GE MFAC 14, MFAC 34 User Manual

Page 1
GE Energy Connections Grid Solutions
MFAC
14, 34
Publication reference: R8007H
Page 2
Page 3
HANDLING OF ELECTRONIC EQUIPMENT
A person’s normal movements can easily generate electrostatic potentials of several thousand volts. Discharge of these voltages into semiconductor devices when handling circuits can cause serious damage, which often may not be immediately apparent but the reliability of the circuit will have been reduced.
The electronic circuits of General Electric products are immune to the relevant levels of electrostatic discharge when housed in their cases. Do not expose them to the risk of damage by withdrawing modules unnecessarily.
Each module incorporates the highest practicable protection for its semiconductor devices. However, if it becomes necessary to withdraw a module, the following precautions should be taken to preserve the high reliability and l
ong life for which
the equipment has been designed and manufactured.
1. Before removing a module, ensure that you are a same electrostatic potential as the equipment by touching the case.
2. Handle the module by its front-plate, frame, or edges of the printed circuit board. Avoid touching the electronic components, printed circuit track or connectors.
3. Do not pass the module to any person without first ensuring that you are both at the same electrostatic potential. Shaking hands achieves equipotential.
4. Place the module on an antistatic surface, or on a conducting surface which is at the same potential as yourself.
5. Store or transport the module in a conductive bag.
More information on safe working procedures for all electronic equipment can be found in BS5783 and IEC 60147-0F.
If you are making measurements on the internal electronic circuitry of an equipment in service, it is preferable that you are earthed to the case with a conductive wrist strap.
Wrist straps should have a resistance to ground between 500k – 10M ohms. If a wrist strap is not available you should maintain regular contact with the case to prevent the build up of static. Instrumentation which may be used for making measurements should be earthed to the case whenever possible.
General Electric strongly recommends that detailed investigations on the electronic circuitry, or modification work, should be carried out in a Special Handling Area such as described in BS5783 or IEC 60147-0F.
Page 4
TYPES: MFAC 14
MFAC 34
CONTENTS
SAFETY SECTION
5
1. INSTALLATION
9
1.1 General
9
1.2 Unpacking
9
1.3 Storage
9
1.4 Site
9
2. COMMISSIONING
10
2.1 Description of relay, calculation of setting and
commissioning
preliminaries
10
2.2
Instructions
to ensure that the relay can be
commissioned
at the specific settings
for the application
12
3. MAINTENANCE
18
4. MECHANICAL SETTINGS
18
4.1 General
18
4.2 Contact settings
18
4.3 Mechanical flag settings
18
5. PROBLEM ANALYSIS
19
5.1 Failure to operate
19
5.2 Output contacts not changing state
19
6. SPARES
20
7. COMMISSIONING TEST RECORD
21
REPAIR FORM 23
4
Page 5
1.
SAFETY SECTION
This Safety Section should be read before commencing any work on the equipment.
1.1
Health and
safety
The information in the Safety Section of the product documentation is intended to ensure that products are properly installed and handled in order to maintain them in a safe condition. It is assumed that everyone who will be associated with the equipment will be familiar with the contents of the Safety Section
.
1.2
Explanatio
n of symbols and
labels
The meaning of symbols and labels may be used on the equipment or in the product documentation, is given below.
Caution
: refer to product documentation
Caution
: risk of electric shock
Protective/safety *earth terminal
Functional *earth terminal Note: This symbol may also be
used for a protective/safety earth terminal if that terminal is part of a terminal block or sub-assembly e.g. power supply.
*NOTE: THE TERM EARTH USED THROUGHOUT THE PRODUCT DOCUMENTATION IS
THE DIRECT EQUIVALENT OF THE NORTH AMERICAN TERM GRO U ND.
2.
INSTALLING, COMMISSIONING AND SERVICIN
G
Equipment connections Personnel undertaking installation, commissioning or servicing work on this
equipment should be aware of the correct working procedures to ensure safety. The product documentation should be consulted before installing, commissioning or servicing the equipment.
Terminals exposed during installation, commissioning and maintenance may present a hazardous voltage unless the equipment is electrically isolated.
If there is unlocked access to the rear of the equipment, care should be taken by all personnel to avoid electrical shock or energy hazards.
Page 6
Voltage and current connections should be made using insulated crimp terminations to ensure that terminal block insulation requirements are maintained for safety. To ensure that wires are correctly terminated, the correct crimp terminal and tool for the wire size should be used.
