Installation
Installing the inverter with the built-in option “MC4 Connector” di󰀨ers only slightly from installing the inverter
without the option “MC4 Connector” The DC connection is described below. The rest of the installation is described in the installation instructions of the inverter - www.fronius.com/QR-link/4204260202EA
WARNING! An electric shock can be fatal. Danger due to grid voltage and DC voltage from the solar modules.
- The DC main switch is only to be used to de-energise the power stage set. The connection area is still live when the DC main
- Ensure that the power stage set and connec­tion area are disconnected from one another before carrying out any maintenance or service tasks.
- The power stage set, which is enclosed in a separate housing, must only be disconnected from the connection area when in a de-ener­gized state.
- Maintenance and servicing of the power stage set of the inverter must only be carried out by Fronius-trained service technicians.
Fronius International GmbH, http://www.fronius.com42,0410,2382 003-01092017
*
*
*
*
*
Conduit size 1/2 in. / 3/4 in. / 1 in.
1 in. Conduit size, suitable for 1/4 in. (6 mm) wall thickness
(expandable to 1.5 inches, be careful to avoid interfering
with any or the internal components and an unbit drill may be used)