elco THISION WH Operation And Installation Manual

Page 1
Operation and Installation manual
THISION WH
02/2011 DOC3078 / 12103187
Page 2
Page 3
Contents
General regulations ................................... 5
Application ................................................. 5
Norms and regulations .............................. 5
Construction Layout of water heater ............................... 7
Operating principle .................................... 7
Technical data ................................................................. 10
Water heater Installation .......................... 12
Connecting the water heater .................... 12
Commissioning Water and hydraulic system ...................... 17
Gas supply ................................................ 18
........................... 18
Flue and air intakeconnections ................. 18
Prepare water heater for first startup ........ 19
Combustion analysis ................................. 20
........... 21
Gas tightness check .................................. 21
Water heater shut down ............................ 21
Maintenance Checklist .................................................... 25
Replacing the electrodes ........................... 25
Cleaning the condensate receptacle ......... 26
Cleaning and refilling the syphon .............. 26
Inspection of the combustion chamber ...... 26
Water pressure and quality ....................... 27
Combustion analysis ................................. 27
Gas pressure ............................................. 27
Gas tightness check .................................. 27
Safety devices ........................................... 27
Maintenance Protocol ................................. 28
Loc
kouts
.................................................................. 22
Safety Provisions ...................................... 6
Thision WH principle ................................. 7
Unvented Applications .............................. 14
Cylinder diagnosis & controls .................... 19
Commissionign protocol ............................. 29
3
Condensate connections
Check functionality of safety devices
Cylinder venting .........................................
17
Page 4
Page 5
Safety General regulations
Application Norms and regulations
5
General regulations
This documentation contains important information, which is a base for safe and reliable installation, commissioning and operation of the THISION L boiler. All activities described in this document may only be excecuted by authorized companies.
Changes to this document may be ef­fected without prior notice. We accept no obligation to adapt previously deliv­ered products to incorporate such changes.
Only original spare parts may be used when replacing components on the boiler, otherwise warranty will be void.
Applic
ation
The THISION water heater may be
used for hot water production purpo-
ses only.
Norms and regulations
When installing and operating the boiler, all applicable norms (european and local) should be fulfilled:
Local building regulations for install­ing combustion air and flue gas sys­tems;
Regulation for connecting the water
heater to the electrical appliance;
Regulations for connecting the water heater to the local gas network;
Norms and regulations according to safety equipment for heating systems;
Any
additional local laws/regulations with regard to installing and operating heating systems.
Additional national standards Germany:
RAL - UZ 61 / DIN 4702-8
Switzerland:
SVGW EKAS-Form. 1942: Flüssiggas-
Richtlinie Teil 2 Vorschriften der kantonalen Instanzen
(z.B. Feuerpoilizeivorschriften)
Netherlands:
GASKEUR BASIS GASKEUR SV GASKEUR HR107
Belgium:
HR TOP
The THISION L boiler is CE approved and applies to the following Euro­pean standards:
92 / 42 / EEC Boiler efficiency directive
2009 / 142 / EEC Gas appliance directive
2006 / 95 / EEC L
ow voltage directiv
e
2004 / 108 / EEC EMC directive
EN 483 Gas-fired central heating boilers ­Type C boilers of nominal heat input not exceeding 70 kW
EN 15420 Gas-fired central heating boilers ­Type C boilers of nominal heat input exceeding 70 kW, but not exceeding 1000 kW
EN 15417 Gas-fired central heating boilers ­Specific requirements for condensing boilers with a nominal heat input greater than 70 kW but not exceeding 1000 kW
EN 50165 Electrical equipment of non-electri
c appliances for household and similar purposes - Safety requirements
EN 15502-1 Gas-fired central heating boilers ­Part 1: General requirements and tests
EN 55014-1 (2000) Electromagnetic compatibility - Re­quirements for household appliances, electric tools and similar apparatus ­Part 1: Emission
EN 55014-2 (1997) Electromagnetic compatibili
ty - Re­quirements for household appliances, electric tools and similar apparatus ­Part 2: Immunity - Product family standard
EN 61000-3-2 (2000) Electromagnetic compatibility (EMC) ­Part 3-2: Limits - Limits for harmonic current emiss
ions (equipment input
current 16 A per phase) EN 61000-3-3 (2001)
Electromagnetic compatibility (EMC) ­Part 3-3: Limitation of voltage changes, voltage fluctuations and flicker in public low-voltage supply systems, for equipment with rated current 16 A per phase and not sub­ject to conditional connection
EN 60335-1 (2002) Household and similar electrical appli­ances - Safety - Part 1: General re­quirements
EN 60335-2-102 (2006) Household an similar electrical appliances: Particular requirements for gas, oil and solid-fuel burning ap­pliance
s having electrical connections
Page 6
Safety Provisions
Conditions It is a statutory requirement that all gas appliances are installed in accordance with the manufactures instructions and
all current regulations in force, all instructions should be fully read before installing or using the appliance. All installations should be carried out by competent persons as described in the Gas Safety (Installation & Use) Regulations. i.e. GasSafe registered and holding current certification. The work must be carried out by a competent person as described in the I.S. 813 Domestic Gas Installations with reference to the following codes of practices. The Manufacturers instructions MUST NOT be taken in any way as overriding statutory obligations.
