This manual contains important instructions that should be followed during installation of your
Liebert NX™ UPS and batteries.
Read this manual thoroughly, paying special attention to the sections that apply to your installation,
before working with the UPS. Retain this manual for use by installing personnel.
WARNING
!
Exercise extreme care when handling UPS cabinets to avoid equipment damage or injury to
personnel. The UPS module weight ranges from 850 to 1400 lb. (386 to 635kg).
Determine unit weight and locate center of gravity symbols
before handling the UPS. Test lift and balance the cabinet
before transporting. Never tilt equipment more than 15 degrees from vertical.
Battery manufacturers supply details of the necessary precautions to be observed when
working on, or in the vicinity of, a large bank of battery cells. These precautions should be
followed implicitly at all times.
Follow all battery safety precautions when installing, charging or servicing batteries. In
addition to the hazard of electric shock, gas produced by batteries can be explosive and
sulfuric acid can cause severe burns. When connected, the nominal battery voltage is 288VDC
and is potentially lethal.
In case of fire involving electrical equipment, use only carbon dioxide fire extinguishers or
those approved for use in fighting electrical fires.
Extreme caution is required when performing maintenance.
Be constantly aware that the UPS system contains high DC as well as AC voltages.
Check for voltage with both AC and DC voltmeters prior to making contact.
WARNING
!
As with other types of high power equipment, dangerous voltages are present within the UPS
and battery enclosure. The risk of contact with these voltages is minimized as the live
component parts are housed behind a hinged, lockable door. Further internal safety screens
make the equipment protected to IP20 standards.
No risk exists to any personnel when operating the equipment in the normal manner,
following the recommended operating procedures.
All equipment maintenance and servicing procedures involve internal access and should be
carried out only by trained personnel.
WARNING
!
High ground leakage current: Ground connection is essential before connecting the input
supply.
This equipment must be grounded in accordance with local electrical codes.
Maximum load must not exceed that shown on the UPS rating label.
1
Page 8
CAUTION
!
This equipment is fitted with RFI suppression filters.
Ground leakage current exceeds 3.5 mA and is less than 1000 mA.
Transient and steady-state ground leakage currents, which may occur when starting the
equipment, should be taken into account when selecting instantaneous residual current
circuit breakers (RCCBs) or residual current devices (RCDs).
RCCBs must be selected sensitive to DC unidirectional pulses (Class A) and insensitive to
transient current pulses.
Note also that the ground leakage currents of the load will be carried by this RCCB or RCD.
WARNING
!
Under typical operation and with all UPS doors closed, only normal safety precautions are
necessary. The area around the UPS system should be kept free of puddles of water, excess
moisture and debris.
Special safety precautions are required for procedures involving handling, installation and
maintenance of the UPS system and the battery. Observe all safety precautions in this
manual before handling or installing the UPS system. Observe all precautions in the
Operation and Maintenance Manual, before as well as during performance of all maintenance
procedures. Observe all battery safety precautions before working on or near the battery.
This equipment contains several circuits that are energized with high voltage. Only
test equipment designed for troubleshooting should be used. This is particularly true for
oscilloscopes. Always check with an AC and DC voltmeter to ensure safety before making
contact or using tools. Even when the power is turned Off, dangerously high electric charges
may exist within the UPS.
All power and control wiring should be installed by a qualified electrician. All power
and control wiring must comply with the NEC and applicable local codes.
ONLY qualified service personnel should perform maintenance on the UPS system.
When performing maintenance with any part of the equipment under power, service
personnel and test equipment should be standing on rubber mats. The service personnel
should wear insulating shoes for isolation from direct contact with the floor (earth ground).
Never work alone, even if all power is removed from the equipment. A second person should
be standing by to assist and summon help in case an accident should occur.
CAUTION
!
This unit complies with the limits for a Class A digital device, pursuant to Part 15 Subpart J
of the FCC rules. These limits provide reasonable protection against harmful interference in a
commercial environment. This unit generates, uses and radiates radio frequency energy and,
if not installed and used in accordance with this instruction manual, may cause harmful
interference to radio communications. This unit is not designed for use in a residential area.
Operation of this unit in a residential area may cause harmful interference that the user must
correct at his own expense.
Battery Cabinet Precautions
The following warning applies to all battery cabinets supplied with UPS systems. Additional warnings and cautions applicable to battery cabinets may be found in 3.0 - Battery Installation.
WARNING
!
Internal battery strapping must be verified by manufacturer prior to moving a battery cabinet
(after initial installation).
• Do not tilt.
Failure to heed this warning could result in smoke, fire or electric hazard.
Call 1-800-LIEBERT before moving battery cabinets (after initial installation).
2
Page 9
GLOSSARYOF SYMBOLS
Risk of electrical shock
!
R
i
-
PbH2SO4
Indicates caution followed by important instructions
AC input
AC output
Requests the user to consult the manual
+
Indicates the unit contains a valve-regulated lead acid battery
Recycle
DC voltage
Equipment grounding conductor
Bonded to ground
AC voltage
3
Page 10
1.0INSTALLATION
The Liebert NX™ UPS is designed primarily for telecommunications and data processing applications. Liebert Corporation neither recommends nor knowingly sells this product for use with life support and other designated “critical” devices.
This section describes the NX’s environmental requirements and mechanical considerations that
must be taken into account when planning the positioning and cabling of the UPS equipment.
Because every site is unique, this section presents a guide to general procedures and practices that
should be observed by the installing engineer, rather than step-by-step installation instructions.
WARNING
!
Do not apply electrical power to the UPS equipment before the arrival of the commissioning
engineer.
WARNING
!
The UPS equipment should be installed by a qualified engineer in accordance with the
information contained in this section.
WARNING
!
Special care should be taken when working with the batteries associated with this equipment.
When connected together, the nominal battery voltage is 288VDC and is potentially lethal.
• Eye protection should be worn to prevent injury from accidental electrical arcs.
• Remove rings, watches and all metal objects.
• Only use tools with insulated handles.
• Wear rubber gloves.
If a battery leaks electrolyte or is otherwise physically damaged, it must be replaced, stored in
a container resistant to sulfuric acid and disposed of in accordance with local regulations.
If electrolyte comes into contact with skin, the affected area should be washed immediately
with large amounts of water.
Installation
NOTE
The NX UPS can be used in TN utility system.
1.1External Inspections
1. While the UPS system is still on the truck, inspect the equipment and shipping container(s) for
any signs of damage or mishandling. Do not attempt to install the system if damage is apparent.
If any damage is noted, file a damage claim with the shipping agency within 24 hours and contact
Liebert Global Services at 1-800-LIEBERT to inform them of the damage claim and the condition
of the equipment.
2. Compare the contents of the shipment with the bill of lading. Report any missing items to the
carrier and your local Liebert representative immediately.
1.2Internal Inspections
1. Remove any packaging material, then visually examine the UPS and battery equipment for
transit damage, both internally and externally. Report any such damage to the shipper and to
Liebert immediately.
2. Check the nameplate inside the cabinet door to verify that the model number and rating
correspond to the ones specified. Record the model number and serial number in the front of this
installation manual. This information is necessary should service be required.
3. Check for loose connections or unsecured components in the cabinet.
4. Check for shipping damage to internal components.
4
Page 11
1.2.1Storing for Delayed Installation
If the equipment will not be installed immediately, it must be stored indoors where the humidity is no
higher than 90% and the temperature is no higher than 104°F (40°C). The storage area must protect
the NX from excessive moisture (see 6.2 - UPS Environmental).
CAUTION
!
If the UPS must remain disconnected from power for more than six (6) months, the battery
must be recharged before use. To charge the batteries, the unit must be connected to utility
power and started up—the charger operates only while the NX is operating.
CAUTION
!
When batteries are installed in the UPS or are cabinet-mounted adjacent to the UPS unit, the
battery—not the UPS—dictates the designed maximum ambient temperature.
1.3Preliminary Checks
1.3.1Identification
The equipment supplied has an identification tag on the back of the main door listing the type and
size of the UPS.
1.4UPS Location
Installation
1.4.1Positioning the UPS
Choose a location for the UPS that offers:
• Easy connection to inputs, outputs and auxiliary equipment
• Enough space to service the UPS
• Air circulation sufficient to expel heat produced by UPS
• Protection against moisture and excessive humidity
• Protection against dust and other particulate matter
• Compliance with fire prevention regulations and practices
• Operating environment temperature of 74-80°F (23-27°C) for maximum battery efficiency
1.4.2Environmental Considerations
Before installing the NX, verify that the UPS room satisfies the environmental conditions stipulated
in 6.2 - UPS Environmental, paying particular attention to the ambient temperature and air
exchange system.
The UPS unit should be installed in a cool, dry, clean-air environment with adequate ventilation to
keep the ambient temperature within the specified operating range 32°F to 104°F (0°C to 40°C).
For optimal UPS and battery system performance and service life, maintain the operating temperature within the range of 74-80°F, (23-27°C).
The NX UPS cooled by internal fans. Cooling air enters the unit through the front of the unit and is
exhausted out the top. To permit proper air flow and prevent overheating, do NOT block or cover the
ventilation openings or blow air down onto the unit. Ventilation clearance above the unit must be a
minimum of 24 in. (610mm).
See Table 9 for details on heat dissipation.
Battery Location
Temperature is a major factor in determining battery life and capacity. Battery manufacturers recommend an operating temperature of 77°F (25°C). Ambient temperatures warmer than this reduce battery life; temperatures below this reduces battery capacity. In a typical installation, battery
temperature should be maintained between 74°F and 80°F (23-27°C). Batteries should be placed
where there are no main heat sources or air inlets to prevent portions of batteries from being either
much warmer or much cooler than other parts of the batteries.
5
Page 12
1.4.3Special Considerations for 1+N Systems
1. Consider the grounding configuration of your system before finalizing module placement. For
optimal ground performance, the NX modules should be close together.
2. For optimal load-sharing performance, the UPS output cables should be approximately the same
length, plus or minus 20 percent.
3. Position modules in such a way as to minimize the length of power cables and control wiring
between UPS modules and the paralleling cabinet.
1.5Considerations in Moving the NX
Ensure that the UPS weight is within the designated surface weight loading (lb./ft2 or kg/cm2) of any
handling equipment. See Table 9 for weights of various units.
To move the UPS and optional battery cabinets:
• The NX may be rolled on its casters when moving the unit a short distance. For longer distances,
move the UPS with a forklift or similar equipment to ease the relocation and to reduce vibration.
