General Air Products DAP500, DAP1000, DAP2000 Installation Manual

Page 1
DRY AIR PAC™
FACTORY MUTUAL APPROVED
AIR DRYING UNITS FOR REFRIGERATED AREA AND
DRY PIPE SPRINKLER SYSTEMS
MODELS DAP500, DAP1000 & DAP2000
ENGINEERED COMPRESSED AIR DRYING SYSTEMS FOR COLD
STORAGE/ FREEZER ROOM DRY PIPE SPRINKLER SYSTEMS
MODEL NUMBER SYSTEM
CAPACITY
DAP500 500 GALLON 2 10 375LBS DAP1000 1000 GALLON 5 20 500LBS DAP2000 2000 GALLON 5 27 550LBS
COMPRESSOR
HORSEPOWER
DRYER RATING
SCFM
APPROXIMATE
SHIPPING WT.
N:\Work\Engineering\Product Files\DRY AIR PAC \INSTRUCTIONS\DAP-INSTRUCTION MANUAL­011606 revision.doc
Page 2
INSTALLATION
1. Install DRY AIR PAC in a clean, dry location, with ambient temperatures at all times above 50o F., adjacent to the sprinkler system piping outside the cold room. NO MORE THAN 3 SYSTEMS ARE TO BE CONNECTED TO A SINGLE DRY AIR PAC;
CAPACITY OF EACH SYSTEM SHOULD NOT EXCEED THE RATED CAPACITY OF THE DRY AIR PAC. The unit must be accessible at the front for servicing all major
components. The unit should be leveled and anchored to the floor (the vibration isolators supplied with the unit MUST be utilized). If the location is below freezing at any time the
unit must be enclosed in a separate, heated enclosure to keep the temperature above 50o F.
NOTE:
Do not install the Dry Air Pac in an area where ammonia vapors or similar contaminants exist. The equipment and desiccant can be damaged by ammonia and other vapors. Locate the Dry Air Pac to ensure no ammonia or other vapors are drawn into the intake.
2. The unit has been filled with oil for test purposes, it is strongly recommended to change this oil after the initial run in period on site. 2 Quarts of oil are shipped with each Dry Air Pac for this purpose. When adding or replacing oil only use General Part Number ACPO1Q Specially
Formulated Compressor Oil.
Oil requirements are as follows:
DAP500 22ounces DAP1000 Approximately 1 1/2 quarts (middle of oil level window) DAP2000 Approximately 1 1/2 quarts (middle of oil level window)
Lightweight lubricants should not be used nor heavy gear oils.
3. Connect proper supply voltage to the starter line terminals in the control panel.
Note: Wire size must be capable of carrying the unit load, without dropping the voltage at the terminals below normal operating levels. Double check incoming wire size; if there are any questions please call us, we can assist you in ensuring you have selected the correct size. Be sure the control power transformer has its primary side jumpers
connected to match the incoming supply voltage. Each unit is run at the factory and results noted for reference so if there are any questions please contact the factory. Motor rotation will always need to be checked. After connecting the power, use the on/off switch on the front of the unit to turn on the compressor briefly to check rotation. An indicating arrow is on the compressor flywheel. If rotation is not correct on three phase units, reverse any two leads. On single phase units refer to the motor nameplate, however it should not require changing as it has been run at
N:\Work\Engineering\Product Files\DRY AIR PAC \INSTRUCTIONS\DAP-INSTRUCTION MANUAL­011606 revision.doc
Page 3
the factory. If you feel this is required please consult with factory personnel as there may have been changes made to the unit, which should be discussed with the factory PRIOR TO starting the unit. Please ensure sufficient power is available at the unit. Long feed line runs can cause voltage drops, which can affect the performance of the unit and damage the motor.
ONLY QUALIFIED ELECTRICAL PERSONNEL SHOULD CONNECT THE UNIT.
4. Each DRY AIR PAC is shipped with desiccant installed. The unit will need to be run for a minimum of 8 hours PRIOR TO any air being used from the Dry Air Pac in the sprinkler system. Air should be bled from the tee after the regulator in an amount to allow the compressor to run NO MORE than 4 times per hour.
