detected in it following its publication.
1.2 GENERAL INFORMATION
The development, documentation, production, testing and shipping of the products described have been performed:
C
in compliance with the applicable safety rules, and
C
in accordance with the Acuster Global, SL. quality assurance requirements.
WARNING !
Only qualified personnel are authorized to perform drilling work with the AcuDrill drilling machine. Qualified personnel must be familiar with all safety measures, potential hazards and maintenance rules described in this Manual.
The safe usage of the products described herein requires appropriate transport, storage, installation and use, careful treatment and compliance with the pre-established regular maintenance.
Page 6
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
- INTRODUCTION
Revision: No. 4
6
1.3 “CE” DECLARATION OF CONFORMITY
ACUSTER GLOBAL, S.L. Ctra. Montcada, 608 08223 Terrassa (Barcelona) SPAIN
we declare, under our sole responsibility that the AcuDrill drilling machine has been manufactured in compliance with the following specifications:
Directive Related specification Model
2006/42/CE
Machine safety Directive
EN-ISO 12100 EN 60204-1
AcuDrill
Sant Just Desvern, 13th May 2005
Jaume Puig General Manager
Page 7
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
Revision: No. 4
INTRODUCTION - 7
1.4 GUARANTEE
Guarantee declaration:
All AcuDrill drilling machines are manufactured from high quality material and have been subjected to rigorous tests for resistance and working order as well as passing all the quality control tests required by the applicable normative (see "CE" Declaration of conformity). Regardless of whether an incident might occur during the period of guarantee, we recommend a careful reading of the following general guarantee conditions.
General conditions of Guarantee:
1. ACUSTER GLOBAL S.L. guarantees that this product has no manufacturing defect at the time of its purchase and extends this guarantee for the period of TWO years.
2. If the product proves defective during this period, due to the materials or its assembly, it will be repaired free of charge, including the cost of materials and labour at Acuster Global, SL.'s Technical Service.
3. The Guarantee is not valid in the following cases:
When the fault in the product is a result of:
!
Usual wear and tear due to usage.
!
Abuse or incorrect use of the unit
!
Repairs carried out without authority from Acuster Global, S.L..
!
Accidents, natural disasters (including lightning, water action etc) as
well as any cause beyond Acuster Global, S.L.'s control.
4. In all claims against this guarantee, information relating to the model, date of purchase, Serial number and any other additional information must at all times be stated.
Page 8
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
- MACHINE DESCRIPTION
Revision: No. 4
8
SECTION 2: MACHINE DESCRIPTION
2.1 COMPONENTS OF THE DRILLING MACHINE
The AcuDrill drilling machine assembly is made of the following components:
Figure 1
1 Carrying case with die cut foam 2 Drilling machine 3 Dome adapter spanner 4 Ratchet wrench with revolving handle 5 3mm Allen key 6 Arbor hole saws (14 to 30 mm) featuring pilot drill with coupon retainer 7 Arbor hole saws (32 to 46 mm) featuring pilot drill with coupon retainer
Page 9
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
Revision: No. 4
MACHINE DESCRIPTION - 9
Main parts of the AcuDrill drilling machine:
1 Dome with spindle
2" BSP threaded with inner O-ring to screw threaded adapters of the saddle or accessory to be drilled.
2 Venting valve
PN16 valve for depressurizing and pressurizing test operations.
3 Machine body
Includes end travel mechanism and absorbing mechanism to optimize drilling power.
4 CE identification plate
Marking pursuant to Machinery Safety Directive.
5 End travel mechanism
Blocks the machine’s end travel but allows a manual release through the retractable handle.
6 Chuckshaft
Features three fastening openings to select the most appropriate length for drilling.
7 Chuckshaft fastening bush
This is the element that joins the chuck s h a f t w i t h t h e a b s o r b i n g mechanism. It features a mark indicating the maximum feed limit.
8 Chuckshaft fastening mechanism
This allows quick and safe fastening of the chuckshaft to the fastening bush.
Figure 2
Page 10
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
- MACHINE DESCRIPTION
Revision: No. 4
10
2.2 MACHINE ACCESSORIES
The AcuDrill drilling machine also features the following accessories:
Figure 3a: Standard accessories Figure 3b: Drilling kit 1" (#141143)
1 Saddle adapter kit of 3/4", 1", 1-
1/4", 1-1/2" and 2" (optional kit of 2-3/4").
1a Saddle adapter. 1b Metal-rubber washer. 1c Variable pitch hole saws of 19,
22, 30, 33 and 46 mm, respectively.
In addition to the hole saws sizes indicated above, other optional sizes can be ordered. There are special hole saws for drilling PE pipes.
For additional information, refer to clause 2.3 of this Manual.
2 ½" Arbor hole saw with drill (for
hole saws of 14 to 30 mm) and arbor hole saws of 5/8" with drill (for hole saws of 32 to 46 mm).
2a Arbor hole saws without drill. 2b Pilot drill of 6.35 mm diameter,
with coupon retainer (optionally
6.25 HSS pilot drills with or without coupon retainer are also available).
3 Chuckshaft adapter to an electric
drilling machine. Two options: 1) female square drive of ½" x ½" thread and 2) female square drive of ½" x 5/8" thread.
4 Ch uc k sh af t ad ap t er to
pneumatic machine. Female square drive of ½".
The kit 1" is composed of:
1 Dome adapter 1"
2 Sandwich valve 1" (with driven key)
3 Arbor hole saw with drill 10 mm.
4 Tool for inside plug installation.
5 2½” sandwich valve with 1½” and 2"
adapters for 3-way tees and TOR­threaded O-rings.
6 2"-2½” drilling machine dome-
sandwich valve adapter.