The optional battery cabinets should be moved with a forklift or similar equipment.
WARNING
!
Ensure that any equipment that will be used to move the NX has sufficient lifting capacity.
The NX weight ranges from 850 to 1400 lb. (386 to 635kg). See Table 9 for details. The UPS
presents a tipping hazard. Do not tilt the NX further than 15 degrees from vertical.
The UPS is fitted with casters—take care to prevent movement when unbolting the
equipment from its shipping pallet. Ensure adequate personnel and lifting equipment are
available when taking the NX off its shipping pallet. Do not tilt the unit more than 15 degrees
from center.
Installation
WARNING
!
The casters are strong enough for movement across even surfaces only. Casters may fail if
they are subjected to shock loading, such as being dropped or rolled over holes in the floor or
obstructions. Such failure may cause the unit to tip over, injuring personnel and damaging
the equipment.
Care must be taken when maneuvering units fitted with batteries. Keep such moves to a
minimum. For further information, see Battery Cabinet Precautions on page 2.
Final Position
When the equipment has been finally positioned, ensure that the adjustable stops are set so that the
UPS will remain stationary and stable (see 7.0 - Installation Drawings).
1.6Mechanical Considerations
The NX is constructed with a steel frame and removable panels. Top and side panels are secured to
the chassis by screws. The doors may be opened for access to power connections bars, auxiliary terminals blocks and power switches.
The UPS comes with an operator control panel, which provides basic operational status and alarm
information. The cabinet houses both the power components and the internal batteries. Cooling is
provided by internal fans. The unit sits on four casters. Adjustable stops are provided to prevent the
UPS from moving once it has been moved to its final position.
6
Page 13
1.6.1Clearances
There are no ventilation grilles on the sides or rear of the UPS. The sides must be accessible during
installation. After installation, the unit may be placed with the rear against a wall and optional cabinets on either side.
To enable routine tightening of power terminations within the UPS, make sure there is sufficient
clearance in front of the NX to permit free passage of personnel with the door fully opened.
Leave a minimum of 2 ft. (610mm) between the top of the UPS and the ceiling to permit adequate air
circulation above the unit. Liebert recommends against using air conditioning or other systems that
blow air onto the top of the unit.
1.6.2Floor Installation
The diagrams in 7.0 - Installation Drawings show the location of holes in the base plate for bolting
the equipment to the floor. An optional anchoring kit is available. For information, see your local Liebert representative.
If the equipment is to be placed on a raised floor, it should be mounted on a pedestal that will support
the equipment point loading. Refer to the bottom view in Figure 28 to design this pedestal.
1.6.3Cable Entry
Cables can enter the NX from the top or bottom. Cable entry is made possible by removing a metal
plate attached to the UPS.
These plates are designed to allow the personnel to punch holes for fitting and securing the conduit.
Once the conduit holes are punched, these plates should be reattached to the UPS.
Installation
Connecting cables to the NX may require that the UPS be accessible from the left side to allow personnel to complete the connections and make necessary adjustments. After installation is complete,
the NX may be serviced from the front.
NOTE
When installing the UPS, the customer must provide a disconnect with overcurrent protection
at the output of the UPS.
10-30kVA UPS
The 10-30kVA NX consists of a single cabinet housing the UPS components and the internal battery
string.
Optional battery cabinets are available to provide extended run time. Each cabinet houses additional
strings of batteries that operate in parallel with the NX’s internal batteries. The cabinets are
designed to be bolted to the right side of the UPS (see Figure 1). Refer to 3.4 - External Battery Cabinet Installation for details.
Optional maintenance bypass/transformer cabinets (MBC-T) are available. These cabinets house the
components necessary to:
• Provide an external wrap-around maintenance bypass switch for servicing the UPS
• Provide voltage transformation for site or application requirements
• Provide a means for neutral isolation and allow installations for site without a neutral conductor
MBC-T cabinets are designed to be bolted to the left side of the UPS (see Figure 1). Refer to 4.5 -
Locating the Cabinet, for further details.
System Composition
A UPS system can comprise a number of equipment cabinets, depending on the individual system
design requirements—e.g., UPS cabinet and External Bypass cabinet. In general, all cabinets used
will be the same height and are designed to be positioned side-by-side to form an aesthetically appealing equipment suite.
7
Page 14
1.6.4Optional Cabinets
If your NX installation includes a Maintenance Bypass Cabinet, the NX must be positioned to allow
the Maintenance Bypass Cabinet to be bolted to left side of the NX (see Figure 1). Cables from the
Maintenance Bypass Cabinet must be brought through the bottom side of the NX for connection.
The Maintenance Bypass Cabinet must be cabled and bolted to the NX before the UPS and bypass
cabinet are moved into their final position. Connect the input wiring to the Maintenance Bypass Cabinet ONLY after the units are connected and positioned.
Battery cabinets may be bolted to either side of the NX, unless used in configurations that include a
Maintenance Bypass Cabinet. If used with a Maintenance Bypass Cabinet, battery cabinets must be
installed on the right side of the UPS; see Figure 1 below.
Figure 1Cabinet arrangement
Installation
ALL UNITS VIEWED FROM ABOVE
Liebert
Maintenance
Bypass
Cabinet
NX connected only to MBC
(MBC must be on left side of the NX)
NX
(Battery Cabinets may be on either side of the NX)
Maintenance
Bypass
Cabinet
NX connected to Maintenance Bypass Cabinet and Battery Cabinets
(MBC must be on left side of the NX)
(Battery Cabinets must be on the right side of the NX in this
Liebert
NX
Battery
Cabinet
NX connected to Battery Cabinets
Liebert
NX
configuration)
Battery
Cabinet
Battery
Cabinet
Battery
Cabinet
8
Page 15
2.0ELECTRICAL CONNECTIONS
The UPS requires both power and control cabling once it has been mechanically installed. All control
cables must run separate from power cables in metal conduits or metal ducts that are electrically
bonded to the metalwork of the cabinets to which they are connected.
WARNING
!
Before connecting input power to the NX, ensure that you are aware of the location and
operation of the overcurrent protection devices that connect the UPS input/bypass supply to
the power distribution panel.
De-energize and lockout or tagout all incoming high- and low-voltage power circuits before
installing cables or making any electrical connections.
2.1Power Cabling
2.1.1Cable Rating
The main factors affecting the choice and size of cable are voltage, current (also taking into account
overcurrent), room temperature and conditions of installation of the cable.
The power cables of the system must be sized with respect to the following description:
• UPS input cables - The UPS input cables must be sized for the maximum input current, including the maximum battery recharge current, given in Table 10, with respect to the unit rating and
the input AC voltage.
• UPS bypass and output cables - The bypass and output cables must be sized for the nominal
output current, given in Table 10, with respect to the unit rating and the output AC voltage.
• Battery cables - Each UPS unit has its own internal batteries factory-wired. If connecting an
external battery cabinet, the battery cables must be sized for the battery discharge current at the
end-of-discharge voltage, as given in Table 10, with respect to the unit rating.
Electrical Connections
NOTE
Table 10 gives nominal currents for determining the size of UPS power cables. Other
important factors to consider include cable route length and coordination with protective
devices.
The power cables can be sized to suit the UPS unit rating according to Table 10.
Lug Size and Torque Requirements
Refer to Table 27 for lug size and torque requirements.
9
Page 16
2.1.2UPS Input Configuration
Figure 2 illustrates the NX in a split bypass (dual-input) configuration. In this configuration the
Static Bypass and the Maintenance Bypass lines are supplied from a separate feed from the Main
input. Both sources must be protected externally with properly sized protective devices. By default,
the unit ships with internal links installed between the Bypass input and Main input (Single Input
configuration). To wire the unit as a dual input UPS, remove the links and wire the bypass to the
input bus bars, then wire the Main input directly to CB1 (see Figure 3).
The following are guidelines only and are superseded by local regulations and codes of practice where
applicable.
1. Take special care when determining the size of the neutral cable, as current circulating on the
neutral cable may be greater than nominal current in the case of non-linear loads. Refer to the
values in 6.4 - UPS Electrical Characteristics.
2. The ground conductor should be sized according to such factors as the fault rating, cable lengths
and type of protection. The ground cable connecting the UPS to the main ground system must
follow the most direct route possible. Control wiring and power wiring must be run in separate
conduit. Output and input cables must be run in separate conduit.
3. Consider using paralleled smaller cables for heavy currents—this can ease installation.
4. When sizing battery cables, a maximum voltage drop of 4VDC is permissible at the current
ratings in Table 10. For terminal connection sizing, see Table 10.
5. In most installations, especially parallel multi-module systems, the load equipment is connected
to a distribution network of individually protected busbars fed by the UPS output, rather than
connected directly to the UPS itself. When this is the case, the UPS output cables can be rated to
suit the individual distribution network demands rather than being fully load-rated.
SW1/D
SW1/C
Battery
Contactor
Charger
Maintenance Bypass
Static Switch
InverterRectifier
Battery
Contactor
SW1/A
SW1/B
UPS
Output
NOTE
If more load is added to the distribution panel, the unit’s cabling must be resized.
6. When laying power cables, do not form coils; this will help avoid increasing formation of
electromagnetic interference.
NOTE
Left-side access may be required when making power connections. Cable connections should be
made before a cabinet is attached to the left side of the NX or before the UPS is placed where
another obstruction, such as a wall, is against the NX’s the left side.
10
Page 17
2.1.4Cable Connections
The rectifier input, bypass and output are easily accessible from the left side of the unit for installation. All require lug type terminations. They are connected to busbars on the left side of the NX and
below the switch, as shown in Figure 3. These busbars are accessible when the left side panel is
removed. Busbars to connect external batteries are accessible from the front of the UPS.
NOTE
External battery connection access requires removal of a protective panel on the lower front of
the UPS to the left of the bottom two battery shelves.
Figure 3Input busbars
Electrical Connections
Remove these links
for dual input
configuration and
wire UPS Main input
directly to CB1
Output Busbars
(Phases are
indicated by
letters below the
bars)
CB
OUTPUTBYPASS
The internal batteries are connected with Anderson connectors inside the battery compartment. The
batteries are connected to fuses to protect the NX and connected equipment (see Figure 4).
