Equipment Supplied by Contractor
Fuji Clean USA * 207-406-2927
* www.fujicleanusa.com
Risers and Covers per Site & Regulatory Requirements
Note: Tuf-Tite and Polylok Risers in 6” or 12” height increments and covers are available from your
distributor . If not already installed, please refer to page 5 for installation instructions.
Allowed 24” riser height or less.
Model CE5: Three (3) 20” Risers
Models CE7, CE10 and CEN Series: Two (2) 20” Risers plus One (1) 24-inch
Insulation for Cold Climate Installations
To maintain optimal treatment conditions, Fuji Clean recommends insulated risers and covers as well as
foam board or insulating material (min. R-Value 8) over the upper half of the treatment tank.
Septic Tank and/or Pump Station.
If local code or site conditions mandate. Fuji Clean system are designed to accept straight wastewater.
Fresh Water
Systems must be filled with fresh water to Low Water Mark (LWM) before start-up. Approx. gallons
required per model: (CE5: 435; CE7: 610; CE10: 925; CEN5: 610; CEN7: 925; CEN10: 1,230).
Piping/Conduit
• 4” Schedule 40 for inlet and outlet lines.
• ¾” PVC conduit for air line (minimum 6-in. deep).
• Electrical conduit for float switch line (or use direct burial line).
Electrical
• Please use licensed electrician and adhere to applicable national/local electrical code(s).
• Two (2) standard 115V, 15A circuits for control/alarm panel connection.
• Float Switch Wire: #18 AWG (comes with standard 30’-ft. length). May extend up to 50-ft.
• Float Switch: May come pre-installed in treatment system. For electrical hookup, please refer to SJE
Rhombus installation instructions.
• Miscellaneous fittings and connectors to assure watertight connections.
Anti-Float Devices, if necessary
• Please refer to high water, anti-float recommendations in this manual.
Materials for Blower / Controller Installation
• Concrete base (or equivalent) on which to set air blower.
• Protective cover for air blower (vented and able to achieve free airflow in all conditions).
• Materials or location on which to mount control panel and protect from elements.
Crushed Stone, Fill, Loam etc.
• Fuji Clean USA is not responsible for design, installation or materials associated with leachfield or
treated wastewater disposal area.
Please note: Proper installation permitting is the responsibility of the installing contractor.
Contractor Installation Manual – Residential Systems