Installation Guide
FHR-B Manifolds
© Danfoss | FEC | 2020.09
Stem Horizontal
Stem Vertical
AN35345646949801-CN0101 / 088U7083 | 1
Airvent open
Manifold
open
Purge close
Airvent open
Manifold
open
Purge open
Installation Guide FHR-B Manifolds
Installation guide
Technical Data
Shutoff
1. The end piece and pipe connectors connected to manifold should be 1” round thread and sealed
by rubber sealing material at the end, the length of thread inserted into the manifold should be less
than 14mm.
2. The valves in both flow and return manifold should be fully opened during pressure test.
3. In order to prevent the misoperation of the end user to open the drain function of airvent end piece,
it is necessary to use the matching end cap for switching operation.
Test pressure 16 bar
Max. working pressure 10 bar
Max. flow temperature 90 °C
5 mm
CloseOpen
2 | © Danfoss | FEC | 2020.09
AN35345646949801-CN0101 / 088U7083