Eco SR30V, SR60V Installation Manual

Page 1
SR30V & SR60V
NEXT GENERATION
Recyclers
INSTALLATION GUIDE
For Technical Assistance call 1 877 629-8202
05-19-2011
Page 2
Innovation and Leading Technology
SECTION 1
SECTION 2
TABLE OF CONTENTS
Tools required ___________________________________________________________
Parts required ___________________________________________________________ 3
Un-packaging the unit ____________________________________________________
How to install a Solvent Saver™ Recycler _____________________________________
Page
3
3
4
Installing the Ground wire _________________________________________________
Electrical connection ______________________________________________________ 4
FINAL SECTION
General Arrangement _____________________________________________________
Warranty & Contact Information ____________________________________________ 7
4
5-6
05-19-2011
2
Installation guide SR30V & SR60V
Page 3
Innovation and Leading Technology
SECTION 1
TOOLS REQUIRED
Phillips Screw Driver for all Screws on The Unit Flat Screw Driv­er or Snips for Removal of Staples Robertson Square Screw Driver for Pallet Screws Teon Tape Adjustable Wrench.
PARTS REQUIRED
Hose and Fittings for connection to Regulator
Disconnect per classication area (See General
Arrangement Drawings)
- 220 Volt 1 Phase Power
- 5 - 6 Ft from units at least
- 18” above the ground
Compressed Air Line next to unit
UNPACKAGING THE UNIT
Step 1 : Carefully inspect the shipping carton for any signs of transport damage.
Step 2 : Begin by removing the staples attaching the box to the skid (A Flat Screw Driver or Snips will do the job).
Step 3 : Carefully remove your solvent recycler from the shipping carton. Remove the four screws from the bottom of the solvent recycler screwed to the palette.
Step 4 : Remove the unit from the palette and place it in the general area for installation.
05-19-2011
You are ready to begin with the installation of the solvent recycler.
3
Installation guide SR30V & SR60V
Page 4
Innovation and Leading Technology
1
SECTION 2
ELECTRICAL CONNECTION
Step 5 : Now we are ready to have the electrician wire the solvent recycler
for model SR30 connect to 220 volts / 1 phase power to the electrical junction box 1 that is provided in the back of the unit. The 7.5 gallons
recycler requires 15 Amp service.
For model SR60 connect to 220 volts / 1 phase power to the electrical junction box that is provided in the back of the unit. The 15 gallons
recycler requires 30 Amp service.
Then connect a ground wire 2 to the back of the unit ans use the
2
ground wire with a clip to ground the 55 gallons drum.
For units that come with the optional used solvent ll pump you will need to connect with an ½ air line to the pump and suggest to put a lter regulator before the air inlet of the pump and then adjust the air pressure on the regulator to 80 PSI.
Note : Please Review the “General Arrangement” Drawing
MAKE SURE ALL CODE REQUIREMENTS ARE FOLLOWED
1
.
.
VACUUM INSTALLATION
2
5
3
4
1. Install the ¼ push in fitting
1
2. Install the air regulator
2
3. Install the clear tube coming from the recycler.
3
4. Install the vacuum generator assembly on the
4
tank and then connect the cleat tube coming from the bottom of the tank.
5. Install the blue tube on the 2 push in fittings.
5
You are now ready to follow the Start-up Process.
Please follow the ECO Start-up
05-19-2011
4
Installation guide SR30V & SR60V
Page 5
Innovation and Leading Technology
FINAL SECTION
General arrangement
mix room
Entire system inside
4160 Industriel Blvd. Laval, Quebec, H7L 6H1
Tel.: 1 877 -629 8202 / 450 963-2200 Fax : 450 963-5122
side
Three sides mix room Free standing mix room
Entire system out-
Classication zones as per :
A ) NFPA 33 standard for spray application using ammmable and combustible materials, sections 4.3.5
B) International re code, chapter 34 ammable and combustible liquids 3403.1.1
Zone requirements apply to both gun cleaners and recyclers together and stand alone.