7 Tool for inside plug installation.
Page 11
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
Revision: No. 4
MACHINE DESCRIPTION - 11
2.3 HOLE SAW DIAMETERS AND CHARACTERISTICS FOR ACUDRILL & ACUDRILL PLUS
ADAPTER
SIZE
ADAPTER
INSIDE
DIAMETER
HOLE SAW DIAMETER (MAX*)
APPLICATION
Bi-metal
HSS
Tungsten
Carbide Grit
For plastic
pipes
3/4" 20 19 19 19 AcuDrill
1" 24,5 22 22 22 AcuDrill
1¼” 32,5 30 29 30 AcuDrill
1½” 37,5 33 32 35 AcuDrill
2" 49 46 44 48 AcuDrill+Acudrill Plus
2½” 65 60 60 60 AcuDrill Plus
3” 78 76 76 76 AcuDrill Plus
DN65/80 78 60 / 76 60 / 76 62/76 AcuDrill Plus
DN100/125 125,8 95 / 121 95 / 121 98/114 AcuDrill Plus
DN150 160,3 146 146 146 AcuDrill Plus
DN200 184,7 177 152 160 AcuDrill Plus
GENERAL CHARACTERISTICS
Bi-metal HSS: Hole saw made of speed steel type M3. Sizes: from 14 to 210 mm; cutting depth of 35 mm. Long series: request information (cutting depth of 48 mm). Application: standard pipelines made of ductile iron, steel and asbestos cement.
Tungsten carbide: Hole saw made from tungsten carbide tooth welded on a solid body of special steel. Sizes: from 19 to 152 mm; cutting depth of 38 mm. Application: pipelines made of ductile iron and steel.
For plastic pipes: Hole saw made of tungsten carbide tooth welded on a sheet body. Sizes: from 16 to 210 mm; cutting depth of 50-55 mm. Application: plastic pipelines, such as PE, PP, PVC, etc.
(MAX*) The indicated hole saw diameter is the one recommended based on:
C
Available diameters according to the hole saw supplier.
C
Maximum diameter depending on the drilling machine adapter used.
C
Maximum diameter depending on the saddle, T-clamp, valve (full bore), connecting accessories, etc., of the DN used.
Page 12
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
- MODE OF USE
Revision: No. 4
12
SECTION 3: MODE OF OPERATION
3.1 DRILLING UNDER PRESSURE OVER ACUSTOP-R BRANCH CONNECTIONS
3.1.1 Initial operations:
Before performing the drilling operations, ensure that you have all the necessary material and that it is in good condition.
C
Complete drilling machine.
C
Arbor hole saw (with pilot drill installed) matching the size of the hole saw to be used.
C
Hole saw of the diameter to be used.
C
Adapter (with washer) of the diameter of the thread matching the saddle to be installed.
C
Tools: 3 mm Allen key, adapter spanner, 17 mm open-end spanner, ½” ratchet wrench (manual drilling) and electrical or pneumatic swivel gear with chuckshaft adaptation elements (if applicable).
3.1.2 Branch connection installation:
The installation of the AcuStop-R branch connection is performed placing the saddle and sealing gasket on the pipe. Next, fasten the clamp between the saddle and mains (the hinge joints should remain above the saddle), equally tightening the two fastening bolts to ensure tightness.
For more information, refer to the Fitting Instructions included with the accessory.
Figure 4
3.1.3 Assembly of the drilling machine:
C
Set up the arbor hole saws with the pilot drill in the chuckshaft. Screw the hole saw matching the threaded outlet of the branch connection into the arbor hole saw. See Figure 5.
C
Choose the adapter that matches the thread of the saddle and screw it into the machine dome. See Figure 6.
This operation can be performed manually. If necessary, use the dome adapter spanner included with the equipment.
C
For this type of branch connection, position the retention mechanism in the lowest of the three anchoring openings on the chuckshaft. See Figure 7.
Page 13
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
Revision: No. 4
MODE OF USE - 13
Figure 5 Figure 6 Figure 7
C
Place the body of the machine in its upper position (unscrew it until the end travel mechanism is released). Now install the AcuDrill drilling machine by screwing it onto the saddle of the branch connection. The adapter must have the washer installed.
WARNING !
If the support face of the saddle is not flat enough, apply Teflon tape to the adapter thread to achieve tightness.
Manually tighten the machine body. If necessary, retighten using the dome adapter spanner included with the equipment.
3.1.4 Pressure test:
Once the drilling machine set and accessories are installed on the saddle of the branch connection, perform a pressure test. To do so, apply compressed air through the venting valve to check tightness of the assembly (see Figure 8). Once the interior is pressurized, and with the venting valve closed, check for leaks in the threaded connections or the gasket at the mains head seat gasket using a spray detector or soapy water. Correct in case of leaks. Once the check is complete, open the venting valve to depressurize, then leaving it in the “closed” position.
Figure 8
Page 14
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
- MODE OF USE
Revision: No. 4
14
3.1.5 Drilling the mains:
Once the pressure test is complete, lower the chuckshaft by rotating the machine body (with your hand in the knurled area), until the pilot drill makes contact with the pipe (the chuckshaft will have risen depending on the contact force: see measurement a of Figure
9). At this point, withdraw the tip of the drill from the pipe by approximately one turn. Now begin drilling the mains by activating the chuckshaft using the ratchet wrench, if drilling is manual, or through the electrical or pneumatic swivel gear.
SWIVEL GEAR
If an electrical actuation swivel gear (drilling machine) or pneumatic swivel gear (pneumatic, non-impact tool) is used, the following considerations must be taken into account:
C
The rotation speed must be that indicated by the hole saw
manufacturer.
C
The adapter components may be supplied by Acuster Global, SL.
C
The usage and safety recommendations given by the manufacturer
must be followed.
The feed is achieved by making the machine body rotate (with the hand placed in the knurled area). The recommended distance produced by the feed is a = 1 or 2 mm (see Figure 9) when drilling with the pilot drill. Once perforated with the drill, remember that distance a will be increased by the internal driving pressure. The feed limit is indicated by a mechanized line on the fastening bush shaft. If due to an excess of compression (feed + internal pressure) this line becomes visible (see Figure 9), turn slightly in the opposite direction to return to the previously­recommended distance. Ensure that the drilling is complete by making one or two additional turns.
