7. Installation
During the assembly of the ECON gate valves, the following rules should be observed:
- the valves should be checked before installation if the have not any defects caused by
transport and/or storage.
- make sure that the applied valves are suitable for working conditions, medium used in the
plant and the right system connections, according to pressure and temperature limits.
- protective hole plugs must be removed.
- the standard installation position for the gate valves is with the stem vertical and in upright
position.
- the interior of the valve and pipeline must be free from foreign particles.
- the valves with threaded ends should be assembled in the pipeline in closed position,
make sure the wire ends of the pipe and the valve according to the same standard, and
also free from pollution. Clamp the valve only on the hex clamping surfaces at the
connection ports during assembly.
- when necessary, use a thread sealant, PTFE tape for low temperature applications and
Grafoil for high temperature applications.
- steam line systems should be designed to prevent water accumulation.
- install pipelines so that damaging transverse, excessive vibrations, bending and tensional
forces are avoided.
- for easy operating the clear distance around the hand wheel shall not be less than
100MM.
- before plant startup, especially after repairs carried out, flash out the pipeline.
8. Maintenance
Before starting any service jobs, make sure that the medium supply to the pipeline is cut off,
pressure was decreased to ambient pressure, the pipeline is completely cleaned and ventilated
and the plant is cooled down. Always keep safety instructions in mind and take all personal safety
precautions.
During maintenance, the following rules should be observed:
- always keep personal safety precautions in mind and always use appropriate protection
e.g. clothing, masks, gloves etc.
- be alert that the temperature still can be very high or low and can cause burns.
- check the valve on all possible leaking possibilities.
- check if all nuts, are still fastened.
- dust, grease and medium residual, must be frequently cleaned of the valve body and all
moving parts, such as stem to maintain all operating functions.
- if there is a leakage across the stem, gradually tighten the stuffing box sealing, evenly in
increments by means of the hex. nut, until leaking stops.
- if required repack the stuffing box gasket, for safety reasons we recommend that the
valves only can be repacked when depressurized, drained and ventilated.
- when cutting the new stuffing box packing from the roll, make sure that the ends are cut
with a slant.
- check if the wedge still open and close in a proper manner.
- the thickness of the body must be checked to ensure safety operation at an interval of at
least three months.