Figure 4Battery fuses and connections
Rectifier Input
Busbars
(Phases are
indicated by
letters below the
bars)
ACBA
Internal battery input
connections
150A 500V AC/DC
B
Bussmann
MADE IN USA
11
150A 500V AC/DC
B
Bussmann
MADE IN USA
Battery fuses
(fuses are behind
access plate on
front of UPS; see
Note on page 11)
Page 18
2.1.5Safety Ground
The safety ground busbar is located below the neutral input and output busbars as shown in
Figure 5 below. The safety ground cable must be connected to the ground busbar and bonded to each
cabinet in the system.
All cabinets and cable conduit should be grounded in accordance with local regulations.
WARNING
!
Failure to follow proper grounding procedures can result in electric shock hazard to personnel
or the risk of fire, should a ground fault occur.
NOTE
Proper grounding significantly reduces problems in systems caused by electromagnetic
interference.
NOTE
The ground and neutral busbars are easily accessible when the left protective cover plate is
removed. Cable connections should be made before a cabinet is attached to the left side of the
NX or before the UPS is placed where another obstruction, such as a wall, is against the NX’s
the left side.
Figure 5Ground and neutral busbar connections
Electrical Connections
Output neutral
busbar
Ground
busbar
2.1.6Protective Devices
For safety, it is necessary to install circuit breakers in the input AC supply and external battery battery cabinets, external to the UPS system. Given that every installation has its own characteristics,
this section provides guidelines for qualified installation engineers with knowledge of operating practices, regulatory standards and the equipment to be installed.
UPS Rectifier and Bypass Input Supply
• Protection from excessive overcurrents and short circuits in power supply input
External overcurrent protection for the AC output circuit is to be provided. See 6.4 - UPS Elec-
trical Characteristics and Table 12 for overload capacity.
High-speed fuses and SCRs are used for internal battery circuit overcurrent protection. When an
external battery supply is used, overcurrent protection for the battery circuit is to be provided by
the customer.
• Dual Input
When wiring the UPS with dual inputs, the Rectifier input and the Bypass input must be protected separately. Size the breakers according to the input currents shown in Table 10.
OUTPUT
NEUTRAL
INPUT
NEUTRAL
Input neutral
busbar
System Output
When using an external distribution panel for load distribution, the output neutral and input neutral
must be separated at the input to the UPS.
12
Page 19
2.1.7Cabling Procedure
CAUTION
!
The operations described in this section must be performed by authorized electricians or
qualified technical personnel. If you have any difficulties, contact your local Liebert
representative or Liebert Global Services.
NOTE
Hydraulic pressure pliers, combinative tools and piston ring pliers should be used to connect
AC wiring.
Once the equipment has been positioned and secured for operation, and the battery and ground collars have been connected (see 2.1.4 - Cable Connections), connect the power cables as described
below. (Study the reference drawing in 7.0 - Installation Drawings.)
1. Verify that all incoming high and low voltage power circuits are de-energized and locked out or
tagged out before installing cables or making any electrical connections.
2. Remove the left side panel to gain easier access to the connections busbars.
3. Connect the safety ground and any easier bonding ground bus cables to the copper ground busbar
located on the bottom of the equipment below the power connections. All cabinets in the UPS
system must be connected to the user’s ground connection.
NOTE
The grounding and neutral bonding arrangement must comply with the National Electrical
Code and all applicable local codes.
Electrical Connections
4. Identify and make power connections with incoming cables according to Steps 5 through 11.
Common Input Connections
5. For common bypass and rectifier inputs, connect the AC input supply cables between the power
distribution panel and the UPS input busbars (A-B-C terminals) and tighten the connections to
44 lb-in. (5 N-m) using the M6 bolt provided.
6. The input neutral cable must be connected to the input neutral busbar (N). See Figure 5.
Dual Input Connections
7. For bypass connect the AC input supply cables between the power distribution panel and the UPS
input busbars (A-B-C terminals) and tighten the connections to 44 lb-in. (5 N-m) using the M6
bolt provided.
8. For Rectifier Input connect AC input supply cables between the power distribution panel and the
UPS input circuit breaker (A-B-C terminals)
9. The bypass and rectifier input neutral cables must be connected to the input neutral busbar (N).
See Figure 5.
NOTE
Both the rectifier and bypass feeds MUST come from the same utility source, except if the UPS
system includes either a configuration F or P external maintenance bypass cabinet.
Output System Connections—Ensure Correct Phase Rotation
10. Connect the system output cables between the UPS output busbars (A-B-C N terminals) and the
critical load and tighten the connections to 44 lb-in. (5 N-m) (M6 bolt).
WARNING
!
If the load equipment will not be ready to accept power on the arrival of the commissioning
engineer, then ensure that the system output cables are safely isolated.
13
Page 20
Internal UPS Battery Connections
The UPS internal batteries will be connected at the factory, EXCEPT the Anderson connections
between the shelves and to the fuses.
WARNING
!
The DC bus is live when this internal battery connection is made. This connection is to be
performed ONLY by Liebert Global Services at startup.
Observe the battery cable polarity. Be sure that the battery connector is made with the correct polarity.
11. Refit all protective covers removed for cable installation
2.2Control Cables
2.2.1Monitor Board Features
Based on your site’s specific needs, the UPS may require auxiliary connections to manage the battery
system (external battery circuit breaker, battery temperature sensor), communicate with a personal
computer or provide alarm signaling to external devices or for Remote Emergency Power Off (REPO).
The monitor board, arranged for this purpose, is located on the rear of the operator access door. The
main features are:
• Input and Output dry contacts signal (one pair of contacts of relay)
• Emergency Power Off control (EPO)
• Environmental parameter input interface
• User communication (for data setting and user background monitor)
• Intellislot™ interface
• Modem interface
• Temperature detect interface
Figure 6 shows the relationship and connection between the monitoring (U2) board and other boards
in the UPS.
The UPS provides input dry contacts and output dry contacts.
2.3.1Input Dry Contacts
There are several input dry contacts at the X3 slot.
X3
Intellislot 2
Intellislot 1
Intellislot 3
J23
J12
J9
J15
J16
J17
X4
X6
PWR
MODEM
SNMP CARD
X5
X4
J24
NOTE: The black square ()
on each slot indicates Pin 1.
Figure 8Input dry contacts
Table 1Input dry contacts at X3
PositionNameDescription
J4.1ENV
J4.2BtGBattery Ground Fault Detection (N.C.)
J4.3GEN
J4.4+12V+12V Power
1 - Must be configured by configuration software before becoming active.
2 - When activated, the charger current can be limited, via software, to a percentage of the full charger current (0-100%).
3 - Activating this feature turns the battery charger off.
3
1,2
NOTE: The black square () on each slot indicates Pin 1.
Battery Room Alarm (N.C.)
Generator Join Detection (N.O.)
15
Page 22
2.3.2Maintenance Bypass Cabinet Interface
J26 and J30 are the MBC interface.
Table 2Maintenance bypass cabinet interface
PositionNameDescription
J26.1T_IT
J26.2AUX_IReserved
J26.3+12V+12V Power
J26.4GNDPower Ground
J30.1FUSEReserved
J30.2F_FANFan Fail Alarm (N.C.)
J30.3T_OT
J30.4AUX_OReserved
1 - Must be configured by software before becoming active
1
Input transformer over temperature (N.C.)
1
Output Transformer Overtemperature (N.C.)
NOTE
All auxiliary cables of terminal must be double-insulated. Wire should be 20-16AWG stranded
for maximum runs between 82 and 164 feet (25-50m), respectively.
2.3.3BCB Box Interface
Electrical Connections
J10 is the BCB box interface.
Table 3BCB box interface
PositionNameDescription
J10.1DRVBCB Driver Signal - Reserved
J10.2FBBCB Contact State
J10.3GNDPower Ground
J10.4OL
BCB On-Line - Input - This pin will become active when
BCB interface is connected. (N.O.)
NOTE
All auxiliary cables of terminal must be double-insulated. Wire should be 20-16AWG stranded
for maximum runs between 82 and 164 feet (25-50m), respectively.
NOTE
If BCB interface is connected, a jumper needs to added between Pin 3 and Pin 4.
Figure 9Jumper connection for BCB interface
UPS Monitoring Board
J10
OL
OL
FB
DRV
GND
Aux – N.O.
Aux – N.O.
Battery Circuit Breaker
16
Page 23
2.3.4Output Dry Contacts
There are three output dry contact relays at the X1 slot (see Figure 10 and Table 4).
Figure 10 Output dry contacts and EPO wiring for firmware before M170
Electrical Connections
+12V
J13
BFP_S
BFP_C
BFP_O
Table 4Output dry contact relays
PositionNameDescription
J13.2BFP_OBypass feedback protection relay. Normally open. Closed when bypass SCR is shorted.
J13.3BFP_SBypass feedback protection relay center
J13.4BFP_CBypass feedback protection relay. Normally closed. Open when bypass SCR is shorted.
J21.2INV_OInverter mode relay. Normally open. Closed when UPS is in inverter mode.
J21.3INV_SInverter mode relay center
J21.4INV_CInverter mode relay. Normally closed. Open when UPS is in inverter mode.
J25.2ACF_OMain input fault relay. Normally open. Closed when main input is in fault.
J25.3ACF_SMain input fault relay center
J25.4ACF_CMain input fault relay. Normally closed. Open when main input is in fault.
NOTE
All auxiliary cables of terminal must be double-insulated. Wire should be 20-16AWG stranded
for maximum runs between 82 and 164 feet (25-50m), respectively.
2.3.5EPO Input—Optional
J21J25J28
EPO-H
INV_S
INV_C
INV_O
ACF_C
ACF_S
ACF_O
X2X1
EPO-L
Firmware Before M200
The UPS has an Emergency Power Off (EPO) function that operates by a button on the control panel
or by a remote contact provided by the user. The EPO button is under a hinged, clear plastic shield.
The X2 slot, shown in Figure 10, is the remote EPO input interface. It is active when shorted from
EPO-L to EPO-H.
If an external Emergency Stop facility is required, it is connected terminals EPO-L to EPO-H of the
auxiliary terminal block (X2). It also is connected to the Normally Open remote stop switch between
these two terminals using shielded cable (see Figure 10 and Table 5). If this function is not used,
terminals EPO-L to EPO-H must be opened.
Table 5EPO input contact relays
PositionNameDescription
J28.2EPO_LEmergency Power Off Low
J28.4EPO_HEmergency Power Off High
NOTE
The Emergency Stop action within the UPS shuts down the rectifier, inverter and static
bypass. It does not internally disconnect the input power supply.
