Introduction
Thank you for selecting the FLIR IR window. This manual applies to models
IRW-6PC (6”), IRW-12PC (12”), and IRW-24PC (24”) aluminum windows and
IRW-6PS (6”), IRW-12PS (12”), and IRW-24PS (24”) stainless steel windows.
Preparation
Check that the package contains the IR
window, fitting template, IR window label, and
fitting hardware. See Fig-1.
The required tools and personal protection
equipment (PPE) are listed below; you will
need these materials to perform a successful
installation. Install the window on a vertical, flat surface; cut the
installation holes using an angle grinder or a nibbler tool.
Required Tools
• Metal cutting tool such as nibbler or
angle grinder (see Fig-2)
• Drill and 8mm (5/16
”
) drill bit
• Center punch
• De-burring tool or another file tool
• Socket or wrench (7/16”)
• Metal treatment product with anti-corrosion properties (paint, sealer)
Personal Protection Equipment (PPE)
Work gloves and safety glasses are required. Please comply with all site PPE
requirements.
Transmission Rate
Determine the transmission rate of the IR window you are installing. Notate
the transmission rate on the supplied IR window label.