Installation Information
Water Piping Connections
Desuperheater Connections
Electrical
Startup Procedures
Troubleshooting
Preventive Maintenance
Envision Residential Installation Manual
IM1585 10/07
ENVISION RESIDENTIAL INSTALLATION MANUAL
Model Nomenclature
Model Type
N= Envision
Compressor Type
D= Dual Capacity
S= Single Speed
Cabinet Configuration
V= Vertical
H= Horizontal
Unit Capacity
Vintage
A= Current
Voltage
1=208-230/60/1
NDV049A111CTL
Return Air Configuration
L=Left
R=Right
Discharge Air Configuration
B=Bottom
T=Top
S=Side
E=End
Coax Options
C=Copper
N=Cupronickel
Fan Option
0=PSC
1=ECM
2=Oversized ECM Blower Option
(036,038,042,048,049)
3=Oversized PSC Blower Option
(022,030,036,042,048)
Hot Water Option
0=None
1=Hot Water Generation with
factory installed pump
Notes: PSC Motor - Single Speed Only
2
ENVISION RESIDENTIAL INSTALLATION MANUAL
T able of Contents
General Installation Information 4-8
Closed Loop Ground Source Systems 9
Open Loop Ground Water Systems 10
Desuperheater Connection & Startup 11-12
Electrical Connections 13-14
Electronic Thermostat Installation 14
Auxiliary Heat Ratings 14
Electrical Data 15
Fan Performance Table 16-17
Setting Fan Speed 16-17
Vertical Dimensional Data 18
Horizontal Dimensional Data 19
Vertical Bottomfl ow Dimensional Data 20
Physical Data 21-22
Wiring Schematics 23-27
Microprocessor Control 28-32
Unit Startup 33
Operation Logic 34
Unit Operating Parameters 35-36
Pressure Drop & Recommended Flow Rates 37
Troubleshooting 38
Preventive Maintenance 39
Replacement Procedures 39
3
ENVISION RESIDENTIAL INSTALLATION MANUAL
General Installation Information
Safety Considerations
WARNING: Before performing service or maintenance operations on a system, turn off main
power switches to the indoor unit. If applicable, turn off the accessory heater power switch.
Electrical shock could cause personal injury.
Installing and servicing heating and air conditioning equipment can be hazardous due to system pressure and electrical
components. Only trained and qualifi ed service personnel should install, repair or service heating and air conditioning equip-
ment. Untrained personnel can perform the basic maintenance functions of cleaning coils and cleaning and replacing fi lters.
All other operations should be performed by trained service personnel. When working on heating and air conditioning equipment, observe precautions in the literature, tags and labels attached to the unit and other safety precautions that may apply.
Follow all safety codes. Wear safety glasses and work gloves. Use a quenching cloth for brazing operations and have a
fi re extinguisher available.
Moving and Storage
Move units in the normal “up” orientation. Horizontal units may be moved and stored per the information on the packaging. Do not stack more than three units in total height. Vertical units may be stored one upon another to a maximum height
of two units. Do not attempt to move units while stacked. When the equipment is received, all items should be carefully
checked against the bill of lading to be sure all crates and cartons have been received. Examine units for shipping damage,
removing the units from the packaging if necessary. Units in question should also be internally inspected. If any damage is
noted, the carrier should make the proper notation on the delivery receipt, acknowledging the damage.
Unit Location
Locate the unit in an indoor area that allows for easy removal of the fi lter and access panels. Location should have
enough space for service personnel to perform maintenance or repair. Provide suffi cient room to make water, electrical
and duct connection(s). If the unit is located in a confi ned space, such as a closet, provisions must be made for return air
to freely enter the space by means of a louvered door, etc. Any access panel screws that would be diffi cult to remove after
the unit is installed should be removed prior to setting the unit. On horizontal units, allow adequate room below the unit for
a condensate drain trap and do not locate the unit above supply piping. Care should be taken when units are located in
unconditioned spaces to prevent damage from frozen water lines and excessive heat that could damage electrical
components.
Installing Vertical Units
Prior to setting the unit in place, remove and discard the compressor hold down
shipping bolt located at the front of the compressor mounting bracket.
Vertical units are available in left or right air return confi gurations. Top air dis-
charge vertical units should be mounted level on a vibration absorbing pad slightly
larger than the base to provide isolation between the unit and the fl oor. It is not
necessary to anchor the unit to the fl oor (see right).