To disconnect ALL power to the UPS, open the upstream feeder breaker(s) when the remote
EPO is activated.
17
Page 24
Firmware M200 or Later
The UPS has an Emergency Power Off (EPO) function operated by a button on the control panel or by
a remote contact provided by the user. The EPO button is under a hinged, clear plastic shield.
The X2 slot, shown in Figure 11, is the remote EPO input interface. The EPO has a NO/NC contact
point becomes active when shorting terminals X2: 3 and 4 or open terminal connection X2: 2 and 1.
If an external Emergency Stop facility is required, it is connected terminals X2: 1&2 or X2: 3 and 4 of
the auxiliary terminal block (X2). It also is connected to the Normally Open or Normally Closed
remote stop switch between these two terminals using shielded cable (see Figure 11 and Table 6). If
this function is not used, terminals X2: 3 and 4 must be opened and X2: 1 and 2 must be closed.
Figure 11 EPO wiring for firmware M200 or later
Electrical Connections
J2 8
EPO - NO
EPO - NC
Table 6EPO input contact relays
PositionNameDescription
J28.1EPO_NCEPO Activated when opened to J28.2
J28.2EPO_NCEPO Activated when opened to J28.1
J28.3EPO_NOEPO Activated when shorted to J28.4
J28.4EPO_NOEPO Activated when shorted to J28.3
NOTE
The Emergency Stop action within the UPS shuts down the rectifier, inverter and static
bypass. It does not internally disconnect the input power supply. To disconnect ALL power to
the UPS, open the upstream feeder breaker(s) when the remote EPO is activated.
NOTE
Normally Closed EPO – X2: 1,2, these terminals are supplied factory-linked on the monitor
board and must remain installed if using NC contacts.
NOTE
All auxiliary cables of terminal must be double-insulated. Wire should be 20-16AWG stranded
for maximum runs between 82 and 164 feet (25-50m), respectively.
X2
18
Page 25
3.0BATTERY INSTALLATION
3.1Introduction
Liebert recommends that the batteries in external cabinets match the internal batteries in the NX in
manufacturer and type.
If using multiple sets of batteries connected in parallel to provide the required battery backup run
times, fit each set with an isolating device to permit working on one of the battery sets while leaving
the others in service and providing backup protection.
When replacing batteries, replace with the same manufacturer and type, or equivalent. See your Liebert representative for a list approve batteries.
NOTE
The NX, as shipped, has 24 12-volt batteries installed internally in each unit.
3.2Safety
Special care should be taken when working with the batteries associated with the NX system equipment. When all batteries are connected together, the battery terminal voltage may exceed 324V and is
POTENTIALLY LETHAL.
Battery Installation
WARNING
!
The NX's internal batteries are connected and energized even if the UPS is turned Off. To
minimize the risk of injury, a qualified service person should disconnect internal batteries
before any maintenance is performed on the unit.
The center of the battery is connected to the neutral of the UPS and is grounded.
A battery can present a risk of electrical shock and high short circuit current. The following
precautions should be observed when working on batteries:
• Remove watches, rings and other metal objects.
• Use tools with insulated handles.
• Wear rubber gloves and boots.
• Do not lay tools or metal parts on top of batteries.
• Disconnect charging source prior to connecting or disconnecting battery terminals.
3.3UPS Batteries
The NX's internal batteries are fully charged before the unit is shipped. During storage and transportation, some charge is lost. All batteries should be recharged before use. The battery charger works
only when the NX is connected to input power and turned On.
NOTE
Full safety instructions concerning the use and maintenance of UPS batteries are provided in
the appropriate battery manufacturer's manuals, available on the manufacturer's Web site.
The battery safety information contained in this section relates to key considerations that must
be taken into account during the installation design process and might affect the design
outcome, depending on your installation.
19
Page 26
3.4External Battery Cabinet Installation
3.4.1Matching Battery Cabinets
Two sizes of optional battery cabinets are available. Refer to Figures 13 and 14. The same model battery cabinet may be installed in parallel in multiple cabinet strings for additional capacity. Battery
run time depends on the cabinet model, the number of cabinets and the load on the UPS.
Handling—The battery cabinet has casters to facilitate movement over short distances. The bottoms
of the battery cabinets are reinforced to permit movement by forklift over longer distances.
Inspection—Remove all panels and visually inspect the batteries, bus connections, and cabinet for
any damage. Exercise caution; voltage is present within the battery cabinet even before installation.
If there are signs of damage, do not proceed. Call Liebert Global Services at 1-800-542-2378.
Storage—The batteries can be stored for up to six months without appreciable deterioration. If planning to store a battery cabinet for longer than six months or at temperatures higher than 77°F (25°C),
contact Liebert Global Services for recommended precautions.
The following notes, in conjunction with the diagrams (Figure 13 through 12), illustrate the broad
principles to be followed when fitting and connecting the majority of battery cabinet installations.
CAUTION
!
Any battery system should be installed by qualified personnel.
When installing an external battery cabinet that is NOT a Liebert NX battery cabinet, the customer
must provide overcurrent protection. See Table 10 for sizing of protection devices.
Battery Installation
NOTE
When using an external battery supply that is not provided with the UPS, please make
reference to the battery manufacturer’s installation manual for battery installation and
maintenance instructions, available on the manufacturer’s Web site. When replacing batteries,
Liebert recommends that the batteries in external cabinets be the same type used internally in
the NX. See Table 11 for a list of batteries that are approved for use with this product.
3.4.2Connecting the Batteries
If the NX battery cabinets are installed on a raised floor, the battery power cables and circuit breaker
control cables may be routed to the UPS cabinet via the floor of the cabinet (bottom entry).
If the NX battery cabinets are installed adjacent to one another on a solid floor, these cables may be
passed between the cabinets through lifting slots in the lower sides of the cabinets.
Intertray connections must be made before the battery cabinet may be used.
Figure 14 Wide battery cabinet, 57 in. (1488mm) - front view
Top cable entry
Battery tray
support
Battery tray
Batteries
BCB plate and
BCB
Service
shelf
21
Page 28
3.4.3Installation Considerations
Position—Liebert battery cabinets come in versions specific to either the left or right side of the
UPS. Control wires and power cables are cut to different lengths for the different versions. If the system includes a matching maintenance bypass cabinet (MBC), the MBC should be mounted to the left
of the UPS (nearest the busbars) and the battery cabinet(s) should be installed to the right of the
UPS. Otherwise, left-side placement of the battery cabinet is preferable.
The battery cabinet(s) are designed to be located conveniently next to each UPS module, and are also
available in stand-alone configurations with painted side panels. The front access design eliminates
side and rear service clearance requirements. Refer to Table 33 for battery cabinet dimensions and
weights.
Bolt-On Cabinets—Matching battery cabinets are designed to bolt onto the side of the UPS module
cabinet. Use bolts that ship with each unit to connect cabinet frames at posts, two places in the front
and two places in the rear.
Service Clearance—Allow front access to the battery cabinet at all times for maintenance and servicing. Electrical codes require that the battery cabinet be installed with no less than 3 feet (1m) of
clearance at the front of the cabinet when operating. Side and rear panels do not require service clearance.
Cables—Cables may be run between the cabinets through cutouts in the top of the cabinet, eliminating the need for external conduit runs. Route cables before moving cabinets into final position for bolting together. No top or bottom entry cables are required, except for remotely located cabinets which
require conduits. Refer to Figure 15.
Software—To allow the UPS to accurately display the battery run time, the number of battery cabinets must be noted when performing initial startup and setup using the configuration software. This
is to be performed by the Liebert Global Services customer engineer when commissioning the unit.
Casters and Adjustable Stops—The adjustable stops are not designed to bear the full weight of the
cabinet. Lower the stops until they are finger-tight in contact with the floor. Then tighten a small
amount with a wrench (less than two turns) to give a good friction fit. When mounting the battery
cabinet on seismic stands, ensure that the casters are bearing the weight of the cabinet.
Battery Support Tray—Be sure to connect the battery tray support to the front of the cabinet
before sliding a battery tray out for connection or service. Without the support, the battery tray may
fall out of the cabinet. See Figure 16 for details.
Battery Installation
22
Page 29
Figure 15 Internal cable wiring from battery cabinet to Liebert NX
Power cables from output power switch
Battery Installation
Power cables
from batteries
Power cables
(black) enter
channel down side
of NX to power
input connections
Power cables exit battery
cabinet, enter Liebert NX
Power cables run
across top
of Liebert NX
RIGHT SIDE CABLE
ENTRY SHOWN;
CUTOUTS ON LEFT
SIDE PERMIT
CONNECTION
FROM THAT SIDE.
Figure 16 Battery tray and supports
Slot in support secured by
screw-in connector at
corner of battery tray ...
... and notched end of support
slips into slot at top corner
of battery compartment
Battery tray supports attach
to interior surface of NX
front door (note notched
ends of supports)
23
Page 30
3.4.4Connecting the Battery Cabinet to the UPS
After the battery cabinet equipment has been positioned and secured for operation and the batteries
have been connected, connect the power cables as described below. (See Figure 34.)
1. Verify that all incoming high and low voltage power circuits are de-energized and locked out or
tagged out before installing cables or making any electrical connections.
2. Remove the UPS left side panel to gain access to the equipment ground busbar.
3. Remove the external battery terminal block plate on the lower left side of the UPS behind the
front door.
4. Remove the battery cabinet front panel to gain access to the connection bars.
5. Connect the safety ground and any necessary bonding ground cables to the copper ground busbar.
(example: UPS located on the bottom of the equipment below the power connections).
All cabinets in the UPS system must be connected to the user's ground connection.
NOTE
The grounding and neutral bonding arrangement must be in accordance with the National
Electrical Code and all applicable local codes.
6. Connect the system battery cables from the UPS battery terminals (+ N -) to battery cabinet BCB
(+ N -) as shown in Figure 34. Be sure that the battery connections are made with the right
polarity, and tighten the connections to 44 lb-in. (5 N-m) (M6 Bolt). Do not close the battery circuit
breaker before the equipment has been commissioned.
7. Connect supplied auxiliary control cable to pins J10.2 and J10.3 on the U2 monitoring board (see
2.3 - Dry Contacts). Add a jumper wire between J10.3 and J10.4.
Battery Installation
3.5Non-Standard Batteries
When batteries other than a matching battery cabinet are used, a remote battery disconnect switch
with overcurrent protection is required per the National Electrical Code. Contact your local Liebert
sales representative about this option.