Before energising the equipment it must be earthed using the protective earth terminal, or the appropriate termination of the supply plug in the case of plug connected equipment. Omitting or disconnecting the equipment earth may cause a safety hazard.
The recommended minimum earth wire size is 2.5mm
2,
unless otherwise stated in
the technical data section of the product documentation. Before energising the equipment, the following should be
checked:
Voltage rating and polarity;
CT circuit rating and integrity of connections;
Protective fuse rating;
Integrity of earth connection (where applicable)
Remove front plate plastic film protection
Remove insulating strip from battery compartment
3.
EQUIPMENT OPERATING CONDITIONS
The equipment should be operated within the specified electrical and environmental limits.
3.1
Current transformer circuits Do not open the secondary circuit of a live CT since the high level voltage produced
may be lethal to personnel and could damage insulation.
3.2
External re
sist
ors
Where external resistors are fitted to relays, these may present a risk of electric shock or burns, if touched.
3.3
Battery replacement Where internal batteries are fitted they should be replaced with the
recommended type and be installed with the correct polarity, to avoid possible damage to the equipment.
3.4
Insulation
and
dielectric strength testing
Insulation testing may leave capacitors charged up to a hazardous voltage. At the end of each part of the test, the voltage should be gradually reduced to zero, to discharge capacitors, before the test leads are disconnected.
3.5
Insertion
of
modules
and pcb
cards
These must not be inserted into or withdrawn from equipment whist it is energised since this may result in damage.
Page 7
3.6
Fibre optic
communication
Where fibre optic communication devices are fitted, these should not be viewed directly. Optical power meters should be used to determine the operation or signal level of the device.
4. OLDER
PRODUCTS
Electrical adjustments Equipments which require direct physical ad ustments to their operating
mechanism to change current or voltage settings, should have the electrical power removed before making the change, to avoid any risk of electrical shock.
Mechanical adjustments The electrical power to the relay contacts should be removed before checking any
mechanical settings, to avoid any risk of electric shock. Draw out case relays
Removal of the cover on equipment incorporating electromechanical operating elements, may expose hazardous live parts such as relay contacts.
Insertion and withdrawal of extender cards When using an extender card, this should not be inserted or withdrawn from the
equipment whilst it is energised. This is to avoid possible shock or damage hazards. Hazardous live voltages may be accessible on the extender card.
Insertion
and
withdrawal
of heavy
current
test
plugs
When using a heavy current test plug, CT shorting links must be in place before inserti
on or removal, to avoid potentially lethal voltages.
5.
DECOMMISSIONING
AND
DISP
OSAL
Decommissioning: The auxiliary supply circuit in the relay may include
capacitors across the supply or to earth. To avoid electric shock or energy hazards, after completely isolating the supplies to the relay (both poles of any dc supply), the capacitors should be safely discharged via the external terminals prior to decommissioning.
Disposal:
It is recommended that incineration and disposal to water courses is avoided. The product should be disposed of in a safe manner. Any products containing batteries should have them removed before disposal, taking precautions to avoid short circuits. Particular regulations within the country of operation, may apply to the disposal of lithium batteries.
Page 8
6. TECHNICAL SPECIFICATIONS
Protective fuse rating
The recommended maximum rating of the external protective fuse for this equipment is 16A, Red Spot type or equivalent, unless otherwise stated in the technical data section of the product documentation.
Insulation
class: IEC 601010-1 : 1990/A2 : 2001
Class
I EN 61010-1: 2001 Class
I
This equipment requires a protective (safety) earth connection to ensure user safety.
Insulation Category (Overvoltage):
IEC 601010-1 : 1990/A2 : 1995 Category III EN 61010-1: 2001 Category III
Distribution level, fixed insulation. Equipment in this category is qualification tested at 5kV peak,
1.2/50
µ
s,
500Ω, 0.5J, between all supply circuits and earth and also between independent circuits.
Environment:
IEC 601010-1 : 1990/A2 : 1995
Pollution degree 2 EN 61010-1: 2001
Pollution degree 2
Compliance is demonstrated by reference to generic safety standards.
Product Safety: 72/23/EEC
EN 61010-1: 2001 EN 60950-1: 2002
Compliance with the European Commission Low Voltage Directive.
Compliance is demonstrated by reference to generic safety standards.