This boiler has been tested and certified to comply with all necessary European directives, latest building regulations and efficiency requirements for the SEDBUK scheme and as been approved with an efficiency band rating of A and is CE marked and
complies with
92
/42/EEC Efficiency of Hot Water Boilers Directive 90/396/EEC Gas Appliance Directive 93/68/EEC Low Voltage Directive (was 73/23) 92/31/EEC Electromagnetic compatibility Directive I.S. 813 Domestic Gas Installations The Thision WH should be installed in compliance with The building regulations (Scotland-consolidated) Building Regulations (Northern Ireland) Building Regulations Water fittings regulations or water bylaws in Scotland Local water company bylaws
The boiler should not be modified in any way. Any modifications will invalidate the gas approval and invalidate the warranty.
ATTENTION: High Voltage Before opening the boiler casing for maintenance or servicing the 230VAC main supply to the boiler must be disconnected!!
5
6
Page 7
Construction
Layout of water heater Operating principle
Layout of water heater
The THISION water heater consists
following main components:
1 Casing 2 Control panel 3 Flue gas connection (+ test point) 4 Air intake connection (+ test point) 5 Flow water connection 6 Return water connection 7 Gas connection 8 Syphon 9 Input for wiring 10 Connection for safety valve 11 Connection for fill/drain valve 12 Manometer 13 Fan 14 Gas valve 15 Ignition and ionisation electrodes 16 Heat exchanger 17 Inspection window 18 Ignition transformer 19 Electrical input connections 20 Controller 21 Condensate receptacle
Operating p
rinciple
The THISION WH is a fully modulating water heater. The control unit of the water heater adapts the modulation ratio automatically to the heat demand required. This is done by controlling the speed of the fan. As a result, the whirl­wind mixing system will adapt the gas ratio to the chosen fan speed, in order to maintain the best possible combustion figures and therewith the best efficiency. The flue gases created by the combustion are transported downwards through the heat exchanger and leave the boiler at
the top into the
chimney connection. The return water from the system en­ters the boiler in the lower section, where is the lowest flue gas tempera­ture in the boiler. In this section con­densation takes place. The water is being transported upwards through the heat exchanger, in order to leave the boiler at the flow connection. The cross flow working principle (water up, flue gas down) ensures the most efficient combustion results.
2
4
1
3
6 5
8 7
9
10 11
12
13
14
15
16
17
18
19
20
21
2
7
of the
Page 8
The Thision WH is a standalone DHW charging system that consists of a buffer tank, plate heatexchanger and a boiler.
The System is suitable for use in any building with medium to large water usage, such as swimming pools, gyms , sports clubs, fitness centres etc.
Hydraulic System Diagram
The Thision WH is a standalone unit that functions exceptionally. Where there is a high demand for hot water there is an option to connect two units together in parallel. It is essential that the units are connected such that flow is distributed evenly through both units
Caution!
The capacity of the built in water recirculation pump is 600 l/hr at the 20 kPa setting. The maximum loss of the flow and recirculation system occurs at 65°C flow and 60°C return (3.kw). A greater loss will cause a lower return temperature and therefore a longer loading period.
Legend: P1: Loading Pump P2: Boiler Pump
T1: Loading Temperature Sensor T2: Start Temperature Sensor T3: Shut Down Temperature Sensor T4: Primary Flow Temperaure Sensor T5: Secondary Return Temperature Sensor
(optional sensor required)
Ensure that pipework is equal from both units to the secondary flow and secondary return connection.
Thision Thision
Plan View of two Thisions in parallel
The Thision WH has been designed for ease of installation. For the unit to provide DHW a minimum of the following is required to be installed from the system to the unit:
1. 230Vac electrical supply
2. Mains cold water supply
3. DHWS secondary flow pipework
4. DHWS secondary return pipework
5. Gas supply pipework
6. Condense drain pipework
7. Flue gas outlet & Air intake pipework
8
Thision WH
Installing 2 Thision WH in parallel
T2
T5
T3
T4
T1
P1
P2
Secondary Return Connection
Page 9
Technical data
9
65
THISION L
85
THISION L
120
Nominal heat output at 80-60ºC max/min
kW 60.8/10.1 81.1/13.4 111.6/18.7
Nominal heat output at 75-60ºC max/min
kW 60.9/10.1 81.3/13.4 111.8/18.7
Nominal heat output at 40/30ºC max/min
kW 63.9/11.1 85.3/14.8 120.0/20.6
Nominal heat input Hi max/min
kW 62.4/10.4 83.3/13.8 114.3/19.2
Efficiency at 80/60ºC
% 97.4 97.4 97.6
Efficiency at 40/30ºC % 102.4 102.4 105.0 Annual efficiency (NNG 75/60ºC)
