Before Commissioning ......................................................................................................................... 41
General Controls ................................................................................................................................... 41
Program Relay ...................................................................................................................................... 54
Light Oil Burner Fuel Ring Line ........................................................................................................... 57
Gas Pass Equipment Required in Gas Line ........................................................................................... 58
Impulse connection detecting combustion air pressure
Impulse connection detecting burner gas head
CLEAN THE GAS BURNER.
CLEAN GAS LINE.
ЧИСТАЯ ЛИНИЯ ГАЗ.
09.06.2017 Rev. 08 3
"Clean the gas line" warning on gas line.
Electric motor direction of rotation
Carry in an upright position. Fragile Item. Protect against water.
Page 5
General Safety Rules
• All personnel engaged in installation, disassembly, commissioning, operation, control,
maintenance and repair should have received the necessary training and fully read and understood
this manual.
• No changes that might damage the safety of the burner unit must be made by persons and/or
organizations on the burner unit.
• All operation, commissioning and installation works (except for burning adjustment) should be
carried out when the burner is not operating and after disconnecting the power supply.
Noncompliance with these rules may lead to serious bodily injuries and even death by electrical
shocks or uncontrolled flame formation.
• Repairs concerned with safety elements should be carried out only by the manufacturing company.
• The device should never be used by children, mentally handicapped and inexperienced persons.
• Children must not be allowed to play with the device.
• Keep the device away from explosive and flammable materials.
• Device must intake air, ventilation and air discharge holes must not be closed.
If you sense gas leakage;
• Shut down valves of all gas devices.
• Open all doors and windows.
• Do not turn on electric devices or do not turn them off if they are working.
• Do not use burner derived tools such as match and lighter.
• Inform the gas company.
Do not store any inflammable materials in boiler room.
Wear hearing protectors if there is noise in boiler room.
In case of fıre or other emergency;
● Switch off the main switch
● Close the main fuel shut-off valve outside the plant.
● Take appropriate actions
09.06.2017 Rev. 08 4
Page 6
The burner installation must be carried out in accordance with the instructions. Vibration can
damage the burner and its components.
Keep boiler doors closed while starting burner and during burner operation.
Check combustion values to be correct by using flue gas analyzer at the whole adjustment range
between minimum, full load, and ignition load.
Use lifting device or belt for lifting fan motor, if necessary
During the first commissioning of the burner or in case of any revision carried out in the electrical
system or motor cables by any reason, direction of the fan rotation must certainly be checked by
the authorized technical service.
09.06.2017 Rev. 08 5
Page 7
TERMS OF WARRANTY
Main and auxiliary equipment and all components used in Ecostar Dual Fuel (Gas-Light Oil)
burners are guaranteed for 1 year by TERMO ISI SİST. A.Ş starting from the date of commissioning
under the maintenance, adjustment, operating conditions and relevant mechanic, chemical and thermal
effects explained herein.
Please note that this warranty is only valid if the device(s) is commissioned and maintained by our
authorized services.
Our company reserves the right to make any modifications on the product and all instructions
thereof for improvement purposes.
Out of Warranty Conditions
• Any damage arising out of or in relation to customers’ non-compliance to their responsibilities
with regards to installation, commissioning, operation and maintenance,
• Any damage arising out of or in relation to commissioning, repairs and maintenance carried out by
unauthorized services,
• Any damage that may occur during transportation or storage of the product,
• Not preserving the product in its original packaging until the installation stage,
• Incorrect and poor electrical connections, Failures due to incorrect voltage applications, frequent
repetition of voltage fluctuations,
• Any damage that may occur as a result of incorrect fuel usage or, foreign substances in the fuel
used or using of the product without any fuel,
• Any damage that may occur due to foreign particles entered into the product during installation
and operation,
• Failures due to incorrect device selection,
• Any damage to unit due to natural disasters,
• Devices without any warranty certificates,
• Warranty Certificates without the stamp and signature of the authorized dealer or service,
• Devices with any falsification on the warranty certificate or without an original serial number.
• The risks during transportation of device under the responsibility of customer belong to the
customer.