Page 9
Section 1. INSTALLATION
1.1 General
Protective relays, although generally of robust construction, require careful treatment prior to installation and a wise selection of site. By observing a few simple rules the possibility of premature failure is eliminated and a high degree of performance can be expected.
The relays are either despatched individually or as part of a panel/rack mounted assembly in cartons specifically designed to protect them from damage.
Relays should be examined immediately they are received to ensure that no damage has been sustained in transit. If damage due to rough handling is evident, a claim should be made immediately to the transport company concerned and the nearest General Electric representative should be promptly notified. Relays which are supplied unmounted and not intended for immediate installation should be returned to their protective polythene bags.
1.2 Unpacking Care must be taken when unpacking and installing the relays so that none
of the parts are damaged or their settings altered and must at all times be handled by skilled persons only.
Relays should be examined for any wedges, clamps, or rubber bands necessary to secure m
oving parts to prevent damage during transit and these
should be removed after installation and before commissioning. Relays which have been removed from their cases should not be left in
situations where they are exposed to dust or damp. This particularly applies to installations which are being carried out at the same time as constructional work.
1.3 Storage If relays are not installed immediately upon receipt they should be stored in a
place free from dust and moisture in their original cartons and where de­humidifier bags have been included in the packing they should be retained. The action of the de-humidifier crystals will be impaired if the bag has been exposed to damp ambient conditions and may be restored by gently heating the bag for about an hour, prior to replacing it in the carton.
Dust which collects on a carton may, on subsequent unpacking, find its way into the relay; in damp conditions the carton and packing may become impregnated with moisture and the de-humidifying agent will lose its efficiency.
The storage temperature range is –25° and +70°C.
1.4 Site The installation should be clean, dry and reasonably free from dust and
excessive vibration. The site should preferably be well illuminated to facilitate inspection.
An outline diagram is normally supplied showing panel cut-outs and hole centres. For individually mounted relays these dimensions will also be found in Publication R6008.
Publication R7012 is a Parts Catalogue and Assembly Instructions. This document will be useful when individual relays are to be assembled as a composite rack or panel mounted assembly.
9
Page 10
Publication R6001 is a leaflet on the
modular
integrated drawout system of
protective relays. Publication R6014 is a list of
recommended
suppliers for the pre-
insulated connectors.
Section
2. COMMISSIONING
2.1 Description of relay, calculation of setting and commissioning preliminaries
2.1.1 Description of MFAC 14/MFAC 34 This is a voltage operated relay having seven equally spaced settings of
15–185 volts, 25–175 volts, 25–375 volts or 100–400 volts which may be selected by means of a plug bridge.
The relays may be used for any type of high impedance circulating current protection.
2.1.2 List of abbreviations. I
E
=
Current transformer
exciting current at relay setting voltage (referred to the
CT secondary current)
I
F
=
Maximum value of primary
through
fault current for which protection must
remain stable.
I
FM
=
Maximum value of primary fault current for internal fault.
I
P
=
Primary current for operation of protection.
I
R
=
Relay operating current.
I
SH
= Current
in
shunt
resistor at relay setting
VR.
N
= Turns
ratio of current transformer.
n
=
No. of current
transformers
in parallel with
relay.
R
CT
=
Secondary resistance of current transformer.
R
L
=
Lead resistance between
furthest
current
transformer
and relay
connection point.
R
R
=
Relay impedance.
R
SH
=
Value of
shunt
resistor.
V
F
=
The theoretical voltage which would be produced across the relay circuit
under internal fault condition. V
F
=
I
FM (RCT
+
2RL +
RR) N
V
K
=
Knee point voltage of current transformer.
V
P
=
Peak voltage across relay circuit under
maximum
internal fault conditions.
V
S
=
Minimum
setting voltage. (calculated)
V
R
=
Relay setting voltage.
2.1.3 Calculation of relay setting. The
minimum
setting voltage to ensure stability is
V
S
I
F (RCT
+
2RL)
N
The relay plug setting voltage V
R
must
be set to the nearest tap above
VS.