NOTE: If you are connecting to an old piping system there may be existing le aks in the system which cause the compressor to cycle more frequently than 4 times per hour. If this is the case there are three suggestions: 1. Fix the leaks. 2. Add a second DRY AIR PAC to provide enough air to bring the cycle times back to less than 4 times per hour. 3. Add a receiver, which can act as a storage buffer to supply more air to the system. This should be discussed with the factory personnel, as it will only work in cases where minor leaks are involved.
5. The DRY AIR PAC is supplied with a removable, threaded inlet air filter so that if the AHJ requires the air to be drawn from the cold room this can be done. These units have been FM
Approved with air NOT being drawn from the freezer room. Therefore WE DO NOT RECOMMEND they be connected to the freezer room. The Dry Air Pac is designed so
that performance will not be adversely affected with the filter left in place directly on the compressor. If connected in the cold room, the piping back to the compressor must be 1 1/2” minimum pipe size for this run, bushed down directly at the compressor inlet elbow. This pipe must be heat traced and insulated. The filter should be mounted on the inlet end of this pipe directly in the cold room. The interconnecting piping should be clean of any foreign matter, which may be drawn into the compressor and cause damage.
6. There is a 1/2” pipe plug installed in the outlet tee. This is provided as a point to install a dew point monitoring device, should you require one. This is after the regulator and gives you the pressure dew point of the system. Be careful to follow the dew point monitor manufacturer’s recommendations as far as installation is concerned.
7. The DRY AIR PAC outlet is from the combination particulate filter with pressure regulator, mounted on the right lower side of the unit facing the control panel. Connect this outlet to the sprinkler system air inlet.
8. The DRY AIR PAC has a UL/FM approved Air Maintenance Device built into the unit. It will require adjustment of the regulator to your system requirements. It replaces the final regulator, which should be left fully open once the Air Maintenance Device has been adjusted and valved into the line. If connecting more than one system to the unit, the Air Maintenance
N:\Work\Engineering\Product Files\DRY AIR PAC \INSTRUCTIONS\DAP-INSTRUCTION MANUAL­011606 revision.doc
Page 4
Device should be left valved out of the system and the individual AMD’s used to control each system should be utilized.
NOTE: Leaks in the piping system will affect the pump up time of the system. The DRY AIR PAC has been factory tested to produce the published capacity.
9. An integral electronic drain valve is installed on each unit. The drain is pre-set when the unit leaves the factory. If necessary you can adjust the time between openings and the length of time the valve is open using the control knobs located above the hour meter on the front of the control panel. Under normal circumstances the maximum time between openings should be sufficient. If more frequent openings are required due to excessive compressor operation simply decrease the duration between openings. The On/Off - Manual Test switch can be used to check operation.
START UP
AS NOTED PREVIOUSLY - The unit must run for a minimum of 8 hours PRIOR TO any air being taken from the Dry Air Pac into the sprinkler system. Air should be bled from the tee after the regulator in an amount to allow the compressor to run NO MORE than 4 times per hour for this period.
1. With all the connections made as described in INSTALLATION, the unit is ready to start. With the valve ahead of the coalescing filter closed, turn the unit on with the switch on the front of the control panel. The compressor should start to fill the receiver tank and the tank pressure gauge on the front of the control panel should indicate the pressure. The unit should pressurize the receiver to approximately 100psig and then shut off.
Note:
Do not adjust the pressure switch on the unit. It is factory set at the values required for correct operation of the unit. Warranty may be void if the pressure switch is reset.
The unloader line will operate to bleed off the pressure in the line from the compressor to the receiver inlet so that the compressor does not start loaded. Air will exhaust from the small valve at the side of the switch immediately after the compressor is shut off. This should not occur when the compressor is running or for long periods of time after the compressor shuts off. If this occurs, contact the factory.
2. Open the valve ahead of the coalescing filter and pressurize the rest of the DRY AIR PAC. The Air Maintenance Device should be in bypass mode, with the 3/4” valve open.
N:\Work\Engineering\Product Files\DRY AIR PAC \INSTRUCTIONS\DAP-INSTRUCTION MANUAL­011606 revision.doc
Page 5
3. The outlet valve should now be open to allow air to begin to purge into the sprinkler system. The final regulator is factory set to 40 psig. The regulator should always be set to maintain pressure on the drying tower between 70 to 100 psig. At no time should the regulator be opened to bleed all pressure off the drying system, as this will adversely affect drying quality.