Install battery racks, cabinets and batteries in accordance with the manufacturer's instructions.
Verify that the battery area has adequate ventilation and battery operating temperature complies
with the manufacturer's specifications and with all applicable national and local codes.
If you have any questions concerning batteries, battery racks or accessories, contact Liebert Global
Services at 1-800-543-2378.
24
Page 31
Maintenance Bypass Cabinet
4.0MAINTENANCE BYPASS CABINET
The Maintenance Bypass Cabinet is designed to operate in UPS mode, bypass mode and maintenance
mode. The mode is selected using the Bypass Switch.
Figure 17 Single UPS with external Maintenance Bypass Cabinet—typical configuration
Input Supply
A B C
N
Sys In CB 1
Qin UPS
N
Input Mains
Supply A B C
Fuse
Batter y 1
Ext Byp
Y
UPS 1
Charger
CB 1
Rectifier
CB 1
SW1-A
A B C
Static
Switch
Inver ter
SW1-C
SW1-D
N
Rotary
Switch
SW
QoutUPS
Sys Out CB2
Ext Byp
4.1Bypass Switch
The Bypass Switch allows easy and rapid transfer of connected loads between the UPS and Bypass
source.
4.2Normal (UPS) Mode
While the Maintenance Bypass Cabinet rotary switch is in the NORMAL position, the UPS is supplying the connected load with continuous, high-quality AC power. In this mode of operation, the load is
protected by the UPS.
N
To Load
25
Page 32
4.3Bypass Mode
When the Maintenance Bypass Cabinet is in the Bypass mode, it provides an alternate path for power
to the connected equipment. Should the UPS need to be taken out of service for limited maintenance
or repair, manual activation of the bypass will cause an immediate transfer of the equipment from the
UPS inverter to the bypass source. In this mode, power will still be supplied to the UPS; however, the
load is NOT protected by the UPS.
4.4Maintenance Mode
When the maintenance bypass cabinet is in the Maintenance mode, it provides an alternate path for
power to the connected equipment. Should the UPS need to be taken out of service for limited maintenance or repair. In this mode of operation, no power is supplied to the UPS and the load is NOT protected by the UPS.
4.5Locating the Cabinet
This Maintenance Bypass Cabinet may be mounted to the left of the UPS or installed as a stand-alone
unit. In either case, ensure that the unit is in a well-ventilated area and that there is clearance for
access to the switches and cable connections as required by national and local codes.
4.6Cable Installation
4.6.1Wiring Preparation
Maintenance Bypass Cabinet
Be sure that the unit is not connected to any AC utility power source or UPS before installing any wiring to this unit. This Maintenance Bypass Cabinet should be installed by a qualified / certified electrician.
WARNING
!
Please read this section thoroughly before attempting to install wiring to this unit.
Removing the Cover Plates
Plates cover the input and output terminals on the front of the Maintenance Bypass Cabinet (see
Figure 18). Remove these and keep the screws and plates for reinstallation.
Extract screws
from corners to
remove the
access plate
26
Page 33
4.6.2Power Cable Installation
Refer to Tables 29, 30 and 32 when selecting cables.
NOTE
Transient and steady state earth leakage currents may occur when starting the equipment.
This should be taken into account when selecting ground current detection devices because
these will carry the earth leakage currents of both the UPS equipment and the load.
4.6.3Input/Output Wiring
Follow the steps below to connect the input wiring:
NOTE
Input wiring must be installed using conduit if cabinet is not mounted to the immediate left of
the UPS.
1. Locate the input wiring access (top or bottom access), remove the conduit landing plate and punch
the appropriate size hole for the size conduit being used. Pull the three/four input wires through
it, allowing some slack for installation. For cabinets that are located to the immediate left of the
UPS, the access plate is on the lower right of the cabinet. Remove the access plate and verify that
the edge guarding is installed and intact.See Figure 19.
Wiring access is on
lower right side of
Maintenance
Bypass Cabinet
Access panel removed,
wiring connects NX and MBC
Edge Guard
2. Secure the conduit to the access plate of the Maintenance Bypass Cabinet.
3. Input power cables connect to the system input circuit breaker. Refer to Figure 35 -
Maintenance Bypass interconnection
4. Connect the ground (earth) wire to the earth busbar and tighten it to 44 lb-in. (5 N-m) (M6 bolt).
5. Locate UPS input and output cables and access panel to UPS on lower right side. See Figure 19.
NOTE
If the maintenance bypass cabinet is not to be bolted to the UPS, use either top or
bottom access plate.
6. Connect the system ground cable between the Maintenance Bypass Cabinet and UPS and tighten
the connections to 44 lb-in. (5 N-m) (M6 bolt).
27
Page 34
7. Connect the system input cables between the Maintenance Bypass Cabinet 'UPS Input' Busbars
(A-B-C N terminals) and UPS input busbars (A-B-C N terminals) and tighten the connections to
44 lb-in. (5 N-m) (M6 bolt).
8. Connect the system outnput cables between the Maintenance Bypass Cabinet 'UPS Output'
Busbars (A-B-C N terminals) and UPS output busbars (A-B-C N terminals) and tighten the
connections to 44 lb-in. (5 N-m) (M6 bolt).
9. Connect supplied control wire to X3 on the Parallel (M3) board (see Figure 20).
WARNING
!
The control wire must be installed to ensure proper operation of the system and fully protect
the load when switching between bypass cabinet and UPS.
Figure 20 Maintenance bypass control wire location
Maintenance Bypass Cabinet
P2X2
2
:X T M AIN T
Terminal Block Location
X3
P1X2
1
DBS
NOTE
For startup procedure, see the UPS operations and maintenance manual, SL-25210.
485-
485+
28
Page 35
4.7Bolting Cabinets Together
NOTE
UPS wiring must be completed before the cabinets are bolted together.
1. Line up cabinets so that mounting holes are aligned.
Maintenance Bypass Cabinet
Place cabinets so mounting holes are
aligned.
A bolt from the adjacent cabinet may be
screwed into the threaded top hole, or a
bolt may be inserted through the lower
hole and screwed into the threaded hole
in the adjacent cabinet.
2. Using supplied hardware, bolt the cabinets together. The bolts may be inserted from either the
UPS side or from the MBS side, whichever is more convenient.
29
Page 36
5.0OPTIONS
5.1Load Bus Synchronization
The Load Bus Synchronizer (LBS) keeps the output of two independent UPS systems or parallel UPS
systems in synchronization even when the systems are operating in different modes and even when
either or both systems are operating on batteries. When the LBS is used, one UPS system is designated as master, the other as slave.
The LBS option is typically used with dual-corded equipment or with either the Liebert SmartSwitch
or Static Transfer Switch (STS) for single-corded equipment.
5.1.1Performance Requirements
The DBS operates under the following conditions:
• Both master and slave are on inverter
(either system may be on inverter through the rectifier or on inverter through the batteries)
• Master on inverter, and slave on bypass
• Master on bypass, and slave on inverter
• Master and slave on bypass IF the bypass source is the same for both systems
5.1.2DBS Cable and Settings
For NX-to-NX dual bus configuration, only one optional LBS cable is required, the built-in LBS will
operate normally without extra LBS control box or interface box. The LBS port is X4 on the parallel
board (M3). The parallel board is on the interior of the NX, above and left of the power electronics; see
Figure 30.
Options
An optional, 9-pin LBS cable is used to connect two UPS systems through each system’s DB9 port on
its parallel board. For two parallel systems, the LBS cable can be mounted between any two units
belonging to different parallel systems. For information about the LBS kit or to order the optional
equipment, see your local Liebert representative.
The LBS cable is connected as illustrated in Figure 21.
Figure 21 Load Bus Synchronization cable connection
LBS Cable
Parallel Board
X3
X4
X2-1 X2-2
X1-1 X1-2
Parallel Board
X4
X2-1 X2-2
X1-1 X1-2
The parallel board is on the
interior of the NX, above and
left of the power electronics;
see Figure 30
UPS Module or
The LBS function is activated with configuration software; when the LBS takes effect, the graphic
LCD will display “LBS active.”
System #1
UPS Module or
System #2
30
Page 37
5.2Configuring Parallel System Operation
5.2.1General
The NX uses intelligent and reliable decentralized technology to achieve parallel operation of two or
more modules of the same rating.
The 1+N system is used to:
• Increase the reliability of the system to ensure adequate power supply to the critical load connected.
• Increase serviceability and allow the execution of maintenance operations and reparations without affecting the ordinary operating conditions of the system (depending on the redundancy level).
5.2.2Features of Parallel System
• The hardware and firmware for parallel UPS module operation is standard in the NX, and the
configuration can be set up by changing the settings in configuration software.
• It is easy to install the parallel cables in a ring, providing high reliability and redundancy. And
the intelligent paralleling logic provides the user with maximum flexibility. For example, shutting down or starting up the UPS modules in the parallel system can be done in any sequence. If
an overload transfer occurs, the whole system can recover automatically from bypass mode after
the overload is cleared.
• The total load of the parallel system can be queried from each module’s liquid crystal display
screen.
Options
Figure 22 1+N system block diagram
Supplied
by Others
Input Mains
Supply A B C
UPS 1
Fuse
Charger
Battery 1
N
CB 1
Rectifier
Static
Switch
Inverter
SW1-A
N
Input Ma ins
Supply A B C
UPS 2
SW1-C
Fuse
Charger
Battery 2
SW1-D
CB 1
Rectifier
SW1-C
Static
Switch
Inverter
SW1-D
SW1-A
A B C
Q1Ext
QUPSParalleling Cabinet
To Load
A B C
Q2Ext
QByp
31
Page 38
5.2.3Operating Principles
Redundancy Paralleling
The 1+N parallel redundant system can noticeably improve system reliability. In normal condition,
none of the UPS modules work at full load. That means that even if the load is increased, the system
will not transfer to bypass. And when a UPS module shuts down due to any failure, the remaining
UPS modules can still power and protect the load. When redundancy is lost due to module failure or
load increase, the parallel system will trigger an alarm.
5.2.4Operation Modes Summary
The parallel system also has operation modes such as normal, battery, bypass and maintenance
bypass. All UPS modules in the 1+N parallel system operate in coordination.
• Normal Mode Operation
The load is powered by the inverters of all the UPS modules in the system. If the frequency of
bypass is within the synchronous range, the inverter will be synchronized with the bypass. Otherwise, the system will operate at nominal frequency.
