DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITY
The information, recommendations, descriptions and safety notations in this document are based on Eaton’s experience and judgment and
may not cover all contingencies. If further information is required, an Eaton sales office should be consulted. Sale of the product shown in
this literature is subject to the terms and conditions outlined in appropriate Eaton selling policies or other contractual agreement between
Eaton and the purchaser.
THERE ARE NO UNDERSTANDINGS, AGREEMENTS, WARRANTIES, EXPRESSED OR IMPLIED, INCLUDING WARRANTIES OF FITNESS
FOR A PARTICULAR PURPOSE OR MERCHANTABILITY, OTHER THAN THOSE SPECIFICALLY SET OUT IN ANY EXISTING CONTRACT
BETWEEN THE PARTIES. ANY SUCH CONTRACT STATES THE ENTIRE OBLIGATION OF EATON. THE CONTENTS OF THIS DOCUMENT
SHALL NOT BECOME PART OF OR MODIFY ANY CONTRACT BETWEEN THE PARTIES.
In no event will Eaton be responsible to the purchaser or user in contract, in tort (including negligence), strict liability or other-wise for any
special, indirect, incidental or consequential damage or loss whatsoever, including but not limited to damage or loss of use of equipment,
plant or power system, cost of capital, loss of power, additional expenses in the use of existing power facilities, or claims against the
purchaser or user by its customers resulting from the use of the information, recommendations and descriptions contained herein. The
information contained in this manual is subject to change without notice.
WARNING
IMPROPERLY INSTALLING OR MAINTAINING THESE PRODUCTS CAN
RESULT IN DEATH, SERIOUS PERSONAL INJURY OR PROPERTY DAMAGE.
READ AND UNDERSTAND THESE INSTRUCTIONS BEFORE ATTEMPTING
ANY UNPACKING, ASSEMBLY, OPERATION OR MAINTENANCE OF THE
SELECTABLE GROUND AND TEST DEVICES.
INSTALLATION OR MAINTENANCE SHOULD BE ATTEMPTED ONLY
BY QUALIFIED PERSONNEL. THIS INSTRUCTION BOOK SHOULD NOT
BE CONSIDERED ALL INCLUSIVE REGARDING INSTALLATION OR
MAINTENANCE PROCEDURES. IF FURTHER INFORMATION IS REQUIRED,
YOU SHOULD CONSULT EATON’S ELECTRICAL SERVICES & SYSTEMS.
THE SELECTABLE GROUND AND TEST DEVICES DESCRIBED IN THIS BOOK
ARE DESIGNED AND TESTED TO OPERATE WITHIN THEIR NAMEPLATE
RATINGS. OPERATION OUTSIDE OF THESE RATINGS MAY CAUSE THE
EQUIPMENT TO FAIL, RESULTING IN DEATH, BODILY INJURY AND
PROPERTY DAMAGE.
ALL APPLICABLE CODES, SAFETY STANDARDS AND/OR REGULATIONS
RELATED TO THIS TYPE OF EQUIPMENT MUST BE STRICTLY FOLLOWED.
THESE SELECTABLE GROUND AND TEST DEVICES ARE DESIGNED TO
BE INSTALLED PURSUANT TO THE AMERICAN NATIONAL STANDARDS
INSTITUTE (ANSI). SERIOUS INJURY, INCLUDING DEATH, CAN RESULT
FROM FAILURE TO FOLLOW THE PROCEDURES OUTLINED IN THIS
MANUAL.
This product was manufactured by Eaton at the Power Breaker
Center (PBC): 310 Maxwell Avenue, Greenwood, SC 29646.
All possible contingencies which may arise during installation,
operation or maintenance, and all details and variations of this
equipment do not purport to be covered by these instructions. If
further information is desired by purchaser regarding his particular
installation, operation or maintenance of particular equipment,
contact an Eaton representative.