10
Page 11
The
minimum
knee point voltage
must
be
V
K
2V
R
The operating current of the relay is 38mA, irrespective of tap selected, excluding the current drawn by the external metrosil. When a standard
metrosil
is included
with the relay, the relay operating current including the
metrosil
is given in the table
below. It
must
be appreciated that
metrosils
have large tolerances and these figures
are given for guidance only.
a) Low range relay (5V steps)
Setting voltage
V
R
15 50 75 100 125 150
175
185
Relay current
I
R
(mA)
38 38 39 42 46 55 72
81
(including metrosil, C = 450)
b) Low range relay
Setting voltage
V
R
25 50 75 100 125 150 175
Relay current
I
R
(mA)
19 19 20 23 27 36 53
(including metrosil, C = 450)
c) High range relay
Setting voltage
V
R
25 75 125 175 225 275 325
Relay current
I
R
(mA)
19 19 20 22 24 31 44
(including metrosil, C = 900)
d) 100–400V version
Setting voltage
V
R
100 150 200 250 300 350 400
Setting voltage IR(mA)
19 19 20 20 23 27 36
(including metrosil, C = 1100)
The primary current for operation is given by
I
P
=
N (I
R
+
n
I
E
)
If the
resultant
value of IP is too low it may be increased by the addition of a
shunt resistor R
SH
to give a current of
I
SH
= V
R
R
SH
The new increased value of primary current
I
P
=
N (I
R
+
nI
E
+
I
SH
)
External metrosils. Each FAC relay is applied with an external
metrosil
which
must
be wired across
the relay circuit. This provides a
shunt
circuit for high internal fault currents and
prevents a high voltage being developed across the CT and relay circuits.
2.1.4 Commissioning preliminaries. Inspection. Carefully examine the module and case to see that no damage has occurred
during transit. Check that the relay serial number on the module, case and cover are identical, and that the model number and rating information are correct.
Carefully remove any elastic bands/packing fitted for transportation purposes. Carefully actuate the armature of each unit in turn with a small screwdriver/probe.
Note that immediately after the point where any normally open contacts just make
11
Page 12
there is a small
further movement
of the
armature.
This ensures that contact follow
through
and wiping action is present. On units fitted with hand reset flag indicators,
check the flag is free to fall before, or just as, any normally open contacts touch. Check that the external wiring is correct to the relevant relay diagram or
scheme diagram. The relay diagram
number
appears inside the
case.
Particular attention should be paid to the correct wiring and value of any external resistors indicated on the wiring diagram/relay rating information.
Note that shorting switches shown on the relay diagram are fitted internally across the relevant case
terminals
and close when the module is withdrawn. It is
essential that such switches are fitted across all CT circuits. If a test block type MMLG is provided, the connections should be checked to the
scheme diagram, particularly that the supply connections are to the ‘live’ side of the test block (coloured orange) and with
terminals
allocated with odd
numbers
(1, 3, 5,
7, etc.). Earthing. Ensure that the case earthing connection above the rear
terminal
block, is used
to connect the relay to a local earth bar. Insulation. The relay, and its associated wiring, may be insulation tested between: a) all electrically isolated circuits b) all circuits and earth An electronic or brushless insulation tester should be used, having a dc voltage
not exceeding 1000V. Accessible
terminals
of the same circuit should first be
strapped together. Deliberate circuit earthing links, removed for the tests, must subsequently be
replaced. Terminal allocation. Terminals of the relay are normally allocated as below, but reference should
always be made to the relevant diagram. a) Single pole relays
Normally open contacts 1, 3 and 2,
4.
AC current input – 27,
28.
An alternative version of the relay has additional normally open contacts connected to 5, 7 and 6,
8.
b) Triple pole relays
Normally open contacts 1, 3 and 2, 4. The contacts are normally connected in parallel for the three phases but
a version of the relay having contacts brought out separately is available. AC current inputs - 23, 24 : 25, 26 : 27,
28.
2.2 Instructions to ensure that the relay can be commissioned at the specific settings for the application
It is only necessary to check the relay at the setting on which it is to be used. The relay
must
not be used at any setting other than that for which the setting has
been calculated.
12
Page 13
2.2.1 Test
equipment
required
1 – Secondary injection test
equipment
capable of providing an ac voltage
supply of up to at least 120% of the relay setting. 1 – Multifinger test plug type MMLB 01 for use with test block type MMLG if fitted. 1 – Miniature split plug type MMLB 03 to fit relay plug bridge. 3 – Calibrated
multimeters
0–10 amp ac, 0–400 volt
ac.
1 – Set primary injection testing equipment.
2.2.2 General If the relay is wired
through
an MMLG test block it is
recommended
that all
secondary injection tests should be carried out using this block. Ensure that the main system current
transformers
are shorted before isolating the
relay from the current
transformers
in preparation for secondary injection tests.