• Battery Mode Operation
The batteries of all UPS modules power the load through their inverters. The system operates at
nominal frequency.
• Bypass Mode Operation
The condition to transfer to bypass mode is essentially the same as that of single module system.
The bypass of all the UPS modules powers the load.
• Maintenance Bypass Mode Operation
The sequence to transfer to maintenance bypass mode is the same as for transferring a single-
module system. The maintenance bypass switches should be switched on as synchronously as possible. Thus the system can be repaired without interrupting the power supply to critical load.
Appendix
5.3Installing Parallel System
The basic installation procedure of parallel system is the same as that of single module system. The
following sections introduce only the installation procedures specific to the parallel system.
5.3.1Conditions for Parallel System
• Each UPS module should have the same rating, the same firmware and hardware version.
• Each UPS module must have the same bypass source.
• The outputs of all UPS modules are connected altogether.
• The main inputs can be from different sources, but the phase rotation sequence of main inputs,
bypass inputs and outputs must be correct and the same.
• The parallel logic cable and load sharing cable must be connected in a ring correctly (see
Figure 23).
5.3.2Cabinet Installation
Parallel system composed of two or more UPS modules using parallel cabinet
The UPS modules that will form the 1+N system should be placed side-by-side. Each battery cabinet
is placed next to its corresponding UPS module.
The parallel cabinet should be placed in the middle of the system.
5.3.3Preliminary Checks
Each UPS module should have the same rating, the same firmware and the same hardware version.
Refer to the instructions in 5.3.1 - Conditions for Parallel System.
5.3.4Protective Devices
For each UPS, refer to Table 10. For each system, refer to Table 31.
32
Page 39
5.3.5Power Cables
Wiring of power cables is similar to that of single module system (See 2.1 - Power Cabling). The
bypass sources of all modules should be the same, and the outputs should be connected altogether correctly.
Power cables will be supplied by customer. Power cables to the UPS’s of the 1+N paralleling cabinet
must be routed through either the top or bottom entry access of the UPS.
For systems using a parallel cabinet, see Figures 36 and 38 through 44 for power cable terminations.
NOTE
The length and specifications of power cables including the bypass input cables and UPS
output cables should be the same, thus the load can be shared evenly in bypass mode.
5.3.6Parallel Control Cables
Parallel System Control Cables
Make the connections listed below on the parallel logic board (M3) inside the NX. (See Figure 30 for
the location of the parallel logic board):
Shielded and double-insulated control cables available in lengths of up to 100 feet (30m) must be
interconnected in a ring configuration between UPS modules as shown below. The ring configuration
ensures high reliability of the control (refer to Figure 23).
See Figure 25 for dry contacts control cable wiring diagram.
Appendix
Figure 23 Connecting '1+N' system parallel control cables
P5
X4
P4P1
UPS
Parallel Board
X3
X2-2 X2-1
P2
X1-1 X1-2
P3
1234
Parallel Bo ard
X3
P5
X4
X2-2 X2-1
P2
X1-1X1-2
P4P1
P3
Parallel Board
X3
X2-2 X2-1
P2
X1-1X1-2
P3
Auxiliary Dry Contact Cables
The external output breaker of each UPS must have Normally Open auxiliary contacts. These contacts must be wired to connector X3 on the Parallel Logic Board (M3). See Figure 24.
P5
X4
P4P1
Parallel Board
X3
P5
X4
X2-2 X2-1
P2
X1-1X1-2
P4P1
P3
Interconnecting
Cables
33
Page 40
Figure 24 Auxiliary dry contact cables for output breaker in multi-module system
Appendix
X3
DBS
:X T M AIN T
485-
485+
P2X2
2
P1X2
1
CAUTION
!
The auxiliary control wire must be installed to ensure proper operation of the system.
NOTE
For startup procedure, see the UPS operations and maintenance manual, SL-25210.
Figure 25 Dry contacts, multiple UPS modules with distribution panel
Input Distribution
UPS 1
M3 Board
X3
Ext. Maint. Ext. Out
QUPS
To Load
UPS 2
M3 Board
X3
Ext. Maint. Ext. Out
UPS N
M3 Board
X3
Ext. Maint. Ext. Out
Q1ExtQ2ExtQnExt
QByp
34
Page 41
5.3.7Emergency Power Off (EPO)
The external emergency stop facility is identical to that described for the single unit installation—
that an individual emergency stop button is provided for each unit.
Figure 26 Connecting EPO push button
Options
UPS2
Normally
Open EPO
X2:3
X2:4
X2:1
X2:2
UPS1
Monitor Board
UPS1
Monitor Board
X2:3
X2:4
X2:1
X2:2
Monitor Board
UPS2
Monitor Board
Normally
Closed EPO
35
Page 42
5.4Battery Circuit Breaker Box
The box contains the same battery isolating circuit breaker as mounted in the battery cabinet.
Two battery circuit breaker boxes are available for use in installations where the battery is not
installed in the battery cabinet, in which case the appropriate battery box is fitted as close as possible
to the battery and connected to the UPS equipment as illustrated in Figure 27.
The battery circuit breaker box, is required to protect the battery from overcurrents. It also provides
electrical isolation between the UPS and the battery, permitting technical service personnel to reduce
the risks involved in maintenance work to a minimum.
A separate safety earth must be connected between the UPS unit and circuit breaker box.
Two boxes are available depending on the UPS power rating.
Table 7Available battery circuit breaker boxes
Dimensions (in)
UPS
10-15 kVA32.25x20.25x8.370A
20-30 kVA32.25x20.25x8.3125A
The circuit breaker has the following features:
• Short-circuit protection.
• Protection against battery cabinet and ups connection errors (polarity reversal +/-).
H-W-DCircuit Breaker
Options
36
Page 43
Figure 27 Battery circuit breaker box connections
Options
3.9"
(98mm)
(3) 1/2" (12.7mm)
dia. knockouts
for control wiring
conduit entry
2.5"
(63.5mm)
TB1
32.3"
(819.2mm)
10.8"
(274mm)
5.4"
(137mm)
Top View
(508mm)
(381mm)
Front View
20.0"
15.0"
4.0"
(101.2mm)
31.5"
(800.1mm)
8.3"
(211.7mm)
1
2
3
4
5
6
TB1
COM Black
N.O. Red
N.C. Blue
From Customer’s Battery System
(field-supplied and field-installed)
Connect to UPS Module
(field-installed)
(-)
(+)
J10.2
J10.3
(GND)
Midpoint
Midpoint
(-)(+)
Circuit Breaker
(-) ( +)
(-)
(+)
72 Cells
(+)
(-)
(-)
(+)
72 Cells
CB
Load
Side
CB
Line
Side
.31" dia.
(Typ. 4 places)
(7.9mm)
.38"
(9.5mm)
(3) 1/2" (12.7mm)
dia. knockouts
Bottom View
for power wiring
conduit entry
(refer to top dimension)
NOTES:
1. NEMA 1 enclosure provided which is suitable for
wall mounting only. Approximate weight is 60 lb.
2. Hardware for connecting cables to the breaker supplied.
3. Circuit breaker, Cutler-Hammer FD4125ED13D15A02 for 20/30 kVA;
FD4070ED13D15A02 for 10/15 kVA
4. Color: IBM off-white.
5. Mount enclosure and pull all cables into enclosure before installing dry contacts.
6. Low voltage wiring needs to enter from the top of the enclosure, in separate conduit from power cables.
7. Line side power connections to lugs: (1) # 6AWG per connection for 10 to 15 kVA.
(1) # 2AWG per connection for 20-30 kVA to lugs:. load side power connections to busbars; see detail.
8. Power cables must be sized to limit voltage drop from battery system to UPS to be a maximum 4 VDC.
.62"
(15.8mm)
NOTE
1. The signal cables in this figure must be shielded and double-insulated.
2. Connect the Pes (Protection Earth) of the UPS cabinet and BCB box to the same point.
.5"
(12.7mm)
1"
(25.4mm)
(11.8mm)
.47"
(11.8mm)
Midpoint Busbar Detail
DPN U3813078 Rev. N
1.93"
(49mm)
.46"
37
Page 44
6.0UPS SPECIFICATIONS
These specifications describe requirements for the Liebert NX UPS.
6.1Conformity and Standards
The UPS has been designed to conform to the following standards:
• IEEC1000-4-5
•ASME
• CSA 22.2, No. 107.1
• FCC Part 15, Class A
• ISO 9001
• National Electrical Code (NFPA-70)
• NEMA PE-1
•OSHA
• UL Standard 1778
The UPS system has UL and c-UL approval.
6.2UPS Environmental
The UPS is designed to operate under the following environmental conditions without damage or degradation in electrical operating characteristics:
Table 8Environmental characteristics
Rated Power10-30kVA
Operating Temperature, UPS32°F to 104°F (0°C to 40°C)
Optimal Operating Temperature, Battery68°F to 86°F (20°C to 30°C)
Relative Humidity0 to 95%, non-condensing
Acoustical Noise, dBA at 39 in. (1m)54
Altitude of Operation≤1000m per IEC 62040/3
Storage-Transport Temperature, UPS-4°F to 158°F (-20°C to 70°C)
Storage-Transport Temperature, Battery-4°F to 86°F (-20°C to 30°C)
UPS Specifications
6.3UPS Mechanical Characteristics
Table 9Mechanical characteristics
Parameter10kVA15kVA20kVA30kVA
Width, in. (mm)24 (600)
Depth, in. (mm)32.5 (825)
Height, in. (mm)63 (1600)
Weight Without Inner Batteries, lb. (kg)450 (205)450 (205)550 (250)550 (250)
<135% load
135% - 170% load
1000% full UPS rated output current
41
Page 48
7.0INSTALLATION DRAWINGS
The diagrams in this section illustrate the key mechanical and electrical characteristics of the NX
UPS System cabinets.
Figure 28 Dimensional view- front and left side views
Installation Drawings
600
Monitoring
Panel
1600
Air intake area.
Do not block
air filter.
90
FRONT VIEWLEFT SIDE VIEW
825
10mm dia. threaded
mounting holes
Leveler
Detail “A” Rear of unit
shown without side panel
Adjustable Stops
(see Note 11)
1. All dimensions are in millimeters.
2. A minimum of 24 inches clearance above the unit is required for air exhaust.
3. Installation and service access required. Left-side access recommended for maximum ease of
installation.
4. Keep cabinet within 15 degrees of vertical while handling.
5. Top and bottom cable entry available through removal access plates. Remove punch to suit conduit size
and replace.
