Fasani Bolted Bonnet Globe Valves, Fasani-EN Manuals & Guides

FASANI BOLTED BONNET GLOBE VALVES
INSTALLATION AND MAINTENANCE INSTRUCTIONS
Basic configuration - Flanged or welded ends
2. All actuated valves must be carefully and securely palleted or crated, in order to ensure that the parts of actuator (especially pneumatic piping or accessories) do not extend beyond the skid/crate.
3. The type of packing must be defined in the Customer’s Order and shall be appropriate to ensure safe transportation to final destination and eventual conservation before installation.
Handling requirements A - Packed valves
Crates: Lifting and handling of the packed
valves in crates will be carried out by a fork lift truck, by means of the appropriate fork hitches.
VALVE STORAGE
Preparation and preservation for shipment
All valves are properly packed in order to protect the parts that are subject to deterioration during transportation and storage on site. In particular, the following precautions should be taken:
1a. Flanged sealing valves: The flange
sealing surfaces (raised faces) of the valves shall be protected with suitable protective grease. The end faces of the valve must be protected with plastic or wooden discs fixed with straps.
1b. Buttweld end valves: The weld ends
surface shall be protected with suitable protective like Deoxaluminite. The end shall be closed with plywood or plastic disc fixed at the edge by straps.
Cases:
The lifting of packed valves in cases should be carried out in the lifting points and at the center of gravity position which have been marked. The transportation of all packed material must be carried out safely and following the local safety regulations.
B - Unpacked valves
1. The lifting and the handling of these valves has to be carried out by using appropriate means and by respecting the carrying limits. The handling must be carried out on pallets, protecting the machined surfaces to avoid any damage.
2. With valves of large dimensions, the sling and the hooking of the load must be carried out by using the appropriate tools (brackets, hook, fasteners, ropes) and load balancing tools in order to prevent them from falling or moving during the lifting and handling.
Emerson.com/FinalControl
VCIOM-01613-EN 19/03© 2017 Emerson. All Rights Reserved.
FASANI BOLTED BONNET GLOBE VALVES
INSTALLATION AND MAINTENANCE INSTRUCTIONS
FIGURE 1 Valve slinging
Storage and preservation before installation
In case the valves have to be stored before installation, the storage has to be carried out in a controlled way, and has to be performed in accordance with the following criteria:
1. The valves have to be stocked in a closed, clean and dry storage room.
2. The disc must be in the closed position, and the end faces must be protected with plastic or wooden discs fixed with straps. If possible, keep the original protection.
3. Periodical checks have to be carried out in the storage area to verify that the above mentioned conditions are maintained.
For actuated valves, in addition to the above, please refer to the warnings in the manual of the actuator.
INSTALLATION
Preparation before installation
1. Carefully remove the valve from the shipping package (box or pallet) avoiding any damage to the valve or, in case of automated valves, to the electric or pneumatic/ hydraulic actuator or instrumentation.
2. The valves are shipped with the ends protected with caps and a thin layer of protective grease. Before installing the valve, remove the caps and clean carefully, then degrease both surfaces with a solvent. Clean the inside of the valve by using an air line. Ensure that there are no solid objects such as pieces of wood, plastic or packing materials within the valve or on the valve seat.
3. Confirm that the materials of construction listed on the valve nameplates (service and temperature) are appropriate for the service intended and are as specified.
4. Define the preferred mounting orientation with respect to the system pressure. If any (see arrow on the body), identify the upstream side (high pressure) and downstream side (low pressure).
WARNING
Verify that the direction of the flow in the line corresponds to the arrow indicated on the valve body. See the actuator user manual for the actuator preparation.
NOTE
Storage in an open area for a limited period can be considered only in case the valves have appropriate packing (packed in cases lined with tarred paper, and contents well protected with barrier sacks). Do not place consignment packages directly on the ground. Do not expose consignment packages to the weather or directly to the sun. Check the packaging every two months.
CAUTION
For valve handling and/or lifting, the lifting equipment (fasteners, hooks, etc.) must be sized and selected while taking into account the valve weight indicated in the packing list and/or delivery note. Lifting and handling must be made only by qualified personnel. Do not use the lifting points located on the actuator, if any, to lift the valve. These lifting points are for the actuator only. Caution must be taken during the handling to avoid that this equipment passes over the workers or over any other place where a possible fall could cause damage. In any case, the local safety regulations must be respected.