ii
Instruction Book IB182312EN June 2016 www.eaton.com
Table of Contents
SECTION 1: INTRODUCTION 4
1.1 AVAIL ABLE 150 VCP-W SELECTABLE
GROUND AND TEST DEVICES 4
SECTION 2 : SAFE PRACTICES 6
SECTION 3 : RECEIVING, HANDLING, AND STOR AGE 7
3.1 RECEIVING 7
3.2 HANDLING 7
3.3 STORAGE 8
3.4 APPROXIMATE WEIGHT BY TYPE 8
SECTION 4: DESCRIPTION AND OPERATION 11
4.1 INSULATING BARRIERS 11
4.2 BUSHINGS AND DISCONNECTING CONTACT ASSEMBLIES 11
4.3 GROUNDING CONTACTS 11
4.4 BRE AKER-CELL CODING PLATES 11
4.5 CELL POSITION DESCRIPTION 11
4.6 DEVICE AMPERAGE CON VERSION PROCEDURE 13
50/75/150 VCP-W
Selectable Ground and Test Device
SECTION 5: INSTALLATION & INSPECTION 14
5.1 EXAMINATION FOR DAMAGE 14
5.1.1 NAMEPL ATE VERIFICATION 14
5.2 OPERATING PROCEDURE 14
5.5 INSERTION PROCEDURE 16
5.5 REMOVAL PROCEDURE 16
SECTION 6: INSPECTION AND MAINTENANCE 18
6.1 INTRODUCTION 18
6.2 FREQUENCY OF INSPECTION 18
6.3 INSPECTION AND MAINTENANCE PROCEDURES 18
6.4 INSULATION INTEGRITY CHECK 18
SECTION 7: REPLACEMENT OF COMPONENTS 19
7.1 GENERAL 19
7.1.1 ORDERING INSTRUCTIONS 19
Instruction Book IB182312EN June 2016 www.eaton.com
iii
50/75/150 VCP-W
Selectable Ground and Test Device
SECTION 1: INTRODUCTION
The purpose of this book is to provide instructions for receiving and
handling, storage, installation, operation and maintenance of 150
VCP-W Selectable Ground and Test Devices. This selectable ground
and test device is designed to be used in existing Westinghouse,
Cutler-Hammer, or Eaton Type VCP-W metal-clad switchgear.
Type VCP-W selectable ground and test devices are designed for
insertion into the breaker compartment to gain access to the primary
stationary contacts. It provides convenient means to:
1. Ground a circuit for maintenance work;
2. Apply potential for testing; and/or,
3. Access both bus and line circuits for “phasing out” tests.
4. Depending on customer specification, key interlocks may be
deleted. Line/Load and Phase labeling may be optionally provided.
CAUTION
BECAUSE OF THE UNIQUE APPLICATION AND VAST VARIETY OF SYSTEM /
USER REQUIREMENTS, SPECIFIC SAFE OPERATING PROCEDURES FOR THE
USE OF THIS DEVICE MUST BE DEVELOPED BY THE USER.
WARNING
SATISFACTORY PERFORMANCE OF SELECTABLE GROUND AND TEST
DEVICES IS CONTINGENT UPON PROPER APPLICATION, CORRECT
INSTALLATION AND ADEQUATE MAINTENANCE. THIS INSTRUCTION
BOOK MUST BE CAREFULLY READ AND FOLLOWED IN ORDER TO OBTAIN
OPTIMUM PERFORMANCE FOR LONG USEFUL LIFE OF THE SELECTABLE
GROUND AND TEST DEVICES.
Refer to Table 1.
THESE SELECTABLE GROUND AND TEST DEVICES ARE PERSONNEL
PROTECTIVE DEVICES, AS SUCH, THEY ARE MAXIMUM RATED DEVICES.
THEREFORE, THEY SHOULD NOT UNDER ANY CIRCUMSTANCES BE
APPLIED OUTSIDE THEIR NAMEPLATE RATINGS.
1.1 AVAILABLE 150 VCP-W SELECTABLE GROUND AND
TEST DEVICES
Table 1. 150 VCP-W Selectable Ground and Test Device Availability and Interchangeability
Instruction Book IB182312EN June 2016 www.eaton.com
5
50/75/150 VCP-W
Selectable Ground and Test Device
SECTION 2: SAFE PRACTICES
Selectable Ground and Test Devices are designed with several built-in
interlocks and safety features to provide safe and proper operating
sequences.
DANGER
TO PROTECT THE PERSONNEL ASSOCIATED WITH INSTALLATION,
OPERATION, AND MAINTENANCE OF THE SELECTABLE GROUND AND TEST
DEVICES, THE FOLLOWING PRACTICES MUST BE FOLLOWED:
•
Only qualified persons, as defined in the National Electrical
Safety Code, who are familiar with the installation and
maintenance of medium voltage circuits and equipment,
should be permitted to work on the selectable ground and
test device.
•
Read these instructions carefully before attempting any
installation, operation or maintenance of the selectable
ground and test device.
•
Always remove the selectable ground and test device from
the enclosure before performing any maintenance on the
device. Failure to do so could result in electrical shock leading
to death, severe personnel injury or property damage.
•
Do not leave the selectable ground and test device in an
intermediate position in the cell. Always have the selectable
ground and test device either in the DISCONNECT or
CONNECTED position. Failure to do so could result in a
flash over and possible death, personnel injury or property
damage.
•
Keep all insulating surfaces, which include primary support
insulation and insulation barriers, clean and dry.
•
Check all primary circuit connections to make certain they are
clean and tight.
•
Take extreme care while using this device to avoid contacting
“live” or “hot” (energized) terminals.
•
These selectable ground and test devices are equipped with
safety interlocks. Do not defeat them. This may result in
death, bodily injury or equipment damage.
•
Correctly identify LINE and BUS terminals for the breaker
compartment before using this device. Remember that line
connection may be on lower terminals when installed in
upper compartment of 2-high switchgear.
•
Store the device in a clean, dry area free from dust, dirt,
moisture, etc.
6
Instruction Book IB182312EN June 2016 www.eaton.com