零件号 零件名称 安装位置 子零件号 子零件名称
1
2
3
注意事项
安装步骤
排气组件 安装于分水器末端
泄水组件 安装于集水器末端
连接管组件
用于连接排气组件出
口及 泄水 组件入口
1. 请按照零件清单核对产品零部件数量。
2. 排气组件1及泄水组件2在出厂前已完成组装,在产品安装过程中,请勿拆卸排气阀1-1 及泄水球阀2-2
3. 检查连接管组件3上各零件的位置,零件位置见图2
4. 请勿反复拆装铜管组件。
必须按图示要求将FHPRO-ED连接至系统
1. 将排气阀组件1连接于分水器主体,通过垫片3密封,进口A和出口B方向见图3。
2. 将泄水阀组件2连接于集水器主体,通过垫片3密封,进口C和出口D方向见图3。
3. 将铜管E端插入排气阀组件出口B,调 整 铜 管 位 置 ,见 图 3
4. 将铜管F端插入泄水阀组件入口C,见 图 3
5. 依次拧紧螺母3-33-4,见 图 1和2。
1-1 1-2 1-3 2-1 2-2 2-3 3-1 3-2
3-3 3-4 3-5
排气阀 排气组件本体 垫片 泄水组件本体 泄水阀 垫片 O型圈 支撑环 螺母 螺母 连接管本体
2 | © Danfoss | FEC | 2019.05
1
3
2
3
)
088U7201 | AN30643811120601-000101 / VIIKJ12P
Installation Guide
DP Bypass End Piece
Installation overview
Part list
Fig. 1
3-1
2-3
1-3
Airvent component Purge component Connector Tube component
1-1
1-2
Fig. 2
2-1
2-2
3-2
3-3
3-4
3-5
© Danfoss | FEC | 2019.05
088U7201 | AN30643811120601-000101 / VIIKJ12P | 3
Danfos produc Al
Danfoss A/S
Heating Segment • heating
Part NO. Part name Installation position Sub-part NO. Sub-part name
1-1 Airvent valve
1 Airvent component
Mounted on the end of manifold
supply pipe
1-2 Body of airvent component 1-3 Gasket 2-1 Body of purge component
2 Purge component
Mounted on the end of manifold
return pipe
2-2 Purge valve 2-3 Gasket 3-1 O-ring
3
Connector Tube
component
As a connector between outlet
of airvent component and
inlet purge component
3-2 Support ring 3-3 Nut 3-4 Nut 3-5 Connector tube
Notice 1. Check the components quantity according to part list.
2. Airvent component 1 and purge component 2 are assembled in factory. Please do not tear down the airvent valve 1-1 and purge valve 2-2 during the product installation.
3. Checked each part position on the connector tube component 3, the parts position shown in g.2.
4. Please do not assemble and disassemble repeatedly.
Installation procedure The FHPRO-ED must be connected to a system according to the illustrations.
1. Mounted airvent component 1 on manifold supply pipe, sealing by gasket 3, direction of inlet A and outlet B as shown in gure 3.
2. Mounted purge component 2 on manifold return pipe, sealing by gasket 3, direction of inlet C and outlet D as shown in gure 3.
3. Insert connector tube end E into airvent component outlet B and adjust copper tube posi­tion, as shown in gure 3.
4. Insert connector tube end F into purge component inlet C, as shown in gure 3.
5. Tighten nuts 3-3 and 3-4 sequentially, as shown in gure 1 and 2.
1
3
2
s can accept no responsibility for possible errors in catalogues, brochures and o ther printed material. Danfoss reserves the right to alter its products w ithout notice. This also applies to ts already on order provided that such alterations can be m ade without subsequential changes being necessary in specications already agreed.
l trademarks in this material are p roperty of the respective companies. Danfoss and all Danfoss l ogotypes are trademarks of Danfoss A/S. All rights reserve d.
4 | © Danfoss | FEC | 2019.05
Fig. 3
.danfoss.com • +45 7488 2222 • E-Mail: heating@danfoss.com
088U7201 | AN30643811120601-000101 / VIIKJ12P
Loading...