FISCHER MINIMAX SERIES
REQUIRED TOOLING
To successfully cable the Fischer MiniMax Series tooling is required to insure proper alignment of the various parts that need to be assembled. The below instructions are valid for cable assemblies on both plug (MP11) and cable receptacle (MR50) for both sizes 06 and 08, independent of locking or coding.
Specific Tools
MiniMax support tool (FC Reference 130254)
MiniMax tool kit
Size 06 (FC Reference 130252) Size 08 (FC Reference 130253)
Generic Tools
Hand press Vogt 4255 (FC Reference 130257) or equivalent
Tool 1. : used for assembly of MP11
Tool 2. : used for assembly of MR50
Tool 3. : double sided tool for insertion of contact block (housing) and back nut for both MP11 and MR50
Tool 1 Tool 2
Tool 3
3
FISCHER MINIMAX SERIES
PARTS DESCRIPTION
2
3 4 51
6 7
Connector parts
In the tube
1. Contact block
2. Insulator tube
3.
Guide mark ring (used for overmolding only)
4. Contact block O-ring
5. Housing O-ring
Separate parts
6. Housing
7. Back nut
Bend relief
1. Clip
2. Boot bend relief
Size Uncut Level 1 Level 2
06 ø2.9 ø3.9 ø5.7
08 ø3.9 ø5.4 ø6.7
CutCut
Uncut
Level 1
Level 2
40.5
CUTTING DIAMETERS
2
1
4
FISCHER MINIMAX SERIES
PROCEDURE
1
Cut the bend relief to adjust it to the cable diameter.
Slide the bend relief +clip + back nut + insulator tube on the cable as shown in the picture.
2
Strip the cable jacket to 14mm.
(for both size 06 and 08).
3
Pull back the braid over the jacket.
We recommended to use a clear tape to hold the braid on the jacket.
Position Trim back Strip
External - 1.5mm
Intermediate 1.5mm 1.5mm
Central 3mm 1.5mm
4
Trim back and strip the conductors according to following specifications:
Illustration shows 19 contacts. Same principle of up to 3 levels (external, intermediate, central) applies for all MiniMax configurations. If only 1 level, use External level. If 2 levels, use External and Intermediate levels.
5
Solder all conductors to the contact block.
See technical specifications for wire numbering. In order to use the correct numbering scheme, please not that the landmark used to fix the contact block on the insulator tube (see arrow in the picture on the right) is OPPOSITE to the grounding pin reprensented on the PCB hole layout diagram in the MiniMax technical specifications.
5
FISCHER MINIMAX SERIES
PROCEDURE
6
Slide the insulator tube onto the contact block using the «poka yoke» mismatch protection for correct orientation.
7
Pull back the braid from the insulator tube on the cable jacket.
8
The insulator tube can be glued on the contact block for better retention.
(Loctite 406 glue recommended)
6
FISCHER MINIMAX SERIES
PROCEDURE
9
Potting of the insulator tube through the hole (upper limit = blue line). Insulator tube can be pre-heated if necessary.
We recommend to use a heat shrinkable sleeve to cover the filling-hole to avoid potting material coming out of the hole once potted.
Curing time and conditions according to your potting material.
10
Put the O-rings on the contact block (with grease) and on the housing.
11
Initial setup
Make sure the support tool (130254) is properly centered on the table press (130257) using the alignment tool provided.
Insertion of the insulator tube with the press.
Insert the insulator tube into the housing with the multifunction press until it clips on.
Use the appropriate tool set for Minimax 08 (130253) or Minimax 06 (130252).
“tool 1” for MP11 “tool 2” for MR50
“tool 3” “Housing” facing up
Make sure to align the nose of the insulator with the housing before the insertion operation.
7
FISCHER MINIMAX SERIES
CABLE ASSEMBLY TYPES
12
Pull up the braided shield.
13
Cut off the braided shield to a length slightly infe­rior to the O-ring location.
14
Fitting of the backnut with the press.
Press-fit the backnut with the multifunction press using the appropriate tool set for Minimax 08 (130253) or Minimax 06 (130252).
“tool 1” for MP11 “tool 2” for MR50
“tool 3” “Back nut” facing up
The backnut is now in position.
8
FISCHER MINIMAX SERIES
PROCEDURES
15
Potting of the back nut through the hole.
First fix the boot bend relief clip on the back nut.
Make sure the potting material entirely fills the space between the clip and the nut, all the way to the top of the clip.
We recommend using a heat shrinkable sleeve to cover the filling-hole to avoid potting material coming out of the hole once potted.
Curing time and conditions according to your pot­ting material
16
Slide the boot bend relief over the back nut until it firmly hooks on the clip.
Congratulations with your terminated MiniMax.
© Fischer Connectors SA – All rights reserved Version 2.3 – 07.2018 – Changes without prior notice
Headquarters
FISCHER CONNECTORS SA
Ch. du Glapin 20 1162 Saint-Prex – Switzerland Phone +41 21 800 95 95
Toll free +41 800 800 008
www.fischerconnectors.com mail@fischerconnectors.ch
United States & Canada
FISCHER CONNECTORS, Inc. Atlanta, GA Phone +1 678 393 5400
Toll free: 800 551 0121
www.fischerconnectors.com/us mail@fischerconnectors.com
France
FISCHER CONNECTORS Sarl Paris Phone +33 1 5578 2578
Appel gratuit: 0 800 590 444
www.fischerconnectors.fr mail@fischerconnectors.fr
Germany, Austria & Eastern Europe
FISCHER CONNECTORS GmbH Zorneding Phone +49 8106 37722 0
Gebührenfrei: 0 800 233 3233
www.fischerconnectors.de mail@fischerconnectors.de
Italy
FISCHER CONNECTORS Srl Monza Phone +39 039 734 072 www.fischerconnectors.it mail@fischerconnectors.it
United Kingdom & Ireland
FISCHER CONNECTORS Ltd. Waterlooville, Hampshire Phone +44 23 9245 9600
Toll free : 0 800 432 0301
www.fischerconnectors.co.uk sales@fischerconnectors.co.uk
India
FISCHER CONNECTORS India Pvt. Ltd. Gurgaon, Haryana Phone +91 124 4255642 to 45 www.fischerconnectors.com salesin@fischerconnectors.in
Asia
FISCHER CONNECTORS ASIA Ltd. Hong Kong Phone +852 2620 6118 www.fischerconnectors.hk mail@fischerconnectors.hk
Japon
FISCHER CONNECTORS K.K Tokyo Phone +81 (0)70 1056 6637 www.fischerconnectors.jp mail@fischerconnectors.jp
Loading...