Figure 9
WARNING !
It is recommended to avoid excess feed, especially in the pilot drill work phase, given that the drill could break specially at low revolutions.
Page 15
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
Revision: No. 4
MODE OF USE - 15
3.1.6 Plugging the branch connection:
Once the mains has been perforated, move the chuckshaft up by turning the machine body counterclockwise until the hole saw is positioned in the upper part of the dome. Carefully open the venting valve to remove chip residues. Next, close the valve again. Now carry out the plugging to facilitate disassembly of the machine and the subsequent connection to the branch connection.
Figure 10 Figure 11
To do so, the slot in the saddle for the introduction of the spatula must be fully accessible. Slightly raise the clamp-gasket assembly of the saddle closure to keep it from interfering with the handle of the spatula during the introduction. See Figure 10.
The clamp-gasket assembly is delivered flush with the upper face of the saddle and with the fastening bolt untightened.
Place the pivoting shaft of the spatula in the opening of the saddle (use the small spatula to plug branch connections with threaded outlets of 3/4” to 1½” and the large spatula for branch connections with 2” threaded outlet). Insert the spatula all the way to the bottom through the slot of the saddle. See Figure 11.
3.1.7 Disassembly of the machine and accessories:
Before carrying out the disassembly of the drilling machine, check the tightness of the spatula by opening the venting valve. There should not be any fluid overflow, unless it is the amount remaining in the interior before fitting the spatula. Correct the position of the spatula in case of leak or determine the causes of any possible loss. Once the check is complete, return the venting valve to the closed position. Disassemble the saddle adapter and drilling machine using the spanner designed for this purpose.
Page 16
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
- MODE OF USE
Revision: No. 4
16
The coupon resulting from drilling the main will have remained trapped by the pilot drill’s coupon retainer mechanism. To extract the coupon, disassemble the drill by loosening the Allen fastening stud. Remove the coupon through the upper part of the drill and fit it to the arbor hole saw again. See Figure 12.
Figure 12 Figure 13
3.1.8 Connecting the branch connection:
Make the proper connections at the threaded outlet of the saddle. If necessary, perform a pressure test on the new section. Completely withdraw the spatula (to allow fluid flow). Next slide the exterior clamp­gasket assembly all the way down. Tighten the fastening bolt of the exterior clamp-gasket assembly to its end travel. See Figure 13.
The tightening bolt must remain positioned on the opposite side from the spatula insertion slot, as it is delivered stock.
Retighten the fastening bolts of the branch connection.
Page 17
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
Revision: No. 4
MODE OF USE - 17
3.2 PRESSURELESS DRILLING OVER CA-R BRANCH CONNECTIONS
3.2.1 Initial operations:
Before performing the drilling operations, ensure that you have all the necessary material and that it is in good condition.
C
Complete drilling machine.
C
Arbor hole saw (with pilot drill installed) matching the size of the hole saw to be used.
C
Hole saw of the diameter to be used.
C
Adapter (with washer) of the diameter of the thread matching the saddle to be installed.
C
Tools: 3 mm Allen key, adapter spanner, 17mm open-end spanner, ½" ratchet wrench (manual drilling) and electrical or pneumatic swivel gear with chuckshaft adaptation elements (if applicable).
3.2.2 Branch connection installation:
The installation of the CA-R branch connection is performed placing the saddle and gasket on the pipe. Next, fasten the clamp between the saddle and mains (the hinge joints should remain above the saddle), equally tightening the two fastening bolts to ensure tightness.
For more information, refer to the Fitting Instructions included with the accessory.
Figure 14
3.2.3 Assembly of the drilling machine:
C
Set up the arbor hole saws with the pilot drill in the chuckshaft. Screw the hole saw matching the threaded outlet of the branch connection into the arbor hole saw. See Figure 15.
C
Choose the adapter that matches the thread of the saddle and screw it into the machine dome. See Figure 16.
This operation can be performed manually. If necessary, use the dome adapter spanner included with the equipment.
Page 18
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
- MODE OF USE
Revision: No. 4
18
Figure 15 Figure 16 Figure 17
C
For this type of branch connection and intervention, position the retention mechanism in the lowest of the three anchoring openings on the chuckshaft. See Figure 17.
C
Place the body of the machine in its upper position (unscrew it until the end travel mechanism is released). Now install the AcuDrill drilling machine screwing it onto the saddle of the branch connection. The adapter must have the washer installed.
WARNING !
If the support face of the saddle is not flat enough, apply Teflon tape to the adapter thread to achieve tightness.
Manually tighten the machine body. If necessary, retighten using the dome adapter spanner included with the equipment.
3.2.4 Drilling the mains:
Once the machine set and saddle accessories are assembled, lower the chuckshaft by rotating the machine body (with your hand in the knurled area), until the pilot drill makes contact with the pipe (the chuckshaft will have risen depending on the contact force: see measurement a of Figure 18). At this point, withdraw the tip of the drill from the pipe by approximately one turn. Now begin drilling the mains by activating the chuckshaft using the ratchet wrench, if drilling is manual, or through the electrical or pneumatic swivel gear.
Page 19
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
Revision: No. 4
MODE OF USE - 19
SWIVEL GEAR
If an electrical actuation swivel gear (drilling machine) or pneumatic swivel gear (pneumatic, non-impact tool) is used, the following considerations must be taken into account:
C
The rotation speed must be that indicated by the hole saw
manufacturer.
C
The adapter components may be supplied by Acuster Global, S.L.
C
The usage and safety recommendations given by the manufacturer
must be followed.