• Presence of misuse faults are indicated in the reports issued by authorized service stations or our
authorized agent, dealer, representative or our factory in case of unavailability of authorized
service stations.
• Customers may apply consumer protection arbitrator committee with regards to this report and
request for an expert report.
09.06.2017 Rev. 08 6
Page 8
BURNER’S GENERAL FEATURES
ECOSTAR Dual Fuel (Gas-Light Oil) burners are designed and manufactured to work with liquid
fuel with max. 2.5- 6 Cst (mm
of min.20 mbar, max.300 mbar and at -%15 to +%10 of nominal voltages, under environmental
temperature of max.60˚C with rated capacity and burner pressure ranges.
Purpose of Use and Work Limits of Burners
• This product works at any load value equivalent to its max. capacity or covered by its capacity
range;
- In hot water and steam boilers,
- In direct and indirect hot air generators,
- Industrial appliances operating at temperature below 600 0C,
9 Electrical panel 37 Pump
10 Handling rod 38 Pump motor console
11 Handling rod fixing plate 39 Motor
12 Bearing 40 Pump housing cover
13 Observation glass 41 Air damper spring
14 Observation glass frame 42 Air damper transmission rod
15 Eyebolt 43 Air damper motion rod
16 Purger 44 Air damper plate
17 Photocell 45 Air damper shaft
18 Pilot gas solenoid valve 46 Air damper plate
19 Pilot gas pipe 47 Air damper shaft
20 Pilot electrode clamp 48 Air damper shaft
21 Pilot Combustion head 49 Air damper gauge
22 Pilot Ignition electrode 50 Air dumper adjustment rod
23 Gas inlet pipe 51 Servomotor
24 Gas solenoid valve 52 Disc console group
25
26 Fuel nozzle 54 Pressure switch adaptor
27
28
VPS
Centring wedge
Combustion head
53 Air pressure switch
55
Pressure switch adaptor
09.06.2017 Rev. 08 30
Page 32
Min.
Max.
Min.
Max.
LIGHT OIL
TECHNICAL DATA
Capacity Table
GAS-LIGHT OIL DUAL BURNERS CAPACITY TABLE
BURNER TYPE
CAPACITY
kcal/h
GAS
kcal/h
GAS
CAPACITY
Min. kWMax. kWMin.
NATURAL GAS
CONSUMPTION
Nm3/h
Max.
Nm3/h
LIGHT OIL
CAPACITY
kcal/h
kcal/h
CAPACITY
Min. kWMax. kWMin.
LIGHT OIL
CONSUMPTION
kg/h
Max.
kg/h
FAN
MOTOR
POWER
OIL PUMP
POWER
kWkWVAC
TWO STAGE GAS-LIGHT OIL DUAL BURNERS
ECO 50 K L C 2215.0001.290.0002501.50026,1156,4337.7501.351.000393 1.571 33,1132,52,200,753N 380
ECO 55 K L C 2258.0001.720.0003002.00031,3208,5386.0001.737.000449 2.020 37,8170,33,000,753N 380
ECO 55 K L C 2a258.0002.150.0003002.50031,3260,6386.0002.123.000449 2.469 37,8208,13,000,753N 380
ECO 60 K L C 2369.8002.580.0004303.00044,8312,7598.5602.580.000696 3.000 58,7252,94,000,753N 380
ECO 65 K L C 2430.0003.010.0005003.50052,1364,8733.5803.010.000853 3.500 71,9295,15,500,753N 380
ECO 70 K L C 2498.8003.500.2005804.07060,5424,3916.7603.500.200 1.066 4.070 89,9343,27,500,753N 380
MODULATING GAS-LIGHT OIL DUAL BURNERS
MAIN
SUPPLY
ECO 50 K L C 3215.0001.290.0002501.50026,1156,4337.7501.351.000393 1.571 33,1132,52,200,753N 380
ECO 55 K L C 3258.0001.720.0003002.00031,3208,5386.0001.737.000449 2.020 37,8170,33,001,103N 380
ECO 55 K L C 3a258.0002.150.0003002.50031,3260,6386.0002.123.000449 2.469 37,8208,13,001,103N 380
ECO 60 K L C 3 369.8002.580.0004303.00044,8312,7598.560 2.580.000696 3.000 58,7252,94,001,103N 380
ECO 65 K L C 3 430.0003.010.0005003.50052,1364,8733.580 3.010.000853 3.500 71,9295,15,501,503N 380
ECO 70 K L C 3 498.8003.500.2005804.07060,5424,3916.760 3.500.200 1.066 4.070 89,9 343,27,501,503N 380
ECO 75 K L C 3 686.0004.800.0007985.58183,2581,8 1.003.620 4.824.600 1.167 5.610 98,4 473,011,001,503N 380
Hu Natural Gas =8250 kcal/Nm
3
Hu Light Oil (L) = 10200 Kcal/kg
09.06.2017 Rev. 08 31
Page 33
Back Pressure-Capacity Diagrams
09.06.2017 Rev. 08 32
Page 34
Burner Dimensions
09.06.2017 Rev. 08 33
Page 35
Gas Hood Pressure Loss Diagram
Gas hood pressure loss measurements are conducted in atmospheric pressure. Consider the
below data while conducting measurement in counter pressure boilers.
