FreeHotWater FHWFC 5000 Series Installation Manual

_______________________________________________________________________________
Manual
Installation Manual
Version 2010.09
_______________________________________________________________________________
Free Hot Water 2146 Bering Dr. San Jose, CA 95131 Tel: 408 218 3660 Fax 408 872 4142 www.FreeHotWater.net
Content _________________________________________
Safety information.........................................................................................3
Transport note ..............................................................................................4
Assembly instructions - Collector .................................................................5
Overview of tools ..........................................................................................6
Overview of materials ...................................................................................7
Attachment points..........................................................................................8
Mounting parallel roof bracket attachment system .......................................9
Technical data - Collector.............................................................................12
Operating tips - Solar power system ........................................................... 13
General Information......................................................................................15
Page 2
Page 3
Attention Do not lift the collectors by the connections and or the screw threads
Page 4
General Assembly instructions
_____________________________________________________________________________
General and transport instructions
The mounting system is suitable for tiled roofs only. Installation must only be carried out by qualified personnel. The entire information in these instructions is intended exclusively for such qualified personnel. Only the supplied material should be used for the installation. Prior to starting installation and operation of the solar collector sy­stem, please inform yourself about the applicable local standards and regulations. The use of a carrying strap is recommended for transporting the collector. The collector must not be lifted at the connections or on the threading. Avoid impacts and mechanical influences on the collector, in particular on the solar glass, the rear panel and pipe connections.
Statics - flat roof
The collectors may only be mounted on sufficiently load-bearing roof surfaces and substructures. It is imperative that the static load bearing capacity of the roof or substructure is checked in terms of local and regional conditions prior to installation of the collectors by the customer, if necessary through the involvement of a structural engineer. Particular attention should be paid to the quality of the (timber) substructure in terms of the stability of the screw connections necessary for fastening the collectors. The checking of the entire collector structure by the customer as per DIN 1055 part 4 and 5 or as per the applicable country-specific regulations is particularly important in areas with heavy snowfall (note: 1 m3 powder snow ~ 60 kg / 1 m3 wet snow ~ 200 kg) or in areas exposed to high wind speeds. The assessment should also take into account any particular circumstances at the place of installation (foehn wind, air jets or eddy formation etc.) which can lead to increased loads. The collector is designed for wind loads of 150 km/h and snow loads of 1,25kN/m2. As a rule, collector arrays must be installed such that any possible collection of snow is prevented from reaching the collectors by snow barriers (or through special forms of installation). The distance to roof ridges/edges must be at least 1 m.
Note: The installation of a collector array is an intervention into a (existing) roof; above all, converted and inhabited loft spaces or roofs with less than the minimum slope (with regards to the covering) require additional measures by the customer, e.g. sarking membranes, as protection against water penetration caused by wind pressure and driving snow. With larger collector arrays, we recommend installing the collectors on a special supporting structure made of steel channels. Alternatively, it is possible to install the collectors without perforating the roof membrane by using concrete ballast with guys. The collectors are mounted on concrete blocks. Rubber mats
should be used if necessary to protect the roof membrane against damage and to increase the friction between the roof and the concrete blocks. In addition, it is necessary to secure the collectors with 5mm steel cables (minimum tensile strength 1450 N/mm2) to absorb any peak wind loads.
Lightning protection / Equipotential bonding of the building
In accordance with the lightning protection standard ÖVE/ÖNORM EN 62305 Part 1-4 the collector array cannot be connected to the building's lightning protection. A safety distance of at least 1 m must be maintained from any possible adjacent conducting object. For installations on metal substructures at the installation site, generally qualified electricians must be consulted. To carry out a building potential equalisation, the metal tubes of the solar circuit and all collector cases or fastenings must be
Page 5
connected to the main potential equalisation bus by a qualified electrician in accordance with ÖVE/ÖNORM E 8001-1 or the country-specific standards.
Connections
Connect the collectors using the cutting ring screw connections. If flexible pipes are not used as connectors, precautions must be taken to protect the connection pipes against temperature fluctuations caused by heat expansion, e.g. expansion bends and flexible piping (see Connecting the collectors to one another/Operational recommendations). Larger collector arrays must be assembled with expansion bends or flexible members inserted in the links. (IMPORTANT: check the pump design). When tightening the union nuts, always balance (counter) the torque with a pipe wrench or another spanner to prevent damage to the absorber.
Collector angle / General notes
The collector is suitable for angles between 15° (minimum) and 75° (maximum). The collector connections and the ventilation openings must be protected against the penetration of water as well as against contamination through dust etc.
Legal guarantee
Legal guarantee claims can only be made if the supplier's own antifreeze has been used and maintenance has been carried out correctly. Installation by qualified personnel with absolute adherence to the instructions is a prerequisite for the justification of claims.
Page 6
Tools Needed
Brackets, hooks, bolts etc.