The feed is achieved by making the machine body rotate (with the hand placed in the knurled area). The recommended distance produced by the feed is a = 1 or 2 mm (see Figure
18). The feed limit is indicated by a mechanized line on the fastening bush shaft. If due to an excess of compression (feed + internal pressure) this line becomes visible (see Figure 18), turn slightly in the opposite direction to return to the previously-recommended distance.
WARNING !
It is recommended to avoid excess feed, especially in the pilot drill work phase, given that the drill could break specially at low revolutions.
Figure 18
3.2.5 Disassembly of the machine and accessories:
Once the mains has been perforated, move the chuckshaft up by turning the machine body counterclockwise. Disassemble the saddle adapter and drilling machine using the spanner designed for this purpose. The coupon resulting from drilling the main will have remained trapped by the pilot drill’s coupon retainer mechanism. To extract the coupon, disassemble the drill by loosening the Allen fastening stud. Remove the coupon through the upper part of the drill and fit it to the arbor hole saw again. See Figure 19.
WARNING !
Do not touch the coupon following drilling, especially if an electrical or pneumatic swivel gear has been used. Hot surfaces.
Figure 19
3.2.6 Connecting the branch connection:
Connect the branch connection to the threaded outlet of the saddle. Retighten the branch connection fasteners.
Page 20
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
- MODE OF USE
Revision: No. 4
20
3.3 DRILLING UNDER PRESSURE OVER CA-R BRANCH CONNECTIONS
3.3.1 Initial operations:
Before performing the drilling operations, ensure that you have all the necessary material and that it is in good condition.
C
Complete drilling machine.
C
Arbor hole saw (with pilot drill installed) matching the size of the hole saw to be used.
C
Hole saw of the diameter to be used.
C
Adapter (with washer) of the diameter of the thread matching the saddle to be installed.
C
Intermediate full bore valve, of the size corresponding to the saddle’s threaded outlet. Adapter fitting (if necessary).
C
Tools: 3 mm Allen key, adapter spanner, 17 mm open-end spanner, ½” ratchet wrench (manual drilling) and electrical or pneumatic swivel gear with chuckshaft adaptation elements (if applicable).
3.3.2 Branch connection installation:
The installation of the CA-R branch connection is performed placing the saddle and gasket on the pipe. Next, fasten the clamp between the saddle and mains (the hinge joints should remain above the saddle), equally tightening the two fastening bolts to ensure tightness.
For more information, refer to the Fitting Instructions included with the accessory.
3.3.3 Assembly of the cutoff valve: Figure 20
Install an intermediate valve (not supplied with the equipment). Screw it directly (or through an adapter fitting) over the CA-R branch connection previously installed on the line. Put the valve actuation lever in OPEN position.
WARNING !
The total height (h) of the branch connection saddle + selected intermediate valve and fitting (once assembled) must not exceed 210 mm. See Figure 21.
Figure 21
Page 21
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
Revision: No. 4
MODE OF USE - 21
3.3.4 Assembly of the drilling machine:
C
Set up the arbor hole saws with the pilot drill in the chuckshaft. Screw the hole saw matching the threaded outlet of the branch connection into the arbor hole saw. See Figure 22.
C
Choose the adapter that matches the thread of the saddle and screw it into the machine dome. See Figure 23.
This operation can be performed manually. If necessary, use the dome adapter spanner included with the equipment.
C
Select the position of the chuckshaft depending on the distance it will have to travel during drilling, placing the retention mechanism in the most appropriate opening of the three located on the shaft. See Figure 24.
Figure 22 Figure 23 Figure 24
C
Place the body of the machine in its upper position (unscrew it until the end travel mechanism is released). With the control mechanism of the intermediate valve in open position, now assemble the AcuDrill drilling machine, screwing it onto the valve installed over the saddle of the branch connection. The adapter must have the washer installed.
WARNING !
If the support face of the intermediate valve is not flat enough, apply Teflon tape to the adapter thread to achieve tightness.
Manually tighten the machine body. If necessary, retighten using the dome adapter spanner included with the equipment.
Page 22
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
- MODE OF USE
Revision: No. 4
22
3.3.5 Pressure test:
Once the drilling machine set and accessories are installed on the intermediate valve, perform a pressure test. To do so, apply compressed air through the venting valve to check tightness of the assembly (see Figure 25). Once the interior is pressurized, and with the venting valve closed, check for leaks in the threaded connections or the gasket at the mains head seat gasket using a spray detector or soapy water. Correct in case of leaks. Once the check is complete, open the venting valve to depressurize, then leaving it in the “closed” position.
Figure 25
3.3.6 Drilling the mains:
Once the pressure test is complete, lower the chuckshaft by rotating the machine body (with your hand in the knurled area), until the pilot drill makes contact with the pipe (the chuckshaft will have risen depending on the contact force: see measurement a of Figure
26). At this point, withdraw the tip of the drill from the pipe by approximately one turn. Now begin drilling the mains by activating the chuckshaft using the ratchet wrench, if drilling is manual, or through the electrical or pneumatic swivel gear.
SWIVEL GEAR
If an electrical actuation swivel gear (drilling machine) or pneumatic swivel gear (pneumatic, non-impact tool) is used, the following considerations must be taken into account:
C
The rotation speed must be that indicated by the hole saw manufacturer.
C
The adapter components may be supplied by Acuster Global, S.L.
C
The usage and safety recommendations given by the manufacturer
must be followed.
Feed is achieved by making the machine body rotate (with the hand placed in the knurled area). The recommended distance produced by the feed is a = 1 or 2 mm (see Figure
26) when drilling with the pilot drill. Once perforated with the drill, remember that distance a will be increased by the internal driving pressure. The feed limit is indicated by a mechanized line on the fastening bush shaft. If due to an excess of compression (feed + internal pressure) this line becomes visible (see Figure 26), turn slightly in the opposite direction to return to the previously-recommended distance. Ensure that the drilling is complete by making one or two additional turns.