% 106.2 106.2 106.2
Annual efficiency (NNG 40/30ºC)
% >110 >110 >110
Standstill losses (T
water
= 70ºC) % 0.20 0.20 0.20
Max. condensate flow
l/h 3.5 4.8 7.7
Gas consumption H-gas max/min (10,9 kWh/m
3
) m3/h 5.7/1.0 7.6/1.3 10.5/1.8
Gas consumption L-gas max/min (8,34 kWh/m
3
) m3/h 7.5/1.2 10.0/1.7 13.7/2.3
Gas consumption LPG. max/min (12,8 kWh/kg)
kg/h 4.9/0.8 6.5/1.1 8.9/1.5
Gas pressure H-gas
mbar 20 20 20
Gas pressure L-gas
mbar 25 25 25
Gas pressure LPG
mbar 30/50 30/50 30/50
Maximum gas pressure
mbar 50 50 50
Flue gas temperature at 80/60ºC max/min
ºC 76/63 76/63 76/63
Flue gas temperature at 40/30ºC max/min
ºC 55/39 55/39 55/39
Flue gas quantity max/min
m
3
/h 119/19 159/25 213/35
CO
2
level natural gas H/E/L max/min % 8.5/8.5 8.5/8.5 8.7/8.5
CO
2
level liguid gas P max/min % -/- -/- -/-
NOx level
mg/kWh 39 39 39
CO level max/min
mg/kWh 98/7 98/7 98/7
Max. permissible flue resistance max/min
Pa 150/15 150/15 200/15
Water volume
l 3.5 4.8 7.7
Water pressure max/min
bar 6/1 6/1 6/1
Max. water temperature (High limit thermostat)
ºC 100 100 100
Maximum temperature setpoint
ºC 90 90 90
Nominal water flow at dT=20K
m
3
/h 2.6 3.4 4.8
Hydraulic resistance at nominal water flow
kPa 16 29 22
Electrical connection
V 230 230 230
Frequency
Hz 50 50 50
Mains connection fuse
A 10 10 10
IP class
- IPX4D IPX4D IPX4D
Power consumption boiler max/min (excl. pump)
W 98/26 167/38 228/36
Power consumption 3-step pump (optional)
W 150 205 210
Power consumption speed controlled pump (opt)
W 124 124 130
Weight (dry) with 250L cylinder
Noise level at 1 meter distance dB(A) - - -
-
Water connections
- R1.1/4" R1.1/4" R1.1/2"
Gas connection
- R3/4" R3/4" R1"
Flue gas connection
mm 100 100 100
Air intake connection (for room sealed use)
mm 100 100 100
Condensate connection
mm 22 22 22
CE-0063CM3576
kg
CE certification code
PH value condensate
Ionisation current minimum
-
µA 3 3 3
3.2 3.2 3.2
Weight (dry) with 500L cylinder kg
160
168 190
170 178 200
THISION L
Weight (wet) with 250L cylinder kg Weight (wet) with 500L cylinder kg
413.5
422.8 447.7
673.5 682.8 707.7
Page 10
Technical data
65
THISION L
85
THISION L
120
10 min peak output at 60ºC (250L storage)
L 424 481 568 L 1292 1640 2163
THISION L
1st hour continous output at 60ºC (250L storage)
Continuous operation at 60ºC
1st hour continous output at 60ºC (500L storage)
10 min peak output at 60ºC (500L storage) L 674 731 818
L 1542 1890 2413
L 1042 1390 1913
10
Electrical Data Maximum Power Consumption
Electrical Supply
Fuse Rating
W
A
328 397 458
10
V
Frequency
Hz
50
50 50
230 230 230
DHW Performance Data
10
10
Page 11
Technical data
Dimensions
W mm B1 mm B2 mm D mm H mm
C1 BSP C2 BSP
E mm F mm
Thision WH 250 - 65/85
W
Thision WH 500 - 65/85
Thision WH 250 - 120
Thision WH 500- 120
585 750 585 750 140 140 140 140
H
2015 1879 2015 1879
B2
380 380 480 480
D
1516134614231248
C1
C2
C3 BSP
C3
G mm
E
F
G
1578 1061
323
1483 1082
352
1578 1061
323
1483 1082
352
1 1/4 “ 1 1/4 “
1 1/4 “ 1 1/4 “
3/4 “ 3/4 “ 3/4 “ 3/4 “
1 1/2 “
1 1/2 “ 1 1/2 “
1 1/2 “
W
B195
D
H1
H1 mm
1952 1821
1952 1821
11
J K
L M N
mm
mm
mm
mm
mm
J
K
L
M
N
1100 1000
800 700 600
1100 1000
800 700
600
DHW Flow
DHW Secondary Return
CW Inlet
1000
900 450 350 250
1000
900 450 350
250
Cable Gland
Cable Gland
Condense Waste
Gas
PRV Drain
O
P
Q
O
mm
1578
1578
1483
1483
P
mm
1215
1215
1122
1122
Q
mm
323
323
352
352
C4
C4 BSP 3/4 “ 3/4 “
3/4 “ 3/4 “
C5 BSP 1 “ 1 “
1 “ 1 “
C4
C4
C5
Page 12
Installation Water heater installation
Connecting the water heater
Water heater installation
The boiler should be positioned in a frost-proof boiler room. If the boiler room is on the roof, the boiler itself may never be the highest point of the instal­lation. When positioning the boiler, please note the recommended minimum clea­rance in the picture. When the boiler is positioned with less free space, mainte­nance activities will be more difficult.
Connecting the
water heater
This chapter will explain how to make all connections to the boiler with regard to:
Hydraulic connections Condensate drain connection Gas connecti
on Flue gas connection Air intake connection Electrical connection
The boiler should always be connected in such a way, that the system applies to all relevant standards and regulati­ons (European, national and local). It’s the responsibility of the installer to en­sure that all standards and regulations are respected.
Hydraulic connections (1,2,3,4)
Condensate connection (5)
After filling with water, the syphon (included in delivery) should be installed to the connection (5) at the bottom of the water heater. Connect the hose to the draining system in the boiler room. The connection to the draining system should always be done with an open connection, in order to avoid flooding the boiler in case of a blocked drain.