4. Open an inspection test point on the far end of the sprinkler system to allow the current wet ai r in the sprinkler system to be purged out of the system. This leak should be adjusted to allow the compressor to run, after filling the system to pressure, NO MORE than 4 times per hour. Allow this to run for 24 hours then close the inspection test port to allow the system to function normally.
5. The automatic drain is set to a mid position at the factory. You should not need to adjust this frequency or duration but if you do, be aware that the quicker the cycle and the longer the open time, the more air will be used and the less will be available at the unit outlet. A light on the control panel will indicate when the drain is operating. A length of tubing is provided at the drain valve outlet for piping to a convenient drain water disposal position.
BE SURE TO PIPE THIS DISCHARGE TO A POSITION WHERE THE DISCHARGED AIR AND WATER WILL NOT BE A HAZARD TO PERSONNEL.
6. Once the system is filled the Air Maintenance Device will need to have the 3/4” valve closed, the two 1/4” valves opened and the regulator set for final system maintenance pressure. The final regulator should then be opened to full to allow the Air Maintenance Device to be the controller.
7. REMEMBER - After the 24-hour period, close the inspection port.
OPERATION
The following is a description of the operation of the DRY AIR PAC.
Typically air is drawn into the compressor intake through the threaded inlet filter. . These units
have been FM Approved with air NOT being drawn from the freezer room. Therefore WE DO NOT RECOMMEND they be connected to the freezer room. If required by the
AHJ, air is drawn in from the cold room through the inlet filter installed inside the cold room. This air then travels to the compressor intake via 1 1/2” minimum line size piping. Upon reaching the compressor, it is drawn into the compressor intake and compressed through the compression cycle and then discharged into the intercooler. The air then crosses over into the air cooled aftercooler where ambient air being pulled over the coil cools the hot compressed air. Water in the compressed air will now drop out of the air as it cools and drops down into the receiver. A check valve in this line prevents any back flow to the compressor. The water settles
N:\Work\Engineering\Product Files\DRY AIR PAC \INSTRUCTIONS\DAP-INSTRUCTION MANUAL­011606 revision.doc
Page 6
into the bottom of the receiver and is discharged from the receiver when the automatic drain valve opens. This air then leaves the receiver and goes into the coalescing filter where it has entrained oil removed. This air then travels to the dryer inlet. The air is diverted to the corresponding tank via two solenoid valves. The air travels upwards through the desiccant bed and exits through the top of the tank. A portion of this dried air is diverted to the opposite tank via the purge valve and gauge/orifice combination. The pressure gauge setting is factory set (see following settings for each model). If re-setting is required, consult the factory for assistance. The purge air enters the top of the tower and travels in a downward direction to pick up the water molecules from the desiccant as the pressure drops to atmosphere. The wet purge air then exits the bottom of the tank and is vented to atmosphere via the purge mufflers. These mufflers act to quiet the discharging air and also reduce the noise when the towers depressurize. These mufflers are removable for cleaning with soap and water periodically. Cleaning will ensure no build up, which will create back pressures in the tanks and decrease dryer performance. Both inlet and outlet of the tanks have screens to retain the desiccant. The exiting air then goes to the Air Maintenance Device. (See Start Up above for operating positions). From the Air Maintenance Device the air goes into the final filter regulator. The air up to this point has been at 70 – 100 psig. When it leaves the filter regulator it is reduced to system pressure.
NOTE: THE DRYER MUST OPERATE AT THE HIGHER PRESSURE IN ORDER TO FUNCTION CORRECTLY. THE AIR MAINTENANCE DEVICE REGULATOR MUST BE SET AND VALVED INTO THE SYSTEM.
SETTING PURGE PRESSURE
The purge pressure set valve is located between the two tanks just over the top of the control panel. This valve is pre-set at the factory, however should it need to be adjusted for any reason, the following listing shows the correct set pressures.
DAP500 20psig DAP1000 30psig DAP2000 27psig
COALESCING FILTER - OPERATION
The coalescing filter is there to protect the desiccant dryer from oil carryover from the compressor. The filter has a built in differential pressure indicator with three color bands. Green is normal condition, yellow is warning that the element is going to need to be replaced, and red indicates the filter is overdue for replacement.
