Maxima 35 S
12
Water treatment
When treatment is used ferroli limited only recommend the use of proprietary Brand, such as Fernox or
Sentinel water treatment products, which must be used in accordance with the manufactures instructions.
for further information contact:
Feronx Manufacturing Co. LTD. Sentinel Division
Tandern house, Marlowe Way Betz Dearborn LTD
Croydon, surrey, CRO 4YS Widnes, Cheshire WA8 8ND
Tel: 0870 5601 5000 Tel: 0151 424 5351
Note - When the boiler is installed with an existing or new system any unsuitable additives or system debris
must be removed by thorough cleansing. All systems should be cleansed according to B.S. 7593.
Note - In hard water areas treatment to prevent lime scale may be necessary.
Note - It is important that the correct concentration of the water treatment product is maintained in
accordance with the manufacturers instructions.
2.4 Connection to the gas system
If necessary the local Gas supplier should be consulted, at the installation planning stage, in order
to establish the availability of an adequate supply of gas.
An existing service pipe must not be used whitout prior consultation with the local Gas sup-
plier.
A gas meter can only be connected by the Local Gas supplier, or by a Local Gas suppliers Contractor.
Installation pipes should be fitted in accordance with BS6891.
Appliance inlet working pressure must be 20 mbar MINIMUM, for NG and 37 mbar minimum for pro-
pane.
Do not use pipes of a smaller size than the combination boiler inlet gas isolation valve (22 mm).
The complete installation must be tested for gas soundness and purged as described in BS6891. All
pipework must be adquately supported. An isolating gas valve is provided and should be fitted on the
boiler gas inlet. Please wait 10 minutes when ligthing from cold before checking the gas rate. Gas pressures should be checked after the boiler has operated for 10 minutes to ensure thermal equilibrium.
The appliance has no facility to check burner pressures, a combuston test should be carried out instead,
see page 26 (combuston analyser testing).
The Isolation valve kits shown in fig. 4 are supplied as standard.
2.5 Electrical Connections
The unit must be installed in conformity with current national and local regulations.
Connection to the electrical grid
The boiler must be connected to a single-phase, 230 Volt-50 Hz electric line.
The unit’s electrical safety is only guaranteed when correctly connected to an efficient earthing
system executed according to current safety standards. Have the efficiency and suitability of the
earthing system checked by professionally qualified personnel. The manufacturer is not responsible
for any damage caused by failure to earth the system. Also make sure that the electrical system
is adequate for the maximum power absorbed by the unit, as specified on the boiler dataplate,
in particular ensuring that the cross sectional area of the system’s cables is suitable for the power
absorbed by the unit.
The boiler is prewired and provided with a cable for connection to the electricity line. The connections to
the supply must be made with a permanent connection and equipped with a double pole switch which