Connection of the encoder
- Use only screened cable to connect the encoder and ensure that
the pin assignment is correct (see sticker next to the cover of the
terminal box).
- When connecting the Namur interface, ensure that the 2-wire
connection has the correct polarity. The SCR interface is
independent of the polarity.
Then install the meter
- gas-tight,
- with the supplied accessories,
- only in flow direction (as marked by an arrow on the meter housing),
- only unstressed and
- preferably in horizontal position with the counter at the top.
The permitted installation/operating positions of the meter are specified on the
meter housing in accordance with the designations “H, V or H/V” represented in
accordance with DIN EN 12261. If you have specified the installation or operating
position when ordering, all attachments will have been fitted in accordance with the
installation position ex-works.
If you wish to install the unit vertically at a later point and if an oil pump is present, the
oil pump must also be fitted vertically. If this is not the case, you must turn the oil pump
and its oil connection line and any other attachments, e.g. volume corrector, through 90°
before installing the meter.
We recommend that you contact our After-Sales Service for such conversion work.
- weatherproof.
- When fitting the seals and gaskets, ensure that they are aligned concentrically and do
not project into the flow channel.
12. Commissioning
For meters without oil pump, continue with point “Placing the system into operation”.
Meters with oil pump must be provided with initial lubrication
Before commissioning:
- First open the cover on the oil supply tank.
- Fill the oil supply tank with the supplied oil.
- The oil quantity is sufficient when the oil level reaches around ¾ of the tank volume.
- Operate the oil pump as instructed in Section “Maintenance and lubrication” and
only then close the oil supply tank.
Placing the system into operation
In order not to damage the meter,
- slowly fill the system until operating pressure is reached.
- The pressure rise may not exceed 350 mbar/s. You should also use a bypass line for
filling (recommendation: 12 mm pipe diameter).
- Do no exceed the measuring range even briefly!
- Conduct a tightness test!
Important! Dirt particles, such as welding beads, swarf and other foreign bodies, may be
contained in the gas for a short while after installation.
For this reason, always fit a coarse filter in order to avoid damage to the counter. Do
not forget to remove the coarse filter after approx. 4-6 weeks since, should it become
saturated, this would produce an obstacle to flow.