DANGER: DO NOT OPEN CIRCUIT THE SECONDARY CIRCUIT OF A CURRENT
TRANSFORMER SINCE THE HIGH VOLTAGE PRODUCED MAY BE LETHAL AND COULD DAMAGE INSULATION.
When type MMLG test block facilities are installed, it is
important
that the sockets in
the type MMLB 01 test plug, which correspond to the current
transformer
secondary windings, are LINKED BEFORE THE TEST PLUG IS INSERTED INTO THE TEST BLOCK. Similarly, a MMLB 02 single finger test plug
must
be
terminated
with an
ammeter BEFORE IT IS INSERTED to
monitor
CT secondary currents.
It is assumed that the initial preliminary checks have been carried out.
2.2.3 Relay CT shorting switches With the relay removed from its case, check electrically that the CT shorting switch
is closed.
2.2.4 Secondary injection testing Connect the circuit as shown in Figure 1 and ensure that the current transformer
primary is open circuit and that if any earthing connections are fitted, they do not short out the primaries of any current transformers.
Increase the voltage until the relay just operates. Note the current in the relay (this can be done using the
miniature
split plug
inserted into the appropriate position of the plug bridge connected to an
ammeter).
It should be approximately 38mA at setting. Note also the voltage at which the relay operates which should correspond to the
setting V
R
of the relay with a tolerance of ±10%. The total secondary current for
operation will be given on ammeter
A1. This test should be repeated for each pole
of the
relay. Drop off/Pick up ratio. Check that this ratio is greater than
50%.
13
Page 14
2.2.5 Primary injection testing It is essential that primary injection testing is carried out to prove the correct
polarity of current transformers. Before
commencing
any primary injection testing it is essential to ensure that the
circuit is dead, isolated from the
remainder
of the system and that only those
earth connections associated with the primary test
equipment
are in position.
2.2.6 Primary fault setting The primary fault setting of any balanced scheme can be checked using the circuit
shown in Figure 2. The primary current is injected into each current
transformer
in turn and increased until the relay operates. The voltage at which the relay operates should be within ± 10% of the relay setting voltage V
R
. The primary
current for operation and relay current should be noted. In the case of machine protection similar tests
must
be carried out by injecting
first into each current
transformer
in turn to determine the primary fault setting.
For large machines the machine itself can be used to provide the fault current to check the primary fault setting as shown in Figure 5. The machine should be run up to speed with no excitation. The excitation should then be increased until the relays have all operated. The primary c
urrent, relay current and relay voltage
should be noted as each relay operates.
2.2.7
Through
fault stability
With any form of unbalanced protection it is necessary to check that the current transformers are correctly connected. For this purpose with a restricted earth fault scheme the circuit shown in Figure 3 may be used. During this test it is necessary to measure the spill current in the relay circuit and short out the relay and stabilising resistor (if fitted). The current is increased up to as near full load as possible and the spill current noted. The spill current should be very low, only a few milliamps if the connections are correct. A high reading (twice the injected current, referred through the current transformer ratio) indicates that one of the current transformers is reversed.
Injection should be carried out through each phase to netural. Where primary injection is not practicable in the case of restricted earth fault
protection on a
transformer
it may be possible to check stability by means of back
energising the
transformer
from a low voltage (415V) supply as shown in Figure 4.
In the case of machine protection, similar stability tests
must
be carried out
by
injecting into one and out of another current
transformer
connected on the same
phase. For large machines, the machine itself can be used to provide the fault current,
but the short circuit
must
now be fitted as shown in Figure 6. The machine should
be run up to
normal
speed and the excitation increased until the primary current is
approximately full load, when the spill current should be checked. All other types of balanced protection should be tested in a similar manner. At the conclusion of the tests ensure that all connections are correctly restored
and any shorting connections removed.
14
Page 15
Stabilising resistor (if fitted)
Relay
A2
A1
Metrosil
Ammeter (in plug bridge circuit)
V
Figure 1 Secondary injection of relay to check secondary operating current, setting voltage and
relay operating current.
A1
Primary injection
test set
V
Stabilising resistor (if fitted)
A2
Relay
Ammeter (in plug
bridge circuit)
Figure 2 Sensitivity check of restricted earth fault scheme by primary injection.
15
Page 16
A1
Primary injection
test set
A
B
C
Temporary connections
A2
Stabilising resistor (if fitted)
Relay
Metrosil
Figure 3 Stability check of restricted earth fault protection.