Gas connection (6)
The gas connection must be made by an authorized installer in accordance w
ith the applicable national and local
standards and regulations. Connect the gas line from the system
tension free to the gas connection (6) of the boiler. A gas cock should be moun­ted directly behind the boiler.
5 6
3 4
The Thision WH should be connected to the mains water supply, The concentration of chloride in the water supply should be less than 200mg/l. Should the hardness be measured at more than 14°dH then a softener should be installed to bring the hardness down to between 6°dH and 8°dH.
Caution!
When installing the Thision WH a mains water kit must be used. The DHWS flow connection should be protected against a vacuum by use of an anti-vacuum valve.
1000mm
100mm
500mm
200mm
12
Page 13
Installation
Connecting the water heater
Flue gas connection (7)
Regulations for the construction of flue gas systems are very different for each country. It should be ensured that all national regulations with regard to flue gas systems are respected.
Connect the flue gas system to the flue gas connection (7) of the water heater, use flue gas systems with seamless connections only. It’s not necessary to make a separate condensate drain for the flue gas system, as the condensate will be drained via the syphon of the boiler.
Please note the following issues:
It’s recommended to use stainless steel or PPS fluegas systems
The diameter of the flue gas system must be chosen by calculation ac­cording to the national regulations
Construct the
flue gas system as short as possible (for maximum length see planner documentation)
Construct horizonal ways with a mini­mum angle of 3º
Air intake connection (8)
The air intake can be connected in ca­se of room sealed installation. The dia­meter should be calculated according to the national regulations, together with the flue gas system. The total re
-
sistance of both systems should never overcome the maximum permissible resistance of the fan inside the boiler (see also chapter: Technical
data).
Elec
trical connection
The electrical connection must be made by an authorized installer in accordance with the applicable national and local standards and re­gulations.
For the power supply it’s necessary to use a mains isolator switch with a contact opening of at least 3 mm within the boiler room. This switch can be used to switch off the power supply for maintenance purposes.
8
7
13
Page 14
The Thision WH can be fed directly from the mains supply to the property without the need for seperate feed cisterns or vent pipes. It is supplied complete with all its necessary inlet and safety controls, thermal cut out and two port motorised valve.
Schematic installation details for unvented applications
PRESSURE REGULATING VALVE c/w NON RETURN VALVE
T&P RELIEF VALVE
PRIMARY FLOW & RETURN
DRAIN COCK (NOT SUPPLIED)
DISCHARGE PIPE
TUNDISH
SECONDARY RETURN TAPPING
TO HOT OUTLETS
MAINS WATER SUPPLY
EXPANSION VALVE
EXPANSION VESSEL
Thermal cut out
Examples of acceptable discharge arrangements are;
i. Ideally below a fixed grating and above the water seal in a trapped gully.
ii. Downward discharges at low level; i.e. up to 100mm above external surfaces such as car parks, hard standings, grassed areas etc. are acceptable providing that where children may play or otherwise come into contact with discharges a wire cage or similar guard is positioned to prevent contact, whilst maintaining visibility.
iii. Discharges at high level; e.g. into a metal hopper and metal downpipe with the end of the discharge pipe is clearly visible (tundish visible or not) or onto a roof capable of withstanding high temperature discharges of water and 3m from any plastic guttering systems that would collect such discharges (tundish visible).
iv. Where a single pipe serves a number of discharges, such as in blocks of flats, the number served should be limited to not more than 6 systems so that any installation discharging can be traced reasonably easily. The single common discharge pipe should be at least one pipe size larger than the largest individual discharge pipe (D2) to be connected. If unvented hot water storage systems are installed where discharges from safety devices may not be apparent i.e. indwellings occupied by blind, infirm or disabled people, consideration should be given to the installation of an electronically operated device to warn when discharge takes place.
Note: The discharge will consist of scalding water and steam. Asphalt, roofing felt and non metallic rainwater goods may be damaged by such discharges.
Unvented Applications
14
Page 15
Valve outletsize Minimumsizeof
discharge pipe D2
Minimumsizeof
fromtundish
Maximum
res is tance
allowed,
expressed as a
length of straight
pipe (i.e. no.
elbowsor bends)
createdbyeach
elboworbend
G1/2 15mm
22mm 28mm 35mm
up to 9m
up to 18m up to 27m
0.8m
1.0m
1.4m
G3/4 22mm
28mm 35mm 42mm
up to 9m
up to 18m up to 27m
1.0m
1.4m
1.7m
G1 28mm
35mm 42mm 54mm
up to 9m
up to 18m up to 27m
1.4m
1.7m
2.3m
Fixed grating
Discharge below fixed grating (Building Regulation G3 section 3.9d gives alternative points of discharge)
Trapped gully
Discharge pipe (D2)from tundish, with continuous fall. SeeBuilding Regulation G3 section 3.9d i-iv, Table4and worked example
300mm minimum
500mm maximum
Metal discharge pipe (D1) from Temperature relief valve to tundish
Tundish
Safety device (e.g. Temperature relief valve)
Sizing of copper discharge pipe (D2) for common T&P relief valve sizes
Schematic discharge pipe arrangement
Unvented Applications
Worked example of discharge pipe sizing.
The example below is for a G1/2 temperature relief valve with a discharge pipe (D2) having 4 No. elbows and length of 7m from the tundish to the point of discharge.