N:\Work\Engineering\Product Files\DRY AIR PAC \INSTRUCTIONS\DAP-INSTRUCTION MANUAL­011606 revision.doc
Page 7
The filter has a built in automatic drain, which in normal service will expel accumulated oil or moisture from the bottom of the bowl. The drain can be tested by pushing up on the needle valve stem, which is in the mouth of the black outlet nipple on the bottom of the filter.
N:\Work\Engineering\Product Files\DRY AIR PAC \INSTRUCTIONS\DAP-INSTRUCTION MANUAL­011606 revision.doc
Page 8
SERVICE KITS ARE AVAILABLE AS DETAILED BELOW. MODEL AND SERIAL NUMBERS ARE REQUIRED WHEN ORDERING SERVICE KITS
KIT# KSMB01 Compressor Intake Filter Element(s),
Coalescing Filter Element, Particulate After Filter Element and Compressor Oil
KIT# KAMA01 Same as Kit # KSMB01 and full
desiccant charge for both dryer towers
OPERATING SEQUENCE - DRYER
The dryer operates on a 4-minute total cycle. There are four valves at the inlet manifold, and four at the outlet manifold. The timing cycle diagram shows the sequence of operation of the four inlet valves. The outlet valves are check valves, which sequence automatically with the operation of the inlet valves. SV1 and SV2 are the inlet valves to the towers, SV3 and SV4 are the opposite purge valves such that when the left tower is drying and its inlet valve is open, the purge valve on that tower is closed.
0 min 2 min 4 min A B SV1
A B SV2
A B X SV3 X
A SV4 B X X
A=VALVE CLOSED B=VALVE OPEN X = 15 seconds
With the unit turned on and the tank pressurized, air is ready to be used from the unit. As air is withdrawn from the unit into the sprinkler system, the pressure will drop and the pressure switch will start the compressor. As the compressor runs, the dryer is energized. The drying tower is indicated by a light on the front of the panel, as shown in the mimic panel. The drying tower will show tank pressure and the opposite tank, when purging will show no pressure; when repressurizing prior to switch over, it will show tank pressure. The purge valve can only be
N:\Work\Engineering\Product Files\DRY AIR PAC \INSTRUCTIONS\DAP-INSTRUCTION MANUAL­011606 revision.doc
Page 9
adjusted during the time the off line tower is purging and is showing no pressure. At this time, if necessary, adjust the purge pressure to the value in the above table. The dryer cycle timer runs only when the compressor is running and accumulates time so that the length of the cycle on any one tower does not get out of line with its normal operation and does not saturate one desiccant bed.
The frequency of change for the oil, filter elements and desiccant is highly dependent upon the following:
Number of times the unit has to operate to satisfy the system air requirement. The tighter the system, the less the unit will have to run.
Cleanliness of the environment in which the compressor is located.
Maintenance schedule for the equipment.
As the desiccant will degrade (age) slightly over time, it is recommended that the desiccant be changed once every year.
Consult the factory for type and quantity per unit.
ADDITIONAL SPECIFICATIONS
MODEL COMPRESSOR
HP
DAP500 2 10 2.9 AMPS 5.8 AMPS 12 GA 12 GA DAP1000 5 20 6.2 AMPS 12.4 AMPS 12 GA 10 GA* DAP2000 5 27 6.2 AMPS 12.4 AMPS 12 GA 10 GA*
*IF UNDER 50’ RUN 12 GA CAN BE USED HOWEVER, CHECK VOLTAGE WHILE RUNNING TO ENSURE NO UNDERVOLTAGE CONDITION EXISTS. FOR RUNS OVER 100’ INCREASE WIRE SIZE TO CORRECT FOR VOLT DROPS.
DRYER RATING CFM
CURRENT LOAD 460V
CURRENT LOAD 230V
WIRE SIZE 460V
WIRE SIZE 230V
N:\Work\Engineering\Product Files\DRY AIR PAC \INSTRUCTIONS\DAP-INSTRUCTION MANUAL­011606 revision.doc
Page 10
DESICCANT REPLACEMENT
NOTE: You will need the following in order to service the unit: Annual Service Kit - “General” part number: KAMA01
1. Close the outlet valve of the unit and turn the power to the unit off.
2. Depressurize the unit completely by opening the petcock on the bottom of the receiver and checking the pressure gauges to ensure all air is removed. If air remains in the desiccant tanks, pull on the relief valve toggles to depressurize the tanks.