Bottomfl ow units should be mounted level and sealed well to fl oor to prevent air
leakage. Bottomfl ow units require the supply air opening to be cut at least 1/2˝ larger
than the unit’s air outlet. Protect the edges of combustible fl ooring with sheet metal
over-wrap or other non-combustible material.
Figure 1: Vertical Unit Mounting
2” Extruded
Polystyrene
4
ENVISION RESIDENTIAL INSTALLATION MANUAL
Installing Horizontal Units
Remove and discard the compressor hold down shipping bolt located at the front of the compressor mounting bracket
prior to setting the unit in place. Horizontal units are available with side or end discharge. Horizontal units are normally suspended from a ceiling by six 3/8-inch diameter threaded rods. The rods are usually attached to the unit by hanger bracket
kits furnished with each unit.
Lay out the threaded rods per the dimensions below. Assemble the hangers to the unit as shown. Securely tighten the
brackets to the unit using the weld nuts located on the underside of the bottom panel. When attaching the hanger rods to
the bracket, a double nut is required since vibration could loosen a single nut. To allow fi lter access, one bracket on the fi lter
side should be installed 180° from the position shown in the fi gure below. The unit should be pitched approximately 1/4-inch
towards the drain in both directions to facilitate the removal of condensate. Use only the bolts provided in the kit to attach
hanger brackets. The use of longer bolts could damage internal parts.
Some residential applications require the installation of horizontal units on an attic fl oor. In this case, the unit should
be set in a full size secondary drain pan on top of a vibration absorbing pad. The secondary drain pan prevents possible
condensate overfl ow or water leakage damage to the ceiling. The secondary drain pan is usually placed on a plywood base
isolated from the ceiling joists by additional layers of vibration absorbing material.
CAUTION: Do not use rods smaller than 3/8-inch diameter since they may not be strong enough to
support the unit. The rods must be securely anchored to the ceiling.
Figure 2: Horizontal Unit Mounting
O
Threaded Rods
Electrical
Disconnect
To Line
Power
To
Thermostat
Line Voltage
Building Water Loop
Flexible Duct
Collar
Insulate supply
plenum and use
at least one 90
elbow to
reduce noise
An air outlet collar is provided on vertical top air discharge units and all horizontal units to facilitate a duct connection
(vertical bottomfl ow units have no collar). A fl exible connector is recommended for discharge and return air duct connec-
tions on metal duct systems. Uninsulated duct should be insulated with a minimum of 1-inch duct insulation. Application of
the unit to uninsulated ductwork in an unconditioned space is not recommended as the unit’s performance will be adversely
affected.
If the unit is connected to existing ductwork, check the duct system to ensure that it has the capacity to accommodate
the air required for the unit application. If the duct is too small, as in the replacement of heating only systems, larger ductwork should be installed. All existing ductwork should be checked for leaks and repaired if necessary.
The duct system should be sized to handle the design airfl ow quietly and effi ciently. To maximize sound attenuation of
the unit blower, the supply and return plenums should include an internal duct liner of fi berglass or constructed of ductboard
for the fi rst few feet. On systems employing a sheet metal duct system, canvas connectors should be used between the unit
and the ductwork. If air noise or excessive airfl ow is a problem, the blower speed can be changed.
CAUTION: Be sure to remove the shipping material from the blower discharge before connecting ductwork.
Water Piping
The proper water fl ow must be provided to each unit whenever the
Figure 4: Swivel Connections
(Residential Units)
unit operates. To assure proper fl ow, use pressure/temperature ports
to determine the fl ow rate. These ports should be located at the supply
and return water connections on the unit. The proper fl ow rate cannot
be accurately set without measuring the water pressure drop through
the refrigerant-to-water heat exchanger.
All source water connections on commercial units are fi ttin g s that
accept a male pipe thread (MPT). Insert the connectors by hand, then
tighten the fi tting with a wrench to provide a leakproof joint. When con-
necting to an open loop (groundwater) system, thread any copper MPT
Stainless
Steel
Snap Ring
Gasket
Material
Locking
Ring
Gasket
Support
Sleeve
fi tting into the connector and tighten in the same manner as described
above.
All source water connections on residential units are swivel piping
fi ttings (see Figure 4) that accept a 1-inch male pipe thread (MPT) .