Figure 26
Page 23
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
Revision: No. 4
MODE OF USE - 23
WARNING !
It is recommended to avoid excess feed, especially in the pilot drill work phase, given that the drill could break specially at low revolutions.
If a length longer than the machine’s travel is necessary, the drilling can be continued by moving the retention mechanism to the next opening above the one it was fastened to on the shaft (unless the highest anchoring has been in use). See Figure 24.
3.3.7 Disassembly of the machine and accessories:
Once the mains has been perforated, move the chuckshaft up by turning the machine body counterclockwise until the end travel mechanism is activated. Continue withdrawing the chuckshaft by pulling the retention mechanism out of the opening where it is located. To do so, first place the ratchet wrench on the end shaft ½” square and push down to facilitate the retention mechanism removal. Then, take control with the ratchet wrench of the moving up of the chuckshaft due to the pipeline pressure (refer to Figure 27). The chuckshaft will fully rise until the hole saw is positioned on the upper part of the dome.
Figure 27
WARNING !
Due to pipeline internal pressure the chuckshaft will be moved upwards. Take the necessary safety cautions to avoid any sort of accident during this operation.
Carefully open the venting valve to remove chip residues. Next, close the valve again. Then switch the intermediate valve to the CLOSED position. Disassemble the saddle adapter and drilling machine using the spanner designed for this purpose. The coupon resulting from drilling the mains will have remained trapped by the pilot drill’s coupon retainer mechanism. To extract the coupon, disassemble the drill by loosening the Allen fastening stud. Remove the coupon through the upper part of the drill and fit it to the arbor hole saw again. See Figure 28.
Figure 28
3.3.8 Connecting the branch connection:
Connect the branch connection to the appropriate outlet for the intermediate valve. Retighten the branch connection fasteners.
Page 24
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
- MODE OF USE
Revision: No. 4
24
3.4 PRESSURELESS DRILLING OVER ACUFLEX/BH525 BRANCH CONNECTIONS
3.4.1 Initial operations:
Before performing the drilling operations, ensure that you have all the necessary material and that it is in good condition.
C
Complete drilling machine.
C
Arbor hole saw (with pilot drill installed) matching the size of the hole saw to be used.
C
Hole saw of the diameter to be used.
C
Adapter (with washer) of the diameter of the thread matching the saddle to be installed.
C
Tools: 3 mm Allen key, adapter spanner, 17 mm open-end spanner, ½” ratchet wrench (manual drilling) and electrical or pneumatic swivel gear with chuckshaft adaptation elements (if applicable).
3.4.2 Branch connection installation:
Installation of the ACUFLEX branch connection is performed by placing the threaded outlet in the opening of the upper sector. Next, set the upper sector and inferior sector through the hinge mechanism they are equipped with and place them over the mains, in the desired position and orientation. Tighten the two fastening bolts to ensure tightness.
For more information, refer to the Fitting Instructions included with the accessory.
Figure 29
3.4.3 Drilling machine assembly:
C
Set up the arbor hole saws with the pilot drill in the chuckshaft. Screw the hole saw matching the threaded outlet of the branch connection into the arbor hole saw. See Figure 30.
C
Choose the adapter that matches the thread of the saddle and screw it into the machine dome. See Figure 31.
This can be performed manually. If necessary, use the dome adapter spanner included with the equipment.
Page 25
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
Revision: No. 4
MODE OF USE - 25
Figure 30 Figure 31 Figure 32
C
For this type of branch connection and intervention, position the retention mechanism in the first (lowest) of the three anchoring openings on the chuckshaft. See Figure 32.
C
Place the body of the machine in its upper position (unscrew it until the end travel mechanism is released. Now install the AcuDrill drilling machine screwing it onto the saddle of the branch connection. The adapter must have the washer installed.
WARNING !
If the support face of the saddle is not flat enough, apply Teflon tape to the adapter thread to achieve tightness.
Manually tighten the machine body. If necessary, retighten using the dome adapter spanner included with the equipment.
3.4.4 Drilling the mains:
Once the machine set and saddle accessories are assembled, lower the chuckshaft by rotating the machine body (with your hand in the knurled area), until the pilot drill makes contact with the pipe (the chuckshaft will have risen depending on the contact force: see measurement a of Figure 33). At this point, withdraw the tip of the drill from the pipe by approximately one turn. Now begin drilling the mains by activating the chuckshaft using the ratchet wrench, if drilling is manual, or through the electrical or pneumatic swivel gear.
Page 26
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
- MODE OF USE
Revision: No. 4
26
SWIVEL GEAR
If an electrical actuation swivel gear (drilling machine) or pneumatic swivel gear (pneumatic, non-impact tool) is used, the following considerations must be taken into account:
C
The rotation speed must be that indicated by the hole saw manufacturer.
C
The adapter components may be supplied by Acuster Global, S.L.
C
The usage and safety recommendations given by the manufacturer must
be followed.
The feed is achieved by making the machine body rotate (with the hand placed in the knurled area). The recommended distance produced by the feed is a = 1 or 2 mm (see Figure
33). The feed limit is indicated by a mechanized line on the fastening bush shaft. If due to an excess of compression (feed + internal pressure) this line becomes visible (see Figure 33), turn slightly in the opposite direction to return to the previously-recommended distance.
WARNING !
It is recommended to avoid excess feed, especially in the pilot drill work phase, given that the drill could break specially at low revolutions.
Figure 33
3.4.5 Disassembly of the machine and accessories:
Once the mains has been perforated, move the chuckshaft up by turning the machine body counterclockwise. Disassemble the saddle adapter and drilling machine using the spanner designed for this purpose. The coupon resulting from drilling the mains will have remained trapped by the pilot drill’s coupon retainer mechanism. To extract the coupon, disassemble the drill by loosening the Allen fastening stud. Remove the coupon through the upper part of the drill and fit it to the arbor hole saw again. See Figure 34.
