1. Unpack the Switch and Check Contents
AS5912-54X, AS5912-54XK or AS5916-54XK
Rack Mounting Kit—2 front-post brackets, 2 rear-post brackets, 20 screws, and 2 ear-locking screws
Power Cord (included with AC PSUs only)
Console Cable—RJ-45 to DB-9
DC Power Cable (included with 48 VDC PSU only)
Dust Cover Kit—6 for QSFP port and 48 for SFP ports
Documentation—Quick Start Guide (this document) and Safety and Regulatory Information
Note:
The switch has the Open Network Install Environment (ONIE) software installer pre-loaded on the switch, but no switch software image. Information about compatible switch software can be found at www.edge-core.com.
Caution:
and fan tray modules that are installed into its chassis. All installed modules must have a matching airflow direction. That is, if the installed power modules have a front-to-back (F2B) airflow direction, all the installed fan tray modules must also have a F2B airflow direction.
The switch includes plug-in power supply (PSU)
Use an additional two screws to secure each of the rear-post brackets at the mid-point on the sides of the switch.
Use the screws and cage nuts supplied with the rack to secure the switch in the rack.
Caution:
people. One person should position the switch in the rack, while the other secures it using the rack screws.
装置の吸排気に必要な領域を マニ ュ アル上に規定して いる。
Installing the switch in a rack requires two
3. Adjust Rear-Post Bracket Ears
Lock the position of the rear-post bracket ears using the included position-locking screws.
You can also adjust the rear-post bracket ears to fit different rack depths from 56 cm to 75 cm.
4. Ground the Switch
Note:
The switch drawings in this document are for illustration only and may not match your particular switch model.
2. Attach the Brackets
Attach each of the front- and rear-post brackets to the switch using four of the included bracket screws.
www.edge-core.com
– 1 –
Ensure the rack is properly grounded and in compliance with ETSI ETS 300 253. Verify that there is a good electrical connection to the grounding point on the rack (no paint or isolating surface treatment).
Attach the grounding wire (#14 AWG) to the grounding point on the switch rear panel. Then connect the other end of the wire to rack ground.
Caution:
unless all supply connections have been disconnected.
The earth connection must not be removed
150200001637A R03
E062018-AP-R03
2
1
1
2
4
3
2
1
132
4
1
1
1
2
2
1
3
123
Quick Start Guide
5. Connect Power
Install one or two AC or DC PSUs in the switch. The switch supports up to two PSUs that must have the
same matching airflow direction as the installed fan tray.
Connect an external AC or DC power source to the PSUs.
Caution:
to connect to a DC converter, and a #14 AWG (for -36 VDC to
-72 VDC PSU) wire to connect to a DC PSU.
Use a UL/IEC/EN 60950-1 certified power supply
Boot the switch. Wait for the ONIE software to locate and execute the NOS installer, and then wait for the installer to load the NOS software image.
Subsequent switch boots will bypass ONIE and directly run the NOS software.
Note:
For switches with ONIE software pre-loaded, refer to
the network operating system (NOS) installer and NOS documentation for details on software options and set up for ONIE.
8. Connect Network Cables
For the RJ-45 Management por t, connect 100-ohm Category 5, 5e or better twisted-pair cable.
Positronic PLA03F7000/AA
-36 – -72 VDC (red wire)
connector
DC Return (black wire) Ground (yellow-green wire)
6. Verify Switch Operation
Verify basic switch operation by checking the system LEDs. When operating normally, the PSU1/PSU2, Diag, and Fan
LEDs should all be on green.
Connect DAC cables to the SFP+/QSFP28 slots. Or first install SFP+/QSFP28 transceivers and then connect fiber optic cabling to the transceiver ports.
The following transceivers are supported:
100GBASE-CR4, AOC, SR4, LR4, and PSM4
40GBASE-CR4, SR4, and LR4
25GBASE-CR4 and AOC
10GBASE-CR, SR, and LR
As connections are made, check the port status LEDs to be sure the links are valid.
For the SFP+ ports:
Green — 10 Gbps mode
Amber — 1 Gbps mode
Each QSFP28 port has four LEDs that indicate valid links in the following modes:
1 LED Green — 100 Gbps mode
1 LED Blue — 40 Gbps mode
1-4 LEDs Amber — 25 Gbps breakout mode (four lanes)
1-4 LEDs Purple — 10 Gbps breakout mode (four lanes)
7. Perform Initial System Boot
If the network operating system (NOS) installer is located on a network server, first connect the RJ-45 Management (Mgmt) port to the network using 100-ohm Category 5, 5e or better twisted-pair cable. (Not required if the NOS installer is located on attached storage.)
– 2 –
Hardware Specifications
Switch Chassis
Size (WxDxH) 438.4 x 501.9 x 44 mm (17.26 x 19.76 x 1.73 inch)
Weight 9.7 kg (21.38 lb), with two installed PSUs
Quick Start Guide
Temperature Operating: 0° C to 40° C (32° F to 104° F)
Humidity Operating: 5% to 95% (non-condensing)
Power Consumption
AC PSU
Power Rating 100–240 VAC, 50-60 Hz, 650 Watts
AC Input 100–240 VAC, 50-60 Hz, 5 A maximum
DC Output 5 VDC @ 4 A, 12 VDC @ 52.9 A
48 VDC PSU
Power Rating 48 VDC, 650 Watts
DC Input 36–75 VDC, 12 A maximum
DC Output 5 VDC @ 4 A, 12 VDC @ 52.9 A
Regulatory Compliances
Emissions EN 55032:2015+AC:2016, Class A
Storage: -40° C to 70° C (-40° F to 158° F)
360 Watts maximum (AS5912-54X) 380 Watts maximum (AS5912-54XK) 400 Watts maximum (AS5916-54XK)
EN 61000-3-2:2014, Class A EN 61000-3-3:2013 FCC Class A VCCI Class A CE Mark CCC GB 9254-2008, Class A BSMI Class A, CNS 13438
Immunity EN 55024:2010+A1:2015
IEC 61000-4-2/3/4/5/6/8/11
Safety UL (CSA 22.2 No 60950-1 & UL60950-1)
CB (IEC/EN60950-1) CCC GB 4943.1-2011, Class A BSMI Class A, CNS 14336-1
Taiwan RoHS CNS 15663
– 3 –