Flex 80 Mil SS User Manual

Product Data Sheet
FLEX SBS 80 Mil S/S BASE SHEET
PRODUCT DESCRIPTION
Flex SBS 80 Mil S/S Base Sheet is designed for use as the base or first ply in Flex's high performance modified bitumen roofing system or multi-ply thermoplastic roofing systems.
FEATURES
· Designed for application in new construction, re-roofing and retrofit roofing.
· SBS polymer provides flow resistance at high temperatures and flexibility at low temperatures for lasting
durability.
· Glass reinforcement provides stability.
PHYSICAL PROPERTIES
Thickness: 0.080 inches (2.0 mm) ±10% Tensile Strength @ 0°F Machine Direction: 135 lbf / inch Cross Machine Direction: 117 lbf / inch Elongation @ 0°F Machine Direction: 4% Cross Machine Direction: 4% Tensile Tear Machine Direction: 80 lbf / inch Cross Machine Direction: 75 lbf / inch Low Temperature Flexibility Machine Direction: -10° F Cross Machine Direction: -10° F Dimensional Stability Machine Direction: < 0.1% Cross Machine Direction: < 0.1%
Material tested in accordance with ASTM D5147 Standard Test Method for Sampling and Testing Modified Bitumen Roofing Membranes.
PACKAGING
Thickness: 2.0 mm (80 mils) Top Surface: Sanded Roll Length : 49.2 ft. Bottom Surface: Sanded Roll Width: 39 3/8" Gross Coverage: 161.4 ft² Net Coverage: 147.8 ft²
__________________________________________________________________________________________________________________________________________________________________________________________________________
Flex Membrane International Corp. 2670 Leisczs Bridge Road, Suite 400, Leesport, PA 19533
Tel: (610) 916-9500 Fax: (610) 916-9501 www.FlexRoofingSystems.com
Page 1
LIMITATIONS
Non-resistant to oils and solvents. Refer to manufacturer for specific chemical resistance. Not designed for permanent exposure. Install Flex SBS Granulated Cap Sheet Membrane over base sheet for permanent exposure.
STORAGE
Store rolls on end, on original pallets or elevated platform. Protect from weather or store in an enclosed area not subject to heat over 120°F.
SURFACE PREPARATION
Refer to Flex's General Specifications for preparation and acceptable substrates.
APPLICATION
Flex SBS 80 Mil S/S Base Sheet must be mopped, nailed or cold adhered to substrate. Begin application of the base sheet at the lowest edge or drain. Proceed up the slope from the lowest point. Position and unroll base sheet to achieve correct overlap and alignment. Re-roll one end a minimum of 10' and adhere membrane to substrate. Complete application of remainder of sheet.
Mopping Application: Roofing asphalt shall be Flex SEBS or ASTM D312 Type III on slopes up to 1:16 and Type IV for slopes greater then 1:16. Use Flex SEBS or Type IV for all flashing.
Asphalt must be applied hot, so that it's mopping temperature is not below 400° F when measured at the mop cart, to facilitate correct interply thickness, adhesion and uniformity. The roofing membrane must be unrolled into the hot asphalt immediately. Mopping should not be more than 4 ahead of unrolling. Unroll into asphalt mopped at the rate of 20-30 lbs./100 ft², lapping 3 on sides and 6 on ends. The Presence of a beed of asphalt should be observed flowing out of the seam. Mopping at ambient Temperatures below 40º F requires special care and treatment. Refer to Flexs General Specifications.
Cold Adhered Application: Apply Flex Bitumen Adhesive by notched squeegee to laps as well as the field of the sheet at the rate of approximately 1.5 gal/100 ft².
A notched squeegee with notches ¼ long, 1/8 deep, spaced on 1 is ideal for smooth surfaces. For irregular surfaces the notches should be ¼ deep. Best results occur above 50ºF. The adhesive thickens at colder temperatures and proper coverage becomes difficult.
Roll out Flex 80 Mil S/S Base Sheet and allow to relax prior to application. Apply adhesive to substrate and allow 3 to 5 minutes open time prior to rolling in membrane. Installation without allowing open time could result in prolonged softening of the membrane or blisters.
For flashings, apply Flex Flashing Cement adhesive by trowel in a 1/8 coat. Ensure full and uniform coverage. Embed Flex 80 Mil S/S Base Sheet and apply pressure over the entire surface. Ensure a bead appears at laps.
Slopes 1:12 (1" in 12") or Greater: In addition to the above, apply membrane parallel to direction of slope and blind nail or mechanically fasten membrane at end or head lap on 6" centers.
WARRANTY
Flex Membrane International warrants to the owner, that the SBS modified bitumen membrane, when installed by a participating contractor subject to the conditions and limitations contained within the warranty, will remain watertight for a period as outlined. All leaks or roof problems, on warranted roofs, must be reported to the manufacturer in writing within a period of 30 days.
__________________________________________________________________________________________________________________________________________________________________________________________________________
Flex Membrane International Corp. 2670 Leisczs Bridge Road, Suite 400, Leesport, PA 19533
Tel: (610) 916-9500 Fax: (610) 916-9501 www.FlexRoofingSystems.com