A1
A
LV
B
supply
C
Temporary short
circuit
A2
Stabilising resistor (if fitted)
Relay
Figure 4 Stability check on restricted earth fault scheme by back energising with a low voltage supply.
16
Page 17
Temporary short
circuit
Generator
Isolating
links
A
B
C
V
87
87
87
87 Generator differential
relay
V
V
oltmeter
Figure 5 Testing sensitivity of generator differential protection using generator to supply
primary current.
Generator
Isolating
links
Temporary short
circuit
A
B
C
A2 A2
A2
87
87
87
87 Generator differential
relay
A2
Ammeter
Figure 6 Checking stability of generator differential protection.
17
Page 18
Section
3. MAINTENANCE
Periodic
maintenance
is not necessary. However, periodic inspection and test is
recommended.
This should be carried out every l2
months
or more often if the relay is
operated frequently or is
mounted
in poor
environmental
conditions.
3.1 Repeat secondary injection tests 2.2.4 to prove operation, with emphasis on contact wear and condition. Mechanical settings may be checked against those shown in Section
4.
Section
4.
MECHANICAL
SETTINGS
4.1 General
Armature gap
measurements
should be made with the top of the feeler gauge
level with the centre line of the core. Contact pressures are measured with a
gramme
gauge at the contact tips.
In general contact gaps and follow
through
are defined by quoting an
armature
gap
at which the tips should be just closed or just open. The relay contact state is always defined with the relay in the unenergised
position, unless otherwise specified on the appropriate circuit diagram.
4.1.1 With the
armature
closed the clearance between the back of the
armature
and
the back stop should be
0.003"/0.008".
4.1.2 Nominal
armature
gap open: 0.060" for all
types.
Set screw in
armature
so that
armature
gap when closed is approximately
0.005"/0.010".
4.2 Contact settings
4.2.1 Normal duty make contacts With the
armature
closed onto a 0.011" feeler gauge the make contacts should be
closed, but should be open using a 0.013" feeler gauge.
Contact settings
2 contacts (MFAC
34)
4 contacts (MFAC
14)
Force to just close the make contacts
20/25 grams 15/20 grams
Force to just lift the fixed contact off its support
15/20 grams
20/25 grams
Nominal contact gap
0.060"/0.080"
4.3 Mechanical flag settings
4.3.1 Settings for self reset units MFAC
l4/34
With the armature closed on to a 0.013" feeler gauge the flag should be free to fall, but should not fall using an 0.018" feeler gauge. Adjustment is made to the catch spring on the flag.
18
Page 19
Section
5.
PROBLEM
ANALYSIS
5.1 Failure to operate
Check diagram for correct input connections. Check tap voltage; this is
marked
above or below the plug bridge on the front of the
module. Note: with the plug removed the relay setting goes to the highest tap value.
Measure the input current at VS, this should be 38mA (excluding the metrosil).
Flag spring may be
jammed
between
armature
and core face, preventing armature
closure. Check internal wiring for damage. Check choke continuity - resistance 240
ohms ±
15%.
Check resistor values - remove pcb from module and fold down to gain access to board.
Setting range Resistors on PCB ZJ0038
R1 – R3 R5–R6 R7–R8
R9
15–185 680 680 150
120
Adjustable resistor
0–1000
Capacitor
3.3µF
Relay coil
190
Setting range Resistors on PCB ZJ0038
R1 –
R6
25–175
1.3K
25–327
2.4K
Adjustable resistor RV1
510
Capacitor C1
1.7
µ
F
±5% 50Hz,
1.18
µF ±5%
60Hz.
Relay coil 560Ω ±
15%
Setting range Resistors on PCB ZJ0038
R1–R6
100–400
2.7K
R9
3.9K
5.2 Output contacts not changing state
Check output
terminals
with reference to appropriate diagram. Operating pushrods not in position Internal
wiring damaged
Contamination
of contacts Contacts should be cleaned with the burnishing tool supplied in the relay tool kits. On no account should knives, files or abrasive materials be used. Check mechanical settings as per Section
4.
19
Page 20
Section 6. SPARES
When ordering spares, quote the full relay model number and any component reference numbers, or briefly describe the parts required.
Should the need arise for the equipment to be returned to General Electric for repair please fill in the RMA form at the back of this manual.
A copy of any commissioning test results should also be sent with the equipment.
20
Page 21
Section
7.
COMMISSIONING TEST
RECORD
High Impedance
Differential
Relay Type
MFAC
Date
Station
Circuit.