6. Unit bottom is structurally adequate for forklift handling.
7. Open door to replace air filter, washable type, size 354x314.
8. Threaded mounting holes used for seismic anchoring or floor stand. Note: If a floor stand is used, the
weight of the unit must be supported under all casters.
9. Each mounting location is supported by two 10 GA. (.135”) galvanized steel. The threaded 12mm insert
is approximately 3/4” deep. Mounting bolts must be threaded into unit.
10. Includes side panel. Refer to Detail A for dimension to frame with side panel removed. Side panels are
removed between adjacent units that are bolted together.
11. Adjustable stops are not designed to carry the full weight of the cabinet. Finger-tighten stop against the
floor, then tighten with a wrench less than two turns for friction against the floor.
42
Page 49
Figure 29 Dimensions continued—top and bottom views
A
Rear stabilizing foot
Air Exhaust
Power Cable
Entry Area
Top and
Bottom
Installation Drawings
10mm dia. threaded
mounting holes 4 (typ).
See Notes 8 and 9 above.
Air
TOP VIEWBOTTOM VIEW
Figure 30 Main components—typical unit
Monitor
Board
(U2)
IntelliSlot
Communication
Ports
Input
Breaker
Rotary
System
Switch
Input Breaker
ccess Plate
Parallel Board (M3)
Power
Electronics
Battery
Trays
Internal and
External Battery
Terminal Block
Access Plate
Front View
(with door open)
43
DPN U3812048
Rev. 1
Page 50
Figure 31 Cable connections
Installation Drawings
AC output cable
connections
Bypass AC input cable
connections
Input Neutral Bus
(side view)
Input/Output
Neutral
Earth
Battery connections (+ N -)
4.1 to battery
4.2 to external battery cabinet
NOTES
Output Neutral Bus
(side view)
Power Earth
(side view)
1. All dimensions are millimeters.
2. Top and bottom cable entry available through removable access plates. Remove, punch to
accommodate conduit size and replace.
3. Control wiring and power wiring must be run in separate conduit. Output and input cables must be
run in separate conduit.
4. Aluminum and copper-clad aluminum cables are not recommended,
5. All wiring is to be in accordance with national and local electrical codes.
44
Page 51
Figure 32 Location of internal batteries
Installation Drawings
417mm
Battery
186mm
687mm
45
Page 52
Figure 33 Battery connections
TOP LAYERMIDDLE LAYER
W50 1 3pcs
Installation Drawings
DYNASTY BATTERY
+
W500 18pcs
+
+
+
W510 to W511W502 to W503 W503 to W502W504 to W505
W511 to W510
-
+
-
+
-
+
-
+
W507 to W506
-
W506 to W507
-
-
-
W509 to W508
+
+
+
+
BOTTOM LAYER
+
-
+
-
+
-
+
-
+
-
+
-
-
-
-
-
-N+
CON4
+
+
+
W505 to W504W508 to W509
46
-
+
-
+
-
+
-
-
-
Page 53
Figure 34 Battery cabinet interconnection
Refer to Table 16 for key to interconnection
Positive (+)
Midpoint (N)
Negative (-)
Breaker
Connection
Detail
Detail
Positive (+)
Midpoint (N)
Breaker
Detail
Installation Drawings
Negative (-)
A
A
B
B
OR
A
UPS Module
Front View
with doors removed
27" Battery Cabinet
Front View
without doors and
protective plates
59" Battery Cabinet
Front View
without doors and
protective plates
NOTES:
1. All Liebert-supplied cable must be repositioned prior to and while the cabinets are being placed in
their final installed location.
2. All interconnection hardware supplied by Liebert
3. All interconnection cables supplied by Liebert when bolted together.
4. Interconnection cables field-supplied when battery cabinets are stand-alone.
5. Refer to the individual drawing of each piece of equipment for additional details.
K1UPS #1 Module AC InputParalleling CabinetPH A, B, C - UPSCR1, DR1
K2UPS #1 Module AC INPUTParalleling CabinetPH A, B, C - UPSCR1, DR1
49
Page 56
Figure 37 Lineup detail—SlimLine distribution cabinet to NX
Installation Drawings
E
H
G
H
A
C
B
D
D
G
E
H
NOTES:
1. All Liebert-supplied cable will need to be repositioned prior to and while setting the cabinets in their
installed location.
2. All interconnection cables and hardware supplied by Liebert.
3. AC connections must be made to the UPS module before attaching.
4. See Figure 45 for placement of distribution cabinet.
5. Refer to the individual drawing of each piece of equipment for additional details.
Table 19Liebert-supplied interconnect wiring—SlimLine distribution cabinet to NX
RunFromToConductors
ADistribution CabinetLoad AC ConnectionIsolated Ground
BDistribution Cabinet Load AC Connection
CDistribution Cabinet Load AC Connection
DDistribution Cabinet Load AC ConnectionPH A,B,C
EUPS Module AC OutputDistribution Cabinet PH A, B, C
GUPS Module AC OutputDistribution CabinetNeutral
HUPS Module AC OutputAll Ground ConnectionsGround
Neutral
Distribution Cabinet
Ground
Distribution Cabinet
50
Page 57
Installation Drawings
e
I
Figure 38 Lineup detail—1+N Type A connection to NX
1 + N Parallel Cabinet
(front view without front door and panel)
1. All Liebert-supplied cable must be repositioned prior to and while setting the cabinets in their installed
location.
2. All interconnection cables and hardware supplied by others.
3. AC connections must be made to the UPS modules before attaching paralleling cabinet to UPS modules
4. The interconnecting output cables between the paralleling cabinet and the UPSes must be the same siz
and the same length.
5. The location of the system output neutral busbar (connection K) and the ground busbar (connections H,
and J) are shown for a left-access style. For right-access version, these busbars are at opposite locations
6. Refer to the individual drawing of each piece of equipment for additional details.
Table 20Interconnect wiring—1+N Type A connection to NX
RUN FROMTOCONDUCTORS
A1-A4Utility AC SourceUPS #1-UPS #4 Module AC InputPh A, B, C - UPS Input
B1-B4Utility AC SourceUPS #1-UPS #4 Module AC InputNeutral - UPS Input
C1-C4 UPS #1-UPS #4 Module AC OutputParalleling CabinetPh A, B, C- UPS Output
E1-E4Paralleling CabinetUPS #1-UPS #4 Module AC GroundGround-UPS
FParalleling CabinetLoad AC ConnectionPh A, B, C - Load
GParalleling CabinetLoad AC ConnectionGround-Load
HParalleling CabinetLoad AC ConnectionNeutral-Load
I1-I4
Paralleling Cabinet
UPS #1-UPS #4 Module
Parallel Logic Board (M3)
Output Breaker Aux Contact
51
Page 58
Figure 39 Lineup detail—1+N Type A1 connection to NX
g
Installation Drawings
1 + N Parallel Cabinet
(front view without front door and panel)
1 + N Cabinet Interior View
(neutral and ground busbar location)
1. All Liebert-supplied cable must be repositioned prior to and while
setting the cabinets in their installed location.
2. All interconnection cables and hardware supplied by others.
3. AC connections must be made to the UPS modules before attachin
paralleling cabinet to UPS modules.
4. The interconnecting input cables between the paralleling cabinet
and the UPSes must be the same size and the same length.
5. The interconnecting output cables between the paralleling cabinet
and the UPSes must be the same size and the same length.
6. The location of the system output neutral busbar (connection K)
and the ground busbar (connections H, I and J) are shown for a
left-access style. For right-access version, these busbars are at
opposite locations.
7. Refer to the individual drawing of each piece of equipment for
additional details.
UPS Module Left Side View
(without side panel)
Table 21Interconnect wiring—1+N Type A1 connection to NX
Run FromToConductors
AUtility AC SourceParalleling CabinetPh A, B, C - System Input
BUtility AC SourceParalleling CabinetGround - System Input
CUtility AC SourceParalleling CabinetNeutral - System Input
D1-D4Paralleling CabinetUPS #1-UPS #4 Module AC GroundPh A, B, C- UPS Input
E1-E4Paralleling CabinetUPS #1-UPS #4 Module AC GroundNeutral - UPS Input
F1-F4 UPS #1-UPS #4 Module AC OutputParalleling CabinetPh A, B, C - UPS Output
H1-H4Paralleling CabinetUPS #1-UPS #4 Module AC GroundGround - UPS
IParalleling CabinetLoad AC ConnectionPh A, B, C - Load
JParalleling CabinetLoad AC ConnectionGround - Load
KParalleling CabinetLoad AC ConnectionNeutral - Load
L1-L4
Paralleling Cabinet
UPS #1-UPS #4 Module
UPS Parallel Logic Board (M3)
Output Breaker Aux Contact
52
Page 59
Figure 40 Lineup detail—1+N Type B connection to NX
I1, I2
Installation Drawings
1 + N Parallel Cabinet
(front view without front door and panel)
1 + N Cabinet Interior View
(neutral and ground busbar location)
1. All Liebert-supplied cable must be repositioned prior to and
while setting the cabinets in their installed location.
2. All interconnection cables and hardware supplied by others.
3. AC connections must be made to the UPS modules before
attaching paralleling cabinet to UPS modules.
4. The interconnecting output cables between the paralleling
cabinet and the UPSes must be the same size and the same
length.
5. The location of the system output neutral busbar (connection
K) and the ground busbar (connections H, I and J) are shown
for a left-access style. For right-access version, these busbars
are at opposite locations.
6. Refer to the individual drawing of each piece of equipment for
additional details.
UPS Module Left Side View
(without side panel)
Table 22Interconnect wiring—1+N Type B connection to NX
Run FromToConductors
A1-A4Utility AC SourceUPS #1-UPS #4 Module AC InputPh A, B, C - UPS Input
B1-B4Utility AC SourceUPS #1-UPS #4 Module AC InputNeutral - UPS Input
C1-C4 UPS #1-UPS #4 Module AC OutputParalleling CabinetPh A, B, C - UPS Output
E1-E4Paralleling CabinetUPS #1-UPS #4 Module AC GroundGround-UPS
FParalleling CabinetLoad AC ConnectionPh A, B, C - Load
GParalleling CabinetLoad AC ConnectionGround-load
HParalleling CabinetLoad AC ConnectionNeutral-load
I1-I4
Paralleling Cabinet
UPS #1-UPS #4 Module
UPS Parallel Logic Board (M3)
Output Breaker Aux Contact
53
Page 60
Figure 41 Lineup detail—1+N Type B1 connection to NX
Installation Drawings
1 + N Cabinet Side View
(without side panel or door)
(front view without front door and panel)
1 + N Parallel Cabinet
1 + N Cabinet Interior View
(neutral and ground busbar location)
1. All Liebert-supplied cable must be repositioned prior to and while
setting the cabinets in their installed location.