WARNING !
Do not touch the coupon following drilling, especially if an electrical or pneumatic swivel gear has been used. Hot surfaces.
Figure 34
3.4.6 Connecting the branch connection:
Connect the branch connection to the threaded outlet of the saddle. Retighten the fasteners.
Page 27
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
Revision: No. 4
MODE OF USE - 27
3.5 DRILLING UNDER PRESSURE OVER STEEL FITTINGS FOR GAS PIPELINES: 3-WAY TEES AND THREADED O-RINGS OF 1½” - 2"
3.5.1 Initial operations:
Before performing the drilling operations, ensure that you have all the necessary material and that it is in good condition.
C
Complete drilling machine.
C
Arbor hole saw (with pilot drill installed) matching the size of the hole saw to be used.
C
Hole saw of the diameter to be used.
C
Drilling machine dome-sandwich valve adapter.
C
Sandwich valve with adapter to the fitting thread (1½” or 2").
C
Tool for internal plug installation.
C
Tools: 3mm & 5mm Allen keys, adapter spanner, 17mm open­end spanner, ½” ratchet wrench (manual drilling) and hydraulic or pneumatic swivel gear with chuckshaft adaptation elements (if applicable), ratchet wrench 3/4".
3.5.2 Fitting installation:
Install the steel fitting (3-way tee or TOR-threaded O-ring) following the procedure established by the Gas Company.
It is recommended to remove the exterior plug but keep the internal plug (without o-ring) fitted in position during the fitting preparation and welding. Once the welds cool, remove the internal plug and install its O-ring.
3.5.3 Sandwich valve installation:
Figure 35
C
Remove the grease from the fitting internal thread.
WARNING !
Use Teflon® tape of equivalent to the sandwich valve adapter thread to achieve tightness. Check good condition of the upper and lower sandwich valve O-rings.
C
Install the 2½” sandwich valve with the adapter corresponding the fitting thread size (1½” or 2"). See Figure 35. The sandwich valve gate shall be in OPEN position.
3.5.4 Assembly of the drilling machine:
C
Set up the arbor hole saws with the pilot drill in the chuckshaft. Screw the hole saw matching the threaded outlet of the branch connection into the arbor hole saw. See Figure 36.
Page 28
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
- MODE OF USE
Revision: No. 4
28
C
Screw in the sandwich valve adapter to the drilling machine dome. See Figure 37.
This operation can be performed manually. If necessary, use the dome adapter spanner included with the equipment.
Figure 36 Figure 37 Figure 38
C
Select the position of the chuckshaft depending on the distance it will have to travel during drilling, placing the retention mechanism in the most appropriate opening of the three located on the shaft (middle orifice for 2" TOR and upper orifice for 1½” and 2" 3-way tees). See Figure 38.
C
Place the body of the machine in its upper position (unscrew it until the end travel mechanism is released). Now assemble the AcuDrill drilling machine, screwing it onto the sandwich valve installed over the fitting.
WARNING !
Manually tighten the machine body. If necessary, retighten using the dome adapter spanner included with the equipment.
3.5.5 Pressure test:
Once the drilling machine set and accessories are installed on the sandwich valve, perform a pressure test. To do so, apply compressed air through the venting valve to check tightness of the assembly (see Figure 39). Once the interior is pressurized, and with the venting valve closed, check for leaks in the threaded connections or the gasket at the mains head seat gasket using a spray detector or soapy water. Correct in case of leaks. Once the check is complete, open the venting valve to depressurize, then leaving it in the “closed” position.
Figure 39
Page 29
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
Revision: No. 4
MODE OF USE - 29
3.5.6 Drilling the mains:
Once the pressure test is complete, lower the chuckshaft by rotating the machine body (with your hand in the knurled area), until the pilot drill makes contact with the pipe (the chuckshaft will have risen depending on the contact force: see measurement a of Figure
40). At this point, withdraw the tip of the drill from the pipe by approximately one turn. Now begin drilling the mains by activating the chuckshaft using the ratchet wrench, if drilling is manual, or through the pneumatic swivel gear.
SWIVEL GEAR
If a pneumatic swivel gear (pneumatic, non-impact tool) is used, the following considerations must be taken into account:
C
The rotation speed must be that indicated by the hole saw manufacturer.
C
The adapter components may be supplied by Acuster Global, SL.
C
The usage and safety recommendations given by the manufacturer must
be followed.
Feed is achieved by making the machine body rotate (with the hand placed in the knurled area). The recommended distance produced by the feed is a = 1 or 2 mm (see Figure 40) when drilling with the pilot drill. Once perforated with the drill, remember that distance a will be increased by the internal driving pressure. The feed limit is indicated by a mechanized line on the fastening bush shaft. If due to an excess of compression (feed + internal pressure) this line becomes visible (see Figure 40), turn slightly in the opposite direction to return to the previously-recommended distance. Ensure that the drilling is complete by making one or two additional turns.
WARNING !
It is recommended to avoid excess feed, especially in the pilot drill work phase, given that the drill could break specially at low revolutions.
Figure 40 Figure 41
Page 30
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
- MODE OF USE
Revision: No. 4
30
3.5.7 Plugging the fitting:
Once the mains has been perforated, move the chuckshaft up by turning the machine body counterclockwise until the hole saw is positioned in the upper part of the dome. On that position, the chuckshaft does not allow the sandwich valve to be closed. Continue withdrawing the chuckshaft by pulling the retention mechanism out of the opening where it is located. To do so, first place the ratchet wrench on the end shaft ½” square and push down to facilitate the retention mechanism removal. Then, take control with the ratchet wrench of the moving up of the chuckshaft due to pipeline pressure (refer to Figure 41). The chuckshaft will fully rise until the hole saw is positioned on the upper part of the dome.
WARNING !