Relay Model
No.
Serial
No.
Setting range
CT ratio
Setting voltage
Relay setting
Type of ext. metrosil
Shunt resistor ohms
(if fitted)
Calculated primary
operating current
Test results
2.2.3 Relay CT shorting
switch
2.2.4 Secondary voltage to operate
relay.
Phase
Total current
(A1)
Relay current
(A2)
PU volts
DO volts
A
B
C
Drop off / pick up ratio check
2.2.6 Primary current to operate relay
Phase
Primary current
(A1)
Relay current
(A2)
Relay voltage
A
B
C
N
21
Page 22
2.2.7 Stability check by primary injection Restricted earth fault
Phases Primary current
(A1)
Spill current
(A2)
A–N
B–
N
C–N
Circulating current between two or more sets of current transformers.
Phases Primary current
(A1)
Spill current
(A2)
A1–A2
B1–B2
C1–C2
Where more than two sets of current
transformers
are involved, injection should
be carried out between set 1 and each other set in turn.
Commissioning
Engineer
Customer
Witness
Date Date
22
Page 23
Page 1 of 2
REPAIR / MODIFICATION RETURN AUTHORIZATION FORM – RMA FORM
FIELD ONLY TO BE FILLED IN BY A GE GRID Automation REPRESENTATIVE
RMA Reference
Date :
ACT Reference (M):
Repair Center address to Ship the Unit:
UK Grid Solution LTD St Leonards Building Harry Kerr Drive, Redhill Business Park, Stafford, ST16 1WT, UK FAO :- After Sales Department
GE GRID Automation Local Contact Information: Name of Contact - Tel No - email –
1. IDENTIFICATION OF UNIT & FAULT INFORMATION - Fields marked (M) are mandatory, delays in return will occur if not completed.
Qty
Type of Material(M) Model N° (M)
Serial
n°(M)
Part n°(M)
SW
Vers
Description of Fault or Modification required(M)
Are Field
Volts Used (M)
Warranty
Y/N ?
(M) Equipment failed during Installation / Commissioning Yes
Equipment failed during service Yes How long?
(M) Equipment failed during Installation / Commissioning Yes
Equipment failed during service Yes How long?
2. SPECIALIST REPAIR INSTRUCTIONS
Do you want an updated firmware version after repair? Yes No
Is the relay being returned in a case? Yes No (If No see repair Term 5)
3. CUSTOMS & INVOICING INFORMATION REQUIRED TO ALLOW RETURN OF REPAIRED ITEMS
Value for Customs (M):
Customer Invoice Address if paid (M)
Customer Return Delivery Address (full street address) (M)
Part Shipment Accepted (Yes/No) –
Contact Name:
Tel No:
Email:
Contact Name:
Tel No:
Email:
4. REPAIR TERMS & CONDITIONS
1. Please ensure a copy of the import invoice is attached with the returned unit/Airwaybill document copy emailed (M)
2. Please ensure the Purchase Order is released, for paid service, to allow the unit to be shipped
3. Submission of equipment to UK Grid Solutions is deemed as authorization to repair and acceptance of quote.
4. Please ensure all items returned are marked as Returned for ‘Repair/Modification’ and protected by appropriate packaging (anti-static
bag for each board / relay with foam protection).
5. If a relay is not being returned in a case, please refer to instructions on Page 2.
Page 24
Page 2 of 2
5. Return Packaging Standards (ALL PRODUCTS)
1. Please ensure the device is clean, no sharp edges are exposed and the device is in
a suitable condition to be handled.
2. Relay’s returned without cases should be placed in to Anti-Static Bags and sealed
to protect hyper-sensitive components.
3. A suitable size box should be used, with packing material at the bottom, the
device placed into box with sufficient gaps to fill with packing material around each side and on the top, extra packaging material placed around the relay.
4. Please include a copy of the completed RMA form then close the lid and seal with
packaging tape.
5. The relay should then be secondary packed if being exported, the primary
packed box should be placed into an oversized box with packaging material surrounding the primary packed box and then sealed.
Page 25
Imagination at work
Grid Solutions St
Leonards Building
Redhill Business Park Stafford, ST16 1WT, UK +44 (0) 1785 250 070 www.gegridsolutions.com/contact
© 2017 General Electric. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular
project.
This will depend on the technical and commercial circumstances. It is provided without liability and is subject to
change without notice.
Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.
R8007H
Loading...