Pm: Gas hood pressure while burner is connected to the boiler and working
PF: Combustion chamber pressure
PBr: Burner net gas hood pressure
PBr = Pm - P
09.06.2017 Rev. 08 34
F
Page 36
09.06.2017 Rev. 08 35
Page 37
09.06.2017 Rev. 08 36
Page 38
Flame Length and Diameter
Natural Gas
Light Oil
Noise Level
Product operates within the range of 75 decibels max. and 85 decibels.
09.06.2017 Rev. 08 37
Page 39
136 X 90 X 66
136 X 90 X 66
136 X 90 X 66
136 X 90 X 66
136 X 90 X 66
BURNER HANDLING INFORMATION
• Lift the product by holding the handles as seen in the picture.
• Prevent strong impacts on top of the product and vibration while handling the product.
• Do not leave the product in wet environment.
Dimensions of the box used for handling
Burner L x W x H (cm) Weight (kg)
ECO 50 KLC2 136 X 90 X 66 130
ECO 50 KLC3
ECO 55 KLC2
ECO 55 KLC2a
ECO 55 KLC3
ECO 55 KLC3a
ECO 60 KLC2 160 X 115 X 74 195
ECO 60 KLC3 170 X 115 X 74 195
ECO 65 KLC2 170 X 115 X 74 200
ECO 65 KLC3 170 X 115 X 74 200
ECO 70 KLC2 170 X 115 X 74 180
ECO 70 KLC3 170 X 115 X 74 180
ECO 75 KLC3 165 X 118 X 80 270
Ø In the installation of the burner, use the installation materials supplied with the burner.
Ø Secure the burner connection flange onto the burner cover by 4 bolts. Gasket must be connected
such that it will remain between connecting flange and boiler cap.
After completing the installation of the burner on the boiler:
Ø Connect the oil feed pipes.
Ø Connect the burner panel to the mains by a cable suitable for the rated power.
Device must be shipped in original packaging!
Do not lift the device holding from servomotor, gas valve, impulse pipes or pressure switch
during installation!
Clean the inside of fuel line thoroughly before installing the burner to the fuel line. Any damage
that may occur due to solid objects and metal particles from the fuel line shall not be covered by
our company.
09.06.2017 Rev. 08 39
Page 41
In reverse flame front mirror boilers
While installing the burner in reverse flame front mirror boilers, flame tube tip must be adjusted
such that it gets inside by 50 mm-100 mm from flue pipes (50mm≤A≤100mm). Otherwise flue gas
temperature will rise and fuel consumption will increase.
In cylindrical (straight flame) boilers
09.06.2017 Rev. 08 40
Page 42
COMMISSIONING
Before Commissioning
Electrical Connection
Perform electrical connections according to the diagram provided with the burner. Follow general
security rules during installation of electric wiring and making connections. Connect the earthing terminal
in electric panel to the earthing installation.
General Controls
Make sure to perform the following controls before commissioning the burner.
Ø Installation of the burner to the boiler is checked.
Ø Check the fuel line (are the pipe diameters and the pipe installation correct?).
