This guide will not replace the service and/or user manual of the product. The guide is only
designed to be a help on first start up of the product as well as a guide through the commissioning process.
All parts and menus of this document is described in depth in the product manual.
▀
Introdction
▀
Symbols in the document
Note!
The icon is shown when a important notice of the products needs to be understood.
High voltage
When the icon is shown extra caution needs to be taken since live parts of the boiler is possible to contact without them being isolated. Personal injury or even death may occur! All
installations must be done by a trained professional and comply with current building redulations.
Hot surfaces
The icon is shown when there is risk for personal scaldings or burns.
Effecta AB - Västra Rågdalsvägen 21 - 434 99 Kungsbacka - 0300 - 22320 - info@effecta.se
3
P. 2 Introduction
P. 2 Symbol description
P. 3 Table of content
P. 4 Check list before powering up the unit
P. 5 Controller
P. 6 Controller setup - fan
P. 7 Controller setup - feeder
P. 8 Calibration of feed rate - Auger model
P. 9 Calibration of feed rate - Auger model
P. 10 Calibration of feed rate - Integrated fuel store model
P. 11 Calibration of feed rate - Integrated fuel store model
P. 12 Calibration of feed rate - Vacuum fed model
P. 13 Calibration of feed rate - Vacuum fed model
P. 14 Calibration of feed rate - Vacuum fed model
P. 15 Calibration of feed rate - Vacuum fed model
P. 16 Controller setup - effect output
P. 17 Controller setup - date / time
P. 17 Controller setup - function test
P. 18 Back end protection
P. 19 Heating circuits
P. 20 Heating circuits
P. 21 Heating circuits
P. 22 Documentation
▀
Table of content
Effecta AB - Västra Rågdalsvägen 21 - 434 99 Kungsbacka - 0300 - 22320 - info@effecta.se
4
Water content
Before powering up the system with electrical mains please ensure that all the boiler is filled with
water. All pumps controlled by the boiler needs to be in water filled heating circuits where there is
no blockages from circulation.
Doors
All doors and cleaning accesses needs to be closed and sealed before powering up.
Flue / chimney
The boiler must be connected to a approved flue system to evacuate smoke gasses before powering up the boiler.
Fuel feeding
Depending on what fuel feed option the boiler is equipped with the fuel feed system needs to be
completed before power up as well as the storage filled with pellets.
When above is confirmed please allow electrical mains to the boiler.
▀
Check list before electrical power feed
Effecta AB - Västra Rågdalsvägen 21 - 434 99 Kungsbacka - 0300 - 22320 - info@effecta.se
5
Language
Choose desired language by pressing any of the
flags on the screen.
If change of language is desired please open OTHER SETTINGS where language change can be done
again.
Home screen
On the home screen there is a image of the boiler
with temperature readings of the flue, flow of first
heating circuit and boiler temperature.
A CO2 vaule is displayed (only in operation phase) if
the a lambda probe is used.
A flame icon indicates the flame value visual inside
the boiler in percent.
If the electrical heater is used and applicable to the
system a current consumption will be displayed.
At the bottom part a operating mode will normally be
displayed for instance; Ignition, pre operation, operation phase etc.
Main menu
When pressing the touch display three icons will appear. In this quick start guide you will be asked to
enter the different menus in order to do different settings.
▀
Control display
Effecta AB - Västra Rågdalsvägen 21 - 434 99 Kungsbacka - 0300 - 22320 - info@effecta.se
6
Controller setup
Press anywhere on the display and then press the OPERATION icon.
Operation settings menu:
Use the + and - buttons together with OK and the Return
key to navigate the menu system.
- Confirm that burner is set to OFF.
Fan menu:
Enter the FAN menu, a passcode is required which is
2233. The fan values are set up during operation with
a flue analyzer according to the installation manual. We
can however recommend the following values to get the
boiler operating enough to be able to measure with a flue
analyzer:
The ”Fan burner low” parameter is set to ON if you which
to have the low power output mode activated. We recommend to have it activated on a Komplett III Light which direct feeds any heating circuit without a accumulator tank.
Please leave the menu by pressing the Return key repeatedly until the home screen appears.
▀
Program setup - fan
Burner
Fan
Feeder settings
Temperature set
Information
Service
Installation
Off
VER: 3.0
Operation settings
20kW 25kW 35kW
Fan burner 55% 65% 55%
Flue boiler 65% 75% 90%
Fan burner
Flue boiler
Fan burner low
Fan alarm
Fan alarm
Fan
65%
75%
Off
Tacho
5s
Effecta AB - Västra Rågdalsvägen 21 - 434 99 Kungsbacka - 0300 - 22320 - info@effecta.se
7
▀
Program setup - feeder settings
Calibration of feed dose
The most critical part of the commissioning is to calibrate the feed doses of pellets correctly. It is
therefore of outmost importance that it is done precisely and according to this manual. If the feed
doses isn´t setup according to our recommendations the boiler will deliver a faulty output which
can damage the system and it will most likely also result in unstable operation of the product.
Auger fed model
The calibration process is described on
page 8-9.
Suction model
The calibration process is described on
page 12-15.
Integrated fuel store model
The calibration process
is described on page
10-11.