From Table 1: Maximum resistance allowed for a straight lenght of 22mm copper discharge pipe (D2) from a G1/2 temperature relief valve is 9.0m. Subtract resistance of 4 No. 22mm elbows at 0.8m each = 3.2m Therefore permitted length equates to 5.8m.
5.8m is less than the actual length of 7m therefore calculate the next largest size. Maximum resistance allowed for straight lenght of 28mm copper discharge pipe (D2) from a G1/2 temperature relief valve equates to 18m. Subtract resistance of 4 No. 28mm elbows at 1.0m each = 4.0m Therefore the maximum permitted length equates to 14m. As the actually length is 7m, a 28mm (D2) copper pipe will be satisfactory.
15
Resistance
discharge pipe D2
Page 16
16
Cylinder Controls
Electrical Connections
Page 17
Commissioning
Water and hydraulic system
17
Commissioning of the water heater should be carried out by authorised personnel only. Failure to respect this condition makes the guarantee void. A protocol of the commiss­ioning should be filled out (see end of this manual for example of commissioning prot­ocol).
This chapter explains the commissioning of the water heater with the standard water heater controller. When an additio­nal controller is installed, please refer to its manual for commissioning the controller.
Filling and venting the domestic hot water system
Step 1:Open the furthest outlet from unit Step 2:Open the mains cold water supply
until all the air has been eliminated from the outlet
Step 3:Open the valve on the reciculation circuit,
when all of the air has been eliminated close the outlet
Step 4:Check pipework for leaks
Further Commissioning
Once the system has been completely filled and vented the unit can be connected to the electrical supply. All DHWS settings are pre-set.
Ensure the following are operating correctly. The recirculation pump should operate continuously,
ensure the pump is running
The load pump will operate intermittently, ensure the pump turns freely
The boiler should operate when the loading pocess has started
The loading process will stop when the sytem has reached the required temperature
During the loading process the pumps speed will be altering this can lead to a pulsing sound from the pumps but is not damaging to their operation
Display codes during use: The display will show various codes during operation including the unit flow temperature.
Temperature Setting
The Thision WH is factory set at 65 C DHW flow and 60 DHW return, the temperature can only be adjsuted using specialist equipment.
Page 18
Commissioning Gas supply
Condensate connection Flue and air intake connections
Gas supply
Check the gas supply connection to the boiler for tightness. If any leakage is found, reseal the leakage before star­ting the boiler!
Remove any air between the gas valve and the gas line. This can be done at the test point (1) at the gas pressure switch.
Don’t forget to close the test
point afterwards! Check the gas type and values with the
local gas company, in order to know for which gas type the boiler should be commissioned.
Condensate connection
Remove the syphon (2) from the con­densate connection. Fill
it with water and place it back in the original positi­on. Make sure the syphon is filled befo­re starting the boiler, in order to prevent flue gases discharging through the condensate connection!
Flue and air intake connections
Check whether the flue and air intake systems are made according to the national and local regulations. Installati­ons which don’t comply with the regula­tions, are not allowed to be commissio­ned.
Make sure that all connections are free. The size of flue gas and air intake con-
nections may not be reduc
ed.
1
2
18
Page 19
Commissioning
Prepare water heater for first startup
19
M
H
B C D E F
I L
G A
Legend:
A On/off switch B Return (ESC) C Room temperature control D Confirmation (OK) E Manual mode F Chimney sweeper mode G Info mode H Reset button I Operation mode heating zone(s) L Display M Operation mode DHW
Preparation for first startup
Open the gas supply; Enable the power supply to the boiler; Switch on the boiler with the on/off
switch (1); Make sure the boiler is in standby
mode (K ); Check the pump operation: make
sure the pump runs in the right direction;
Release all air from the pum
p
motor.
It‘s recommended to put the boiler on 50% load after the first startup, as this is the best starting point to do a proper combustion analysis. This can be done with the following procedure:
Push button I >3 Sek, the boiler goes into controller Stopp mode.
Push the Info button (G), the actual boiler load (%) appears in the display;
Choose „set up“ (confirm with OK button), now the boiler load can be changed by rotating the wheel (C) and confirming the 50% setting with the OK button.
After checking the combustion values (see
next page), the controller Stopp mode can be stopped by pushing the control mode button (I) >3 Sek.
1
Cylinder Diagnosis
It is possible to view the operational data of each of the Thision WH i.e. temperatures, this is achieved by
holding the button on the cylinder controller for approximately 5 seconds. The diagnosis number is shown for 1 second then the value for 3 seconds.
The diagnosis setting can be exited by holding the button for
5 seconds or if the button is not depressed for 10 minutes.
So software version D0 Operating Status D1 Current T1 temperature D2 Current T2 temperature D3 Current T3 temperature D4 Current T4 temperature D5 N/A D6 Load pump P1 speed (rpm) D7 Required temperature
Temperature Setting
The Thision WH is factory set for 60 C DHW flow and can be adjusted by 5 C by switching the unit off and back on whilst holding the control button on the P CB.
º
º
Page 20
Commissioning
Combustion analysis
Combustion check at full load
Start the water heater in controller stop mode
and go to 50% load. Now the
boiler operates at 50% load. Allow the
boiler to stabilise the combustion for 3
minutes. Then increase the waterheater
load step by step up to 100%. Check the
gas pressure on the inlet of the gas valve while increasing the water heater
load: the gas pressure should never go
below the minimum required value see technical data. When an (optional) minimum gas pressure switch is con­nected, this must be set to 75% of the required gas pressure.
