Assembly Instructions For
Mounting Bar
Outlet Box Mounting Screw
Threaded Pipe
Pan
Bulb (not included)
Long Threaded Pipe
Supply Ground Wire
Supply Wire
Fixture Ground Wire
Coupler
FM324
Carefully unpack and identify all parts before assembly. Bulb
1. Attach mounting bar securely to ceiling junction box with
Fixture Wire
2. Fasten one hex nut about 3/4" (19 mm) down from one end
Socket
3. Spread the electrical wires so that the black wires are on one
Lock Washer
4. Electrical connections: Connect the white wire from the fixture to the white wire of
NOTE: Black outlet box wire may be red, round & smooth
(E) 11/08
IMPORTANT
TURN OFF THE POWER AT THE MAIN FUSE OR
CIRCUIT BREAKER BOX
BEFORE STARTING INSTALLATION
not included.
two machine screws (supplied with junction box) through slot at each end of mounting bar. Note: mounting bar should be installed with "GND" imprint and/or two dimples facing down.
of threaded pipe. Then screw same end of threaded pipe into center hole in mounting bar. At this point test install the pan onto ceiling through this threaded pipe and make certain 3/8" (10 mm) of pipe protrude below. If not, then adjust the threaded pipe location by screwing up or down accordingly. Once correct threaded pipe location has been adjusted, remove pan and tighten hex nut against mounting bar. Make certain not to spin threaded pipe during tightening.
side of the outlet box and the white wires are on the other side.
the outlet box. Connect the black wire from the fixture to the black wire of the outlet box.
and/or have copper conductor. White outlet box wire may be square & ridged and/or have a silver conductor.
Shade
Cover
Finial
Flat Washer
Hex Nut
5. Grounding Connection: Connect fixture ground wire (without insulation) to ground
wire from outlet box (usually with green insulation) with wire connector (not provided).
IMPORTANT: Never connect ground wire to black or white
power supply wires.
6. Place pan thru top threaded pipe so that it sits flush against ceiling. Be sure all wires are inside pan. Secure pan to ceiling by fastening lock washer and coupler onto top threaded pipe. Note: Coupler must turn at least 3 times, if it does not you must remove coupler and lengthen threaded pipe accordingly.
7. Install bulb (not included). See relamping label located at socket area for type and maximum allowed wattage.
8. Install a hex nut onto one end of long threaded pipe leaving about 1/2" (13 mm) thread exposed. Screw same end of threaded pipe into coupler. Tighten hex nut.
9. Slip glass shade up till it checks into bottom of pan. Then lock into position by fastening with flat washer and hex nut. Do not over tighten.
10. Slip lower font through same threaded pipe and secure by
fastening with finial.