The swivel connector has a rubber gasket seal similar to a rubber hose
gasket, which when mated to the fl ush end of any 1-inch threaded pipe
provides a leak-free seal without the need for thread sealing tape or
compound. Check to ensure that the rubber seal is in the swivel connector prior to attempting any connection. The rubber seals are shipped
attached to the waterline. To make the connection to a ground loop system, mate the brass connector (supplied in CK4L connector kit) against
the rubber gasket in the swivel connector and thread the female locking
ring onto the pipe threads, while maintaining the brass connector in the
desired direction. Tighten the connectors by hand, then gently snug the
fi tting with pliers to provide a leak-proof joint. When connecting to an open loop (ground water) system, thread any 1-inch
MPT fi tting (SCH80 PVC or copper) into the swivel connector and tighten in the same manner as noted above. The open
and closed loop piping system should include pressure/temperature taps for serviceability.
Never use fl exible hoses smaller than 1-inch inside diameter on the unit. Limit hose length to 10 feet per connection.
Check carefully for water leaks.
6
ENVISION RESIDENTIAL INSTALLATION MANUAL
Water Quality
In ground water situations where scaling could be heavy or where biological growth such as iron bacteria will be present, a closed loop system is recommended. The heat exchanger coils in ground water systems may, over a period of time,
lose heat exchange capabilities due to a buildup of mineral deposits inside. These can be cleaned, but only by a qualifi ed
service mechanic, as special solutions and pumping equipment are required. Desuperheater coils can likewise become
scaled and possibly plugged. In areas with extremely hard water, the owner should be informed that the heat exchanger
may require occasional fl ushing.
Units with cupronickel heat exchangers are recommended for open loop applications due to the increased resistance to
build-up and corrosion, along with reduced wear caused by acid cleaning.
7
ENVISION RESIDENTIAL INSTALLATION MANUAL
Freeze Protection
Set the freeze sensing switch SW2-2 on the printed circuit board for applications using a closed loop antifreeze solution
to “LOOP”. On applications using an open loop/ground water system (or closed loop no antifreeze), set this dip switch to
“WELL”, the factory default setting. (Refer to the Dip Switch Field Selection table on page 24.)
Condensate Drain
On vertical units, the internal condensate drain assembly consists of a drain tube which is connected to the drain pan, a
3/4-inch PVC female adapter and a fl exible connecting hose. The female adapter may exit either the front or the side of the
cabinet. The adapter should be glued to the fi eld-installed PVC condensate piping. On vertical upfl ow units, a condensate
hose is inside all cabinets as a trapping loop; therefore, an external trap is not necessary.
On horizontal units, a PVC stub is provided for condensate drain piping connection. An external trap is required (see
below). If a vent is necessary, an open stand pipe may be applied to a tee in the fi eld-installed condensate piping.
Figure 5: Horizontal Drain Connection
3/4” PVC tube stub
Figure 6: Unit Pitch for Drain
3/4" PVC
Coupling
1.5"
Vent (if needed)
3/4" PVC
1/8" per foot
1.5"
1/2'' Pitch
Drain
8
ENVISION RESIDENTIAL INSTALLATION MANUAL
Closed Loop Ground Source Systems
Note: For closed loop systems with antifreeze protection, set SW2-2 to the “loop” position (see table on page 28).
Once piping is completed between the unit, pumps and the ground loop (see fi gure below), fi nal purging and charging
of the loop is required. A fl ush cart (or a 1.5 HP pump minimum) is needed to achieve adequate fl ow velocity in the loop
to purge air and dirt particles from the loop itself. Antifreeze solution is used in most areas to prevent freezing. Flush the
system adequately to remove as much air as possible then pressurize the loop to a static pressure of 40-50 PSI (summer)
or 50-75 PSI (winter). This is normally adequate for good system operation. Loop static pressure will fl uctuate with the
seasons. Pressures will be higher in the winter months than during the cooling season. This fl uctuation is normal and should
be considered when initially charging the system.
After pressurization, be sure to open the plug 1 turn in the end of the loop pump motor(s) (if applicable) to allow trapped
air to be discharged and to ensure that the motor housing has been fl ooded. Ensure that the loop pumps provide adequate fl ow through the unit(s) by checking the pressure drop across the heat exchanger and comparing it to the unit capacity data
in the specifi cation catalog. 2.5 to 3 GPM of fl ow per ton of cooling capacity is recommended in earth loop applications.
Figure 7: Closed Loop Ground Source Application
Auxiliary Heat
Disconnects
(If Applicable)
Unit Supply
Thermostat
Supply
Low
Voltage to
Vibration Absorbing Pad
Polyethylene w/
P/T Plugs
Multiple Units on
One Flow Center
When two units are connected to
one loop pumping system, pump control is
automatically achieved by connecting the
SL terminals on connector P2 in both units
with 2-wire thermostat wire. These terminals
are polarity dependant (see Figure 8). The
loop pump(s) may be powered from either
unit, whichever is more convenient. If either
unit calls, the loop pump(s) will automatically start. The use of two units on one fl ow
center is generally limited to a total of 20
GPM capacity.