Check the combustion settings via the test point in the chim
ney connection (1). If necessary, correct the settings with the small adjustment screw at the top of the gas valve (2).
Combustion check at minimum load
Switch the water heater to minimum load
(0%). Check the combustion settings the
same way as described for full load. If necessary, correct the settings with the large adjustment screw at the top of the gas valve (3).
Combustion check at 50% load
An additional reference check of com­bustion values at 50% load is recom­mended in order to check if the gas valve is set in such way, that the modu­lating behaviour is norma
l. The CO
2
value should be in between the settings of full load and minumum load. CO value should be equal to full load and minimum load values.
Make sure that the boiler is set to auto­matic operation and controller stop mo­de is disabled after the combustion test is finished.
1
Combustion settings max. load
for natural gas G20 / G25
TH-L 100-145 CO
2, max
% 8.7±0.2
CO
max
ppm < 70
TH-L 65-85 CO
2, max
% 8.5±0.2
CO
max
ppm < 70
Combustion settings max. load
for LPG G31
Convert boiler before operation
(see coversion kit instruction)
TH-L 100-145 CO
2, max
% -
CO
max
ppm -
TH-L 65-85 CO
2, max
% -
CO
max
ppm -
Combustion settings min. load
for natural gas G20 / G25
TH-L 65-145 CO
2, min
% 8.5 ± 0.2
CO
min
ppm < 30
Combustion settings min. load
for LPG
G31
Convert boiler before operation
(see coversion kit instruction)
TH-L 65-145 CO
2, min
% -
CO
min
ppm -
2
3
20
Page 21
Commissioning Check functionality of safety devices
Gas tightness check Water heater shut down
Flow temperature sensor (1)
Disconnect the plug from the sensor while the water heater is switched on. This should result in a lockout no. 20. The lockout should disappear as soon as the plug is placed back in position, the water heater will restart.
Return temperature sensor (2)
Disconnect the plug from the sensor while the water heater is switched on. This should result in a lockout no. 40. The lockout should disappear as soon as the plug is placed back in position. The water heater will restart.
Flue gas temperature sensor (3)
Disconnect the plug from the sensor while the water heater is switched on. The should result in a lockout no. 28. The lockout should disappear as soon as the plug is placed back in position, the boiler will restart.
Ionisation electrode (4)
Remove electrical connection from the ionisation electrode while the water heater is running, the water heater will go to lock­out no. 128. The water heater will try to restart. With the electrical connection remo­ved, the restart will result in lockout no. 133. When the connection is remade the restart will be successful.
Measuring the ionisation current can be done by mounting a multi-meter (set to µA) in between the ionisation elec­trode and its electrical connection. The ionisation current should always be above 1.2 µA, in normal conditions it w
ill be 6 µA and above.
Check functionality of safety devices
All safety devices have to be checked on good functioning. Safety devices on a standard water heater are a water flow temperature sensor, water return temperature sensor, flue gas temperat­ure sensor and ionisation electrode. These devices can be checked as described below.
Gas tightness check
Check the gas tightness of all sealed connections with an approved soap or electronic gas analyzer, for example:
Test points; Bolt connections; Gaskets of mixing system, etc.
Water heater shut down
When the water heater will not be used for longer periods, shut down the boiler by following procedure:
Switch the boiler in standby operation (K );
Switch off the boiler with the on/off switch (5);
Disable power supply to the boiler by deactivating the mains isolator switch in the boiler room;
Close the gas supply to the boiler.
1
2
3
4
5
21
Page 22
22
In case of a lockout, a warning symbol ( ) and a flashing error code appears on the display. The cause of a fault should first be determined and eliminated before the boiler is being reset. The table below shows all possible lockouts with indication of possible cause.