Due to pipeline internal pressure the chuckshaft will be moved upwards. Take the necessary safety cautions to avoid any sort of accident during this operation.
Put in the close position the sandwich valve to allow the disassembling of the drilling machine and later internal plug installation. Carefully open the venting valve to remove chip residues and depressurize.
3.5.8 Disassembly of the machine and accessories:
Before disassembling the drilling machine, check sandwich valve tightness opening the venting valve. No fluid must flow out except the one which remains inside before the sandwich valve closing. Investigate the reason of any suspicious leakage. Once carried out the above check, close again the venting valve. Disassemble the drilling machine and its sandwich valve adapter using the spanner designed for this purpose. The coupon resulting from drilling the mains will have remained trapped by the pilot drill’s coupon retainer mechanism. To extract the coupon, disassemble the drill by loosening the Allen fastening stud. Remove the coupon through the upper part of the drill and fit it to the arbor hole saw again. See Figure 42.
3.5.9 Installation of the fitting internal plug:
C
Fit the fitting internal plug (ensure that the O-ring is fitted) in the plug installation tool.
C
Assembly the plug installation tool (with the plug on it) over the sandwich valve. See Figure 43.
This operation can be carried out by hand. If necessary, use the dome adapter spanner included with the equipment.
C
Open the sandwich valve.
C
Move downwards the installation plug tool shaft as far the plug makes contact with the fitting (3-way tee or TOR).
Page 31
USER MANUAL
AcuDrill
DRILLING MACHINE
Edition: June 2016
Revision: No. 4
MODE OF USE - 31
Figure 42 Figure 43 Figure 44
C
Once the plug and fitting are in contact, turn the shaft clockwise by means of a 3/4" ratchet wrench, open-end spanner, etc. to screw in the plug into its fitting location. After several turns, the torque resistance will dramatically increase indicating that the plug has completed its screwing travel. See Figure 44.
C
Move the shaft upwards: pull up without turning.
C
Disassembly the plug installation tool and the sandwich valve.
C
Install the fitting exterior plug following the Gas Company established procedure.
Page 32
USER MANUAL
AcuDrill DRILLING MACHINE
Edition: June 2016
- MODE OF USE Revision: No. 4 32
3.6 DRILLING UNDER PRESSURE OVER STEEL FITTINGS FOR GAS PIPELINES: 3-WAY TEES OF 1"
3.6.1 Initial operations:
Before performing the drilling operations, ensure that you have all the necessary material and that it is in good condition.
C Complete drilling machine. C Arbor hole saw with 10mm drill installed. C Drilling machine dome-sandwich valve 1" adapter. C Sandwich valve 1". C Tool for internal plug installation. C Tools: 3mm Allen key, adapter spanner, 17mm open-end spanner, ½” ratchet
wrench (manual drilling) and hydraulic or pneumatic swivel gear with chuckshaft adaptation elements (if applicable).
3.6.2 Fitting installation:
Install the steel fitting following the procedure established by the Gas Company.
It is recommended to remove the exterior plug but keep the internal plug (without o-ring) fitted in position during the fitting preparation and welding. Once the welds cool, remove the internal plug and install its O-ring.
3.6.3 Sandwich valve installation:
C Clean the fitting internal thread (the internal thread of the 3-Way Tee should be
free of grease, oil, etc., since otherwise chips produced when drilling could remain).
C Install the 1” sandwich valve. See Figure 45.
WARNING !
Check good condition of the sandwich valve O-ring.
C The sandwich valve gate shall be in OPEN position.
Figure 45
Page 33
USER MANUAL
AcuDrill DRILLING MACHINE
Edition: June 2016 Revision: No. 4 MODE OF USE - 33
3.6.4 Assembly of the drilling machine:
C Set up the arbor with the 10mm drill in the chuckshaft. See Figure 46. C Screw the dome adapter into the drilling machine dome. See Figure 47.
This operation can be performed manually. If necessary, use the dome adapter spanner included with the equipment.
Figure 46 Figure 47 Figure 48
C Select the position of the chuckshaft depending on the distance it will have to
travel during drilling, placing the retention mechanism in the most appropriate opening of the three located on the shaft: in our case on the lower shaft orifice. See Figure 48.
C Place the body of the machine in its upper position (unscrew it until the end travel
mechanism is released). Now assemble the AcuDrill drilling machine, screwing it onto the sandwich valve installed over the fitting.
WARNING !
Manually tighten the machine body. If necessary, retighten using the dome adapter spanner included with the equipment.
3.6.5 Pressure test:
Once the drilling machine set and accessories are installed on the sandwich valve, perform a pressure test. To do so, apply compressed air through the venting valve to check tightness of the assembly (see Figure 49). Once the interior is pressurized, and with the venting valve closed, check for leaks in the threaded connections using an spray detector or soapy water. Correct in case of leaks. Once the check is complete, open the venting valve to depressurize, then leaving it in the “closed” position.
Figure 49
Page 34
USER MANUAL
AcuDrill DRILLING MACHINE
Edition: June 2016
- MODE OF USE Revision: No. 4 34
3.6.6 Drilling the mains:
Once the pressure test is complete, lower the chuckshaft by rotating the machine body (with your hand in the knurled area), until the drill makes contact with the pipe (the chuckshaft will have risen depending on the contact force: see measurement a of Figure
50). At this point, withdraw the tip of the drill from the pipe by approximately one turn. Now begin drilling the mains by activating the chuckshaft using the ratchet wrench, if drilling is manual, or through the hydraulic or pneumatic swivel gear.
SWIVEL GEAR
If a hydraulic or pneumatic swivel gear (pneumatic, non-impact tool) is used, the following considerations must be taken into account:
C The rotation speed must be that indicated by the hole saw manufacturer. C The adapter components may be supplied by Acuster Global, SL. C The usage and safety recommendations given by the manufacturer must
be followed.