Ø Check energy input cables and voltages.
Ø Check the boiler safety thermostats and, if it is a two-stage burner, then make sure that there are
two thermostats.
Ø Check the fuel nozzles according to the boiler capacity.
Ø Prior to operating the burner, control the boiler water level.
Ø Make sure water circulation system is turned on, and steam boiler and water feed pumps and
boiler inlet - outlets are open.
Ø Is there electricity current?
Ø Is there gas?
Ø Has the boiler explosion lid been controlled?
Ø Is there sufficient air in boiler room (ventilation section cm² = boiler capacity kW x 7)
Ø Has the air of the gas line been removed? Has a sealing test been made?
Commissioning order
Operating with Light Oil ;
Ø After performing the above mentioned controls, open the fuel tank valve.
Ø Open the valve upstream of the fuel filter.
Ø Check direction of motor rotation.
Ø Open the pump’s vent plug and place the manometer (0-40 bar).
Ø Turn on the burner switch (turn to position 1).
Ø When the burner starts up, the motor is activated and turns the pump at the same time.
Ø It actuates pre-purge and discharges the residual gases remaining in the boiler from the funnel.
Ø After the pre-purge, fuel is delivered from the nozzle. The fuel meets the flame from the ignition
electrodes and the combustion starts.
Ø After combustion of the burner, the pump pressure is adjusted (light oil: two stage; 14 bar,
modulating; 25 bar).
Ø If the burner has two stages, the switch is brought to position “2”, and the capacity of the burner is
increased through servomotor. Ideal combustion is obtained by increasing the amount of air by the
fuel given according to analyses value.
Ø The boiler thermostat is adjusted as desired (70-90°C for central heating boilers).
Ø For the safety of the system, check the boiler thermostats and observe the deactivation of the
burner.
09.06.2017 Rev. 08 41
Page 43
Operating with Gas ;
Operation of two-stage burner
Ø Open the main gas valve, check the gas pressure from the manometer at the valve. (max.300
mbar)
Ø Check the boiler thermostat or pressure switch settings.
Ø Bring the operating switch on the burner panel to position 2.
Ø Burner fan motor will be activated.
Ø Ignition will take place at the end of pre-purge process.
Ø 3 sec. later, the gas valve will be opened and combustion will occur.
Ø Flame control system (ionization) will start flame control.
Ø Burner will switch to the second stage (max. capacity) according to the heat requirement.
Ø After the boiler water heated up or the boiler pressure has risen, the burner will turn off.
Operation of a modulating burner
Ø Open the main gas valve; check max 300 mbar gas pressure from the manometer.
Ø Open operating switch on the burner panel.
Ø Switch on the modulating control switch.
Ø Switch automatic-hand switch to automatic.
Ø Check the temperature and pressure set values from the modulating control unit.
Ø Ignition will take place at the end of pre-purge process.
Ø 3 sec. later, the gas valve will be opened and combustion will occur.
Ø Flame control system (ionization) will start flame control.
Ø In modulating burner, the burner goes into max. capacity according to the signal from the
modulating control unit.
Ø When the boiler water temperature or steam pressure increase, the modulating control unit will
cause burner to run with min. capacity.
Ø If the boiler water temperature or steam pressure increases despite the operation of burner with
min. capacity, the modulating control unit will stop the burner.
09.06.2017 Rev. 08 42
Page 44
Combustion Adjustment
Ø Fuel nozzle
Use proper wrench in installation and dismantle of the fuel
nozzle.
Use diesel oil to clean the fuel nozzle. Do not use thinner
and its derivatives.
Ø Photocell
Check the photocell weekly. Clean the dust or fume stains on the glass of
photocell by a dry cloth.
1-Suction
2-Nozzle outlet
3-Return
4-Manometer inlet
5-Vacuum or inlet manometer and internal return inlet
6-Pressure adjustment
7-Pre heater location
09.06.2017 Rev. 08 44
Page 46
Ø Two Stages Light Oil Burner Fuel Circuit
Ø Modulating Light Oil Burner Fuel Circuit
09.06.2017 Rev. 08 45
Page 47
CAUTION!