GENERAL ARRANGE-
05-19-2011
Class 1 - Div 1
Class 1 - Div 2
Class 1 - Div 2 18’’ High only
Intermediate mix room
5
Legend
Installation guide SR30V & SR60V
EXCLUSIVE RIGHTS
This drawing is the exclusive property of ECO inc. and informations
contained herein can be used only when specifically authorized
by ECO inc. Possession of this drawing does not authorize use nor
transmission to any other organisation.
Page 6
Innovation and Leading Technology
FINAL SECTION
General arrangement (cont’d)
- This will
required on
additionnal
roof
Exhaust must
run straight out
and vertical of
the gun cleaner
for approx. 3-4
ft before making
only osets
Separate exhaust stack
penetration
CODE INFORMATION
ECO oers a complete line of spray gun cleaners and solvents
recyclers that conform to the requirements of :
* NFPA-33 Standard for spray application using ammable and
combustible materials.
* NFPA-30 ammable and combustible liquid code
* IFC : International Fire Code
* UL 2208 standard for solvent distillation unit
* CSA for U.S. & Canada requirements report #154896
The recycler has been certied and listed :
The recycler has been rewied and approved by :
disconnect
Explosion proof
General purpose
disconnect
Min. 5 ft away
from unit
Location
In mix room/
Non-classified
classified area
a
are
required
Conformity of all these requirements is dependent upon the manner
in which the equipment is installed. The contractor will make cetain
Min 18’’ off the
floor
that all of the electrical wiring and conduit, piping, gas supply, roof
penetrations, automatic re protection systems, and the location of
the equipment within the building also conforms to the cited codes
EXHAUST INFORMATION
and the other references.
cfm Notes
Prefered exhaust option Notes
Separate Exhaust stack (see
below)
exhaust
3’’ diam.
Model Description
GWA
Factory set at
85-90 psi
5
20
10
Attach to mix room exhaust or
separate exhaust stack (see below)
exhaust
6’’ diam.
GWM
GWMA
EXHAUST OPTION
ECO Thermic Heat Transfer Oil
Part # 330066 — 4 liters
- The preferred method is to make
Mix
Attach to mix room exhaust
Part # 330067 — 10 liters
Part # 330068 — 20 liters
connection to the auction side of
the blower.
the push side of the blower, use a
- If connection is required to be on
room
duct
Use ex duct connector for 2-3 feet.
This will allow future service access
to control panel.
gravity damper.
Connection should be made of an
angle + or > 45 degrees.
Exhaust flex connector — GWM / GWA
gun
duct
cleaner
20’’ x 25’’
Fiberglass lter
GWM
GWMA
Gun
Item Model Description
washer
4160 Industriel Blvd. Laval, Quebec, H7L 6H1
Tel.: 1 877 -629 8202 / 450 963-2200 Fax : 450 963-5122
GENERAL ARRANGE-
DATA & SPECS
24.3
SR 60
SR 120—SR 180
11.7
Full load Amp Draw
220V 480V 600V
Model
Electrical Requirements
Amp Draw listed for entire unit — including motor and heating element
SR 30
05-19-2011
Air Line
’’ @ 100 psi
’’ @ 100 psi
8
8
/
/
½’’ @ 100 psi
3
3
Specifications
Item
Gun cleaner
SR30V-60V
Air Requirements
SR120V-180V
Model Capacity Description
Oil
6
10 liters oil
SR 30
20 liters oil
SR 60
55 liters oil
55 liters oil
SR 120
SR 180
300006
300019
300008
300009
EXCLUSIVE RIGHTS
Model Part number
SR 30
SR 60
SR 120
Recycler Bags Filters
SR 180
This drawing is the exclusive property of ECO inc. and informations
contained herein can be used only when specifically authorized
by ECO inc. Possession of this drawing does not authorize use nor
transmission to any other organisation.
Installation guide SR30V & SR60V
Page 7
Innovation and Leading Technology
WARRANTY INFORMATION / TECHNICAL ASSISTANCE
For more information, prices or technical assistance,
contact your local ECO distributor or call / fax our
Consumer Information Numbers :
1 877 629-8202 450 963-2200 450 963-5122
Tel. : Tel. : Fax :
Or visit us at :
www.ecoind.com
4160 Industriel Blvd. Laval, Quebec, H7L 6H1
05-19-2011
7
Installation guide SR30V & SR60V
Loading...