Lockouts
Error code
Description of error
0 No error 10 Outside temperature sensor error 20 Boiler temperature 1 sensor error 26 Common flow temperature sensor error 28 Flue gas temperature sensor error 30 Flow temperature 1 sensor error 32 Flow temperature 2 sensor error 38 Flow temperature primary controller sensor error 40 Return temperature 1 sensor error 46 Return temperature cascade sensor error 47 Common return temperature sensor error 50 DHW temperature 1 sensor error 52 DHW temperature 2 sensor error 54 DHW primary controller sensor error 57 DHW circulation temperature sensor error 60 Room temperature 1 sensor error 65 Room temperature 2 sensor error 70 Buffer storage tank temperature 1 sensor error 71 Buffer storage tank temperature 2 sensor error 72 Buffer storage tank temperature 3 sensor error 73 Collector temperature 1 sensor error 74 Collector temperature 2 sensor error 82 LPB address collision 83 BSB wire short-circuit 84 BSB address collision 85 BSB RF communication error 91 EEPROM error lockout information 98 Extension module 1 error (collective error) 99 Extension module 2 error (collective error)
100 2 clocktime masters (LPB) 102 Clocktime master without reserve (LPB) 103 Communication error 105 Maintenance message 109
Boiler temperature supervision 110 STB lockout 111 TW cutout 121 Flow temperature 1 (HC1) supervision 122
Flow temperature 2 (HC2) supervision
125 Pump supervision error 126 DHW charging supervision 127 Legionella temperature not reached
128 Loss of flame during operation 129 Fan error or LP error
130
Flue gas temperature limit exceeded
131
Burner fault
132 GP or LP error 133 No flame during safety time 146 Configuration error collective message
Page 23
Lockouts
Error code
Description of error
151 Internal error 152 Parameterization error 153 Unit manually locked 160 Fan error 162 LP error, does not close 164 Error heating circuit flow switch 166 LP error, does not open 171 Alarm contact H1 or H4 active 172 Alarm contact H2 (EM1, EM2 or EM3) or H5 active 173 Alarm contact H6 active 174 Alarm contact H3 or H7 active 178 Limit thermostat heating circuit 1 179 Limit thermostat heating circuit 2 183 Unit in parameterization mode 193 Pump supervision error after flame on 216 Fault boiler 217 Fault sensor 241 Flow sensor solar sensor error 242 Return sensor solar sensor error 243 Swimming pool temperature sensor error 270 Limit function 317 Mains frequency outside permissible range 320 DHW charging temperature sensor error 324 BX same sensors 325 BX / extension module same sensors 326 BX / mixing group same sensors 327 Extension module same function 328 Mixing group same finction 329 Extension module / mixing group same function 330 Sensor BX1 no function 331 Sensor BX2 no function 332 Sensor BX3 no function 333 Sensor BX4 no function 334 Sensor BX5 no function 335 Sensor BX21 no function (EM1, EM2 or EM3) 336 Sensor BX22 no function (EM1, EM2 or EM3) 337 Sensor BX1 no function 338 Sensor BX12 no function 339 Collector pump Q5 not available 340 Collector pump Q16 not available 341 Solar Collector sensor B6 not available 342 DHW sensor B31 not available 343 Solar integration not available 344 Solar controlling element buffer K8 not available 345 Solar controlling element swimming pool K18 not available 346 Solid fuel boiler pump Q10
not available
347
Solid fuel boiler comparison sensor not available 348 Solid fuel boiler address error
23
Page 24
24
Lockouts
Error code
Description of error
349 Buffer return valve Y15 not available 350 Puffer address sensor 351 Primary controller / system pump address error 352 Pressureless header address error 353 Common flow sensor B10 not available 371 Flow temperature 3 (heating circuit 3) supervision 372 Limit thermostat heating circuit 3 373 Extension module 3 error (collective error) 349 Buffer return valve Y15 not available 350 Puffer address sensor 351 Primary controller / system pump address error 352 Pressureless header address error 353 Common flow sensor B10 not available 371 Flow temperature 3 (heating circuit 3) supervision 372 Limit thermostat heating circuit 3 373 Extension module 3 error (collective error) 386 Fan speed has lost valid range 388 DHW error no function 426 Feedback flue gas damper 427 Configuration flue gas damper 431 Sensor primary heat exchanger 432 Functional earth not connected 433 Temperature primary heat exchanger to high
Cylinder Lockouts
Error code
Description of error
01 TT1 sensor fault 02 TT2 sensor fault 03 TT3 sensor fault 04 TT4 sensor fault 05 TT5 sensor fault 06 Low temperature for extended time 07 Frost protection active 08 Boiler fault 09 No communication with boiler
Page 25
Maintenance
Checklist Replacing the electrodes
25
Maintenance of the water heater
should be carried out by authorized
personnel
only.
In order to ensure continued good and safe operation of the water heater, it sh-
ould be inspected at least once per year.
A maintenance protocol should be filled out (see end of this chapter for example of maintenance protocol).
Checklist
The following activities must be carried out, see following paragraphs for an extensive description of the main activi­ties:
Replace the ignition and ionisation electrodes;
Clean the condensate receptacle; Clean and refill the syphon; Inspect the
combustion chamber, clean if necessary (DON'T use water !);
Check the water pressure of the sys­tem;
Check the water quality of the system water as well as supply water;
Check/correct the combustion values at full and mimimum load with a com­bustion analyzer;
Check the gas pressure to the water heater; Check the tightness of all sealed con­nections and test points;
Check the functionality of all safety devices;
Fill out a maintenance protocol.
Replacing the electrodes
The electrodes are positioned on the top side of the boiler. Replace the
igniti­on electrode (1) and ionisation electro­de (2) as shown on the picture.
2
1
Page 26
Maintenance Cleaning the condensate receptacle
Cleaning and refilling the syphon Inspection of combustion chamber
Cleaning the condensate receptacle
Disconnect the plug of the fluegas temperature sensor (1);
Remove the condensate receptacle (2);
Clean the receptacle; Mount the condensate receptacle; Connect the plug of the fluegas tem-
perature sensor.
Cleaning and refilling the syphon
Remove the syphon (3) from the con­densate connection;
Clean and fill it with fresh water; Mount the syphon back in the original
position.
Inspection of combustion chamber
For inspection of the combustion cham­ber the mixing system and burner must be disassembled.
Switch off the boiler and close the gas supply;
Remove the electrical connection from the fan and gas valve
(4);
Remove the electrical connection from the electrodes (5);
Undo the gas connection at the inlet of the gas valve (6);
Disassemble the top plate incl. mixing system (7);
Remove the burner from the combustion chamber (8);
Inspect the combustion chamber and clean it with a vacuumcleaner if necessary;
Assemble all components in opposite order;
Open the gas su
pply and check all
connections for gas leakage; Switch on the boiler.