2
FASANI BOLTED BONNET GLOBE VALVES
INSTALLATION AND MAINTENANCE INSTRUCTIONS
FIGURE 2 Installation positions recommended
40° max
40° max
Flow
Installation instructions
Globe valves are normally installed in horizontal pipe with vertical stem. These valves can also be installed in vertical or horizontal pipe with stem other than vertical, but this may require special construction depending on valve size, service condition, material and type of operator. For a correct operation, Fasani recommends that the valve shall be installed and oriented following the indications of Figure 2. Different positions from those indicated may cause a non-correct valve operation, and/or a quick deterioration of the valve. Unless otherwise recommended by Fasani, the valve should be installed with the disc in the closed position, to ensure that the seat ring in the disc is not damaged during installation. Particular care should be taken with those valves equipped with ‘fail-open’ actuators. For operating temperatures above 200 °C (392 °F) thermal insulation of the valve body is recommended. Handling and lifting of the valves during installation MUST be performed following the same criteria and instructions described in previous points “Handling requirements” and “Storage and preservation before installation”.
Buttweld valves
Position the valve and check the alignment with the pipe, then proceed with welding, in accordance with the applicable welding procedure.
Flanged valves
Place the valve between the two flanges of the pipe and put the seal gasket between the valve flange and the pipe flange; make sure that it is correctly positioned. Then assemble the valve to the pipe by the bolts which will be tightened crossing. Progressively reach the requested torque value indicated by the Engineering Company that designed the plant.
40° max
40° max
IMPORTANT
After the valves installation and before the line testing, it is recommended to perform an accurate cleaning of the lines to eliminate dirt and any foreign objects that could seriously jeopardize the tightness between seat/disc and the correct operation of the valve.
After the valve installation on the line and before the line pressurization, the following activities must be performed:
- all the threads plugs tightening shall be
verified
- the packing bolts must be tightened
- the torque of the body-bonnet bolts shall be
verified
- the valve has to be fully stroke operated
- the paper protecting the stem must be
removed; stem and bearings must be greased.
See Table 1 (Bolt torque figures for body­bonnet flanged connections) and table 2 (Bolt torque figures for packing bolts). If any, see the actuator instruction manual for the related commissioning start-up procedure.
Valve verification before start up
1. Tighten the packing just enough to prevent stem leakage. Over-tightening will decrease packing life and increase operating torque. The bolt torque figures for the packing bolts can be calculated as indicated in Table 1.
2. Check the operation of the valve by stroking it to “full open” and “full close”.
IMPORTANT
If piping system is pressurized with water for testing, and in case the piping system has been shut down after testing for a long time, the following recommendations should be adopted. a. Use corrosion inhibitor with water to
pressurize the piping system
b. After testing, the piping system should be
depressurized and the test water completely drained.
3
FASANI BOLTED BONNET GLOBE VALVES
INSTALLATION AND MAINTENANCE INSTRUCTIONS
Operations instructions
The following instructions will help provide a satisfactory and long life service of the bolted bonnet globe valves:
1. Make sure to perform periodic valve verification as described in the next paragraph.
2. In case of actuated valves always follow the specific instructions given by the actuator’s manufacturer.
3. Never change the setting of torque and/or limit switches which have been carefully set during the final test at workshop.
Periodic valve verification during service A - Normal check
1. Verify monthly that there is no leakage from packing or in the body/bonnet area. If the leakage has been detected from the packing, tighten nuts according to the procedure described in following Maintenance Section.
If the leakage does not stop, follow the
procedure for packing maintenance.
If the leakage has been detected from the
body/bonnet, tighten the nuts as indicated in Table 1.
If the leakage does not stop, follow the
maintenance procedure for the replacement of the body/bonnet gasket.
2. Every 2/3 months, depending on operating frequency, verify the greasing of bearings and stem thread.
3. For actuated valves, in addition to the above, please refer also to the warnings in the actuator manual.
B - Preventive actions
1. Every 3 months verify the tightness of gland bolts.
2. Every 6 months on motorized valves and every 8 months on hand operated valves, grease stem and bearings.
3. Every 12 months check the travel of the gland follower, setting a new packing when the end of the travel is approaching.