ALL PRESSURE MUST BE OUT OF THE UNIT PRIOR TO WORKING ON THE
UNIT.
3. The tanks have separate desiccant fill and drain ports at the top and bottom.
TANK OUTLET
FILL PORT
DRAIN PORT
TANK INLET
4. Once the pressure has been removed from each tank, remove the lower (drain) port plug. Desiccant will start to drop out of the 1/2” port. It is easiest to vacuum the desiccant out with a shop vac; however, the desiccant will drop out of the tower. You may have to probe the outlet with a thin probe in order to keep the desiccant from jamming together at the port. The desiccant is white in color; yellow means the desiccant has oil on it.
5. Ensure that all desiccant is removed from the tower. Replace the plug ensuring the threads are cleaned and re-doped with thread sealant before replacing.
CHECK the condition of the lower desiccant. As flow is upward through the bed, the lower desiccant will see any major contaminants and any carryover from the inlet filter if this has not been serviced correctly. Oil on the lower desiccant means that the filter element has been over saturated allowing oil to be carried over into the desiccant bed.
N:\Work\Engineering\Product Files\DRY AIR PAC \INSTRUCTIONS\DAP-INSTRUCTION MANUAL­011606 revision.doc
Page 11
CHECK the filter drain and element before putting the new desiccant into the towers.
Consult the factory if any oil is in the towers.
6. Remove the upper plug from the fill port.
7. Using “General” part number 34006-50, refill the tower with new, white desiccant.
NOTE: Only add desiccant beads to towers when refilling. Avoid adding chips and dust, which may be in the bottom of the bag of desiccant, to the towers.
8. Reinstall the fill port ensuring that you clean the threads and re-dope prior to installation.
9. Remove and replace the pre & afterfilter elements prior to putting the unit back in service. This is accomplished by unscrewing the bowls and following the kit instructions to replace the elements. We would be happy to look at the old elements if you feel there is any question as to the condition. Please contact the factory for shipping instructions. Replace the filter bowls and tighten securely prior to re-pressurizing the unit.
10. Turn the power back on to the unit (see 11.).
11. Open the discharge valve of the unit, then the valve ahead of the coalescer, turn power back on to the unit and allow the unit to repressurize.
12. Operate the drain valve manually to bleed air to force the dryer through a full cycle to ensure that the towers pressurize and repressurize correctly and go through their cycle. This is simply a check to see that the unit is operating normally. The unit is now ready to go back in operation.
Run the unit for the 8 hours as above in INSTALLATION, item 4, before letting air feed back into the system.
NOTE:
The purge mufflers must be removed during the first 2 hours of the 8-hour break-in period detailed above. Reinstall the mufflers only after 2 hours of operation.
Once this has been done, valve the unit back into the system.
Should you have any questions, please call the factory and ask for Customer Service at 1­800-345-8207.
N:\Work\Engineering\Product Files\DRY AIR PAC \INSTRUCTIONS\DAP-INSTRUCTION MANUAL­011606 revision.doc
Page 12
TROUBLE SHOOTING GUIDE
PROBLEM PROBABLE CAUSE SOLUTION
POOR DEWPOINT
PERFORMANCE
Check to see that Air
Check compressor output to
Check no leaks have
Excessive water &/or oil in
Low purge flow . Check purge pressure setting.
Desiccant contamination. Check compressor intake is
Check when the last time the
Check condition of coalescing
High inlet temperature to
EXCESSIVE PRESSURE
DROP
Low pressure on desiccant dryer.
dryer.
dryer. Low inlet pressure. See alternatives above.
Switching valve failure. Check tower-operating
Desiccant breakdown.
Dryer is set to operate at 70 to 100 psig. Re-set regulator on DAP Air Maintenance Device to hold back pressure on dryer side to normal settings.
Maintenance Device bypass valve has not been opened.
ensure compressor is running normally.
developed in DAP system such as drain valve sticking open, filter drain valves sticking open, etc.