Ø End of the line to the main tank must be open to the atmosphere and line pressure must be
zero, otherwise no healthy modulating operation can be ensured since the pressure, which is
to form in return, will also affect nozzle pressure. Fuel may drop from nozzle end during
stops.
Ø For good pulverization, periodically check durability of the o-ring. In the event of earing of
the o-ring, fuel to the nozzle can by-pass and go directly to the return and reduces the
working performance of the nozzle.
Ø Maximum operating pressure of the nozzle is 30 bars. This value should not be exceeded
during working. Even if these out of control value are exceeded, nozzle must be taken to
emergency maintenance and all O-rings must be replaced.
Ø Do not use solvent based materials (thinner and derivatives) during cleaning of the fuel
nozzle; clean with gas oil or diesel oil. Fuel nozzle inner kit is very sensitive and even
invisible deformations can reduce working performance; dismantling-installing work must
be performed only by trained personnel.
Ø Spring has lost its function if dropping from fuel nozzle or fuel exit at large scale is observed
when the nozzle performs circulation. It must be checked and replaced if necessary.
09.06.2017 Rev. 08 46
Page 48
Gas Adjustment
Ø VGD 20 4011 - 5011 Series Gas Valve
SKP 75 Connection Diagram
1 – Air-gas adjustment ratio
2 – Zero "0" point (start) adjustment
3 – Boiler counter pressure impulse connection
4 – Gas pressure impulse connection
5 – Air pressure impulse connection
09.06.2017 Rev. 08 47
Page 49
Ø MB ZRD(LE) 405 – 412 Series Gas Valve
09.06.2017 Rev. 08 48
Page 50
Air Pressure Switch Adjustment
While the burner is working without any problem, the air pressure switch
is adjusted to desired minimum pressure as follows.
Ø Unscrew the screw of the transparent cover and remove the cover.
Ø Turn the adjustment wheel in the direction to increase the pressure,
note the pressure value at which the burner is failed.
Ø Set the pressure switch to a value 1 mbar lower than the pressure
value at which the burner failed and close the pressure switch lid.
Ø It is recommended that this adjustment is carried out when the
burner is at minimum load.
Servomotor Adjustment
The amount of air is adjusted by means of the servomotor. The servomotor adjustment at two-stage
and modulating burners is made by the cams on the servomotor.
Ø SQN70
At Two-stage Burners;
I. Red Cam:Adjusts 2nd level max. air.
II. Blue Cam: Resets the clamp.
III. Orange Cam: Adjusts 1st level min. air.
IV. Black Cam: Adjusts 2nd level valve opening degree.
At Modulating Burners;
I. Red Cam: Performance max. air adjustment.
II. Blue Cam: Resets the clamp.
III. Orange Cam: Performs min. air adjustment.
IV. Black Cam: Not used.
09.06.2017 Rev. 08 49
Page 51
Ø SQM10
Do not open servomotor. Do not interfere with. It may damage servomotor or change burner
settings.
I. Cam: Opening
II. Cam: Resets the clamp
III. Cam: Commissioning air
IV. V.VI. and VII. Cam not used
09.06.2017 Rev. 08 50
Page 52
Ø MODULATING MECHANISM ADJUSTMENT
1- Air adjustment disk
2- Fuel adjustment disk
3- Servomotor
4- Fuel regulator
5- Air control lever
6- Fuel control lever
ADJUSTMENT:
1- Start positions prior to disc mechanism adjustment operation must be as follows:
Ø Servomotor: 0°
Ø Fuel adjustment disc at start position
Ø Air adjustment disc at start position
Ø Fuel regulator at position 10
Ø Air klappes at fully closed position: 0°
Start position for discs Start position for fuel regulator
09.06.2017 Rev. 08 51
Page 53
2 – If disc mechanism start positions are correct, start the burner and ensure that it activates in basic load.
Detect min capacity activation fuel amount of the burner by checking min. return pressure. If the
activation fuel amount is insufficient, set fuel regulator start adjustment to 9 or 8 value by changing
spring adjustment from adjusting bolt on fuel disc number 2.When you start the burner again after this
operation, you will see that your fuel return pressure has increased and hence activation fuel amount has
risen.