4. Every 4 years disassemble the critical service valves and/or actuated valves, verifying the sealing surfaces and lap them again when necessary. Substitute the bonnet gasket and the packing, grease the stem.
5. For the actuator, proceed as indicated in its maintenance manual.
TABLE 1 - BOLT TORQUE FIGURES FOR BODY-BONNET FLANGED CONNECTIONS (Corresponding to approx. 40% Of yield strength on dry steel surface)
Materials: A193 B7 / A193 B16 / A320 L7 Material: A193 B8 Nominal bolt Diameter (In.)
½ 9 66 90 3 19 26 ⅝ 18 129 175 5 37 50 ¾ 31 224 305 9 64 87 ⅞ 50 358 487 14 102 139 1 74 533 725 21 152 207 1⅛ 107 772 1050 31 221 300 1¼ 149 1075 1462 43 307 418 1⅜ 201 1447 1968 57 413 562 1½ 263 1896 2579 75 542 737 1⅝ 339 2445 3325 97 699 950 1¾ 426 3072 4178 122 878 1194 1⅞ 527 3798 5165 150 1085 1476 2 642 4630 6297 183 1323 1799 2¼ 921 6640 9030 263 1897 2580 2½ 1271 9162 12460 363 2618 3560 2¾ 1537 11085 15076 439 3167 4307 3 2003 14447 19648 572 4128 5614 3¼ 2556 18428 25062 730 5265 7161 3½ 3201 23079 31387 914 6594 8968
Kgm Ft⋅lb Nm Kgm Ft⋅lb Nm
Torque Torque
TABLE 2 - Torque (Nm) for packing bolts
Diameter (In.)
¼ 39 12 ⅜ 74 24 ½ 127 40 ⅝ 305 96 ¾ 588 186 ⅞ 793 251 1 1006 318 1⅛ 1973 623 1¼ 2662 841 1⅜ 3418 1080 1½ 4395 1389 1⅝ 5436 1718 1¾ 6751 2133 1⅞ 8125 2568 2 10443 3300 2¼ 12978 4102 2⅜ 16317 5157 2½ 19457 6149 2⅝ 23515 7431
B7/L7/B16 B8/B8M
Material
4
FASANI BOLTED BONNET GLOBE VALVES
INSTALLATION AND MAINTENANCE INSTRUCTIONS
TROUBLESHOOTING GUIDE
Symptom Possible cause Solution
Stem packing leaking
Body-Bonnet leaking Valve leaking 1. Valve not fully closed 1. Close valve
Jerky operation 1. Packing is too tight 1. Loosen gland nuts, cycle valve, retighten
Back seat leaking 1. Back seat damage 1. Replace the back seat
MAINTENANCE
1. Gland flange nuts too loose 1. Tighten gland flange nuts.
2. Packing damaged 2. Replace packing (See paragraph Packing maintenance)
1. Body-bonnet flange bolting loose 1. Tighten bottom flange bolting
2. Gasket damage 2. Replace the gasket
2. Debris trapped in valve 2. Cycle and flush (with valve open) to remove debris
3. Sealing surface damaged 3. Recondition the sealing surface
2. Air supply inadequate
(for pneumatic act.)
2. Increase air supply pressure
1. Open completely the valve up to the backseat position.
The Fasani bolted bonnet globe valves have been designed to require minimum maintenance. This manual describes on site repairs as:
- Packing maintenance
- Body/bonnet flange gasket maintenance
2. Remove the nuts (16) of the gland bolts (15)
3. Lift the gland flange (10) and the gland (9)
4. Remove the worn-out packing using a hooking wire
5. For a better tightness, proceed to an accurate cleaning of the stem and stuffing box and make sure there are no scratches
All the other repairs should be performed by Emerson
or signs of seizing
6. The repacking shall be carried out by placing one ring at a time around the stem,
Packing maintenance
If leakage is observed through the packing, tighten the gland nuts slowly and evenly until the leakage stops.
inside the stuffing box and by making sure that they are correctly oriented. Press it into the bottom (refer to Figure 3).
7. When the stuffing box is filled, replace the gland (9) and gland flange (10) in their
CAUTION
Do not over-tighten packing gland nuts. Over­tightening will increase the torque required to operate the valve. When tightening the gland nut, use half-turn increments until leakage has stopped.
original position.