®
GeoLink
®
Armaflex
Insulation
Flexible Duct
Collar
Auxiliary
Heater
Knockout
Unit Power
Desuperheater
Connections
Drain
P/T
Envision to Envision
Microprocessor Units
Dual Capacity
Envision Unit #1
Shut
CC
Down
With pump
wired to Unit 1
With pump
wired to
Unit 2
Shut
CC
Down
Envision Unit #2
Dual Capacity
Link
o
Ge
Flow
nt
e
C
Insulated piping
or hose kit
SL1InSL1
Out
SL1InSL1
Out
TO
LOOP
®
r
e
Note: Additional information can be found
in Flow Center installation manual (IM1961)
and Flush Cart manual (WFS302).
Figure 8: Primary/Secondary Hook-up
Envision to Envision
Microprocessor Units
Single Speed
Envision Unit #1
Shut
Down
Shut
Down
Envision Unit #2
Single Speed
CC
CC
SL1InSL1
Out
SL1InSL1
Out
With pump
wired to Unit 1
With pump
wired to
Unit 2
Envision to
Electromechanical Units
Envision Unit #1
Shut
Down
To Electromechanical Unit
CC
C
SL1InSL1
S
Out
9
ENVISION RESIDENTIAL INSTALLATION MANUAL
)
)
)
Open Loop Ground Water Systems
Typical open loop piping is shown below. Always maintain water pressure in the heat exchanger by placing water control
valves at the outlet of the unit to prevent mineral precipitation. Use a closed, bladder-type expansion tank to minimize
mineral formation due to air exposure. Insure proper water fl ow through the unit by checking pressure drop across the heat
exchanger and comparing it to the fi gures in unit capacity data tables in the specifi cation catalog. 1.5-2 GPM of fl ow per ton
of cooling capacity is recommended in open loop applications. Due to only minor differences in fl ow rate from low to high,
only one solenoid valve should be used. The valve should be sized for full fl ow .
Discharge water from the unit is not contaminated in any manner and can be disposed of in various ways, depending
on local codes, i.e. recharge well, storm sewer, drain fi eld, adjacent stream or pond, etc. Most local codes forbid the use of
sanitary sewer for disposal. Consult your local building and zoning departments to assure compliance in your area.
Note: For open loop/groundwater systems or systems that do not contain an antifreeze solution, set SW2-Switch #2 to the
“WELL ” position. (Refer to the table on page 28.) Slow opening/closing solenoid valves ( type VM) are recommended to eliminate
water hammer.
Figure 9a: Open Loop Solenoid Valve Connection Option
Typical quick operating external 24V water solenoid valve
(type PPV100 or BPV100) wiring.
C
P1
R
SV
Acc Com
Acc NC
Acc NO
1
2
P3
3
Solenoid
Valve
Note:
SW2-3 should be in the Comp “ON” position.
Figure 10: Open System - Groundwater Application
Unit Supply
Aux. HeatSupply
Figure 9b: Open Loop Solenoid Valve Connection Option
To m a x i m i ze t h e b e n e fi ts of the desuperheater a minimum 50- gallon water heater is recommended. For higher
demand applications, use an 80 -gallon water heater or two 50 -gallon water heaters connec ted in a series as shown
below. Electric water heaters are recommended. Make sure all local electrical and plumbing codes are met for installing
a desuperheater.
Note: Under certain conditions, Envision dual capacity units operate with very low refrigerant discharge temperatures,
producing little or no water heating capability. This scenario occurs when the unit is operating with cold entering source
water (loop or well). Allowing the desuperheater pump to operate during these conditions actually removes heat from the
DHW circulating through the unit. To overcome this, En vision unit microprocessors have been programmed to disengage
the desuperheater pump during such conditions. (Dur ing low capac ity c ooling oper ation, the pump will operate only if
the DHW temperature entering the unit is less than the liquid line temperature plus 35º F. During high capacity cooling
operation, the pump will operate only if the DHW temperature is less than the l i quid line t emperature plus 60º F.) Using
a preheat tank, as shown in Figure 12, will maximize desuperheater capabilities.
Water Tank Preparation
To install a unit with desuperheater, follow these installation guidelines.
Turn off the power to the water heater.
1.
Attach a water hose to the water tank drain connection and run the other end of the hose to an open drain or
2.
outdoors.