Check coalescing filter & automatic drain operation.
not in an area where chemicals can be drawn into the intake filter with air.
desiccant was changed. Recommended frequency of change, 1 to 2yrs.
filter element and drain.
sequence to verify and identify which valves are operating.
Change desiccant.
N:\Work\Engineering\Product Files\DRY AIR PAC \INSTRUCTIONS\DAP-INSTRUCTION MANUAL­011606 revision.doc
Page 13
EXCESSIVE PRESSURE
DROP (continued)
Clogged filters. Change filter elements.
Valve shut. Open valve.
SWITCHOVER FAILURE Electric power loss. Turn dryer off; check
connections to cam timer and inlet to unit.
Solenoid valve failure. Check valve operating
sequence. Replace valve.
REPRESSURIZATION
FAILURE OR PURGE
Purge flow control valve orifice clogged.
Clean or replace.
FAILURE/TOWER
BACKPRESSURE
Failed check valve. Replace.
Purge exhaust solenoid valve
failure.
Turn dryer off, check connections to cam timer, inspect valve and solenoid, replace if necessary.
Purge exhaust muffler
Clean or replace.
clogged.
THANK YOU FOR USING OUR PRODUCTS, WE APPRECIATE YOUR BUSINESS.
N:\Work\Engineering\Product Files\DRY AIR PAC \INSTRUCTIONS\DAP-INSTRUCTION MANUAL­011606 revision.doc
Page 14
UL/FM APPROVED
AIR MAINTENANCE DEVICE
STANDARD ON DRY AIR PACS
NOTE 1 IF REQUIRED BY AHJ, CONNECT TO COLD ROOM WITH MINIMUM OF 1 1/2" PIPE SIZE
BUSHED DOWN AT COMPRESSOR INLET
THIS PIPE MUST BE HEAT TRACED AND INSULATED.
CONTROL PANEL CUSTOMER CONNECTION AREA
NOTE 2 AMBIENT TEMPERATURE MUST REMAIN OVER 50 DEGREES F. AT ALL TIMES
1" THICK VIBRATION ISOLATION PADS SHIPPED WITH UNIT. UNIT MUST BE MOUNTED ON VIBRATION PADS.
MODELS DAP 500, 1000 & 2000
500 1000
2000
A
17 5/8"
17 5/8"
B
18"
18"
44"
44"
AIR
OUT
DRY AIR
OUTLET
D
in
Z
1
B
C
in
2
in
TEST PORT
A
DRY AIR OUTLET
in
G
in
E
in
F
in
1. COALESCING FILTER - AHEAD OF DRYER.
2. FILTER REGULATOR, AFTERFILTER - AFTER DRYER.
AIR FLOW
OVER
AFTERCOOLER
12" MIN
TO WALL
NOTE
in
DIMENSIONS
C
D
69 1/2"
72 1/2"
13"
13"
E
F
23 1/2"
23 1/2"
10"
10"
G
Z
Revisions
1/2" FPT
1/2" FPT
Title:
DRY AIR PAC OUTLINE DIMENSIONS
DAPOL
General Air Products
Date:
Drawn By: Drawing #
8/15/96
RGP
G-9646
Rev#
Rev Date: Scale:
6
7/22/97
NTS
Page 15
SEE TRANSFORMER CONNECTIONS
FOR 575V, 460V OR 230V 60Hz OR 50Hz VOLTAGES
FUSE BLOCKS
POWER INPUT FROM CUSTOMER
A
B
C
A
TRANSFORMER
2
1
2
7
TIMER MOTOR
LT3 L.TOW
B
A
B
3
1
A
B
MOTOR STARTER
MS1
7
1
4
OL
MS
3
11
10