8. T
ighten gland nuts in accordance with Table 2
(Bolt torque figures for packing bolts).
9. Cycle the valve.
10. Pressurize the line.
11. If a leakage is detected, tighten the gland nuts slowly and evenly until the leakage
Please refer to Figure 4.
stops.
To replace the packing proceed as follows:
Body-bonnet flange gasket maintenance
WARNING
Before starting any maintenance, depressurize, drain and vent the line; check that the valves are not in temperature; disconnect any electrical power supply. Failure to do so may cause serious personal injury and/or equipment damage.
WARNING
Before starting any maintenance, depressurize, drain and vent the line; check that the valves are not in temperature; disconnect any electrical power supply. Failure to do so may cause serious personal injury and/or equipment damage.
FIGURE 3
1 = Braided graphite rings 2 = Die formed graphite (4 rings)
FIGURE 4
15 16
10
9
5
FASANI BOLTED BONNET GLOBE VALVES
INSTALLATION AND MAINTENANCE INSTRUCTIONS
FIGURE 5
1. Before replacing the gasket, carefully clean the flange surfaces.
2. Place the gasket in its seat and begin to carefully position the bonnet flange. Position it perfectly parallel to the gasket face; do not use the bolts to obtain this alignment.
3. In case the coupling is vertical (valve with horizontal stem), position the bonnet flange by means of a hoist; lock it with four bolts placed at 90° on from the other and tighten them until the flanges are perfectly coupled in their seat. Insert all the other bolts.
4. During tightening, make sure that the faces of the flanges remain perfectly parallel.
5. Tighten the bolts in the sequence indicated in Figure 5, using for the first turn a torque of approx. ¼ of the maximum torque listed on table 1. For a better performance of the joint, tighten again all the bolts after the equipment has been pressurized.
VALVE REMOVAL
If the valve needs to be removed from the line for some extraordinary reason, the user should ensure the following:
1.
The valve is depressurized, drained and vent.
2. The pipe shall be cut as far away from the valve as possible (only for welded valves).
GREASES AND SPECIAL TOOLS
Greases
To lubricate the bearings on manual and gearbox operated valves, we suggest to use the grease AGIP GRMUEP2 or an equivalent product, as showed in the following table:
TABLE 3 - GREASE AND LUBRICANT LIST
Manufacturer Grease
AGIP GRMUEP2 API PGX2 BP GREASE LTX2 ESSO BEACON 2 FINA FINAGREASE HP FINAGREASE EPL2 MOBIL MOBILUX EP2 Q8 REMBRANDT EP2 SHELL ALVANIA R2 SUPERGREASE A TEXACO MULTIFAK EP2 GREASE L2 TOTAL MULTIS EP2 MULTIS 2 VISCOL SIGNAL ROLSFER 2
For the lubrication of the stem thread, use the grease SIGNAL CEP 30 produced by Viscol. As an alternative you can utilize:
- CEPLATTYN 300 produced by REINER-FUCHS
- GRAFLOSCON produced by KLUBER You can also use a grease having more than 25% pure graphite content (carbon 98%) granulometry 5 microns, without any abrasive agent. For the lubrication of the actuator, refer to the relevant manual.
Special tools
No special tool required for the maintenance operation described in this manual.
6
FASANI BOLTED BONNET GLOBE VALVES
INSTALLATION AND MAINTENANCE INSTRUCTIONS
7
Neither Emerson, Emerson Automation Solutions, nor any of their affiliated entities assumes responsibility for the selection, use or maintenance of any product. Responsibility for proper selection, use, and maintenance of any product remains solely with the purchaser and end user.
Fasani is a mark owned by one of the companies in the Emerson Automation Solutions business unit of Emerson Electric Co. Emerson Automation Solutions, Emerson and the Emerson logo are trademarks and service marks of Emerson Electric Co. All other marks are the property of their respective owners.
The contents of this publication are presented for informational purposes only, and while every effort has been made to ensure their accuracy, they are not to be construed as warranties or guarantees, express or implied, regarding the products or services described herein or their use or applicability. All sales are governed by our terms and conditions, which are available upon request. We reserve the right to modify or improve the designs or specifications of such products at any time without notice.
Emerson.com/FinalControl
8