Close the cold water inlet valve to the water heater tank.
3.
Drain the tank by opening the valve on the bottom of the tank, then open the pressure relief valve or hot water
4.
faucet.
Flush the tank by opening the cold water inlet valve to the water heater to free the tank of sediments. Close when
5.
draining water is clear.
Disconnect the garden hose and remove the drain valve from the water heater.
6.
Refer to Plumbing Installation and Desuperheater Startup on page 12.
7.
Residential units with desuperheaters contain an internal circulator and fi ttings.
CAUTION: Elements will burn out if energized dry.
Figure 11: Typical Desuperheater Installation
3/4 x 3/4 x 1/2 tee
Venting Waste
Valve or Vent
Coupling
DHW
Water In
DHW
Water Out
Cold
Water In
P/T Relief
Drain Valve
Valve
Water Out
In
Hot
Figure 12: Desuperheater Installation In Preheat Tank
Venting Waste Valve
or Vent Coupling
Note: This confi guration maximizes desuperheater capability.
3/4" x 3/4" x 1/2"
tee
DHW
Water In
DHW
Water Out
Cold
Water In
P/T Relief
Valve
In
Drain ValveDrain Valve
Hot
Water Out
P/T Relief
Valve
11
ENVISION RESIDENTIAL INSTALLATION MANUAL
Plumbing Installation
1. Inspect the dip tube in the water heater cold inlet for a check valve. If a check valve is present it must be removed
or damage to the desuperheater circulator will occur.
2. Remove drain valve and fi tti n g .
3. Thread the 3/4-inch NPT x 3-1/2-inch brass nipple into the water heater drain port.
4. Attach the center port of the 3/4-inch FPT tee to the opposite end of the brass nipple.
5. Attach the 1/2-inch copper to 3/4-inch NPT adaptor to the side of the tee closest to the unit.
6. Install the drain valve on the tee opposite the adaptor.
7. Run interconnecting tubing from the tee to DHW water out.
8. Cut the cold water “IN” line going to the water heater.
9. Insert the reducing solder tee in line with cold water “IN” line as shown.
10. Run interconnecting copper tubing between the unit DHW water “IN” and the tee (1/2-inch nominal).
The recommended maximum distance is 50 feet.
11. To prevent air entrapment in the system, install a vent coupling at the highest point of the interconnecting lines.
12. Insulate all exposed surfaces of both connecting water lines with 3/8-inch wall closed cell insulation.
Note: All plumbing and piping connections must comply with local plumbing codes
.
Desuperheater Startup
1. Close the drain valve to the water heater.
2. Open the cold water supply to the tank.
3. Open a hot water faucet in the building to bleed air from the system. Close when full.
4. Open the pressure relief valve to bleed any remaining air from the tank, then close.
5. If so equipped, unscrew the indicator plug 1 turn on the motor end of the pump until all air is purged from the pump,
then tighten the plug. Use vent couplings to bleed air from the lines.
6. Carefully inspect all plumbing for water leaks and correct as required.
7. Before restoring electrical supply to the water heater, adjust the temperature setting on the tank.
• On tanks with both upper and lower elements, the lower element should be turned down to the lowest setting,
approximately 100°F. The upper element should be adjusted to 120°F to 130°F. Depending upon the specifi c needs of the customer, you may want to adjust the upper element differently.
• On tanks with a single element, lower the thermostat setting to 120°F.
8. After the thermostat(s) is adjusted, replace the access cover and restore electrical supply to the water heater.
9. Make sure that any valves in the desuperheater water circulating circuit are open.
10. Turn on the unit to fi rst stage heating.
11. The DHW pump should be running. When the pump is fi rst started, open the inspection port 1 turn (if equipped) until water dribbles out, then replace. Allow the pump to run for at least fi ve minutes to ensure that water has fi lled the circulator properly. Be sure the switch for the DHW pump (SW4) is “ON”. The DHW “OFF” LED on the unit should not
be illuminated.
12. The temperature difference between the water entering and leaving the desuperheater should be 5°F to 15°F. The
water fl ow should be approximately 0.4 GPM per ton of nominal cooling.
13. Allow the unit to heat water for 15 to 20 minutes to be sure operation is normal.
CAUTION: Never operate the DHW circulating pump while dry. If the unit is placed in operation
before the desuperheater piping is connected, be sure that the pump switch is set to the OFF
position.
12
Loading...
+ 28 hidden pages
You need points to download manuals.
1 point = 1 manual.
You can buy points or you can get point for every manual you upload.