3 –Slowly increase the capacity following burner basic load adjustment provided that modulating control
device is in manual position. By setting 7 or 8 points during capacity increase, at these points:
Ø Measure emission values
Ø Record fuel return pressure
Ø Observe air klappe position
Ø Check fuel regulator scale value moves from 10 to 0.
4- If you haven't been able to reach the max capacity required by the boiler in 90° position of the air
klappe and 0° position of the fuel regulator once you have completed the maximum adjustment, follow
the below fuel regulator adjustment procedure:
1- Remove the housing cover number 6
2- Loosen the fixing bolt number 4
3- When you rotate the shaft number 5 (when looked from the shaft end) clockwise, the pressure
value you observe from return manometer will increase, and burner consumption will also
increase since nozzle pressure increases.
4- When you rotate the shaft number 5 (when looked from the shaft end) anti-clockwise, the
pressure value you observe from return manometer will decrease, and burner consumption
will also decrease since nozzle pressure decreases.
5- When the adjustment is completed, make sure that the adjustment you have made is permanent
by tightening the fixing bolt number 4.
6- Place the housing cover number 6.
09.06.2017 Rev. 08 52
Page 54
5 - Set the burner to the correct capacity required by the boiler by considering the below nozzle pressure
and consumption values.
Diagram valid for fuel nozzles having 45° spraying angle
Diagram valid for fuel nozzles having 60° spraying angle
6 – Once the burner modulating adjustment is completed, set modulating control device to automatic
position, change set values and observe capacity changes. Air and fuel will increase and decrease
simultaneously according to the adjustment you previously made.
09.06.2017 Rev. 08 53
Page 55
Emission Measurement
In emission measurements, the following values are accepted as reference according to TS EN 676 +A2
standard.
Ø CO < 100 mg/ kWh
Ø %3 ≤ O2 ≤ %5
Ø NOx < 170 mg/ kWh
Ø Excess air ratio 1,2≤λ≤ 1,3
In emission measurements, the following values are accepted as reference according to TS EN 267
standard.
Ø CO < 110 mg/ kWh
Ø %3 ≤ O2 ≤ %5
Ø NOx < 250 mg/ kWh
Ø Excess air ratio 1,2≤λ≤ 1,3
It is important for the boiler to be sealed in order to avoid incorrect measurements during
emission measurements.
Boiler temperature must be between 40 C˚ and 80 C˚ while making emission measurement in
hot water boilers.
Program Relay
LFL 1.32
09.06.2017 Rev. 08 54
Page 56
If the value measure from PL point is below 0.5 bar, set the impulse pipe as follows.
09.06.2017 Rev. 08 55
Page 57
If the flame tube of the burner is longer than standard (standard flame tube length of the burner),
please do not forget to support burner body during maintenance and installation/commissioning.
Threaded and flanged connections may vary depending on the gas pressure and consumption.
09.06.2017 Rev. 08 58
Page 60
MAINTENANCE
Weekly Maintenance
Weekly maintenance is a routine cleaning and adjustment procedure which is performed to ensure
smooth and continuous operation of the system. Burner components must be adjusted after each
maintenance work in accordance with the instructions. Otherwise, the burner cannot be operated
efficiently.
Ø Clean all filters in fuel ring system.
Ø Clean fuel nozzle of the burner.
Ø If the fin spaces and surface of the diffuser are covered with particles and formed a layer, clean it
with a wire brush.
Ø Clean heads of ignition electrodes. Check by performing manual ignition, adjust the distance
between the ignition electrode and diffuser according to the adjustment instructions.
Monthly Maintenance
Monthly maintenance is a more comprehensive maintenance compared to weekly maintenance,
where general checks of burner and peripheral components are performed to prevent possible faults. After
completion of maintenance and adjustment processes, make sure to perform a combustion analysis.
Ø Clean the filters on the fuel line to the burner.
Ø Clean fuel nozzle of the burner.
Ø Clean the surface of the diffuser.
Ø Clean flame pipe.
Ø Check all wiring points. Tighten loose connections.
Ø Clean the solenoid valves.
Ø Clean the photocell.