LT
SV
9
TIMER CAMS
7
7
CAM MICRO SWITCH CONNECTIONS ARE AS FOLLOWS: BOTTOM CONNECTION IS COMMON MIDDLE CONTACT IS NORMALLY CLOSED TOP CONACT IS NORMALLY OPEN
8
RT
SV
2
LT4 R.TOW
TRANSFORMER
TRANSFORMER
TIMER MOTOR
STARTER
HOUR METER
DVA TIMER
LIGHTS DOOR
POWER
SWITCH
DVA
SWITCH
DVA
DV
SV
DAP 3 PHASE POINT TO POINT.TCW
1 2 2 2
2 2 2 2
2
POWER SWITCH
4 SOL VALVES
JUMPER
JUMPER
JUMPER
JUMPER
JUMPER
JUMPER
JUMPER
JUMPER
5
TIMER
BLACK
DV
62YELLOW
LT PV
LT1 COMP
LT2 DRAIN
RT
PV
POWER SWITCH
1
3
DVA SW
COMMON
2
3
FOR TIMER
PRESSURE SW
POWER SW
PRESSURE SW
LT-1
DVA TIMER
DVA SW
LT-2
DVA SW
TIMER CAM
3 3 3 4
4 5 6 6
7
STARTER
JUMPER
JUMPER
JUMPER
STARTER JUMPER
JUMPER
HOUR METER
DVA BOX
JUMPER
JUMPER
DVA TIMER
TIMER MOTOR
STARTER
1
3
2
6
DVA SWITCH
3
Revisions
5
5
REV 7: 8/24/99 ADDED 575V REV 8:01/19/01 CLARIFIED TIMER CONNECTIONS
Title:
4
PS
2
2
HOUR METER
General Air Products
Date:
8/23/96
Drawn By:
Drawing #
DRY AIR PAC ELECTRICAL - POINT TO POINT
RGP
E-9645
3
Rev#
Rev Date: Scale:
4
8
01/19/01
NTS
Page 16
CUSTOMER CONNECTIONS (SEE NOTE 1) SEE ACCEPTABLE VOLTAGES
L1
L2
L3
M-1
MS
FU-A
SS-1 (LIGHTED)
ON
OFF
3
PL-1
PS
AUTO
MS
1
G
MANUAL
7
FU-1
4
3
1
5
6
CAM TIMER
MTR
NO
CAM1
C
NC
115 V
HM
FU-B
TRANSFORMER (SEE NOTE 2)
4
4
2
5
6
YELLOW
6
6
11
10
BLACK
MS
DVA
TIMER
BOARD
GROUND
CONTROL POWER SWITCH
2
"POWER ON" LIGHT
PRESSURE SWITCH
OL
MOTOR STARTER
COMPRESSOR LIGHT
HOUR METER
DRAIN VALVE TIMER
AUTOMATIC DRAIN VALVE
DRAIN VALVE LIGHT
CAM TIMER
RIGHT TOWER LIGHT
RIGHT TOWER INLET VALVE
LEFT TOWER INLET VALVE
LEFT TOWER LIGHT
DAP 3 PHASE ELEC SCHEME.TCW
NO
CAM2
NC
C
NO
CAM3
C
NC
NOTES:
1) INPUT VOLTAGE IS CONNECTED TO L1, L2 AND L3 CONNECTIONS ON THE MOTOR STARTER.
2) TRANSFORMER CONNECTIONS ARE DETERMINED BY SUPPLY VOLTAGE.
3) CAM TIMER MICRO-SWITCH CONNECTIONS ARE: BOTTOM CONTACT IS COMMON, MIDDLE CONTACT IS NORMALLY CLOSED, TOP CONTACT IS NORMALLY OPEN.
ACCEPTABLE VOLTAGES: DAP500B, DAP1000B AND DAP2000B: 460V/230V/208V/3PH/60HZ DAP500B-5, DAP1000B-5 AND DAP2000B-5: 575V/3PH/60HZ DAP500B-50: 190V/200V/208V/220V/380V/400V/415V/3PH/50HZ DAP1000B-50 AND DAP2000B-50: 190V/200V/208V/220V/380V/400V/415V/440V/3PH/50HZ
9
8
REV 1: 2/24/06: ADDED ACCEPTABLE VOLTAGES
TITLE
SIZE
A
SCALE
LEFT TOWER PURGE VALVE
RIGHT TOWER PURGE VALVE
GENERAL AIR PRODUCTS
ELECTRICAL SCHEMATIC
3 PHASE DRY AIR PAC
DRAWN BY:
NTS
DPH
DWG NO
DATE:
E-204028
05/03/04
SHEET
REV
1
1 of 1
Loading...