2. All interconnection cables and hardware supplied by others.
3. AC connections must be made to the UPS modules before attaching
paralleling cabinet to UPS modules.
4. The interconnecting input cables between the paralleling cabinet and
the UPSes must be the same size and the same length.
5. The interconnecting output cables between the paralleling cabinet and
the UPSes must be the same size and the same length.
6. The location of the system output neutral busbar (connection K) and
the ground busbar (connections H, I and J) are shown for a left-access
style. For right-access version, these busbars are at opposite locations.
7. Refer to the individual drawing of each piece of equipment for
UPS Module Left Side View
(without side panel)
additional details.
Table 23Interconnect wiring—1+N Type B1 connection to NX
RunFromToConductors
AUtility AC SourceParalleling CabinetPh A, B, C - System Input
BUtility AC SourceParalleling CabinetGround - System Input
CUtility AC SourceParalleling CabinetNeutral -system Input
D1-D4Paralleling CabinetUPS #1-UPS #4 Module AC InputPh A, B, C - UPS Input
E1-E4Paralleling CabinetUPS #1-UPS #4 Module AC InputNeutral - UPS Input
F1-F4UPS #1-UPS #4 Module AC OutputParalleling CabinetPh A, B, C - UPS Output
H1-H4Paralleling CabinetUPS #1-UPS #4 Module AC GroundGround-UPS
IParalleling CabinetLoad AC ConnectionPh A, B, C - Load
JParalleling CabinetLoad AC ConnectionGround-load
KParalleling CabinetLoad AC ConnectionNeutral-Load
L1-L4
M1-M4
Paralleling Cabinet
Paralleling Cabinet
UPS #1-UPS #4 Module
UPS Parallel Logic Board (M3)
UPS #1-UPS #4 Module
UPS Parallel Logic Board (M3)
Output Breaker Aux Contact
Rotary Switch Aux Contact
54
Page 61
Figure 42 Lineup detail—1+N Type C connection to NX
Installation Drawings
1 + N Cabinet Side View
(without side panel or door)
(front view without front door and panel)
1 + N Parallel Cabinet
1. All Liebert-supplied cable must be repositioned prior to and while
setting the cabinets in their installed location.
2. All interconnection cables and hardware supplied by others.
3. AC connections must be made to the UPS modules before attaching
paralleling cabinet to UPS modules.
4. Utility AC source neutral not required for maintenance bypass/
transformer cabinet Type C.
5. The interconnecting input cables between the paralleling cabinet and
the UPSes must be the same size and the same length.
6. The interconnecting output cables between the paralleling cabinet
and the UPSes must be the same size and the same length.
7. The location of the system output neutral busbar (connection K) and
the ground busbar (connections H, I and J) are shown for a left-access
style. For right-access version, these busbars are at opposite locations.
UPS Module Left Side View
(without side panel)
8. Refer to the individual drawing of each piece of equipment for
additional details.
Table 24Interconnect wiring—1+N Type C connection to NX
Run FromToConductors
AUtility AC SourceParalleling CabinetPh A, B, C-system Input
BUtility AC SourceParalleling CabinetGround - System Input
C1-C4Paralleling CabinetUPS #1-UPS #4 Module AC InputPh A ,B, C - UPS Input
D1-d4Paralleling CabinetUPS #1-UPS #4 Module AC InputNeutral - UPS Input
E1-E4 UPS #1-UPS #4 Module AC OutputParalleling CabinetPh A, B, C - UPS Output
H1-H4Paralleling CabinetUPS #1-UPS #4 Module AC GroundGround - UPS
IParalleling CabinetLoad AC ConnectionPh A ,B, C - Load
JParalleling CabinetLoad AC ConnectionGround - Load
KParalleling CabinetLoad AC ConnectionNeutral - Load
L1-l4
M1-M4
Paralleling Cabinet
Paralleling Cabinet
UPS #1-UPS #4 Module
UPS Parallel Logic Board (M3)
UPS #1-UPS #4 Module
UPS Parallel Logic Board (M3)
1 + N Cabinet Interior View
(neutral and ground busbar location)
Output Breaker Aux Contact
Rotary Switch Aux Contact
55
Page 62
Figure 43 Lineup detail—1+N Type C1 connection to NX
Installation Drawings
1 + N Cabinet Side View
(without side panel or door)
UPS Module Left Side View
(without side panel)
Table 25Interconnect wiring—1+N Type C1 connection to NX
Run FromToConductors
AUtility AC SourceParalleling CabinetPh A, B, C - System Input
BUtility AC SourceParalleling CabinetGround - System Input
CUtility AC SourceParalleling CabinetNeutral -System Input
D1-D4Paralleling CabinetUPS #1-UPS #4 Module AC InputPh A, B, C - UPS Input
E1-E4Paralleling CabinetUPS #1-UPS #4 Module AC InputNeutral - UPS Input
F1-F4 UPS #1-UPS #4 Module AC OutputParalleling CabinetPh A, B, C - UPS Output
G1-G4UPS #1-UPS #4 Module AC OutputParalleling CabinetNeutral - UPS Output
H1-H4Paralleling CabinetUPS #1-UPS #4 Module AC GroundGround-UPS
IParalleling CabinetLoad AC ConnectionPh A, B, C - Load
JParalleling CabinetLoad AC ConnectionGround-Load
KParalleling CabinetLoad AC ConnectionNeutral- Load
L1-L4Paralleling CabinetUPS #1-UPS #4 Module
1 + N Parallel Cabinet
(front view without front door and panel)
1. All Liebert-supplied cable must be repositioned prior to and while setting
the cabinets in their installed location.
2. All interconnection cables and hardware supplied by others.
3. AC connections must be made to the UPS modules before attaching
paralleling cabinet to UPS modules.
4. The interconnecting input cables between the paralleling cabinet and the
UPSes must be the same size and the same length.
5. The interconnecting output cables between the paralleling cabinet and the
UPSes must be the same size and the same length.
6. The location of the system output neutral busbar (connection K) and the
ground busbar (connections H, I and J) are shown for a left-access style.
For right-access version, these busbars are at opposite locations.
7. Refer to the individual drawing of each piece of equipment for additional
details.
UPS Parallel Logic Board (M3)
1 + N Cabinet Interior View
(neutral and ground busbar location)
Output Breaker Aux Contact
56
Page 63
Figure 44 Lineup detail—1+N Type D connection to NX
Installation Drawings
1 + N Cabinet Side View
(without side panel or door)
(front view without front door and panel)
1 + N Parallel Cabinet
1 + N Cabinet Interior View
(neutral and ground busbar location)
1. All Liebert-supplied cable must be repositioned prior to and while
setting the cabinets in their installed location.
2. All interconnection cables and hardware supplied by others.
3. AC connections must be made to the UPS modules before attaching
paralleling cabinet to the UPS modules.
4. The interconnecting input cables between the paralleling cabinet and
the UPSes must be the same size and the same length.
5. The interconnecting output cables between the paralleling cabinet and
the UPSes must be the same size and the same length
6. The location of the system output neutral busbar (connection K) and the
ground busbar (connections H, I and J) are shown for a left-access style.
For right-access version, these busbars are at opposite locations.
7. Refer to the individual drawing of each piece of equipment for additional
UPS Module Left Side View
(without side panel)
details.
Table 26Interconnect wiring—1+N Type D connection to NX
Run FromToConductors
AUtility AC SourceParalleling CabinetPh A, B, C - System Input
BUtility AC SourceParalleling CabinetGround - System Input
CUtility AC SourceParalleling CabinetNeutral - System Input
D1-D4Paralleling CabinetUPS #1-UPS #4 Module AC InputPh A, B, C - UPS Input
E1-E4Paralleling CabinetUPS #1-UPS #4 Module AC InputNeutral - UPS Input
F1-F4 UPS #1-UPS #4 Module AC OutputParalleling CabinetPh A, B, C - UPS Output
H1-H4Paralleling CabinetUPS #1-UPS #4 Module AC GroundGround - UPS
IParalleling CabinetLoad AC ConnectionPh A, B, C - Load
JParalleling CabinetLoad AC ConnectionGround - Load
KParalleling CabinetLoad AC ConnectionNeutral -L oad
L1-L4Paralleling CabinetUPS #1-UPS #4 Module
UPS Parallel Logic Board (M3)
M1-M4Paralleling CabinetUPS #1-UPS #4 Module
UPS Parallel Logic Board (M3)
Output Breaker Aux Contact
Rotary Switch Aux Contact
57
Page 64
Figure 45 SlimLine locations
Installation Drawings
SlimLine
UPS
UPSBattery
SlimLine
MBCUPS
SlimLine
UPS
SlimLine
SlimLine
SlimLine
1 + N
Paralleling
Cabinet
58
BatteryMBCUPS
1 + N
Paralleling
Cabinet
SlimLine
Page 65
8.0SPECIFICATIONSAND TECHNICAL DATA
8.1Lug Size and Torque Requirements
Use commercially available solderless lugs for the wire size required for your application. Refer to
Table 27. Connect wire to the lug using tools and procedures specified by the lug manufacturer.
Table 27Torque specifications
Nut and Bolt CombinationS
Grade 2 Standard
Bolt Shaft Size
1/4536.0465.2
5/1610712606.8
3/8192229511
1/24282225629
Circuit Breakers With Compression Lugs (For Power Wiring)
8.2Cable Lengths: Floor to Connection Point Inside UPS
To help calculate the total cable length required, refer to Table 37 for the distance from the floor to
selected connection points inside the NX. Determine the cable length required to reach the NX, then
add the appropriate length from the table and adequate slack for repair and maintenance.
Table 37Distance to connection points on the NX UPS
Ensuring The High Availability
0f Mission-Critical Data And Applications.
Emerson Network Power, the global leader in enabling business-critical
continuity, ensures network resiliency and adaptability through
a family of technologies—including Liebert power and cooling
technologies—that protect and support business-critical systems.
Liebert solutions employ an adaptive architecture that responds
to changes in criticality, density and capacity. Enterprises benefit
from greater IT system availability, operational flexibility and