Ø Clean the dust and layers accumulated on the fan and air valves.
Ø Check pump pressure. Check if necessary (Light Oil: Two stage 14 bar, modulating; 25 bar)
Ø Check ignition electrodes. Adjust it if necessary. Check ignition cables and sockets.
Ø Perform cleanliness control of inside panel. Clean if necessary.
Ø Check all bolts of the burner. Tighten loose bolts.
Ø Clean the filters on the main line and multiblock.
Ø Check the burner gas tip.
Ø Check gas line pressure, it must be the same with the first adjusted pressure, otherwise burner load
and emission values will also have changed.
Ø After starting the burner and adjusting air klappe, perform flue gas analysis and check if there is
an ideal combustion.
09.06.2017 Rev. 08 59
Page 61
Seasonal Maintenance
Comprehensive maintenance work when the burner is re-started after long periods of shut-down or
interruptions. After completion of maintenance and adjustment processes, make sure to perform a
combustion analysis.
Ø Check insulation resistance of electric motor.
Ø Make surface cleaning of ignition electrodes and porcelains. Replace cracked or broken
porcelains.
Ø Clean air fan and clamps.
Ø Check the operating function.
Ø Check cleanliness of the nozzle. Replace it if necessary.
Ø Clean the N.C. solenoid valve. Measure the coil winding resistance.
Ø Clean the strainer (filter) under the pump cover.
Ø Clean the photocell.
Ø Clean fuel filter. Replace it if necessary.
Ø Check boiler thermostats.
Ø Check cleanliness of boiler inside and clean if necessary.
09.06.2017 Rev. 08 60
Page 62
TROUBLESHOOTING
Problem Cause Explanation-Suggestion
Burner cannot be
commissioned
Flame appears and goes
into failure mode.
Light Oil or Gas is
cut or does not come
Fuse failure
Relay failure
Boiler thermostat,
pressure switch
failure
Light Oil or Gas
pressure error
Photocell failure
Program relay failure
Light Oil or Gas valve might be closed. Open
the valve.
Check burner power supply. The fuse on the
main panel or the fuse on the burner might be
tripped.
Reset the thermal relay. Check adjustment of the
thermal relay according to the current in motor
label. If the failure is not removed, replace the
thermal relay.
If there is a problem with the burner thermostats,
pressure switches and steam tank this may be due
to an unadjusted or faulty water level device;
adjust it and if broken, replace it.
Circuit light oil or gas pressure might have
dropped.
Photocell may be faulty or contaminated. Remove
and clean..
Replace it with a new one.
Burner starts up, but fails
after 10 seconds.
Program relay failure
Air pressure switch
adjustment
Air pressure switch might be adjusted to a high
value. There may be dirt in the air pressure switch.
Replace it with a new one.
Air pressure switch might be broken.
Check fan motor coils, motor contactor and outlet
from program relay.
Light Oil or Gas valve might be closed. Circuit
fuel oil or gas pressure might have dropped.
Check Light Oil or Gas inlet manometer.
Ignition electrodes might be misadjusted or
ignition cables might have come out of their
terminals. Adjust ignition electrodes with a
Burner starts up, but fails
after 30 seconds.
Fan motor failure
Light Oil or Gas
valve, fuel oil or gas
pressure drop
Ignition electrode
failure
distance of 3-5 mm. between them.
Ensure sealing between the boiler cover and
Boiler cover is
overheating.
Sealing problem
burner. If required, use insulating material
between the boiler connecting flange and boiler
cover.
09.06.2017 Rev. 08 61
Page 63
PERIODICAL FLUE GAS MEASUREMENT REPORT
Fuel
Consumption
(kg/h)
Fuel
Consumption
(m3/h)
CO
(ppm)
O
2
(%)
CO
2
(ppm)
NO
X
(ppm)
Yield
(%)
Flue
Temp.
(ºC)
Date
Signature
09.06.2017 Rev. 08 62
Page 64
AFTER SALES SERVICES
Dear Customer,
We believe that providing a good service is as important as providing a good product. Therefore, we
continue offering wide range of comprehensive services to our conscious customers.
Our contact details for your requests and complaints