Ditek D200M-277-4803Y, D200M-277-4803YT Installation Instructions

INSTALL INSTRUCTIONS
DITEK Corporation
Expected System Voltages
L - L HiL-G,N L - G L - N N - G
D200-277/4803Y
ONE DITEK CENTER
1720 Starkey Road
Largo, FL 33771
This Surge Protective Device (SPD) is a high performance device, designed to provide protection for
D200-277/4803Y
sensitive electronic loads connected to service panels, fire panels, or where the SPD is directly connected to the electronic device. Maximum protection will only be achieved if the SPD is properly installed. Please read and follow the installation instructions carefully.
NOTICE: This SPD should be installed by a licensed contractor in accordance with the National and Local Electrical Codes and the following instructions.
APPLICATION
Type 1 SPD, Type 2 SPD for hardwired parallel installations on 277/480 VAC three phase circuits.
INSTRUCTIONS:
Caution: Measure all voltages to insure applied voltage does not exceed the voltage rating of
the unit. Improper installation voids the warranty. NOTE: Suitable for use on a circuit capable of delivering not more than 100,000 rms symmetrical Amperes. This SPD Contains no serviceable parts.
1. Turn off the power at the circuit breaker or main disconnect before beginning installation.
2. Remove front cover from the panel.
3. Remove 3/4" knockout on side of panel box.
4. Make sure the leads are as short as possible with the ground wire being the shortest of all.
5. Unscrew nut from unit. The flexible conduit between the locknuts can be cut down to size as necessary.
6. Feed all wires and the nipple through knockout hole then through nut, tighten nut securing the unit.
7. Connect the Ground wire (Green) to the ground bus making sure the ground wire is as short as possible. Ground Resistance Rule: Max ground resistance is 25 ohms, 5 ohms or less is optimum. This cannot be an assumed value and must be measured to assure proper grounding.
8. Connect the Neutral wire (White) to the Neutral bus of the panel.
9. Connect the Phase wires (Black) to the line side or load side of the Phase A, Phase B and Phase C, 3 pole breaker.
10. Securely mount the enclosure using the mounting feet located at each corner.
11. After all connections have been made and no hazards exist, replace panel cover and restore power.
12. This device features an internal protection that will disconnect the surge proctective component but will maintain power to the load - now unprotected. If this situation is undesirable for the application, follow the manufacturer’s instructions for replacing the device.
Dry Contact Connection: This is a Form C Dry Contact Circuit, 0.9A, 240VAC maximum input. Normally Open (NO)=Black Wire, Common (COM)= Red Wire, Normally Closed (NC)=White Wire. Note: Remote Alarm Wires To Be Connected To Class 1 Circuits Only.
BREAKER PANEL
NEUTRAL BUS
BLACK WIRES
3 POLE BREAKER
WHITE WIRE
GREEN WIRE
GROUND BUS
INSTALLATION
Drawn By: B. Aycock 5-19-16 Approved By: R. Mitchell 5-20-16
DITEK Technical Support Available 24/7 1-888-472-6100 www.ditekcorp.com
DITEK
MADE IN THE USA
120V Single Ø NA NA 120 120 0
240V Single Ø NA NA 240 240 0
120/240V Split Ø 240 NA 120 120 0 120/240V Hi Leg Δ 240 240 120 120 0 120/208V 3 Ø Wye 208 NA 120 120 0
277/480V 3 Ø Wye 480 NA 277 277 0
347/600V 3 Ø Wye 600 NA 347 347 0
240V 3 Ø Δ 480V 3 Ø Δ 600V 3 Ø Δ
240 480 600
NA 240 NA 480 NA 600
Max
NA 0
Max
NA 0
Max
NA 0
Doc # INT-100139-001 Part No. 191561 Rev. 3
Loading...