Feed is achieved by making the machine body rotate (with the hand placed in the knurled area). The recommended distance produced by the feed is a = 1 or 2 mm (see Figure
40) when drilling with the pilot drill. Once perforated with the drill, remember that distance a will be increased by the internal driving pressure. The feed limit is indicated by a mechanized line on the fastening bush shaft. If due to an excess of compression (feed + internal pressure) this line becomes visible (see Figure 40), turn slightly in the opposite direction to return to the previously-recommended distance. Ensure that the drilling is complete by making one or two additional turns.
Figure 50
WARNING !
It is recommended to avoid excess feed, given that the drill could break specially at low revolutions.
3.6.7 Plugging the fitting:
Once the mains has been perforated, move the chuckshaft up by turning the machine body counterclockwise until actuate the end travel mechanism. On that position, the chuckshaft will fully rise until the drill is positioned on the upper part of the dome. Put in the CLOSE position the sandwich valve to allow the disassembling of the drilling machine and later internal plug installation.
WARNING !
Ensure that the gate of the sandwich valve does not touch the drill when closing to prevent damage that could occur in the gate.
Carefully open the venting valve to remove chip residues and depressurize. Close the again the venting valve.
Page 35
USER MANUAL
AcuDrill DRILLING MACHINE
Edition: June 2016 Revision: No. 4 MODE OF USE - 35
3.6.8 Disassembly of the machine and accessories:
Before disassembling the drilling machine, check sandwich valve tightness opening the venting valve. No fluid must flow out except the one which remains inside before the sandwich valve closing. Investigate the reason of any suspicious leakage. Once carried out the above check, close again the venting valve. Disassemble the dome adapter as well as the drilling machine using the spanner designed for this purpose.
3.6.9 Installation of the fitting internal plug:
To remove the sandwich valve, the 3-Way Tee incorporates an internal thread that hosts a plug. Perform the following procedure:
C Fit the fitting internal plug (ensure that the O-ring is fitted) in the plug installation
tool. See Figure 51.
C Assembly the plug installation tool (with the plug on it) over the sandwich valve.
See Figure 52.
Check that the plug has been held in the tool and does not fall under its own weight.
C Open the sandwich valve.
Figure 51 Figure 52 Figure 53 Figure 54
Page 36
USER MANUAL
AcuDrill DRILLING MACHINE
Edition: June 2016
- MODE OF USE Revision: No. 4 36
C Move downwards the installation plug tool shaft as far the plug makes contact
with the fitting.
C Once the plug and fitting are in contact, turn the shaft as far as the end travel.
See Figure 53.
C Move the shaft upwards: pull up without turning. C Disassembly the plug installation tool and the sandwich valve. C Finish to screw in the inner plug so that it is slightly inserted into the 3-Way Tee
internal body. See Figure 54.
C Install the fitting exterior plug following the Gas Company established procedure.
Page 37
USER MANUAL
AcuDrill DRILLING MACHINE
Edition: June 2016 Revision: No. 4
MAINTENANCE - 37
SECTION 4: MAINTENANCE
4.1 GENERAL INFORMATION As a general principle, we recommend maintaining the drilling machine (and all
components and accessories) in perfect conditions of cleanliness and lubrication, ready for use, and stored in their original carrying case. The preventive maintenance for the equipment is minimal; cleaning and lubricating the chuckshaft, the spindle threads and machine dome is sufficient. Monitor the cutting condition of the drill and hole saws before usage. It is recommended they be replaced in case of fault. On a regular basis, and especially when the equipment is used over a prolonged period, we recommend it be sent to the ACUSTER GLOBAL, SL. After-Sales Service Department for a complete inspection (generally, with time and use, the O-rings and gaskets need to be changed).
Page 38
USER MANUAL
AcuDrill DRILLING MACHINE
Edition: June 2016
- TECHNICAL CHARACTERISTICS Revision: No. 4 38
SECTION 5: TECHNICAL CHARACTERISTICS
Usage: : Drilling of mains made of steel, gray cast iron, ductile
casting, asbestos cement, clay, polyester, PVC, PE, PP, etc. Acuster branch connections : ACUSTOP-R, CA-R and ACUFLEX. Other brands : All types of saddles with threaded
outlets 3/4”, 1”, 1-1/4”, 1-1/2” and 2”
BSP. Fittings for gas : 3-way tees and TORs of 1½” and 2". Maximum drilling capacity : Up to
N. 48 mm
Maximum range : 117 mm from the machine body
124 mm from the chuckshaft (moving
the fastening openings).
241 mm Total, adding range travel
and fastening shaft
Service pressure : 16 bar for water mains
5 bar for gas mains Operation : Manual by means of a ratchet wrench
provided with a revolving handle.
Optionally by means of an electric or
pneumatic-actuated swivel gear. Total equipment weight : 6.9 kg (with carrying case and without
adapters) Outer dimensions : Carrying case:
Length: 700 mm
Width: 260 mm
Height: 105 mm
Weight of optional components:
Kit saddle adapter 3/4" : 0.590 Kg Kit saddle adapter 1" : 0.555 Kg Kit saddle adapter 1-1/4" : 0.575 Kg Kit saddle adapter 1-1/2" : 0.575 Kg Kit saddle adapter 2" : 0.640 Kg Dome-sandwich valve adapter : 1.110 Kg 2½” sandwich valve w/o adapter : 7.395 kg 1½” sandwich valve adapter : 0.910 Kg 2" sandwich valve adapter : 0.835 Kg Plug installation tool : 2.075 Kg Electric propeller (rotary machine) : 6.690 Kg (with shaft adapter and t ransport case)
Weight of kit for 3-Way Tees 1" (#141143):
Total kit weight : 2.5 Kg approx.
Page 39
USER MANUAL
AcuDrill DRILLING MACHINE
Edition: June 2016 Revision: No. 4
TECHNICAL CHARACTERISTICS - 39
RESERVED FOR NOTES
Loading...