1
2
5
4
6
7
8
3
26
Page 27
Maintenance
27
Water pressure and quality
Check if the water pressure and quality meet the requirements. Consult the chapter “commissioning: water and hydraulic system” for more detailed information.
Combustion analysis
Check the combustion at full load and minumum load, correct the settings if necessary. An additional reference check at 50% load is recommended. Consult the chapter “commissioning: combustion analysis” for more detailed information.
Gas pressure
Check the dynamic pressure of the gas supply to the boiler, when the water heater is ru
nning at full load.
Gas tightness check
Check the tightness of all sealed con­nections with an approved soap or electronic analyzer, for example:
Test points; Bolt connections; Gaskets of mixing system, etc.
Safety devices
Check the functionality and the settings of all safety devices connected. Consult the chapter “commissioning: Check functionality of safety devices” for more detailed information.
It is possible to clean out the cylinder using fresh mains cold water if so desired. To carry out this operation isolate and disconnect all water supplies and ensure all electrical supplies are isolated. Run a drain hose from the drain valve to an operating drain, then connect a controlled mains water supply to the unit, drain the unit fully and then slowly supply water to the unit at the rate of drainage. carry on at this rate until the water running out of the bottom of the cylinder runs clear, then carry out two full fills and drains. Reconnect and re-commission.
Draining and cleaning the cylinder
Page 28
Maintenance
Maintenance Protocol
Maintenance Protocol THISION L
Project
tcejorP epyt relioB sserddA rebmun laireS ytiC raeY etaD ]Wk[ )iH( daol lanimoN reenignE ]Wk[ )iH( tuptuo lanimoN
System
]rab[ erusserp retaW ]-[ Hp retaW ]Hdº[ ssendrah retaW ]l/gm[ edirolhc retaW
Water ]Cº[ daol lluf T Water p
boiler
]aPk[
m[ wolf retaW
3
/h]
]-[ gnittes pmuP
Safety devices
aW ]Cº[ gnittes timil hgiH ter flow sensor checked
dekcehc rosnes sageulF ]Cº[ gnittes retimil .pmeT
Min. gas
pressure switch setting [mbar] Water flow switch checked
]ces[ renrub emit noitingI
Combustion analysis
100% load 50% load Min. load
m[ noitpmusnoc saG
3
m[ ]h/
3
/h] [m3/h]
]rabm[ ]rabm[ ]rabm[ erusserp saG
CO
2
]%[ [%] [%]
O
2
]%[ [%] [%] ]mpp[ OC [ppm] [ppm] ]mpp[ xON [ppm] [ppm]
T
atmospheric
]Cº[ [ºC] [ºC]
T
fluegas
]Cº[ [ºC] [ºC]
T
water, flow
]Cº[ [ºC] [ºC]
T
water, return
]Cº[ [ºC] [ºC]
Ionisation current [µA] [µA] [µA] p
fan
]rabm[ [mbar] [mbar]
p
top panel
]rabm[ [mbar] [mbar]
p
combustion chamber
]rabm[ [mbar] [mbar]
Remarks
28
Page 29
Commissioning
Commissioning protocol
29
Commissioning Protocol THISION L
Project
tcejorP epyt relioB sserddA rebmun laireS ytiC raeY etaD ]Wk[ )iH( daol lanimoN reenignE ]Wk[ )iH( tuptuo lanimoN
System
[ erusserp retaW bar] Installati-
on:
Roof top
roolf dnuorG ]-[ Hp retaW
tnemesaB ]Hdº[ ssendrah retaW
......................... :rehtO ]l/gm[ edirolhc retaW
Water -uardyH ]Cº[ daol lluf T
lics:
Low velocity header
Water p
boiler
[kPa] Plated heat exchanger
Water flow [m
3
/h] Bypass boiler
Pump setting [-] Other: .........................
Safety devices High limit setting [ºC] Water flow sensor checked
Temp. limiter setting [ºC] Fluegas sensor checked
Min. gas pressure switch setting [mbar] Water flow switch checked
Ignition time burner [sec]
Combustion analysis
100% load 50% load Min. load
Gas consumption [m
3
m[ ]h/
3
/h] [m3/h]
]rabm[ ]rabm[ ]rabm[ erusserp saG
CO
2
]%[ [%] [%]
O
2
]%[ [%] [%] ]mpp[ OC [ppm] [ppm] ]mpp[ xON [ppm] [ppm]
T
atmospheric
]Cº[ [ºC] [ºC]
T
fluegas
]Cº[ [ºC] [ºC]
T
water, flow
]Cº[ [ºC] [ºC]
T
water, return
]Cº[ [ºC] [ºC] Ionisation current [µA] [µA] [µA] p
fan
]rabm[ [mbar] [mbar] p
top panel
]rabm[ [mbar] [mbar] p
combustion chamber
]rabm[ [mbar] [mbar] Remarks
Page 30
Service:
ELCO GmbH D - 64546 Mörfelden-Walldorf
ELCO Austria GmbH
A - 2544 Leobersdorf
ELCOTHERM AG
CH - 7324 Vilters
ELCO Netherlands / Rendamax B.V.
NL - 6465 AG Kerkrade
ELCO Belgium n.v./s.a.
B - 1731 Zellik
ELCO Italia S.p.A.
I - 31023 Resana
ELCO UK / MHS Boilers ltd.
UK - Basildon, Essex, SS15 6SJ
ELCO France / Chaffoteaux SAS
F - 93521 Saint-Denis Cedex
Loading...