1. Unpack the Switch and Check Contents
AS5812-54T
Rack Mounting Kit—2 front-post brackets, 2 rear-post brackets, 20 screws, and 2 ear-locking screws
Power Cord (included with AC PSUs only)
Ground Wire (included with DC PSUs only)
Console Cable—RJ-45 to DB-9
Documentation—Quick Start Guide (this document) and Safety and Regulatory Information
Note:
The switch has the Open Network Install Environment (ONIE) software installer pre-loaded on the switch, but no switch software image. Information about compatible switch software can be found at www.edge-core.com.
Caution:
and fan tray modules that are installed into its chassis. All installed modules must have a matching airflow direction. That is, if the installed power modules have a front-to-back (F2B) airflow direction, all the installed fan tray modules must also have a F2B airflow direction.
The switch includes plug-in power supply (PSU)
Use the screws and cage nuts supplied with the rack to secure the switch in the rack.
Caution:
people. One person should position the switch in the rack, while the other secures it using the rack screws.
装置の吸排気に必要な領域を マニ ュ アル上に規定 して いる。
Installing the switch in a rack requires two
3. Adjust Rear-Post Bracket Ears
Lock the position of the rear-post bracket ears using the included position-locking screws.
You can also adjust the rear-post bracket ears to fit different rack depths from 56 cm to 75 cm.
4. Ground the Switch
Note:
The switch drawings in this document are for illustration only and may not match your particular switch model.
2. Attach the Brackets
Attach each of the front- and rear-post brackets to the switch using four of the included bracket screws.
Use an additional two screws to secure each of the rear-post
brackets at the mid-point on the sides of the switch.
www.edge-core.com
– 1 –
Ensure the rack is properly grounded and in compliance with ETSI ETS 300 253. Verify that there is a good electrical connection to the grounding point on the rack (no paint or isolating surface treatment).
Attach the grounding wire #14 AWG to the grounding point on the switch rear panel. Then connect the other end of the wire to rack ground.
For details on grounding the switch with a 12 VDC PSU in an Open Rack, refer to the Edgecore ORSA-1U Open Rack Tray Set Installation Guide.
Caution:
unless all supply connections have been disconnected.
The earth connection must not be removed
E022017-AP-R02
150200001294A
2
1
1
2
3
2
1
4
132
411
1
2
2
1
1
2
1
Quick Start Guide
5. Connect Power
Install one or two AC or DC power modules in the switch. The switch supports up to two PSUs that must have the
same matching airflow direction as the installed fan tray.
Connect an external AC or DC power source to the modules.
7. Perform Initial System Boot
If the network operating system (NOS) installer is located on a network server, first connect the RJ-45 Management (Mgmt) port to the network using 100-ohm Category 5, 5e or better twisted-pair cable. (Not required if the NOS installer is located on attached storage.)
Boot the switch. Wait for the ONIE software to locate and execute the NOS installer, and then wait for the installer to load the NOS software image.
Subsequent switch boots will bypass ONIE and directly run the NOS software.
Note:
For switches with ONIE software pre-loaded, refer to
the network operating system (NOS) installer and NOS documentation for details on software options and set up for ONIE.
8. Connect Network Cables
36 75 VDC Return (blue wire)
-36
-75 VDC (brown
wire)
Caution:
Use a UL/IEC/EN 60950-1 certified power supply
Chassis Ground (yellow­green wire)
Open Rack tray connector for 12 VDC PSU
to connect to a DC converter, and a #14 AWG (for 36–75 VDC PSU) or #10 AWG (for 12 VDC PSU) wire to connect to a DC PSU.
6. Verify Switch Operation
Verify basic switch operation by checking the system LEDs. When operating normally, the PSU1/PSU2, Diag, and Fan
LEDs should all be on green.
For RJ-45 ports, use 100-ohm Category 6, 6a, or 7 twisted­pair cable for 10GBASE-T connections, or Category 5e or better cable for 100/1000BASE-T connections.
Connect DAC cables to the QSFP+ slots. Or, first install QSFP+ transceivers and then connect fiber optic cabling to the transceiver ports.
The following transceivers are supported:
40GBASE-CR4
40GBASE-SR4
Note:
As connections are made, check the port status LEDs
to be sure the links are valid.
9. View the Product Label
The switch product label is located below RJ-45 ports 7–12 on left side of the front panel. Pull the label out to view the product information.
– 2 –
Hardware Specifications
Switch Chassis
Size (WxDxH) 442.5 x 473 x 43.95 mm (17.42 x 18.62 x 1.73 inches)
Weight 9.5 kg (20.94 lb), with two installed PSUs
Temperature Operating: 0° C to 40° C (32° F to 104° F)
Storage: -40° C to 70° C (-40° F to 158° F)
Humidity Operating: 5% to 95% (non-condensing)
Quick Start Guide
Power Consumption
AC PSU
Power Rating 100–240 VAC, 50-60 Hz, 400 Watts
AC Input 100–240 VAC, 50-60 Hz, 6–3 A
DC Output 5 VSB @ 3 A, 12 VDC @ 33 A
48 VDC PSU
Power Rating 48 VDC, 400 Watts
DC Input 36–75 VDC, 16 A maximum
DC Output 5 VDC @ 0.5 A, 12 VDC @ 33 A
12 VDC PSU (PSU-12V-650)
DC Input 12 VDC (from Open Rack busbar)
Regulatory Compliances
Emissions EN 55032:2012/AC:2013, Class A
384 Watts maximum
EN 61000-3-2:2014 EN 61000-3-3:2013 FCC Class A VCCI Class A CE Mark CCC GB 9254-2008, Class A BSMI EMI Standard CNS 13438:2006
Immunity EN 55024:2010
IEC 61000-4-2:2008 IEC 61000-4-3:2006/A1:2007/A2:2010 IEC 61000-4-4:2012 IEC 61000-4-5:2014 IEC 61000-4-6:2013 IEC 61000-4-8:2009 IEC 61000-4-11:2004
Safety UL (CSA 22.2 No 60950-1 & UL60950-1)
CB (IEC/EN60950-1) CCC GB4943.1-2011 BSMI Safety Standard CNS14336-1